Temporary transverse support constructed in benching tunneling method and installation method of temporary transverse support
A technology of horizontal bracing and step method, applied in tunnels, tunnel linings, shaft equipment, etc., can solve the problems that horizontal bracing cannot be reused, a large amount of construction waste and scrap steel, and the installation process takes a long time, so as to reduce the need for installation experience. , The effect of low installation efficiency and difficult installation
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2020-07-10
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention relates to the field of temporary support for tunnels, in particular to a temporary horizontal support for tunnel construction by step method and an installation method thereof. Background technique
[0002] The three-step method is often used in large-section tunnels with weak surrounding rocks. When the steps are excavated step by step, the surrounding rock pressure of the tunnel excavation increases, the bending moment and axial force on the support device gradually increase, and the primary support structure undergoes obvious sliding deformation into the tunnel. The traditional treatment method is to install reinforced concrete For horizontal support, steel arches need to be welded and concrete poured. After the construction is completed, the concrete is broken with a hand-held jackhammer, and the fixed rods and steel arches are cut off with oxygen welding. During this process, the cross support cannot be reused. The problems of thi...
Examples
Embodiment
[0039] Such as figure 1 As shown, the temporary horizontal support in this embodiment, which is suitable for the construction of the tunnel step method, is supported on the transverse chord line of the steel arch 1 of the main tunnel, and the two ends are connected with the steel arch 1 of the main tunnel to provide transverse support for the tunnel primary support structure. The supporting force can avoid the sliding deformation of the primary support structure into the hole. Different from the existing cast-in-place horizontal support, the temporary horizontal support in this embodiment is a prefabricated rod-shaped horizontal support, which is a horizontal support that can be reused, so steps such as pouring are omitted during installation, saving Construction materials such as steel support and shotcrete can be quickly installed and subjected to force in a timely manner; there is no need to go through steps such as oxygen welding and cutting when dismantling, which is not ...