An automatic flood discharge flap gate for steel dams

By designing an automatic flood discharge flap steel dam gate, using hydraulic automatic flood discharge and a four-bar linkage mechanism, the problems of mechanical drive incompatibility and hydraulic cylinder failure of the existing steel dam gates in projects with a wide dam surface have been solved, achieving low-cost, Low maintenance water engineering solutions.

CN111074858BActive Publication Date: 2024-10-29CHANGJIANG SURVEY PLANNING DESIGN & RES CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202010066956.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-01-20
Publication Date
2024-10-29
Estimated Expiration
2040-01-20

AI Technical Summary

Technical Problem

Existing steel dam gates have problems such as mechanical drive incompatibility in water conservancy projects with wide dam surfaces and failure problems caused by the service life of the hydraulic rod push-type steel dam gates and sediment blockage.

Method used

An automatic flood discharge flap steel dam gate is designed, which uses hydraulic power to automatically discharge floods. The gate is opened and closed through a water-filled pipe and a four-bar linkage mechanism, avoiding the use of mechanical equipment. The problem of dam surface width is solved by installing multiple gates side by side. .

Benefits of technology

It realizes no need for mechanical drive, simple structure, low cost, low operation and maintenance costs, suitable for remote areas, simple construction, saving construction period, and suitable for projects to increase reservoir storage capacity and adjust water levels.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111074858B_ABST
    Figure CN111074858B_ABST
Patent Text Reader

Abstract

The present invention provides an automatic flood discharge flap steel dam gate, comprising a gate leaf, an upper support rod, a lower support rod, a platform, a retaining rod, and a water filling pipe. The upstream side and the downstream side of the gate leaf are respectively provided with a water filling pipe inlet and a water filling pipe outlet connected through the water filling pipe, and the water filling pipe inlet is higher than the gate top of the gate leaf; the bottom of the gate leaf is rotatably connected to the downstream concrete bottom plate, one end of the upper support rod is rotatably connected to the downstream side of the upper part of the gate leaf, the other end of the upper support rod is rotatably connected to one end of the lower support rod, and the other end of the lower support rod is rotatably connected to the downstream concrete bottom plate; the platform is located below the upper support rod, the lower support rod and the gate leaf, the right side of the platform is rotatably connected to the downstream concrete bottom plate, the left side of the platform is supported on the water filling pipe outlet, one end of the retaining rod is rotatably connected to the left side of the platform, the other end of the retaining rod contacts the lower support rod, and the lower support rod is provided with a retaining rod limit block for supporting the retaining rod. The present invention utilizes hydraulic power to automatically discharge flood, has a simple structure, low cost, and low operation and maintenance costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of water conservancy and hydropower engineering, and in particular to an automatic flood discharge flap steel dam gate, which is particularly suitable for low-head water retaining projects such as increasing reservoir capacity, regulating upstream water levels of small and medium-sized rivers, and urban river landscape. Background Art

[0002] Steel dam gates are mainly used in agricultural irrigation, urban flood control, urban river landscape projects and increasing reservoir capacity.

[0003] There are two common types of steel dam gates:

[0004] (1) The bottom horizontal axis drives the steel dam gate. The bottom horizontal axis is driven by hydraulic equipment to rotate to open and close the steel dam gate. It mainly includes the bottom horizontal axis, steel dam gate leaf, and the gate hoist installed in the gate chamber. The two ends of the bottom horizontal axis pass through the gate chamber walls on both sides of the river channel and are connected to the gate hoist in the gate chamber. The bottom horizontal axis rotates under the drive of the gate hoist, thereby driving the gate to rotate and realize the opening and closing functions. The bottom horizontal axis of this steel dam gate is subjected to both the bending moment generated by the water pressure and the huge torque when the gate is opened and closed. In order to meet the strength and rigidity requirements, the cross-sectional size of the bottom horizontal axis is very large, and the corresponding gate hoist size must also be large. Therefore, this gate is not suitable for water conservancy projects with a wider dam surface.

