Construction technology of wet joint rapid assembly platform for urban smart expressway cap beam

By designing a rapid assembly operation platform for wet joints of urban smart expressway cover beams, the problems of single functionality and insufficient strength of traditional platforms are solved, and efficient and safe construction of wet joints of cover beams is achieved, and construction efficiency is improved.

CN111236084BActive Publication Date: 2024-11-05THE THIRD CONSTR OF CHINA CONSTR EIGHTH ENG BUREAU
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202010182131.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-03-16
Publication Date
2024-11-05
Estimated Expiration
2040-03-16

AI Technical Summary

Technical Problem

The traditional wet joint assembly working platform of cover beams is single in functionality, the overall structural strength is not high, and the installation and removal are inconvenient, which affects construction efficiency.

Method used

A quick assembly operation platform for wet joints of urban smart expressway cover beams is designed, including bottom beams, top beams, hanging rods, side molds, protective outer frames and platform beams, adopting an open-closable structure, which is fixed by hinges and nuts. Achieve stable connections between the boom and the side mold, add top support structure and jack to improve overall strength, and use tire lift trucks and tensioning platforms to perform prestressing and pipe grouting of the cover beams.

Benefits of technology

It improves the overall structural strength and stability of the working platform, facilitates installation and dismantling during construction, and significantly improves construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111236084B_ABST
    Figure CN111236084B_ABST
Patent Text Reader

Abstract

The present invention discloses a construction process for a wet-joint rapid assembly work platform for a cap beam of an urban smart expressway, comprising: a bottom beam, wherein two bottom beams are provided; a No. 1 top beam, wherein two No. 1 top beams are provided; a hanger, wherein the hanger is rotatably installed on both sides of the top end of the bottom beam by hinges, and four hangers are provided; a side form, wherein the side form is fixedly installed on the inner side of the hanger, and two groups of side forms are provided, wherein a horizontal tie rod is fixedly installed between the two groups of side forms near the axis through a nut, and four horizontal tie rods are provided; a protective outer frame, wherein a wire mesh is fixedly installed on the outside of the protective outer frame; the main load-bearing structure system of the present invention is provided with two No. 2 top beams on the upper part, which are supported on the top surface of the No. 1 top beam, and four vertical hangers are connected on both sides as the main hangers of the structure, and the lower ends of the hangers are connected to the main load-bearing cross beams of the bottom formwork of the steel formwork. The overall structure has high strength and good stability, can effectively prevent collapse, and has very good safety.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of assembly between cap beam segments, and specifically to a construction process for a wet joint rapid assembly work platform for urban smart expressway cap beams. Background Art

[0002] The cap beam refers to the beam set on the top of the frame pile pier to support, distribute and transfer the load of the superstructure. It is also called the cap beam. The beam of reinforced concrete or less reinforced concrete is set on the pier (platform) or on the pile. Its main function is to support the superstructure of the bridge and transfer all the loads to the lower structure. There are bridge piles directly connected to the cap beam, and there are also bridge piles connected to the column and then connected to the cap beam. In bridge design, column piers are the most commonly used structural type. For simply supported bridges, the cap beam is an important component that connects the upper and lower parts. The load of the superstructure is transferred to the lower structure and foundation through the cap beam. The cap beam is the main load-bearing structure. The changes in span, slope, bridge width, and vehicle load standards in the design have a great impact on the beam design. It is difficult to fully apply standard drawings and general drawings. The degree of standardization of the cap beam design is very high, and more calculations are required for the cap beam. Therefore, the cap beam design is a key part of the bridge design. Generally, in the construction of wet joints of concrete cap beams, it is necessary to build a working platform.

[0003] However, the current traditional assembly work platforms have relatively simple functionality and are very inconvenient to use. The overall structural strength of the traditional assembly work platforms is not high, and they are not convenient for installation and dismantling during construction, which seriously affects work efficiency. Summary of the invention

[0004] The purpose of the present invention is to provide a construction process for a wet-joint rapid assembly work platform for a cap beam of an urban smart expressway, so as to solve the problems raised in the above-mentioned background technology.

