An external plug-type assembled station connection device
By adopting an outer plug connection device in the prefabricated station node and using high-strength mortar and cover plate limit block structure, the problems of poor integrity and insufficient earthquake resistance in the prior art are solved, and high-strength, rapid assembly and waterproof performance are achieved. promote.
Patent Information
- Application Number
- CN202010503818.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-06-04
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2040-06-04
AI Technical Summary
The existing prefabricated station node connection methods have problems such as poor integrity, insufficient seismic resistance and poor waterproof performance, especially in the earthquake environment of subway stations, and cast-in-place nodes are prone to mortar leakage affecting the intensity.
The external plug-in assembly station connection device is adopted, and high-strength mortar is poured into the main body of the connecting pipe and the cover plate and limit block structure to ensure the strength and waterproofness of the connection, and quickly assembled in combination with prefabricated components.
The seismic resistance and stress strength of the nodes are improved, the construction time is shortened, the integrity and waterproof performance of the prefabricated station are ensured, the mortar leakage is avoided, and the reliability and strength of the connection are enhanced.
Smart Images

Figure CN111733984B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of construction engineering, and in particular to an external plug-in assembled station connection device. Background Art
[0002] At present, the node processing methods of prefabricated stations mainly adopt cast-in-place nodes, mortise and tenon connections, plug-in connections, corbel anchor connections, bolt connections, etc. Among them, cast-in-place node connections use cast-in-place concrete at the nodes; mortise and tenon connections and plug-in connections are mainly connected by making concave and convex tenons at both ends of the connector; corbel anchor connections and bolt connections mainly rely on bolts and anchors to connect the nodes.
[0003] The node connection of the existing technology mainly relies on cast-in-place treatment at the node, such as cast-in-place nodes, mortise and tenon connections, plug-in connections, etc. Although prefabricated components are used, they still need to be cast-in-place when connected. Since cast-in-place concrete requires a certain amount of time to produce a high strength, it generally takes 28 days. Among them, the corbel anchor connection and bolt connection mainly rely on anchor bolts and bolts. In the earthquake resistance of subway stations, these nodes are reliable and easily damaged in earthquakes. The above connection methods, the connection of prefabricated assembled components, except for cast-in-place nodes, the other connection methods have poor integrity, and the nodes are prone to water seepage, which cannot meet the requirements of underground waterproofing of subway stations.
[0004] In addition, the joints of existing cast-in-place nodes are prone to mortar leakage, which affects the strength of the joints, thereby causing insufficient strength of the prefabricated station. Summary of the invention
[0005] The purpose of the present invention is to provide an external plug-in assembled station connection device, which has a simple structure, is easy to construct and install, and has high strength and strong earthquake resistance.
[0006] In order to achieve the above-mentioned purpose, the present invention provides an external plug-in type assembled station connection device, the assembled station includes a plurality of first components and a second component, the external plug-in type assembled station connection device includes a connecting pipe body, the connecting pipe body includes a first connecting end and a second connecting end, the first connecting end is connected to the first component by a thread, the second connecting end is provided with a connecting port adapted to the second component, the second component is provided with a protrusion, the bottom of the protrusion is provided with a cover plate, the protrusion is inserted in the connecting port, the cover plate is arranged at the end of the connecting port, and the connecting pipe body is provided with an injection port and an exhaust port in sequence.
[0007] Preferably, a slide groove for the cover plate to slide is provided in the connection port, a limit block is provided in the slide groove, and at least one protrusion is provided on the cover plate extending outwardly along the circumferential direction of the cover plate.
[0008] Preferably, the connecting pipe body includes a first horizontal connecting pipe and a second horizontal connecting pipe arranged in parallel in the horizontal direction and a first vertical connecting pipe and a second vertical connecting pipe arranged in the vertical direction. The first horizontal connecting pipe, the second horizontal connecting pipe, the first vertical connecting pipe and the second vertical connecting pipe are interconnected to form a U-shape. The first connecting end and the second connecting end are respectively arranged on the first vertical connecting pipe and the second vertical connecting pipe. The infusion port and the exhaust port are arranged on the horizontal connecting pipe connecting the first vertical connecting pipe and the second vertical connecting pipe.
[0009] Preferably, a step surface is formed between the first connecting end and the first vertical connecting pipe.
[0010] Preferably, the protrusion is a steel bar, the cover plate is connected to the connecting surface of the steel bar and the second component, and the cover plate is arranged to protrude from the connecting surface of the second component.
