An integral beam-dropping structure and beam-dropping method for a steel box girder bridge
By using a steel frame platform structure and a multi-layer pad structure support system in the dropped beams of the steel box girder bridge, and using pushing equipment and auxiliary jacks to reduce the bridge height layer by layer, it solves the problem that the height of the steel columns is not easy to control in the traditional dropped beam method. solve the problems of low safety and low construction efficiency, and achieve efficient and safe falling beam construction.
Patent Information
- Application Number
- CN202010197161.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-03-19
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2040-03-19
AI Technical Summary
The traditional falling beam method of steel box girder bridges has the problems of difficulty in controlling the consistency of steel column heights, low construction efficiency, poor safety and heavy workload, especially when cutting steel column supports at high altitude or on water.
An overall dropped beam structure including a steel frame platform structure, a movable support system and a fixed support system is adopted. The height of the steel box girder bridge is reduced layer by layer through jacks of pushing equipment and auxiliary jacks, and the pad structure and bolt pairs are used to achieve a smooth descent.
It improves the construction efficiency of dropped beams of steel box girder bridges, reduces the workload, enhances construction safety, and the materials can be reused many times with good economy.
Smart Images

Figure CN111254840B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of steel structure bridge construction, and in particular to an integral beam-dropping structure and a beam-dropping method for a steel box girder bridge. Background Art
[0002] When the jacking method is used to construct steel box girders, the steel box girder bridge is first pre-assembled in sections or as a whole at the pre-assembly position at the bridge head (or bridge tail), and then the pre-assembled steel box girder bridge is vertically jacked up for a distance using jacking equipment, and then horizontally pushed for a distance in the direction of the bridge installation position, and then the jack of the jacking equipment is lowered and returned to the initial position without load, and then the above method is repeated to gradually push the bridge forward; since the bridge bottom plate is not necessarily horizontal in the length direction, but has a certain curvature, the bridge bottom plate needs to be jacked at a position higher than the actual installation height to ensure that the bridge bottom plate will not collide with the jacking equipment during the jacking process; therefore, there is a large height difference between the jacking curve of the bridge bottom plate and the beam-dropping curve of the bridge installation. It is necessary to carry out beam dropping construction; the traditional beam dropping method is to add multiple steel column supports under the steel box girder bridge and under the jacking equipment, and gradually reduce the height of the jacking equipment and the steel box girder bridge by cutting the steel column support height in batches. This method has the following defects: 1) It is difficult to grasp the consistency of the height of each steel column by cutting the steel column support height in batches. When the steel box girder bridge is dropped as a whole, the contact area between the bottom plate of the steel box girder and the jacking equipment jack is easy to be vacant, causing local deformation of the bottom plate of the steel box girder; 2) The speed of cutting steel column supports at high altitude or on water is slow, the labor intensity is high, and the safety is poor; 3) After cutting the steel column short, the upper and lower sections of the steel column need to be re-welded together to work as a whole steel support, which greatly increases the workload of beam dropping and reduces construction efficiency; these are not what technical personnel in this field want to see. Summary of the invention
[0003] In view of the above problems, the present invention discloses an integral beam drop structure of a steel box girder bridge, which comprises: a steel frame platform structure, a movable support system and a fixed support system;
[0004] The steel box girder bridge is arranged on the steel frame platform structure, the movable support system and the fixed support system are arranged between the steel frame platform structure and the steel box girder bridge, and the fixed support system is arranged on both sides of the movable support system;
[0005] The fixed support system includes a pad beam arranged on the steel frame platform structure and a first pad structure arranged on the pad beam, the first pad structure includes a plurality of first pads stacked up and down in sequence, the movable support system includes a jacking device jack, a second pad structure, an auxiliary jack and a third pad structure, the second pad structure includes a plurality of second pads stacked up and down, the third pad structure includes a plurality of third pads stacked up and down, the jacking device jack is arranged between the steel box girder bridge and the second pad structure, the second pad structure is arranged on the steel frame platform structure, the auxiliary jack is arranged between the jacking device jack and the third pad structure, and the third pad structure is arranged on the steel frame platform structure.