[0005] (2) Hydraulic rod push-type steel dam gate. Support hinges are evenly arranged on the concrete slab at the bottom of the steel dam. The bottom of the steel dam gate leaf is connected to the support hinge, and the gate leaf can rotate around the support hinge. A hinge is arranged on the upper part of the downstream surface of the gate leaf, which is connected to the support structure downstream of the gate leaf. The sliding rod support rod is used to support the movable steel dam gate leaf. A hydraulic cylinder and a limit card are configured to form an exchange between the support fixation and the movement of the steel dam. Multiple oil cylinders can be used to push the steel dam support structure to achieve the function of raising the dam to block water or lowering the dam to release water. It is particularly suitable for water conservancy projects with wide rivers or dam surfaces. Multiple leaves can be installed in parallel. However, the disadvantage is that the push cylinder is soaked in water all year round, which affects the service life of the cylinder, and the cylinder is easily blocked by silt, resulting in failure when driving the steel dam gate. Summary of the invention

[0006] The purpose of the present invention is to provide an automatic flood discharge flap steel dam gate with a simple structure and multiple gates that can be installed side by side. It uses hydraulic power to automatically discharge flood water and does not require mechanical equipment to operate. It solves the problems that the existing bottom horizontal axis driven steel dam gate cannot adapt to the wider dam surface and the service life of the oil cylinder pushed by the hydraulic rod push type steel dam gate is short and the silt blockage causes failure.

[0007] The present invention adopts the following technical solutions to solve the above technical problems:

[0008] An automatic flood-discharging flap steel dam gate comprises a gate leaf, an upper support rod, a lower support rod, a platform, a retaining rod and a water-filling pipe. A water-filling pipe inlet and a water-filling pipe outlet connected through the water-filling pipe are respectively provided on the upstream side and the downstream side of the gate leaf, and the water-filling pipe inlet is higher than the gate top of the gate leaf; the bottom of the gate leaf is rotatably connected to the downstream concrete bottom plate, one end of the upper support rod is rotatably connected to the downstream side of the upper part of the gate leaf, the other end of the upper support rod is rotatably connected to one end of the lower support rod, and the other end of the lower support rod is rotatably connected to the downstream concrete bottom plate; the platform is located below the upper support rod, the lower support rod and the gate leaf, the right side of the platform is rotatably connected to the downstream concrete bottom plate, the left side of the platform is supported on the water-filling pipe outlet, one end of the retaining rod is rotatably connected to the left side of the platform, the other end of the retaining rod contacts the lower support rod, and the lower support rod is provided with a retaining rod limit block for supporting the retaining rod.

[0009] Furthermore, a door leaf support hinge is fixed on the downstream concrete bottom plate, and the door leaf is connected to the downstream concrete bottom plate through the door leaf support hinge, and the door leaf can rotate around the door leaf support hinge; a door leaf hinge is arranged on the downstream side of the upper part of the door leaf, and the upper support rod is connected to the door leaf through the door leaf hinge, and the upper support rod can rotate around the door leaf hinge.

[0010] Furthermore, the lower support rod is connected to the upper support rod through a support rod hinge, and the lower support rod and the upper support rod can rotate around the support rod hinge.

[0011] Furthermore, a lower support rod hinge is fixed on the downstream concrete bottom plate, the bottom end of the lower support rod is connected to the lower support rod hinge, and the lower support rod can rotate around the lower support rod hinge.

[0012] Furthermore, a platform support hinge is fixed on the downstream concrete bottom plate, the right side of the platform is connected to the platform support hinge, and the platform can rotate around the platform support hinge.

[0013] Furthermore, a barrier rod hinge is arranged on the left upper surface of the platform, one end of the barrier rod is connected to the barrier rod hinge and can rotate around the barrier rod hinge, and the other end is in contact with the lower support rod for supporting the lower support rod.

[0014] Furthermore, a trash rack is provided at the inlet of the water filling pipe.

[0015] Furthermore, a door leaf support is arranged beside the door leaf hinge at the upper part of the door leaf, and a supporting device is correspondingly arranged on the downstream concrete bottom plate. When the door leaf lies down, the door leaf support contacts the supporting device.

[0016] Furthermore, an elastic buffer pad is provided on the supporting device.

[0017] Furthermore, the gate leaf, the upper support rod, the lower support rod and the rotating device therebetween form a four-bar linkage. When blocking water, there is no water in the water filling pipe, the upper support rod and the lower support rod support the gate leaf, the blocking rod supports the lower support rod, and the flap steel dam gate is in a balanced state; when discharging flood, the water filling pipe is filled with water, and the pressure difference between the water filling pipe inlet and the water filling pipe outlet causes the blocking rod to fall down, the lower support rod loses support, and the four-bar linkage rotates until the gate lies down.