[0011] Preferably, the length of the steel bar is greater than or equal to half the length of the first horizontal connecting pipe or the second horizontal connecting pipe.
[0012] Preferably, the filling port and the exhaust port are both provided with covers.
[0013] Preferably, a waterproof layer is provided between the external plug-type assembled station connection device and the first component and the second component.
[0014] The embodiment of the present invention provides an external plug type assembled station connection device, which has the following beneficial effects compared with the prior art:
[0015] In the outer plug type assembled station connection device of the embodiment of the present invention, the first component and the second component are connected through the outer plug type assembled station connection device, the outer plug type assembled station connection device connects the first component and the second component on both sides of the prefabricated assembly, and high-strength mortar can be poured into the connecting pipe body through the pouring port. When the high-strength mortar fills the connecting pipe body, mortar will flow out of the exhaust port, which makes it easy to determine that the pouring is completed. When the mortar pouring is completed, the outer plug type assembled station connection device is connected to the first component and the second component, and the component integrity is good. The node using this connection method has stronger seismic resistance than the node of the tongue and groove connection and the plug-in connection. The use of high-strength mortar poured into the connecting pipe body can ensure that there is still a gripping force on the outside of the plug-in part, thereby enhancing the stress strength of the node. At the same time, due to the early strength effect of the mortar, compared with the cast-in-place node, the construction time of the node in this embodiment can be shortened, meeting the requirements of rapid assembly of the prefabricated station, and the cover plate is arranged at the bottom of the protrusion of the second component. When the protrusion of the second component is inserted into the connecting port, the cover plate is sealed at the end of the connecting port, which is convenient for subsequent grouting, and the cover plate is arranged on the protrusion, which enhances the strength of the cover plate and avoids the mortar in the external plug-type prefabricated station connection device from flowing out due to damage to the cover plate, further ensuring the reliable connection between the first component and the second component, thereby ensuring the strength of the prefabricated station. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is an exploded view of the cross-sectional view of the assembly structure of the grouting external plug type assembled station according to an embodiment of the present invention;
[0017] Figure 2 yes Figure 1 A partial enlarged view of the middle A;
[0018] Figure 3 It is a schematic structural diagram of a cross section of an external plug-type assembled station connection device according to an embodiment of the present invention;
[0019] Figure 4 yes Figure 3 A partial enlarged view of the middle A;
[0020] In the figure, 1. first component, 11. first component connecting end, 2. second component, 21. second component connecting end, 3. external plug type assembled station connecting device, 31. first horizontal connecting pipe, 32. second horizontal connecting pipe, 33. first vertical connecting pipe, 34. second vertical connecting pipe, 35. filling port, 36. exhaust port, 37. cover, 4. cover plate, 41. raised portion, 5. slide groove, 6. limit block. DETAILED DESCRIPTION
[0021] The specific embodiments of the present invention are further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in the field without making creative work are within the scope of protection of the present invention.
[0022] It should be understood that the present invention uses the terms "first", "second", "third", "fourth", etc. to describe various information, but these information should not be limited to these terms, and these terms are only used to distinguish the same type of information from each other. For example, without departing from the scope of the present invention, the "first" information may also be referred to as the "second" information, and similarly, the "second" information may also be referred to as the "first" information.
[0023] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "connected" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0024] like Figures 1 to 4 As shown, an external plug-in assembled station connection device 3 of a preferred embodiment of the present invention, the assembled station includes a plurality of first components 1 and a second component 2, the external plug-in assembled station connection device 3 includes a connecting pipe body, the connecting pipe body includes a first connecting end and a second connecting end, the first connecting end is connected to the first component 1 by a thread, the second connecting end is provided with a connecting port matched with the second component 2 (not shown in the drawings), the second component 2 is provided with a protrusion, the bottom of the protrusion is provided with a cover plate 4, the protrusion is inserted in the connecting port, the cover plate 4 is arranged at the end of the connecting port, the cover plate 4 abuts against the connecting port, thereby completing the blocking of the connection device 3, the cover plate 4 plays a role of blocking the connecting port, the connecting pipe body is provided with a pouring port 35 and an exhaust port 36 in sequence, thereby facilitating the pouring of high-strength mortar, exhaust and observation of the pouring condition.