[0005] To achieve the above object, the present invention provides the following technical solution: a construction process for a wet joint rapid assembly work platform for a cap beam of an urban smart expressway, comprising:

[0006] Bottom beams, two bottom beams are provided;

[0007] A first top beam, wherein two of the first top beams are provided;

[0008] A suspension rod, which is rotatably mounted on both sides of the top of the bottom beam through hinges, and four suspension rods are provided;

[0009] Side molds, the side molds are fixedly installed on the inner side of the suspension rod, and there are two sets of side molds, wherein a horizontal tie rod is fixedly installed between the two sets of side molds near the axis through nuts, and there are four horizontal tie rods;

[0010] A protective outer frame, wherein a steel wire mesh is fixedly installed on the outside of the protective outer frame;

[0011] A second top beam, the second top beam is fixedly installed on both sides of the top of the first top beam, wherein two groups of the second top beams and the bottom beam are fixedly installed with vertical tie rods through nuts, and four vertical tie rods are provided, and the vertical tie rods are located on both sides of the horizontal tie rods;

[0012] Among them, two of the No. 1 top beams are fixedly installed on the top ends of the four suspension rods through a fixed frame, and the protective outer frame is fixedly installed on both sides of the bottom beam and the No. 1 top beam.

[0013] Preferably, a top support structure is fixedly installed between the suspension rod and the side form, and the top support structure includes a No. 1 connection frame and a No. 2 connection frame, the No. 1 connection frame is fixedly installed on the surface of the side form, the No. 2 connection frame is fixedly installed on the surface of the suspension rod, a threaded sleeve is fixedly installed on one end of the No. 2 connection frame, a screw is installed on the internal thread of the threaded sleeve, an end of the screw away from the threaded sleeve is fixedly connected to one end of the No. 1 connection frame, and a nut is installed on the external thread of the screw;

[0014] Wherein, the suspension rod and the side form are fixedly connected via a top support structure.

[0015] Preferably, a jack and a rigid support are respectively fixedly installed at the bottom ends of the two No. 1 top beams, and the jack is located on the inner side of the rigid support.

[0016] Preferably, it also includes:

[0017] A ladder is fixedly mounted on the outer wall surfaces of two sets of the side molds.

[0018] Preferably, it also includes:

[0019] The platform beam is fixedly installed on both sides of the bottom ends of the two bottom beams.

[0020] Preferably, the side formwork adopts a common steel formwork structure of steel plate + steel back rib.

[0021] Preferably, the protective outer frame adopts a steel-constructed space truss structure system.

[0022] Preferably, the method comprises the following steps:

[0023] S1. After the segments on both sides are spliced ​​and anchored, a tire-type lifting vehicle is used to hang the formwork and working platform on the assembled segments, connect the main reinforcement of the cap beam at the joint, install the cap beam stirrups, and use a pump truck to pour wet joint concrete;

[0024] S2. After the wet joint concrete reaches the design strength, use a tire-type lift and a tensioning platform to tension the cap beam prestressing and pipe grouting in batches and steps according to the design requirements, and the cap beam is connected into a whole.

[0025] Preferably, in step S1, the steel formwork is pre-assembled before leaving the factory, and the first piece is subjected to a load test to confirm that it meets the requirements before it can be used.

[0026] Preferably, in step S1, after each formwork is completed, pre-pressing should be performed to eliminate elastic deformation of the formwork and ensure the accuracy of the external dimensions of the wet joint of the cap beam.

[0027] Compared with the prior art, the present invention has the following beneficial effects:

[0028] 1. The main load-bearing structure system of the present invention is provided with two No. 2 top beams on the upper part to support the top surface of the No. 1 top beam, and four vertical hangers are connected on both sides as the main hangers of the structure, and the lower ends of the hangers are connected to the main load-bearing cross beams of the bottom template of the steel formwork. The overall structure has high strength and good stability, can effectively prevent collapse, and has very good safety.

[0029] 2. The present invention is designed as an openable and closable structure. During installation, all the accessory components are installed in place on the ground in advance and then hoisted and installed in place at one time, which is convenient for installation and removal during construction and improves production efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 It is a schematic diagram of the overall structure of the present invention;

[0031] Figure 2 This is a schematic diagram of the structure before installation of the present invention;

[0032] Figure 3 It is a schematic diagram of the connection structure of the side form and the suspension rod of the present invention;

[0033] Figure 4 It is a schematic diagram of the side mold structure of the present invention;

[0034] Figure 5 It is a schematic diagram of the top support structure of the present invention.

[0035] In the figure: 1- bottom beam; 2- top beam No. 1; 3- hinge; 4- hanging rod; 5- side form; 6- protective outer frame; 7- wire mesh; 8- horizontal pull rod; 9- top beam No. 2; 10- jack; 11- rigid support; 12- vertical pull rod; 13- fixed frame; 14- top support structure; 15- connecting frame No. 1; 16- nut; 17- screw rod; 18- threaded sleeve; 19- connecting frame No. 2; 20- ladder; 21- platform beam. DETAILED DESCRIPTION

[0036] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0037] Embodiment 1:

[0038] See also Figure 1-5 The present invention provides a technical solution: a construction process for a wet joint rapid assembly work platform for a city smart expressway cap beam, comprising: a bottom beam 1, a No. 1 top beam 2, a hanger 4, a side form 5, a protective outer frame 6 and a No. 2 top beam 9.