[0006] The above-mentioned steel box girder bridge integral drop beam structure, wherein the steel frame platform structure includes steel pipe piles, distribution beams and track beams, the distribution beams are arranged on the steel pipe piles, the track beams are laid on the distribution beams along the longitudinal direction of the steel box girder bridge, and the cushion beams, the second cushion block structure and the auxiliary jacks are all arranged on the track beams.
[0007] The above-mentioned steel box girder bridge integral drop beam structure, wherein the distribution beam and the track beam are both box-type structures welded by double H-shaped steel.
[0008] In the above-mentioned integral dropped beam structure of the steel box girder bridge, the first pad, the second pad and the third pad are all box-type steel structures.
[0009] In the above-mentioned integral beam-dropping structure of the steel box girder bridge, the heights of the first pad, the second pad and the third pad are all smaller than the maximum vertical lifting stroke of the jack of the jacking equipment and the maximum vertical lifting stroke of the auxiliary jack.
[0010] The above-mentioned integral drop beam structure of the steel box girder bridge, wherein a lifting lug is provided at the bottom of the steel box girder bridge, and a fall chain is hung on the lifting lug, and holes are opened on the edges of the first pad, the second pad and the third pad.
[0011] In the above-mentioned integral dropped beam structure of the steel box girder bridge, adjacent first pads, adjacent second pads, adjacent third pads, and the first pad structure and the pad beam are all connected by bolt pairs.
[0012] The present invention also discloses a method for integrally dropping a steel box girder bridge, based on the above-mentioned integrally dropping structure of the steel box girder bridge, wherein the method for dropping a steel box girder bridge comprises the following steps:
[0013] Step S1, after the steel box girder bridge is lifted by a jacking device so that the first cushion block structure and the steel box girder bridge are separated from each other, the first cushion block located at the top of the first cushion block structure is removed;
[0014] Step S2, lowering the jack of the jacking device so that the weight of the steel box girder bridge falls entirely on the first cushion block structure, and the steel box girder bridge and the jack of the jacking device are separated;
[0015] Step S3, after the auxiliary jack is used to lift the third cushion block structure so that the jack of the jacking device and the second cushion block structure are vacated, the second cushion block located at the top of the second cushion block structure is removed;
[0016] Step S4, lowering the auxiliary jack so that the jack of the jacking device is lowered onto the second cushion block structure, and the third cushion block structure and the jack of the jacking device are vacated, and removing the third cushion block located at the top of the third cushion block structure;
[0017] Step S5, repeating steps S1 to S4 until the height of the steel box girder bridge drops to the design required elevation, and then stopping, completing the beam lowering construction of the steel box girder bridge.
[0018] The above invention has the following advantages or beneficial effects:
[0019] The invention discloses an integral beam-dropping structure and beam-dropping method for a steel box girder bridge. A fixed support system and a movable support system are arranged between the steel box girder bridge and a steel frame platform structure. The fixed support system includes a cushion beam and a first cushion block structure arranged on the cushion beam. The movable support system includes a jack of a jacking device, a second cushion block structure, an auxiliary jack and a third cushion block structure. The auxiliary jack and the third cushion block structure are only used to support the use of the jack of the jacking device. Thus, the steel box girder bridge can be lifted as a whole by the jack of the jacking device, and the height of the first cushion block structure under the steel box girder can be reduced layer by layer. At the same time, a beam-dropping cycle can be realized by lowering the jack of the jack of the jacking device layer by layer through the auxiliary jack. The steel box girder can be lowered to the design required elevation through multiple beam-dropping cycle operations. The beam-dropping construction method has the characteristics of high construction efficiency, small workload, stable overall drop of the steel box girder bridge, safe and reliable construction, repeated use of materials, and good economy. The method can be widely used in the construction of integral beam-dropping of steel box girder bridges. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] The present invention and its features, appearance and advantages will become more apparent by reading the detailed description of non-limiting embodiments with reference to the following drawings. The same reference numerals indicate the same parts in all the drawings. The drawings are not drawn to scale, and emphasis is placed on illustrating the subject matter of the present invention.