[0018] Compared with the traditional flap steel dam gate, the structure of the present invention has the following advantages:

[0019] (1) No mechanical drive is required, no electricity is required, the structure is simple, the cost is low, the operation and maintenance cost is low, the economic benefits are significant, and it is suitable for remote areas.

[0020] (2) The construction is simple and saves construction period. It is particularly suitable for projects such as increasing reservoir capacity and improving power station head.

[0021] (3) When the dam surface is wide, multiple flap steel dam gates can be installed side by side. Each gate is equipped with a set of water filling pipes. When discharging flood water, the order of the gates can be determined according to needs. For example, when the steel dam gate in the middle of the dam surface needs to be opened first, the inlet elevation of the water filling pipe corresponding to the steel dam gate in the middle of the dam surface can be lower than the inlet elevation of the water filling pipes of other steel dam gates. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a schematic diagram of the structure of the automatic flood discharge flap steel dam gate of the present invention when it is blocking water;

[0023] Figure 2 It is a schematic diagram of the flood discharge state when the automatic flood discharge flap steel dam gate of the present invention is at a flood level;

[0024] Figure 3 It is a schematic diagram of the supporting structure state of the automatic flood discharge flap steel dam gate of the present invention when it is lying down;

[0025] Figure 4 It is a schematic diagram of the supporting state of the automatic flood discharge flap steel dam gate of the present invention when it is lying down.

[0026] In the figure: 1-door leaf, 2-door leaf support hinge, 3-door leaf hinge, 4-upper support rod, 5-support rod hinge, 6-lower support rod, 7-lower support rod support hinge, 8-platform support hinge, 9-platform, 10-blocking rod, 11-blocking rod support hinge, 12-blocking rod limit block, 13-water filling pipe, 14-water filling pipe inlet, 15-water filling pipe outlet, 16-door leaf support, 17-supporting device. DETAILED DESCRIPTION

[0027] The technical solution of the present invention will be clearly and completely described below in conjunction with the accompanying drawings of the present invention.

[0028] See also Figure 1 An embodiment of the present invention provides an automatic flood discharge flap steel dam gate, including a gate leaf 1, an upper support rod 4, a lower support rod 6, a platform 9, a barrier rod 10, a water filling pipe 13, a gate leaf support hinge 2 arranged at the bottom of the gate leaf 1, and a gate leaf hinge 3 arranged at the upper part of the gate leaf 1.

[0029] The door leaf hinge 2 is fixed on the downstream concrete bottom plate, the door leaf 1 can rotate around the door leaf hinge 2, the door leaf hinge 3 is arranged on the downstream side of the upper part of the door leaf, the upper support rod 4 is connected to the door leaf 1 through the door leaf hinge 3, the upper support rod 4 can rotate around the door leaf hinge 3, the other end of the upper support rod 4 is arranged with a support rod hinge 5, the lower support rod 6 is connected to the upper support rod 4 through the support rod hinge 5, the lower support rod 6 and the upper support rod 4 can rotate around the support rod hinge 5. The other end of the lower support rod 6 is connected to the lower support rod hinge 7, the lower support rod hinge 7 is fixed on the downstream concrete bottom plate, and the lower support rod 6 can rotate around the lower support rod hinge 7.

[0030] A platform 9 is arranged below the upper support rod 4, the lower support rod 6 and the door leaf 1. The right side of the platform 9 is connected to the platform support hinge 8, and the platform support hinge 8 is fixed on the downstream concrete bottom plate. The platform 9 can rotate around the platform support hinge 8. The left side of the platform 9 is supported on the water filling pipe outlet 15, and the platform 9 is in contact with the water filling pipe outlet 15. A baffle rod support hinge 11 is arranged on the left upper surface of the platform 9. One end of the baffle rod 10 is connected to the baffle rod support hinge 11 and can rotate around the baffle rod support hinge 11, and the other end is in contact with the lower support rod 6 for supporting the lower support rod 6.

[0031] A baffle rod limit block 12 is welded on the lower support rod 6. In the water blocking state, the baffle rod limit block 12 can support the baffle rod 10 to prevent the baffle rod 10 from rotating clockwise around the baffle rod support hinge 11 under the action of its own weight and falling, resulting in failure to support the lower support rod 6.

