Guide sinking system suitable for underground shaft group construction and underground shaft group construction method
Through the use of the guide sinking system, the problem of sinking control in the construction of underground wellbore groups has been solved, the uniformity of the wellbore sinking and construction speed have been improved, the construction quality and mechanization rate have been improved, and soil deformation and on-site concrete pouring have been reduced. .
Patent Information
- Application Number
- CN202010710526.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-07-22
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2040-07-22
AI Technical Summary
It is difficult to effectively control the wellbore subsidence during the construction of underground wellbore groups with the existing technology, resulting in slow construction speed, poor quality, and prone to uneven subsidence and soil deformation.
A sinking guide system is used, including counterweight piers, caisson guide channels, sinking guide devices and control systems. Through components such as weighted mud, pumping grout pipes and anchor rods, the wellbore sinking is precisely controlled to ensure the stability of the sinking attitude and rate.
It achieves uniformity of shaft sinking and improvement of construction speed, reduces soil deformation, improves construction quality and mechanization rate, avoids on-site concrete pouring, and simplifies the construction process.
Smart Images

Figure CN111719576B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to a guide sinking system suitable for underground shaft group construction, and also relates to an underground shaft group construction method, which can be used to construct underground projects in areas with high groundwater levels, and belongs to the technical field of construction of underground multi-barrel structures. Background Art
[0002] At present, urban construction land is in short supply, especially for built shopping malls, residential areas, office areas, tourist areas and other crowded places, which are facing the situation of no vacant land. The utilization and development of underground space will solve the increasingly serious "urban disease". However, the development of underground space has considerable technical and engineering risks, and the geological conditions are complex and changeable, which brings considerable difficulty to the construction of underground space.
[0003] The underground tube structure has the advantages of small footprint, large vertical length, compact structure, and easy construction. The construction of multi-tube underground space structures provides a new option for creating new "business formats" in modern cities, further improving the value of land and living comfort, and has huge social and economic value, and the market prospects are extremely broad.
[0004] For the construction of underground engineering, there are several solutions in the prior art:
[0005] Option 1: Reverse approach.
[0006] The reverse construction method is a relatively advanced method for constructing underground space structures. The reverse construction method is an unconventional construction method, which is generally used in special cases such as deep foundations, complex geology, and high groundwater levels. First, the underground continuous wall or other supporting structure is constructed along the axis or around the basement of the building. At the same time, the intermediate support piles and columns are cast or driven in the relevant positions inside the building as a support for the deadweight and construction load of the upper structure before the bottom slab is sealed during the construction period. Then the earth is excavated to the bottom elevation of the first basement, and the beam and slab floor structure of this layer is completed as the horizontal support of the underground continuous wall. Subsequently, the earth is excavated downward layer by layer and the underground structure of each layer is cast until the bottom slab is sealed. At the same time, since the floor structure of the first floor has been completed, it has created conditions for the construction of the upper structure, so the construction of the above-ground structure can be carried out upward layer by layer at the same time. In this way, construction is carried out simultaneously on the ground and underground until the project is completed.
[0007] Specifically, the "underground continuous wall" refers to: using a trenching machine on the ground to dig a long and narrow deep trench along the peripheral axis of the deep foundation pit under the condition of mud wall protection. After the trench is cleared, a steel cage is suspended in the trench, and then underwater concrete is poured using the conduit method to form a unit trench section. This process is carried out section by section to build a continuous reinforced concrete wall underground as a water-cutting, anti-seepage, load-bearing and water-retaining structure.
[0008] The disadvantages of using the reverse construction method to construct underground space are: more processes, longer construction period, high cost, and the need to cast components on site.
[0009] Option 2: Caisson method.
[0010] "Caisson" is a well-shaped structure. It is excavated in the well, and sinks to the designed elevation by relying on its own gravity to overcome the friction resistance of the well wall. Then, the bottom is sealed with concrete and the well hole is filled to make it the foundation of bridge piers or other structures. The specific construction method is: at the designed position, a pre-made ring of 6m to 7m long whole well wall is placed in the soil, and then under its cover, it sinks while digging and building the well wall accordingly. As the depth of the caisson increases, the friction resistance between the well wall and the well side increases, and the sinking depth is limited, generally only 20m to 30m can be sunk.
[0011] The disadvantages of using the caisson method to construct underground space are: if there is groundwater, water will be carried over during construction, and the construction conditions are not good. When digging the caisson, there will definitely be over-excavation beyond the bottom of the well. This is the principle of caisson construction and is inevitable, which will cause large deformation of the surrounding land. Caisson construction is prone to uneven sinking, and it is difficult to control and adjust the posture. Summary of the invention
[0012] The first technical problem to be solved by the present invention is to provide a sinking guide system suitable for the construction of underground shaft groups, which can conveniently control the sinking of the shafts and improve the construction speed and quality after being applied to the construction of underground shaft groups.
[0013] In order to solve the above technical problems, the technical solution adopted by the present invention is: a guide sinking system suitable for underground shaft group construction, including a construction site, a counterweight pier is arranged at the center of the pre-sunk shaft at the construction site, a caisson guide groove is arranged at the corresponding position of the pre-sunk shaft, the cross-sectional shape and specification of the caisson guide groove are adapted to the cross-sectional shape and specification of the pre-sunk shaft, and weighted mud is injected into the caisson guide groove; a grouting hole for extracting and injecting weighted mud is arranged on the side of the caisson guide groove, and the grouting hole is equipped with a grouting pipe; a guide sinking device is arranged on the top surface of the counterweight pier, and the guide sinking device It includes a moving frame, a lifting jack, a telescopic jack, a movable block and a force distribution block. The lifting jack is arranged on the top surface of the counterweight pier, the moving frame is placed on the top of the lifting jack and is supported by the movable end of the lifting jack. The telescopic jack is a plurality of pieces arranged at intervals along the circumference of the moving frame. The fixed end of the telescopic jack is connected to the moving frame, and the movable end of the telescopic jack is connected to the force distribution block through the movable block. The end face shape of the force distribution block on the side away from the center of the moving frame is consistent with the shape of the inner wall of the pre-sunk shaft corresponding to the position of the force distribution block.
[0014] Furthermore, each telescopic jack is provided with a corresponding push rod, and all the push rods are fixedly connected into a whole to form a mobile frame; and a lifting jack is provided under each push rod.
[0015] Furthermore, the outer end of the force distribution block is provided with spaced-apart pushing blocks, and the pushing blocks are arranged toward the inner wall of the pre-sunk shaft.