[0021] Figure 1 It is a front view of the overall beam-dropping structure of the steel box girder bridge before beam-dropping in an embodiment of the present invention;
[0022] Figure 2 for Figure 1 Sectional view at AA in the middle;
[0023] Figure 3 The front view of the overall beam-dropping structure of the steel box girder bridge after beam-dropping in the embodiment of the present invention
[0024] Figure 4 It is a flow chart of the method for integrally dropping the beam of a steel box girder bridge in an embodiment of the present invention;
[0025] In the figure: 1 is a steel pipe pile, 2 is a distribution beam, 3 is a track beam, 4 is a cushion beam, 5 is a first cushion block structure, 6 is a second cushion block structure, 7 is a third cushion block structure, 8 is a bolt pair, 9 is a jacking device jack, 10 is an auxiliary jack, 11 is a lifting lug, 12 is a fall chain, and 13 is a steel box girder bridge. DETAILED DESCRIPTION
[0026] The structure of the present invention is further described below in conjunction with the accompanying drawings and specific embodiments, but is not intended to limit the present invention.
[0027] Embodiment 1:
[0028] like Figures 1 to 3 As shown, the present invention discloses an integral beam-dropping structure of a steel box girder bridge. Specifically, the integral beam-dropping structure of the steel box girder bridge comprises: a steel frame platform structure, a movable support system and a fixed support system; the steel box girder bridge 13 is arranged on the steel frame platform structure, the movable support system and the fixed support system are arranged between the steel frame platform structure and the steel box girder bridge 13, and the fixed support system is arranged on both sides of the movable support system; the fixed support system comprises a cushion beam 4 arranged on the steel frame platform structure and a first cushion block structure 5 arranged on the cushion beam 4, the first cushion block structure 5 comprises a plurality of first cushion blocks stacked up and down in sequence, the movable support system The system includes a jacking device jack 9, a second pad block structure 6, an auxiliary jack 10 and a third pad block structure 7, wherein the second pad block structure 6 includes a plurality of second pads stacked up and down, and the third pad block structure 7 includes a plurality of third pads stacked up and down, the jacking device jack 9 is arranged between the steel box girder bridge 13 and the second pad block structure 6, the second pad block structure 6 is arranged on the steel frame platform structure, the auxiliary jack 10 is arranged between the jacking device jack 9 and the third pad block structure 7, the third pad block structure 7 is arranged on the steel frame platform structure, and the auxiliary jack 10 and the third pad block structure 7 are only used to support the jacking device jack 9.
[0029] In a preferred embodiment of the present invention, the above-mentioned steel frame platform structure includes steel pipe piles 1, distribution beams 2 and track beams 3 to provide sufficient supporting force to support the weight of the upper structures; the distribution beam 2 is arranged on the steel pipe piles 1, and the distribution beam 2 is a box-type structure welded by double H-shaped steels to distribute the gravity transmitted from the upper part to the steel pipe piles 1 in a balanced manner; the track beam 3 is laid on the distribution beam 2 along the longitudinal direction of the steel box beam bridge 13, and the steel frame platform structure has two track beams 3, and the track beam 3 is a box-type structure welded by double H-shaped steels, and the pad beam 4, the second pad block structure 6 and the auxiliary jack 10 are all arranged on the track beam 3.
[0030] In a preferred embodiment of the present invention, the first pad, the second pad and the third pad are all box-type steel structures. Specifically, the first pad, the second pad and the third pad are all welded box-type steel structures, which have great rigidity and bearing capacity, and the elevation of the above-mentioned pad beam 4 should be smaller than the elevation of the steel box beam bridge 13 after the beam is finally dropped, so that the steel box beam bridge 13 can be completely lowered onto the permanent bridge pier.
[0031] In a preferred embodiment of the present invention, the heights of the first pad, the second pad and the third pad are all smaller than the maximum vertical lifting stroke of the jack 9 of the jacking device, and the heights of the first pad, the second pad and the third pad are also smaller than the maximum vertical lifting stroke of the auxiliary jack 10, so that a pad can be smoothly taken out within each stroke of the jack 9 of the jacking device and the auxiliary jack 10.