[0032] The water filling pipe inlet 14 is located on the upstream side of the door leaf 1, and a trash rack is provided on the water filling pipe inlet 14. The water filling pipe inlet 14 is higher than the door top of the door leaf 1, and the water filling pipe outlet 15 is located on the downstream side of the door leaf 1. Figure 4 As shown, a leaf support 16 is arranged beside the leaf hinge 3 at the upper part of the leaf 1, and a supporting device 17 is correspondingly arranged on the downstream concrete bottom plate. When the leaf 1 lies down, the leaf support 16 contacts the supporting device 17. The height of the supporting device 17 from the ground needs to ensure that the supporting structure is in a relaxed state when the steel dam gate lies down.

[0033] The blocking rod 10 is similar to the trigger on a pistol. When blocking water, there is no water in the water filling pipe 13, the upper support rod 4 and the lower support rod 6 support the gate leaf 1, the blocking rod 10 supports the lower support rod 6, and the flap steel dam gate is in a balanced state. When discharging flood water, the water filling pipe 13 is filled with water, and the pressure difference between the water filling pipe inlet 14 and the water filling pipe outlet 15 pulls the trigger, the blocking rod 19 falls down, the lower support rod 6 loses support, and the four-bar linkage (gate leaf 1, upper support rod 4, lower support rod 6 and its support hinges and hinges) rotates until the gate lies down.

[0034] like Figure 1 As shown, when the steel dam gate is in a water-retaining state, the upstream water level is generally not higher than the gate top of the gate leaf 1. When the upstream water level is higher than the gate top of the gate leaf 1 and lower than the water filling pipe inlet 14, the water flows down along the top of the steel dam gate to form a water curtain. Under the action of the upstream water pressure, the upper support rod 4 and the lower support rod 6 tend to rotate toward the inside of the gate leaf 1. At this time, the blocking rod 10 plays a role to prevent the lower support rod 6 from rotating. The blocking rod limit block 12 welded on the lower support rod 6 prevents the blocking rod 10 from falling, thereby maintaining the stability of the supporting structure system.

[0035] When the upstream water volume is greater than the discharge volume of the steel dam, the upstream water level rises. Figure 2 As shown, when the upstream water level rises to the elevation of the water filling pipe inlet 14, the water flows into the water filling pipe 13 through the inlet trash rack, and then the water filling pipe 13 is filled with water. Due to the pressure difference between the upstream and downstream of the steel dam gate, the water in the water filling pipe 13 forms an upward pressure at the bottom of the platform 9. Under the action of the water pressure, the platform 9 rotates around the platform support hinge 8, and the platform 9 drives the blocking rod 10 to push the lower support rod 6 to rotate clockwise. At this time, the gate leaf 1, the upper support rod 4, the lower support rod 6 and their support hinges and hinges form a four-bar linkage.

[0036] When the platform 9 is opened to a certain angle, the blocking rod 10 is disengaged from the lower support rod 6, and the blocking rod 10 rotates under its own weight until it contacts the platform 9 (such as Figure 3 As shown in the figure, under the action of upstream water pressure, the four-bar linkage rotates clockwise, the gate gradually rotates and descends, the pressure difference between the upstream and downstream of the water filling pipe 13 is gradually reduced, and the platform 9 rotates counterclockwise and descends around the platform support hinge 8. When the gate leaf support 16 contacts the support device 17, the four-bar linkage stops rotating, and the steel dam gate finally lies down. The support device 17 is provided with an elastic buffer pad to ensure that no impact vibration occurs when the steel dam gate lies down, thereby protecting the steel dam gate.

[0037] When the dam surface is wide, multiple flap steel dam gates can be installed side by side, and one gate is equipped with a set of water filling pipes. The width of each gate, the number of supporting rod structures and the area of ​​the water filling pipes are determined according to the specific project. When discharging flood water, the order of the gates can be determined according to needs. For example, when the steel dam gate in the middle of the dam surface needs to be opened first, the water filling pipe inlet 14 of the steel dam gate in the middle of the dam surface can be lower than the water filling pipe inlet 14 of other steel dam gates.

[0038] After a flood, the gate can be reset using simple methods such as lifting brackets and guide chains.

[0039] The above description is only a specific implementation mode of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily thought of by technicians in this technical field within the technical scope disclosed by the present invention should be covered by the protection scope of the present invention.