[0016] Furthermore, the pre-sinking shaft has one unit cylinder or multiple unit cylinders, each unit cylinder corresponds to a group of sinking guide devices; in the same group of sinking guide devices, the telescopic jacks are four pieces distributed in a rectangular shape.
[0017] Furthermore, a control system is also included, and each force distribution block is provided with a wireless displacement sensor A for monitoring the elevation of its position, and the wireless displacement sensor A, the lifting jack, and the telescopic jack are all electrically connected to the control system.
[0018] Furthermore, the inner wall of the pre-sunk shaft is arranged with a wireless displacement sensor B for monitoring the elevation of its location. The wireless displacement sensor B is a plurality of pieces arranged at intervals along the circumference of the pre-sunk shaft. The wireless displacement sensor B is electrically connected to the control system.
[0019] Furthermore, a pre-buried anchor rod is arranged in the counterweight pier, the outer end of the pre-buried anchor rod passes through the movable frame in the vertical direction, and an anchor rod tensioner is arranged at the outer end.
[0020] Furthermore, steel sheet piles are arranged continuously or at intervals in the outer peripheral direction of the underground shaft group to be constructed at the construction site, and the inner wall of the steel sheet piles also serves as the inner wall of the caisson guide groove.
[0021] Furthermore, the driving depth of the steel sheet piles is below the bottom elevation of the pre-sunk shaft; a top channel steel is arranged at the top elevation of the steel sheet pile, the bottom of the top channel steel is arranged horizontally with its groove facing upward, and the groove is clamped downward on the top of the steel sheet pile; a rigid floor and an anti-slip pier are arranged along the outer periphery of the steel sheet piles; prestressed anchor cables are arranged on both sides of the steel sheet piles on the pre-sunk shaft, an anchor block is arranged at one end of the prestressed anchor cable, and an anchor tensioner is arranged at the other end, the anchor block is arranged on the outside of a steel sheet pile, and the anchor tensioner is arranged on the outside of another steel sheet pile arranged oppositely, and force distribution parts are respectively arranged between the anchor block and the steel sheet pile, and between the anchor tensioner and the steel sheet pile; a guide groove corner guard is arranged at the top of the caisson guide groove on the inner periphery of the pre-sunk shaft.
[0022] On the basis of the above-mentioned guide sinking system, another object of the present invention is to provide a method for constructing an underground shaft group, which is conducive to the industrialization and automation of underground space construction.
[0023] The underground shaft group construction method comprises the following steps:
[0024] 1. Determine whether steel sheet piles are needed based on terrain conditions. If steel sheet piles are needed, construct them in advance;
[0025] 2. During the construction of the counterweight pier, if there are pre-buried anchor rods in the counterweight pier, the pre-buried anchor rods shall be set at the same time during the construction of the counterweight pier;
[0026] 3. Use a slotting machine to dig the caisson guide groove, and protect the wall by adding weighted mud during the excavation process; the excavation depth is determined according to the bottom elevation of the pre-sunk shaft; preferably, the cross-sectional width of the caisson guide groove is less than or equal to the shaft wall thickness at its corresponding position;
[0027] 4. Arrange the grouting holes and insert the grouting pipes into the grouting holes;
[0028] 5. Install the sinking guide device on the counterweight pier;
[0029] 6. The shaft is pre-made in sections; a section of the shaft is hoisted to the designed position and inserted into the guide groove of the caisson; under the control of the guide sinking device, the shaft is gradually sunk into the guide groove of the caisson until it reaches the bottom of the guide groove of the caisson;
[0030] The control method of the sinking device is:
[0031] Step a, raising the mobile frame to a designated high position by means of a lifting jack, extending the telescopic jack, and tightening the force distribution block against the wellbore inside the wellbore;
[0032] Step b, the lifting jack is gradually retracted, and the wellbore gradually sinks under its own weight; the moving frame sinks together with the wellbore;
[0033] Step c, when the mobile frame descends to the designated low position, the telescopic jack retracts, the friction between the force distribution block and the inner wall of the wellbore is reduced, and the wellbore remains in place; the lifting jack raises the mobile frame to the designated high position, the telescopic jack extends, and the force distribution block presses against the wellbore inside the wellbore;
[0034] Step d, repeating steps b and c to control the sinking of the wellbore; further preferably, when the wellbore sinks, the height of the weighted mud liquid level in the caisson guide groove is controlled by pumping the grouting pipe, thereby controlling the buoyancy generated on the wellbore, and further controlling the sinking rate of the wellbore;
[0035] 7. After one section of the shaft is sunk, the next section is hoisted and assembled by workers in the shaft;
[0036] 8. After all the wellbore guide sinkers are assembled in place, remove the guide sinker device; grout the well bottom by pumping out the grouting pipe; then excavate the soil in the well, and when the excavation reaches the wellbore design elevation, perform secondary bottom sealing; preferably, use an unmanned excavator to excavate the soil in the well, and use a long-arm grab and a soil transporter to transport the soil in the well to the outside of the well;
[0037] 9. Install the shaft bottom plate and top plate; if steel sheet piles are installed, pull out the steel sheet piles on all sides one by one, and then reinforce the soil around the shaft group after pulling out the steel sheet piles by grouting. Preferably, the installation method of the shaft bottom plate is as follows: the shaft bottom plate adopts a precast bottom plate of reinforced concrete structure, the precast bottom plate is provided with bottom plate keyways around the four sides, and bottom plate connecting steel bars are arranged at the bottom plate keyway positions and are arranged extending outward relative to the precast bottom plate; a shaft keyway is provided at the bottom end position of the shaft inner wall, and an embedded sleeve is provided in the shaft keyway, and the embedded sleeve is fixed by the embedded sleeve steel bars; the shaft keyway is provided with a keyway protection plate, and during the shaft sinking construction, the keyway protection plate is fixed in the shaft keyway in advance by screws; after the shaft sinks into place, when installing the shaft bottom plate, the keyway protection plate is first removed, and then the secondary steel bar is screwed into the embedded sleeve in the shaft keyway, and the other end of the secondary steel bar is overlapped with the bottom plate connecting steel bar of the precast bottom plate, and the interval space between the bottom plate keyway and the shaft keyway is filled with expanding concrete, so that the shaft bottom plate forms a closed type relative to the shaft inner wall. Installation structure, if the prefabricated bottom plate is multiple pieces, the bottom plate connecting steel bars of adjacent prefabricated bottom plates are connected into a whole through secondary steel bars, and the interval space between the bottom plate keyways of the adjacent prefabricated bottom plates is filled with expansive concrete; further preferably, the prefabricated bottom plate includes a left bottom plate and a right bottom plate, the upper steel bars of the left bottom plate and the upper steel bars of the right bottom plate are common steel bars of the integral structure, the lower steel bars of the left bottom plate and the lower steel bars of the right bottom plate are disconnected structures, and the prefabricated bottom plate has a first state during transportation and a second state during installation and use, when the prefabricated bottom plate is in the first state, the upper common steel bars are bent into a U shape, so that the left bottom plate and the right bottom plate overlap; when the prefabricated bottom plate is in the second state, the upper common steel bars are straightened into a straight shape, the left bottom plate and the right bottom plate are arranged side by side on the same installation surface, and the lower steel bars of the left bottom plate and the lower steel bars of the right bottom plate form a lap structure.