[0039] Wherein, two bottom beams 1 are provided.

[0040] Furthermore, the bottom beam 1 is made of 2[25a channel steel.

[0041] There are two No. 1 top beams 2.

[0042] Furthermore, the No. 1 top beam 2 is made of 2[25a channel steel.

[0043] The suspension rods 4 are rotatably mounted on both sides of the top of the bottom beam 1 through hinges 3, and four suspension rods 4 are provided.

[0044] The side molds 5 are fixedly installed on the inner side of the suspension rod 4, and two groups of side molds 5 are provided, wherein a horizontal tie rod 8 is fixedly installed between the two groups of side molds 5 near the axis through a nut, and four horizontal tie rods 8 are provided.

[0045] Wherein, a steel wire mesh 7 is fixedly installed on the outside of the protective outer frame 6 .

[0046] Among them, the No. 2 top beam 9 is fixedly installed on both sides of the top of the No. 1 top beam 2, and vertical pull rods 12 are fixedly installed between the two groups of the No. 2 top beams 9 and the bottom beam 1 through nuts, and four vertical pull rods 12 are provided, and the vertical pull rods 12 are located on both sides of the horizontal pull rods 8.

[0047] Among them, two of the No. 1 top beams 2 are fixedly installed on the top ends of the four suspension rods 4 through a fixed frame 13, and the protective outer frame 6 is fixedly installed on both sides of the bottom beam 1 and the No. 1 top beam 2.

[0048] Among them, a top support structure 14 is fixedly installed between the suspension rod 4 and the side mold 5, and the top support structure 14 includes a No. 1 connection frame 15 and a No. 2 connection frame 19. The No. 1 connection frame 15 is fixedly installed on the surface of the side mold 5, and the No. 2 connection frame 19 is fixedly installed on the surface of the suspension rod 4. A threaded sleeve 18 is fixedly installed on one end of the No. 2 connection frame 19, and a screw 17 is installed on the internal thread of the threaded sleeve 18. The end of the screw 17 away from the threaded sleeve 18 is fixedly connected to one end of the No. 1 connection frame 15, and a nut 16 is installed on the external thread of the screw 17;

[0049] The suspension rod 4 and the side mold 5 are fixedly connected via a top support structure 14 .

[0050] Among them, a jack 10 and a rigid support 11 are respectively fixedly installed at the bottom ends of two of the No. 1 top beams 2, and the jack 10 is located on the inner side of the rigid support 11.

[0051] It also includes: a ladder 20, which is fixedly installed on the outer wall surfaces of two groups of the side molds 5.

[0052] Wherein, it also includes: a platform beam 21, and the platform beam 21 is fixedly installed on both sides of the bottom ends of the two bottom beams 1.

[0053] Wherein, the side formwork 5 adopts a common steel formwork structure of steel plate + steel back rib.

[0054] The protective outer frame 6 adopts a steel-structured space truss structure system.

[0055] In summary of the above embodiments, during installation, all accessory components are installed in place on the ground in advance and then hoisted and installed in place at one time.

[0056] Embodiment 2:

[0057] See also Figure 1-5 The present invention provides a technical solution: a construction process for a wet joint rapid assembly work platform for a cap beam of an urban smart expressway, comprising the following steps:

[0058] S1. After the segments on both sides are spliced ​​and anchored, a tire-type lifting vehicle is used to hang the formwork and working platform on the assembled segments, connect the main reinforcement of the cap beam at the joint, install the cap beam stirrups, and use a pump truck to pour wet joint concrete;

[0059] S2. After the wet joint concrete reaches the design strength, use a tire-type lift and a tensioning platform to tension the cap beam prestressing and pipe grouting in batches and steps according to the design requirements, and the cap beam is connected into a whole.

[0060] Among them, in step S1, the steel formwork is pre-assembled before leaving the factory, and the first piece is subjected to a load test to confirm that it meets the requirements before it can be used.

[0061] Among them, in step S1, after each formwork is completed, pre-pressing should be performed to eliminate the elastic deformation of the formwork to ensure the accuracy of the external dimensions of the wet joint of the cap beam.

[0062] In the several embodiments provided by the present invention, it should be understood that the disclosed device can be implemented in other ways. The welding or threaded connection or winding connection shown or discussed can be completed with the assistance of equipment, such as welding with a welding gun, threaded connection with a wrench, etc. The materials of the device components are various, such as aluminum alloy, steel, copper and other metal materials, which are formed by casting or mechanical stamping.