[0032] In a preferred embodiment of the present invention, a lifting lug 11 is provided at the bottom of the steel box girder bridge 13, and a fall chain 12 is hung on the lifting lug 11, and holes are opened on the edges of the first pad, the second pad and the third pad; specifically, the present invention welds a lifting lug 11 under the bottom plate of the steel box girder bridge 13; and circular holes are cut on the edges of the first pad, the second pad and the third pad to be used as connecting holes for bolting the fall chain 12, so as to facilitate the removal of the first pad, the second pad and the third pad through the fall chain 12.
[0033] In a preferred embodiment of the present invention, adjacent first pads, adjacent second pads, adjacent third pads, and the first pad structure 5 and the pad beam 4 are all connected by bolt pairs 8 to increase the integrity between the pads and the high slippage during construction and facilitate disassembly.
[0034] In a preferred embodiment of the present invention, the multiple jacks 9 in the above-mentioned beam-dropping structure can achieve unified action through computer control and hydraulic drive, so as to achieve uniform force on all supporting points of the steel box girder bridge 13, lower the overall height, and avoid deformation of the steel box girder bridge 13 due to local unbalanced force.
[0035] Embodiment 2:
[0036] like Figure 3 and Figure 4 As shown, the present invention also discloses a method for integrally dropping a steel box girder bridge. Based on the integrally dropping structure of the steel box girder bridge in the first embodiment, the method comprises the following steps:
[0037] Step S1, after using the jacking device jack 9 to lift the steel box girder bridge 13 so that the first cushion block structure 5 and the steel box girder bridge 13 are vacated, the weight of the steel box girder bridge 13 is supported by the jacking device jack 9, and the fall chain 12 is used to remove the first cushion block structure 5 located at the top.
[0038] Step S2, lowering the jack 9 of the jacking device so that the weight of the steel box girder bridge 13 falls entirely on the first cushion block structure 5, and the steel box girder bridge 13 and the jack 9 of the jacking device are separated.
[0039] Step S3, start the auxiliary jack 10, and use the auxiliary jack 10 to lift the third cushion block structure 7 so that the jack 9 of the jacking device and the second cushion block structure 6 are emptied (at this time, the auxiliary jack 10 and the third cushion block structure 7 support the weight of the jack 9 of the jacking device), and use the fall chain 12 to remove the second cushion block located at the top of the second cushion block structure 6).
[0040] Step S4, lowering the auxiliary jack 10 so that the jacking device jack 9 is lowered onto the second cushion block structure 6, and the third cushion block structure 7 and the jacking device jack 9 are vacated, and the third cushion block located at the top of the third cushion block structure 7 is removed.
[0041] Step S5, repeating steps S1 to S4 (restarting the jack 9 of the jacking equipment, lifting the steel box girder bridge 13 as a whole, and starting the beam-dropping cycle of the lower wheel), until the height of the steel box girder bridge 13 drops to the design required elevation and then stops, completing the beam-dropping construction of the steel box girder bridge 13; specifically, in each of the above beam-dropping cycles, the first cushion block structure 5, the second cushion block structure 6, and the third cushion block structure 7 are respectively removed by one cushion block, and when the height of the steel box girder bridge 13 drops to the design required elevation, the jack 9 of the jacking equipment is stopped, and the beam-dropping construction is completed. Figure 3 The structure shown.
[0042] It is not difficult to find that this embodiment is a method embodiment corresponding to the embodiment of the above-mentioned steel box girder bridge integral beam drop structure, and this embodiment can be implemented in conjunction with the above-mentioned embodiment of the steel box girder bridge integral beam drop structure. The relevant technical details mentioned in the above-mentioned embodiment of the steel box girder bridge integral beam drop structure are still valid in this embodiment, and in order to reduce repetition, they are not repeated here. Accordingly, the relevant technical details mentioned in this embodiment can also be applied in the above-mentioned embodiment of the steel box girder bridge integral beam drop structure.
[0043] Those skilled in the art should understand that those skilled in the art can implement variations by combining the prior art and the above embodiments, which will not be described in detail here. Such variations do not affect the essential content of the present invention, and will not be described in detail here.