[0038] Furthermore, the control method of the sinking guide device further comprises the following steps:
[0039] Step e: the control system compares and analyzes the data of each sensor through a pre-set control program, thereby obtaining the sinking posture and sinking rate of the wellbore, and controls the lifting jack, telescopic jack, anchor jack, and anchor cable jack to keep the wellbore posture and sinking rate in a normal state; the specific control method is:
[0040] When one side of the wellbore encounters greater resistance and thus sinks more slowly, the control system retracts the lifting jack on that side and lifts the lifting jack on the opposite side, adjusting the wellbore posture to horizontal. At this time, the wellbore's center of gravity is biased toward the side with greater resistance, thereby increasing the gravity distributed to that side, so that the wellbore resumes overall uniform sinking. If that side still cannot sink, the counterweight vibrator is hoisted onto the force distribution block on that side, and the counterweight vibrator's own gravity and vibration kinetic energy accelerate the sinking of that side. The structure of the counterweight vibrator includes a hook, a vibrator and a steel box. The hook is fixedly set at the top of the vibrator, the steel box is fixedly set at the bottom of the vibrator, and steel sand is poured into the steel box.
[0041] When the wellbore is difficult to sink as a whole, the lifting jacks are all retracted. If the wellbore still cannot sink due to the full gravity, the anchor tensioner is activated through the anchor jack to pull the wellbore down as a whole, thereby driving the wellbore to sink, and at the same time cooperate with the counterweight vibrator to adjust the wellbore posture;
[0042] When the buoyancy of the weighted mud and the friction between the wellbore and the inner wall of the caisson guide groove are not enough to offset the gravity of the wellbore, resulting in a too fast sinking rate, the telescopic jack is extended to increase the friction between the wellbore and the force distribution block, thereby increasing the sinking resistance and controlling the sinking rate of the wellbore; if the sinking rate is still too fast, the anchor tensioner is tightened by the anchor jack to adjust the stress of the prestressed anchor cable, so that the anchor block applies pressure to the force distribution component, and the force distribution component transfers the pressure to the steel sheet pile, thereby increasing the friction between the steel sheet pile and the wellbore and controlling the sinking rate.
[0043] The beneficial effects of the present invention are as follows: from the construction process of the underground shaft group, it can be seen that the present invention can control the sinking of the shaft more conveniently through the sinking guide system, and the problems such as uneven sinking, too fast sinking rate, and difficulty in sinking during the sinking of the shaft are effectively solved.
[0044] The invention can construct underground engineering by entirely using prefabricated assembled components without on-site concrete pouring, and the mechanization rate of soil excavation, soil taking and soil transportation is high.
[0045] In the traditional caisson construction, the advance excavation will cause large deformation of the surrounding soil. The underground shaft in the present invention is completely sunk into place at one time, and then the soil in the well is excavated, which can overcome the problem of large deformation of the surrounding soil caused by simple caisson construction. The method of the present invention has a fast construction speed, less cross-construction, and is conducive to controlling the construction quality.
[0046] The present invention can realize waterless operation in the well and has good construction conditions through grouting bottom sealing before excavating the soil in the well and secondary bottom sealing after excavating the soil in the well.
[0047] When the present invention is implemented, it is a planar combination of multiple shafts, not a single shaft construction, and has wide functional applicability. BRIEF DESCRIPTION OF THE DRAWINGS
[0048] Figure 1 The present invention is based on the plan view of the wellbore group after the steel sheet piles are driven into the wellbore group;
[0049] Figure 2 yes Figure 1 AA elevation drawing of
[0050] Figure 3 It is a plan view of the caisson guide channel after excavation in the present invention;
[0051] Figure 4 yes Figure 3 BB elevation drawing;
[0052] Figure 5 It is a schematic plan view of the implementation of the wellbore sinking in the present invention;
[0053] Figure 6 yes Figure 5 CC elevation drawing;
[0054] Figure 7 It is a plan view of one set of sinking guide devices of the present invention when it is implemented;
[0055] Figure 8 yes Figure 7 DD elevation drawing;
[0056] Fig. 9 yes Figure 7 EE elevation drawing;
[0057] Fig.10 It is a plan view schematic diagram of the present invention in the well bottom sealing, water pumping and soil excavation;
[0058] Fig.11 It is a schematic elevation view of the present invention for sealing the bottom, pumping water and digging soil in a well;
[0059] Fig.12 It is a plan view of the present invention during pile extraction, side wall grouting, and equipment installation;
[0060] Fig.13 It is a schematic elevation diagram of the present invention during pile extraction, side wall grouting, and equipment installation;
[0061] Fig.14 It is a plan view of the present invention when installing the wellbore bottom plate;
[0062] Fig.15 yes Fig.14 FF elevation drawing;
[0063] Fig.16 yes Fig.14 The large-scale drawing of location G;
[0064] Fig.17yes Fig.16 HH elevation drawing;
[0065] Fig.18 It is a schematic diagram of the assembly structure of the wellbore keyway and the keyway protection plate in the present invention;
[0066] Fig.19 is a schematic structural diagram of the prefabricated bottom plate in the present invention in a first state;
[0067] Fig. 20 It is a structural schematic diagram of the prefabricated bottom plate in the present invention in the process of unfolding;
[0068] Markings in the figure: 1-counterweight pier, 2-caisson guide groove, 3-weighted mud, 4-extraction grouting hole, 5-extraction grouting pipe, 6-sinking guide device, 601-lifting jack, 602-telescopic jack, 603-movable block, 604-force distribution block, 605-thrust rod, 606-control system, 607-wireless displacement sensor A, 608-wireless displacement sensor B, 609-thrust block, 7-embedded anchor rod, 8-anchor tensioner, 9-counterweight vibrator, 901-hook, 902-vibrator, 903-steel box, 10-steel sheet pile, 11-top channel steel, 12-rigid floor, 13-anti-sliding pier, 14-prestressed anchor cable, 15- Anchor block, 16-anchor tensioner, 17-force distribution part, 18-guide groove corner guard, 19-independent caisson, 20-parallel caisson, 21-unmanned excavator, 22-long arm grab, 23-grouting bottom sealing structure, 24-secondary bottom sealing structure, 25-side wall grouting structure, 26-shaft bottom plate, 27-assembler, 28-grooving machine, 29-sheet pile monitoring point, 30-prefabricated bottom plate, 31-bottom plate keyway, 32-bottom plate connecting steel bar, 33-shaft keyway, 34-embedded sleeve, 35-sleeve steel bar, 36-secondary steel bar, 37-keyway protection plate, 38-screw, 39-upper steel bar, 40-lower steel bar, 41-secondary concrete. DETAILED DESCRIPTION
[0069] The shaft involved in the present invention is a steel cylinder structure. The shaft can be an independent shaft with only one unit cylinder, or a parallel shaft with multiple unit cylinders. The cross-sectional shape of the shaft can be rectangular, circular or irregular. The wellbore shown in the accompanying drawings of the present invention is a rectangular wellbore, which is also commonly referred to as a "rectangular caisson", including the independent caisson 19 and the parallel caisson 20 shown in the figure.