[0063] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0064] The above description is only an implementation mode of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. The construction process of the wet joint rapid assembly work platform for the urban smart expressway cap beam is characterized by: The working platform comprises: A bottom beam (1), wherein two bottom beams (1) are provided; A first top beam (2), wherein two first top beams (2) are provided; A suspension rod (4), wherein the suspension rod (4) is rotatably mounted on both sides of the top end of the bottom beam (1) via a hinge (3), and four suspension rods (4) are provided; Side molds (5), the side molds (5) are fixedly installed on the inner side of the suspension rod (4), and two groups of side molds (5) are provided, wherein a horizontal tie rod (8) is fixedly installed between the two groups of side molds (5) near the axis through a nut, and four horizontal tie rods (8) are provided; A protective outer frame (6), wherein a steel wire mesh (7) is fixedly mounted on the outside of the protective outer frame (6); A second top beam (9), the second top beam (9) being fixedly mounted on both sides of the top end of the first top beam (2), wherein vertical tie rods (12) are fixedly mounted between two groups of the second top beams (9) and the bottom beam (1) via nuts, and four vertical tie rods (12) are provided, and the vertical tie rods (12) are located on both sides of the horizontal tie rod (8); Wherein, two of the No. 1 top beams (2) are fixedly mounted on the top ends of the four suspension rods (4) via a fixed frame (13), and the protective outer frame (6) is fixedly mounted on both sides of the bottom beam (1) and the No. 1 top beam (2); A top support structure (14) is fixedly installed between the suspension rod (4) and the side mold (5), and the top support structure (14) comprises a No. 1 connection frame (15) and a No. 2 connection frame (19), wherein the No. 1 connection frame (15) is fixedly installed on the surface of the side mold (5), and the No. 2 connection frame (19) is fixedly installed on the surface of the suspension rod (4); a threaded sleeve (18) is fixedly installed on one end of the No. 2 connection frame (19), and a screw rod (17) is installed on the inner thread of the threaded sleeve (18); an end of the screw rod (17) away from the threaded sleeve (18) is fixedly connected to one end of the No. 1 connection frame (15), and a nut (16) is installed on the outer thread of the screw rod (17); Wherein, the suspension rod (4) and the side mold (5) are fixedly connected via a top support structure (14); The working platform construction process comprises the following steps: S1. After the segments on both sides are spliced ​​and anchored, a tire-type lifting vehicle is used to hang the formwork and working platform on the assembled segments, connect the main reinforcement of the cap beam at the joint, install the cap beam stirrups, and use a pump truck to pour wet joint concrete; S2. After the wet joint concrete reaches the design strength, use a tire-type lift and a tensioning platform to tension the cap beam prestressing and pipe grouting in batches and steps according to the design requirements, and the cap beam is connected into a whole.

2. According to claim 1, the construction process of the wet joint rapid assembly work platform for the urban smart expressway cap beam is characterized by: A jack (10) and a rigid support (11) are respectively fixedly mounted at the bottom ends of the two No. 1 top beams (2), and the jack (10) is located on the inner side of the rigid support (11).

3. The construction process of the wet joint rapid assembly work platform for the urban smart expressway cap beam according to claim 1 is characterized by: Also includes: A ladder (20), wherein the ladder (20) is fixedly mounted on the outer wall surfaces of two sets of the side molds (5).

4. The construction process of the wet joint rapid assembly work platform for the urban smart expressway cap beam according to claim 1 is characterized by: Also includes: A platform beam (21), wherein the platform beam (21) is fixedly mounted on both sides of the bottom ends of the two bottom beams (1).

5. The construction process of the wet joint rapid assembly work platform for the urban smart expressway cap beam according to claim 1 is characterized by: The side formwork (5) adopts a common steel formwork structure of a steel plate and a profiled steel back rib.

6. The construction process of the wet joint rapid assembly work platform for the urban smart expressway cap beam according to claim 1 is characterized by: The protective outer frame (6) adopts a steel-structured spatial truss structure system.

7. The construction process of the wet joint rapid assembly work platform for the urban smart expressway cap beam according to claim 1 is characterized by: In step S1, after each formwork is completed, pre-pressing should be performed to eliminate the elastic deformation of the formwork and ensure the accuracy of the external dimensions of the wet joint of the cap beam.

Citation Information

Patent Citations

  • Multiple-joint linkage type integrated formwork surrounding wet connection section and method

    CN105178196A

  • Assembly box type hollow floor bottom plate wet demolding production device and a use method thereof

    CN109382902A

  • Prefabricated bent cap installation method and system

    CN110644371A

  • Strength nature skeleton concrete beam construction suspend template in midair

    CN205025086U

  • A portable assembling die for prestressed concrete trough plate stake

    CN205704661U