[0044] The above describes the preferred embodiments of the present invention. It should be understood that the present invention is not limited to the above-mentioned specific embodiments, and the devices and structures that are not described in detail should be understood to be implemented in a common manner in the art; any technician familiar with the art can use the above-disclosed methods and technical contents to make many possible changes and modifications to the technical solutions of the present invention without departing from the scope of the technical solutions of the present invention, or modify them into equivalent embodiments of equivalent changes, which does not affect the essential content of the present invention. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solutions of the present invention are still within the scope of protection of the technical solutions of the present invention.
Claims
1. A steel box girder bridge integral beam drop structure, characterized in that: include: Steel frame platform structure, movable support system and fixed support system; The steel box girder bridge is arranged on the steel frame platform structure, the movable support system and the fixed support system are arranged between the steel frame platform structure and the steel box girder bridge, and the fixed support system is arranged on both sides of the movable support system; The fixed support system includes a cushion beam arranged on the steel frame platform structure and a first cushion block structure arranged on the cushion beam, the first cushion block structure includes a plurality of first cushion blocks stacked up and down in sequence, the movable support system includes a jacking device jack, a second cushion block structure, an auxiliary jack and a third cushion block structure, the second cushion block structure includes a plurality of second cushion blocks stacked up and down, the third cushion block structure includes a plurality of third cushion blocks stacked up and down, the jacking device jack is arranged between the steel box girder bridge and the second cushion block structure, the second cushion block structure is arranged on the steel frame platform structure, the auxiliary jack is arranged between the jacking device jack and the third cushion block structure, and the third cushion block structure is arranged on the steel frame platform structure; The steel frame platform structure comprises steel pipe piles, distribution beams and track beams, wherein the distribution beams are arranged on the steel pipe piles, the track beams are laid on the distribution beams along the longitudinal direction of the steel box girder bridge, and the cushion beams, the second cushion block structure and the auxiliary jacks are all arranged on the track beams; The first cushion block, the second cushion block and the third cushion block are all box-type steel structures.
2. The integral dropped beam structure of a steel box girder bridge according to claim 1, characterized in that: The distribution beam and the track beam are both box-type structures welded by double H-shaped steel.
3. The integral dropped beam structure of a steel box girder bridge according to claim 1, characterized in that: The heights of the first cushion block, the second cushion block and the third cushion block are all smaller than the maximum vertical lifting stroke of the jack of the jacking device and the maximum vertical lifting stroke of the auxiliary jack.
4. The integral dropped beam structure of a steel box girder bridge according to claim 1, characterized in that: A lifting lug is arranged at the bottom of the steel box girder bridge, a fall chain is hung on the lifting lug, and holes are opened at the edges of the first pad, the second pad and the third pad.
5. The integral dropped beam structure of a steel box girder bridge according to claim 1, characterized in that: Adjacent first cushion blocks, adjacent second cushion blocks, adjacent third cushion blocks, and the first cushion block structure and the cushion beam are all connected by bolt pairs.
6. A method for integrally dropping a steel box girder bridge, based on the integrally dropping structure of a steel box girder bridge according to any one of claims 1 to 5, characterized in that: The beam dropping method comprises the following steps: Step S1, after the steel box girder bridge is lifted by a jacking device so that the first cushion block structure and the steel box girder bridge are separated from each other, the first cushion block located at the top of the first cushion block structure is removed; Step S2, lowering the jack of the jacking device so that the weight of the steel box girder bridge falls entirely on the first cushion block structure, and the steel box girder bridge and the jack of the jacking device are separated; Step S3, after the auxiliary jack is used to lift the third cushion block structure so that the jack of the jacking device and the second cushion block structure are vacated, the second cushion block located at the top of the second cushion block structure is removed; Step S4, lowering the auxiliary jack so that the jack of the jacking device is lowered onto the second cushion block structure, and the third cushion block structure and the jack of the jacking device are vacated, and removing the third cushion block located at the top of the third cushion block structure; Step S5, repeating steps S1 to S4 until the height of the steel box girder bridge drops to the design required elevation, and then stopping, completing the beam lowering construction of the steel box girder bridge.