[0070] The present invention will be further described below by taking a rectangular caisson as an example in conjunction with the accompanying drawings.
[0071] like Figures 1 to 9As shown, the guide sinking system in the present invention includes a construction site, a counterweight pier 1 is arranged at the center of the pre-sunk shaft at the construction site, a caisson guide groove 2 is arranged at the corresponding position of the pre-sunk shaft, the cross-sectional shape and specification of the caisson guide groove 2 are adapted to the cross-sectional shape and specification of the pre-sunk shaft, and weighted mud 3 is injected into the caisson guide groove 2; a grouting hole 4 for extracting and injecting the weighted mud 3 is arranged on the side of the caisson guide groove 2, and the grouting hole 4 is equipped with a grouting pipe 5; a guide sinking device 6 is arranged on the top surface of the counterweight pier 1, and the guide sinking device 6 includes a moving frame, a lifting jack 601, a telescopic jack 602, and a movable block 603. 03 and force distribution block 604, the lifting jack 601 is arranged on the top surface of the counterweight pier 1, the mobile frame is placed on the top of the lifting jack 601, and is supported by the movable end of the lifting jack 601, the telescopic jack 602 is a plurality of pieces arranged at intervals along the circumference of the mobile frame, the fixed end of the telescopic jack 602 is connected to the mobile frame, and the movable end of the telescopic jack 602 is connected to the force distribution block 604 through the movable block 603, and the end face shape of the force distribution block 604 away from the center of the mobile frame is consistent with the shape of the inner wall of the pre-sunk shaft corresponding to the position of the force distribution block 604. It should be particularly noted that the mobile frame of the present invention is placed on the top of the lifting jack 601, that is, it is placed on the top of the lifting jack 601, and the two are separable structures to facilitate the adjustment and control function of the sinking guide device 6. The specific control method will be described in detail in the construction method of the underground shaft group later.
[0072] See also Figure 7 to Figure 9 In order to make the structure simple and reliable and to give full play to the automatic adjustment function of the guide sinking device 6, in the guide sinking device 6, the preferred structural form of the mobile frame is: each telescopic jack 602 is correspondingly provided with a push rod 605, and all the push rods 605 are fixedly connected as a whole to form a mobile frame; and a lifting jack 601 is correspondingly provided under each push rod 605. That is, the lifting jack 601 and the telescopic jack 602 are preferably in a one-to-one correspondence.
[0073] The pre-sunk shaft has one unit cylinder or multiple unit cylinders, and each unit cylinder corresponds to a group of guide sinking devices 6; in the same group of guide sinking devices 6, multiple telescopic jacks 602 can be set. The more the number, the better the control performance, but the cost will increase. In order to make the structure simple and easy to implement, the telescopic jacks 602 are four pieces distributed in a rectangular shape, that is, when implemented, the force distribution blocks 604 can be arranged in two directions of the X axis and two directions of the Y axis, a total of four directions. When implemented, the movable block 603, the force distribution block 604, and the push rod 605 can all be made of steel. To facilitate force transmission, the outer end of the force distribution block 604 is provided with spaced push blocks 609, which are arranged toward the inner wall of the pre-sunk shaft. When implemented, the shaft is tightened by the push blocks 609.
[0074] Due to the uneven distribution of stratum soil, the sinking resistance of each wall plate of the caisson is different during the sinking process, resulting in uneven sinking. In order to facilitate the control of the sinking posture and sinking rate of the caisson, the present invention also includes a control system 606, each force distribution block 604 is provided with a wireless displacement sensor A607 for monitoring the elevation of its position, and the wireless displacement sensor A607, the lifting jack 601, and the telescopic jack 602 are all electrically connected to the control system 606. The control system 606 can generally adopt a servo controller. During implementation, the wireless displacement sensor A607 will promptly feed back the sinking elevation of each side to the servo controller. The servo controller compares and analyzes the data of each sensor through a pre-set control program, thereby obtaining the sinking posture and sinking rate of the caisson, and controls the lifting jack 601 and the telescopic jack 602 to keep the caisson posture and sinking rate in a normal state. For example, when the wireless displacement sensor A607 returns the elevation parameter of AAAA, it means that the caisson is sinking normally. If the parameter is ABBB, it means that the wall panel on the A side is over-sunk or difficult to sink. If the next moment the parameter is aaaa, the sinking rate can be obtained by the ratio of the difference between the two parameters and the time. The specific control method will be described in detail in the underground shaft group construction method later.
[0075] Preferably, the inner wall of the pre-caisson shaft is provided with a wireless displacement sensor B608 for monitoring the elevation of the position thereof, and the wireless displacement sensor B608 is a plurality of pieces arranged at intervals along the circumference of the pre-caisson shaft, and the wireless displacement sensor B608 is electrically connected to the control system 606. During implementation, by comparing the two sets of data measured by the wireless displacement sensor A607 and the wireless displacement sensor B608, it is also possible to detect whether there is a relative displacement between the force distribution block 604 and the inner wall of the caisson, thereby more accurately judging the posture and sinking rate of the caisson.