Claims

1. An automatic flood discharge flap steel dam gate, characterized by: The invention comprises a door leaf (1), an upper support rod (4), a lower support rod (6), a platform (9), a baffle rod (10), and a water filling pipe (13). The upstream side and the downstream side of the door leaf (1) are respectively provided with a water filling pipe inlet (14) and a water filling pipe outlet (15) which are connected through the water filling pipe (13). The water filling pipe inlet (14) is higher than the door top of the door leaf (1). The bottom of the door leaf (1) is rotatably connected to the downstream concrete bottom plate. One end of the upper support rod (4) is rotatably connected to the downstream side of the upper part of the door leaf (1). The other end is rotatably connected to one end of the lower support rod (6), and the other end of the lower support rod (6) is rotatably connected to the downstream concrete bottom plate; the platform (9) is located below the upper support rod (4), the lower support rod (6) and the door leaf (1), the right side of the platform (9) is rotatably connected to the downstream concrete bottom plate, the left side of the platform (9) is supported on the water filling pipe outlet (15), one end of the blocking rod (10) is rotatably connected to the left side of the platform (9), the other end of the blocking rod (10) is in contact with the lower support rod (6), and the lower support rod (6) is provided with a support The gate leaf (1), the upper support rod (4), the lower support rod (6) and the rotating device therebetween form a four-bar linkage. When blocking water, there is no water in the water filling pipe (13), the upper support rod (4) and the lower support rod (6) support the gate leaf (1), the barrier rod (10) supports the lower support rod (6), and the flap steel dam gate is in a balanced state. When discharging flood water, the water filling pipe (13) is filled with water, and the pressure difference between the water filling pipe inlet (14) and the water filling pipe outlet (15) causes the barrier rod (10) to move. ) falls down, the lower support rod (6) loses support, and the four-bar linkage rotates until the gate lies down; a platform support hinge (8) is fixed on the downstream concrete bottom plate, the right side of the platform (9) is connected to the platform support hinge (8), and the platform (9) can rotate around the platform support hinge (8); a blocking rod support hinge (11) is provided on the left upper surface of the platform (9), one end of the blocking rod (10) is connected to the blocking rod support hinge (11) and can rotate around the blocking rod support hinge (11), and the other end is in contact with the lower support rod (6) for supporting the lower support rod (6).

2. The automatic flood discharge flap steel dam gate according to claim 1, characterized in that: A door leaf support hinge (2) is fixed to the downstream concrete bottom plate, the door leaf (1) is connected to the downstream concrete bottom plate via the door leaf support hinge (2), and the door leaf (1) can rotate around the door leaf support hinge (2); a door leaf hinge (3) is arranged on the downstream side of the upper part of the door leaf, an upper support rod (4) is connected to the door leaf (1) via the door leaf hinge (3), and the upper support rod (4) can rotate around the door leaf hinge (3).

3. The automatic flood discharge flap steel dam gate according to claim 1, characterized in that: The lower support rod (6) and the upper support rod (4) are connected via a support rod hinge (5), and the lower support rod (6) and the upper support rod (4) can rotate around the support rod hinge (5).

4. The automatic flood discharge flap steel dam gate according to claim 1, characterized in that: A lower support rod hinge (7) is fixed on the downstream concrete bottom plate, the bottom end of the lower support rod (6) is connected to the lower support rod hinge (7), and the lower support rod (6) can rotate around the lower support rod hinge (7).

5. The automatic flood discharge flap steel dam gate according to claim 1, characterized in that: The water filling pipe inlet (14) is provided with a trash rack.

6. The automatic flood discharge flap steel dam gate according to claim 1, characterized in that: A door leaf support (16) is arranged on the side of the door leaf hinge (3) at the upper part of the door leaf (1), and a supporting device (17) is correspondingly arranged on the downstream concrete bottom plate. When the door leaf (1) lies down, the door leaf support (16) contacts the supporting device (17).

7. The automatic flood discharge flap steel dam gate according to claim 6, characterized in that: An elastic buffer block is provided on the supporting device (17).

Citation Information

Patent Citations

  • Dam is folded to four connecting rods

    CN206015616U

  • Flood discharge anti-seepage dam for water conservancy project

    CN209779568U

  • Automatic flood discharge flap steel dam gate

    CN211948305U