[0076] Preferably, a pre-buried anchor rod 7 is provided in the counterweight pier 1, the outer end of the pre-buried anchor rod 7 passes through the mobile frame vertically, and an anchor rod tensioner 8 is arranged at the outer end. The pre-buried anchor rod 7 and the anchor rod tensioner 8 are auxiliary facilities when the caisson is difficult to sink, and the specific control method will be described in detail in the underground shaft group construction method later.
[0077] Preferably, the construction site is continuously or intermittently arranged with steel sheet piles 10 in the peripheral direction of the underground shaft group to be constructed, and the inner wall of the steel sheet pile 10 also serves as the inner wall of the caisson guide groove 2. Whether to arrange the steel sheet piles 10 is determined according to the geological conditions. After the steel sheet piles 10 are arranged, the deformation resistance of the caisson guide groove 2 can be improved. During implementation, if there is groundwater, the steel sheet piles 10 should be interlocked with each other and closed all around; if there is no groundwater, the steel sheet piles 10 can be arranged intermittently. The driving depth of the steel sheet piles 10 is below the bottom elevation of the pre-sunk shaft to reduce the water gushing from the bottom of the shaft and the deformation of the soil around the shaft during excavation. In addition, sheet pile monitoring points 29 can be set at the corners of the steel sheet piles 10 to monitor the deformation during the construction process. This technology is a mature technology in the field of foundation pit monitoring.
[0078] Preferably, a top channel steel 11 is provided at the top elevation of the steel sheet pile 10, the bottom of the top channel steel 11 is arranged horizontally upward, and the slot is clamped downward on the top of the steel sheet pile 10; the top channel steel 11 can coordinate the deformation of the steel plate and create a horizontally arranged construction surface at the top of the steel sheet pile 10, which is convenient for later construction.
[0079] Preferably, the steel sheet piles 10 are arranged with prestressed anchor cables 14 on both sides of the pre-sunk shaft, an anchor block 15 is provided at one end of the prestressed anchor cable 14, and an anchor cable tensioner 16 is provided at the other end, the anchor block 15 is arranged on the outside of one steel sheet pile 10, and the anchor cable tensioner 16 is arranged on the outside of another steel sheet pile 10 arranged opposite to each other, and force distribution components 17 are respectively provided between the anchor block 15 and the steel sheet pile 10, and between the anchor cable tensioner 16 and the steel sheet pile 10, and the force distribution components 17 can be made of steel sections; when the caisson sinks too fast, the anchor cable tensioner 16 can be started as an emergency measure, and the specific control method will be described in detail in the underground shaft group construction method later.
[0080] Preferably, a guide groove corner guard 18 is provided at the top of the caisson guide groove 2 on the inner periphery of the pre-caisson shaft; a rigid floor 12 and an anti-slip pier 13 are provided along the outer periphery of the steel sheet pile 10; this is conducive to the movement of construction equipment and reduces the displacement of the shaft top during the construction period.
[0081] Based on the above-mentioned guide sinking system, the present invention also provides a method for constructing an underground shaft group, such as Figures 1 to 13 As shown, the underground wellbore group construction method includes the following steps:
[0082] 1. Determine whether it is necessary to set steel sheet piles 10 according to the terrain conditions. If it is necessary to set steel sheet piles 10, construct the steel sheet piles 10 in advance;
[0083] 2. Construct the counterweight pier 1. If a pre-buried anchor rod 7 is provided in the counterweight pier 1, the pre-buried anchor rod 7 is provided during the construction of the counterweight pier 1;
[0084] 3. Use the slotting machine 28 to excavate the caisson guide slot 2, and use the weighted mud 3 to protect the wall during the excavation process; the specific method is that as the excavation depth of the slot increases, the weighted mud 3 is injected into the slot, and the mud liquid level is slightly lower than the slot mouth elevation to maintain the stability of the slot wall; the excavation depth is determined according to the bottom elevation of the pre-sunk shaft; preferably, the cross-sectional width of the caisson guide slot 2 is less than or equal to the shaft wall thickness at the corresponding position, which can reduce the sinking deviation of the shaft;
[0085] 4. Arrange the grouting holes 4, and insert the grouting pipes 5 into the grouting holes 4; preferably, a grouting hole 4 is arranged on each groove line around the wellbore;
[0086] 5. Installing the sinking guide device 6 on the counterweight pier 1;
[0087] 6. The shaft is pre-made in sections; a section of the shaft is hoisted to the designed position and inserted into the caisson guide groove 2; under the control of the guide sinking device 6, the shaft is gradually sunk into the caisson guide groove 2 until it reaches the bottom of the caisson guide groove 2;
[0088] The control method of the sinking guide device 6 is:
[0089] Step a, the mobile frame is raised to a designated high position by the lifting jack 601, the telescopic jack 602 is extended, and the force distribution block 604 is pressed against the wellbore inside the wellbore;
[0090] Step b, the lifting jack 601 is gradually retracted, and the wellbore gradually sinks under its own weight; the moving frame sinks together with the wellbore;
[0091] Step c, when the mobile frame descends to the designated low position; the telescopic jack 602 retracts, the friction between the force distribution block 604 and the inner wall of the wellbore is reduced, and the wellbore remains in place; the lifting jack 601 raises the mobile frame to the designated high position, the telescopic jack 602 extends, and the force distribution block 604 presses the wellbore tightly inside the wellbore;
[0092] Step d, repeating step b and step c to control the sinking of the wellbore; further preferably, when the wellbore sinks, the liquid level of the weighted mud 3 in the caisson guide groove 2 is controlled by pumping the grouting pipe 5, thereby controlling the buoyancy generated on the wellbore, and then controlling the sinking rate of the wellbore; during implementation, before the weighted mud 3 is injected into the caisson guide groove 2, the required buoyancy is calculated in advance, and the ratio of the weighted mud 3 is adjusted to control the weight of the weighted mud 3.
[0093] Preferably, the control method of the sinking guide device 6 further includes the following steps:
[0094] Step e: the control system 606 compares and analyzes the data of each sensor through a pre-set control program, thereby obtaining the sinking posture and sinking rate of the wellbore, and controls the lifting jack 601, the telescopic jack 602, the anchor jack, and the anchor cable jack to keep the wellbore posture and sinking rate in a normal state; the specific control method is:
[0095] When one side of the wellbore encounters greater resistance and thus sinks more slowly, the control system 606 retracts the lifting jack 601 on that side and lifts the lifting jack 601 on the opposite side, adjusting the wellbore posture to horizontal. At this time, the wellbore center of gravity is biased toward the side with greater resistance, thereby increasing the gravity distributed to that side, so that the wellbore resumes overall uniform sinking; if that side still cannot sink, the counterweight vibrator 9 is hoisted to the force distribution block 604 on that side, and the counterweight vibrator 9's own gravity and vibration kinetic energy accelerate the sinking of that side; the structure of the counterweight vibrator 9 is, including a hook 901, a vibrator 902 and a steel box 903, the hook 901 is fixedly arranged at the top end of the vibrator 902, the steel box 903 is fixedly arranged at the bottom end of the vibrator 902, and steel sand is poured into the steel box 903.
[0096] When the wellbore is difficult to sink as a whole, the lifting jack 601 is fully retracted. If the wellbore still cannot sink due to the whole gravity, the anchor tensioner 8 is activated by the anchor jack to pull the wellbore down as a whole, thereby driving the wellbore to sink, and at the same time, the counterweight vibrator 9 is used to adjust the wellbore posture;
[0097] When the buoyancy of the weighted mud 3 and the friction between the wellbore and the inner wall of the caisson guide groove 2 are not sufficient to offset the gravity of the wellbore, resulting in a too fast sinking rate, the telescopic jack 602 is extended to increase the friction between the wellbore and the force distribution block 604, thereby increasing the sinking resistance and controlling the sinking rate of the wellbore; if the sinking rate is still too fast, the anchor tensioner 16 is tightened by the anchor jack to adjust the stress of the prestressed anchor 14, so that the anchor block 15 applies pressure to the force distribution component 17, and the force distribution component 17 transmits the pressure to the steel sheet pile 10, thereby increasing the friction between the steel sheet pile 10 and the wellbore and controlling the sinking rate.
[0098] 7. After one section of the shaft is sunk, the next section is hoisted and assembled by workers in the shaft;
[0099] 8. After all the shaft guide sinkings are assembled in place, the guide sinking device 6 is removed; the bottom of the well is sealed by grouting through the grouting pipe 5 to consolidate the foundation and reduce the permeability coefficient of the soil; then the soil in the well is excavated, and when the excavation reaches the designed elevation of the shaft, a secondary bottom sealing is performed; preferably, an unmanned excavator is used to excavate the soil in the well, and the soil in the well is transported out of the well with the help of a long-arm grab and a soil transport vehicle; when the excavation reaches the groundwater level, the groundwater in the well can be extracted through the grouting pipe 5 to speed up the excavation speed.
[0100] 9. Install the shaft bottom plate and top plate; if steel sheet piles 10 are provided, pull out the steel sheet piles 10 around one by one; then perform grouting reinforcement on the soil around the shaft group after the steel sheet piles 10 are pulled out.
[0101] like Figures 14 to 20 As shown, preferably, the installation method of the shaft bottom plate 26 is as follows: the shaft bottom plate 26 adopts a prefabricated bottom plate 30 of a reinforced concrete structure, and the prefabricated bottom plate 30 is provided with a bottom plate keyway 31 around it, and a bottom plate connecting steel bar 32 is arranged at the position of the bottom plate keyway 31 and is arranged to extend outward relative to the prefabricated bottom plate 30; a shaft keyway 33 is provided at the bottom end position of the shaft inner wall, and a pre-embedded sleeve 34 is provided in the shaft keyway 33, and the pre-embedded sleeve 34 is fixed by a pre-embedded sleeve steel bar 35; when the shaft is sunk, in order to protect the shaft keyway 33 from damage, the shaft keyway 33 is equipped with a keyway protection plate 37, and when the shaft is sunk, the keyway protection plate 37 is fixed to the shaft in advance by screws 38. In the keyway 33; after the shaft is sunk into place, when installing the shaft bottom plate 26, first remove the keyway protection plate 37, then screw the secondary steel bar 36 into the embedded sleeve 34 in the shaft keyway 33, and overlap the other end of the secondary steel bar 36 with the bottom plate connecting steel bar 32 of the prefabricated bottom plate 30, and use expansive concrete to fill the interval between the bottom plate keyway 31 and the shaft keyway 33, so that the shaft bottom plate 26 forms a closed installation structure relative to the inner wall of the shaft. If the prefabricated bottom plate 30 is multiple pieces, the bottom plate connecting steel bars 32 of adjacent prefabricated bottom plates 30 are connected as a whole through the secondary steel bars 36, and expansive concrete is used to fill the interval between the bottom plate keyways 31 of the adjacent prefabricated bottom plates 30. The shaft bottom plate 26 adopts prefabricated assembled components, which is conducive to industrialized production and improves construction efficiency. Expansive concrete generally uses high-strength concrete, which refers to concrete with a strength grade of C60 or above.
[0102] It is further preferred that the prefabricated bottom plate 30 includes a left bottom plate and a right bottom plate, the upper steel bars of the left bottom plate and the upper steel bars of the right bottom plate are common steel bars of an integral structure, the lower steel bars of the left bottom plate and the lower steel bars of the right bottom plate are a disconnected structure, and the prefabricated bottom plate 30 has a first state during transportation and a second state during installation and use. When the prefabricated bottom plate 30 is in the first state, the upper common steel bars are bent into a U shape so that the left bottom plate and the right bottom plate overlap, which is convenient for transportation; when the prefabricated bottom plate 30 is in the second state, the upper common steel bars are straightened into a flat shape, the left bottom plate and the right bottom plate are arranged side by side on the same installation surface, and the lower steel bars of the left bottom plate and the lower steel bars of the right bottom plate form a lap structure. When installing the prefabricated bottom plate 30, first screw the secondary steel bar 36 into the embedded sleeve 34 in the shaft keyway 33, and after the other end of the secondary steel bar 36 is overlapped with the bottom plate connecting steel bar 32 of the prefabricated bottom plate 30, the space between the bottom plate keyway 31 and the shaft keyway 33 is filled with expansion concrete, and the space between the left bottom plate and the right bottom plate is also filled with expansion concrete, so that the shaft bottom plate 26 forms a closed installation structure relative to the shaft inner wall. Compared with the structure that completely uses secondary steel bars 36 to connect adjacent prefabricated bottom plates 30, the above-mentioned combination of the left bottom plate and the right bottom plate has the advantages of more convenient implementation and better overall structural performance.
Claims
1. A guide sinking system suitable for underground shaft group construction, including a construction site, characterized by: A counterweight pier (1) is arranged at the center of a pre-caisson shaft at a construction site, a caisson guide groove (2) is arranged at a corresponding position of the pre-caisson shaft, the cross-sectional shape and specification of the caisson guide groove (2) are adapted to the cross-sectional shape and specification of the pre-caisson shaft, and weighted mud (3) is injected into the caisson guide groove (2); a grouting hole (4) for extracting and injecting the weighted mud (3) is arranged on the side of the caisson guide groove (2), and the grouting hole (4) is provided with a grouting pipe (5); a sinking guide device (6) is arranged on the top surface of the counterweight pier (1), and the sinking guide device (6) comprises a moving frame, a lifting jack (601), a telescopic jack (602), a movable block (603) and a force distribution block (604), and the lifting jack (601) is arranged on the counterweight pier (1). The top surface of the heavy pier (1), the mobile frame is placed on the top of the lifting jack (601) and supported by the movable end of the lifting jack (601), the telescopic jack (602) is a plurality of pieces arranged at intervals along the circumference of the mobile frame, the fixed end of the telescopic jack (602) is connected to the mobile frame, the movable end of the telescopic jack (602) is connected to the force distribution block (604) through the movable block (603), and the end face shape of the force distribution block (604) away from the center of the mobile frame is consistent with the shape of the inner wall of the pre-sunk shaft corresponding to the position of the force distribution block (604).
2. The guide sinking system suitable for underground shaft group construction as claimed in claim 1, characterized in that: Each telescopic jack (602) is provided with a corresponding push rod (605), and all the push rods (605) are fixedly connected to form a whole to form a mobile frame; a lifting jack (601) is provided below each push rod (605); and push blocks (609) are provided at intervals at the outer end of the force distribution block (604), and the push blocks (609) are arranged toward the inner wall of the pre-sunk shaft.
3. The guide sinking system suitable for underground shaft group construction as claimed in claim 1, characterized in that: The pre-sinking shaft has one unit cylinder or a plurality of unit cylinders, each unit cylinder corresponding to a group of sinking guide devices (6); in the same group of sinking guide devices (6), the telescopic jacks (602) are four pieces distributed in a rectangular shape.
4. The guide sinking system suitable for underground shaft group construction according to any one of claims 1 to 3, characterized in that: It also includes a control system (606), each force distribution block (604) is provided with a wireless displacement sensor A (607) for monitoring the elevation of its location, and the wireless displacement sensor A (607), the lifting jack (601), and the telescopic jack (602) are all electrically connected to the control system (606).
5. The guide sinking system suitable for underground shaft group construction as claimed in claim 4, characterized in that: The inner wall of the pre-sunk shaft is provided with a wireless displacement sensor B (608) for monitoring the elevation of the position thereof. The wireless displacement sensor B (608) is a plurality of wireless displacement sensors arranged at intervals along the circumference of the pre-sunk shaft. The wireless displacement sensor B (608) is electrically connected to the control system (606).
6. The guiding and sinking system suitable for underground shaft group construction according to any one of claims 1 to 3, characterized in that: A pre-buried anchor rod (7) is arranged in the counterweight pier (1), the outer end of the pre-buried anchor rod (7) passes through the movable frame in the vertical direction, and an anchor rod tensioner (8) is arranged at the outer end.
7. The guide sinking system suitable for underground shaft group construction according to any one of claims 1 to 3, characterized in that: Steel sheet piles (10) are arranged continuously or at intervals in the outer peripheral direction of the underground shaft group to be constructed at the construction site, and the inner wall of the steel sheet piles (10) also serves as the inner wall of the caisson guide groove (2).
8. The guiding and sinking system suitable for underground shaft group construction as claimed in claim 7, characterized in that: The driving depth of the steel sheet pile (10) is below the bottom elevation of the pre-sunk shaft; a top channel steel (11) is arranged at the top elevation of the steel sheet pile (10); the bottom of the top channel steel (11) is arranged horizontally upward, and the slot is clamped downward on the top of the steel sheet pile (10); a rigid floor (12) and an anti-slip pier (13) are arranged along the outer periphery of the steel sheet pile (10); prestressed anchor cables (14) are arranged on both sides of the pre-sunk shaft of the steel sheet pile (10), and one end of the prestressed anchor cable (14) is arranged An anchor block (15) is provided, and an anchor cable tensioner (16) is provided at the other end. The anchor block (15) is provided on the outside of a steel sheet pile (10), and the anchor cable tensioner (16) is provided on the outside of another steel sheet pile (10) arranged opposite to each other. A force distribution member (17) is provided between the anchor block (15) and the steel sheet pile (10), and between the anchor cable tensioner (16) and the steel sheet pile (10). A guide groove corner guard (18) is provided at the top end of the caisson guide groove (2) on the inner periphery of the pre-caisson shaft.
9. A method for constructing an underground shaft group, characterized in that: The sinking guide system suitable for underground shaft group construction according to any one of claims 1 to 8 comprises the following steps:
1. Determine whether it is necessary to set steel sheet piles (10) according to the terrain conditions. If it is necessary to set steel sheet piles (10), construct the steel sheet piles (10) in advance; 2. constructing the counterweight pier (1), if a pre-buried anchor rod (7) is provided in the counterweight pier (1), during the construction process of the counterweight pier (1), the pre-buried anchor rod (7) is simultaneously provided; 3. using a trenching machine (28) to dig a caisson guide groove (2), and during the digging process, using weighted mud (3) to protect the wall; the digging depth is determined according to the bottom elevation of the pre-caisson shaft; the cross-sectional width of the caisson guide groove (2) is less than or equal to the shaft wall thickness at the corresponding position; 4. Arranging the grouting holes (4), and inserting the grouting pipes (5) into the grouting holes (4); 5. Installing a sinking guide device (6) on the counterweight pier (1); 6. The shaft is prefabricated in sections; a section of the shaft is hoisted to the designed position and inserted into the caisson guide groove (2); under the control of the guide sinking device (6), the shaft is gradually sunk into the caisson guide groove (2) until it reaches the bottom of the caisson guide groove (2); The control method of the sinking guide device (6) is: Step a, the mobile frame is raised to a designated high position by means of a lifting jack (601), the telescopic jack (602) is extended, and the force distribution block (604) is pressed against the wellbore inside the wellbore; Step b, the lifting jack (601) is gradually retracted, and the wellbore gradually sinks under its own weight; the moving frame sinks together with the wellbore; Step c, when the mobile frame descends to the designated low position, the telescopic jack (602) retracts, the friction between the force distribution block (604) and the inner wall of the wellbore is reduced, and the wellbore remains in place; the lifting jack (601) lifts the mobile frame to the designated high position, the telescopic jack (602) extends, and the force distribution block (604) presses against the wellbore inside the wellbore; Step d, repeating steps b and c to control the sinking of the wellbore; when the wellbore sinks, the liquid level of the weighted mud (3) in the caisson guide groove (2) is controlled by pumping the grouting pipe (5), thereby controlling the buoyancy generated on the wellbore, and further controlling the sinking rate of the wellbore; 7. After one section of the shaft is sunk, the next section is hoisted and assembled by workers in the shaft; 8. After all the shaft guide sinkers are assembled in place, the guide sinker device (6) is removed; the shaft bottom is sealed by grouting the grouting pipe (5); then the soil in the shaft is excavated, and when the excavation reaches the shaft design elevation, a secondary bottom sealing is performed; the soil in the shaft is excavated using an unmanned excavator (21), and the soil in the shaft is transported to the outside of the shaft in conjunction with a long arm grab (22) and a soil transport vehicle; IX. Install the shaft bottom plate (26) and the top plate; if steel sheet piles (10) are provided, pull out the steel sheet piles (10) on the periphery one by one, and then perform grouting reinforcement on the soil around the shaft group after the steel sheet piles (10) are pulled out; the shaft bottom plate (26) is installed as follows: the shaft bottom plate (26) adopts a prefabricated bottom plate (30) of a reinforced concrete structure, the prefabricated bottom plate (30) is provided with a bottom plate keyway (31) on the periphery, and a bottom plate connecting steel bar (32) is arranged at the position of the bottom plate keyway (31) and is arranged to extend outward relative to the prefabricated bottom plate (30); a shaft keyway (33) is provided at the bottom end of the shaft inner wall , and an embedded sleeve (34) is arranged in the shaft keyway (33), and the embedded sleeve (34) is fixed by the embedded sleeve steel bar (35); the shaft keyway (33) is provided with a keyway protection plate (37), and when the shaft is sunk, the keyway protection plate (37) is fixed in the shaft keyway (33) by screws (38) in advance; after the shaft is sunk into place, when the shaft bottom plate (26) is installed, the keyway protection plate (37) is first removed, and then the secondary steel bar (36) is screwed into the embedded sleeve (34) in the shaft keyway (33), and the other end of the secondary steel bar (36) is connected to the prefabricated bottom plate (3 0), the bottom plate connecting steel bars (32) of the bottom plate are overlapped, and the space between the bottom plate key groove (31) and the shaft key groove (33) is filled with expansion concrete, so that the shaft bottom plate (26) forms a closed installation structure relative to the inner wall of the shaft. If the prefabricated bottom plate (30) is a plurality of pieces, the bottom plate connecting steel bars (32) of adjacent prefabricated bottom plates (30) are connected into a whole through secondary steel bars (36), and the space between the bottom plate key grooves (31) of the adjacent prefabricated bottom plates (30) is filled with expansion concrete; the prefabricated bottom plate (30) comprises a left bottom plate and a right bottom plate, and the upper steel bar of the left bottom plate The upper steel bars of the left and right bottom plates are common steel bars of an integral structure, and the lower steel bars of the left and right bottom plates are of a disconnected structure. The prefabricated bottom plate (30) has a first state during transportation and a second state during installation and use. When the prefabricated bottom plate (30) is in the first state, the upper common steel bars are bent into a U shape, so that the left and right bottom plates overlap. When the prefabricated bottom plate (30) is in the second state, the upper common steel bars are bent straight into a straight shape, and the left and right bottom plates are arranged side by side on the same installation surface, and the lower steel bars of the left and right bottom plates form an overlap structure.
10. The underground shaft group construction method according to claim 9, characterized in that: The control method of the sinking guide device (6) further comprises the following steps: Step e, the control system (606) compares and analyzes the data of each sensor through a pre-set control program, thereby obtaining the wellbore sinking posture and sinking rate, and controls the lifting jack (601), the telescopic jack (602), the anchor jack, and the anchor cable jack to keep the wellbore posture and sinking rate in a normal state; the specific control method is: When one side of the wellbore is subjected to greater resistance and thus sinks more slowly, the control system (606) causes the lifting jack (601) on that side to retract and the lifting jack (601) on the opposite side to lift up, and adjust the wellbore posture to be horizontal. At this time, the center of gravity of the wellbore is biased toward the side with greater resistance, thereby increasing the gravity distributed to that side, so that the wellbore resumes overall uniform sinking; if that side still cannot sink, the counterweight vibrator (9) is hoisted onto the force distribution block (604) on that side, and the self-gravity and vibration kinetic energy of the counterweight vibrator (9) accelerate the sinking of that side; the structure of the counterweight vibrator (9) comprises a hook (901), a vibrator (902) and a steel box (903), wherein the hook (901) is fixedly arranged at the top end of the vibrator (902), the steel box (903) is fixedly arranged at the bottom end of the vibrator (902), and steel sand is poured into the steel box (903); When the wellbore is difficult to sink as a whole, the lifting jack (601) is fully retracted. If the wellbore still cannot sink due to the entire gravity of the wellbore, the anchor tensioner (8) is activated by the anchor jack to pull the wellbore as a whole downward, thereby driving the wellbore to sink, and at the same time, the counterweight vibrator (9) is used to adjust the wellbore posture; When the buoyancy of the weighted mud (3) and the friction between the wellbore and the inner wall of the caisson guide groove (2) are insufficient to offset the wellbore gravity, resulting in an excessively fast sinking rate, the telescopic jack (602) is extended to increase the friction between the wellbore and the force distribution block (604), thereby increasing the sinking resistance and controlling the wellbore sinking rate; if the sinking rate is still too fast, the anchor cable tensioner (16) is tightened by the anchor cable jack to adjust the stress of the prestressed anchor cable (14), so that the anchor block (15) applies pressure to the force distribution member (17), and the force distribution member (17) transmits the pressure to the steel sheet pile (10), thereby increasing the friction between the steel sheet pile (10) and the wellbore and controlling the sinking rate.
Citation Information
Patent Citations
Process of jacking utilizing horizontal trolley of jack for caisson
CN101586342A
Rapid sinking construction device for pile anchor press-in type sinking well
CN108487281A
Open caisson sinking control system and construction method thereof