[0025] Based on the above technical solution, the first component 1 and the second component 2 are connected through the outer plug type assembled station connection device 3, which connects the first component 1 and the second component 2 on both sides of the prefabricated assembly, and the high-strength mortar can be poured into the connecting pipe body through the pouring port 35. When the high-strength mortar fills the connecting pipe body, the mortar will flow out of the exhaust port 36, which makes it easy to determine that the pouring is completed. When the mortar pouring is completed, the outer plug type assembled station connection device 3 is connected to the first component 1 and the second component 2, and the integrity of the components is good. The nodes connected in this way have stronger seismic resistance than the nodes connected by tongue and groove and plug-in. The use of high-strength mortar poured into the connecting pipe body can ensure that there is still a gripping force on the outside of the plug-in part, thereby enhancing the stress strength of the node. At the same time, due to the early strength effect of the mortar, compared with the cast-in-place node, the construction time of the node in this embodiment can be shortened, meeting the requirements of rapid assembly of the prefabricated station, and the cover plate 4 is arranged at the bottom of the protrusion of the second component 2. When the protrusion of the second component 2 is inserted into the connecting port, the cover plate 4 is sealed at the end of the connecting port, which is convenient for subsequent grouting, and the cover plate 4 is arranged on the protrusion, which enhances the strength of the cover plate 4 and avoids the mortar in the external plug-type prefabricated station connecting device 3 from flowing out due to damage to the cover plate 4, further ensuring the reliable connection between the first component 1 and the second component 2, thereby ensuring the strength of the prefabricated station.
[0026] Furthermore, a slide groove 5 for the cover plate 4 to slide is provided in the connection port, so that the cover plate 4 can be inserted into the connection port, increasing the contact area between the second component 2 and the high-strength mortar, increasing the connection strength, and at the same time, the cover plate 4 can fill the connection port. Since the cover plate is arranged on the second component 2, the high-strength mortar will not affect the position of the second component during pouring, thereby avoiding leakage of the high-strength mortar. Specifically, a protrusion 41 is also provided in the circumferential direction of the cover plate 4, and an elastic reset device is provided at the bottom of the limit block 6. Therefore, during installation, the protrusion of the second component 2 is inserted into the connection port. Due to the action of external force, the protrusion and the cover plate 4 slide in the slide groove 5 toward the direction close to the first component 1, and the elastic reset device at the bottom of the limit block 6 is compressed, and the cover plate 4 continues to slide toward the direction close to the first component 1. When the cover plate 4 passes the limit block 6, the elastic reset device lifts the limit block 6. At this time, the limit block 6 abuts against the step surface between the cover plate 4 and the second component and the protrusion on the cover plate 4. In the accommodation position limited by 41, even if the force of pouring high-strength mortar pushes the cover plate 4 and the second component 2, and squeezes the cover plate 4 so that the cover plate 4 has a tendency to slide in the direction of the second component 2, at this time, the relative position of the second component 2 and the outer plug-type assembled station connection device 3 has been determined, which can ensure that the protrusion of the second component 2 is inserted into the outer plug-type assembled station connection device 3. At the same time, when the limit block 6 limits the position of the second component 2, the high-strength mortar can connect the second component 2 and the outer plug-type assembled station connection device 3 together to ensure the installation strength. Specifically, the top of the limit block 6 is provided with an inclined surface, which gradually rises from the second component 2 to the direction of the first component 1, thereby facilitating the movement of the cover plate 4 when pouring high-strength mortar. At the same time, it can also ensure that during the assembly process of the cover plate 4, after the cover plate slides over the protrusion, it cannot move in the direction of the second component 2 even when it is subjected to the force of pouring high-strength mortar, ensuring that the first component 1 and the second component 2 are reliably connected after pouring mortar.
[0027] Specifically, the connecting pipe body includes a first horizontal connecting pipe 31 and a second horizontal connecting pipe 32 arranged in parallel in the horizontal direction, and a first vertical connecting pipe 33 and a second vertical connecting pipe 34 arranged in the vertical direction. The first horizontal connecting pipe 31, the second horizontal connecting pipe 32, the first vertical connecting pipe 33 and the second vertical connecting pipe 34 are interconnected to form a square shape. The first horizontal connecting pipe 31, the second horizontal connecting pipe 32, the first vertical connecting pipe 33 and the second vertical connecting pipe 34 are interconnected to form a quadrilateral, thereby ensuring that the strength of the external plug-type assembled station connection device 3 is high after the mortar is poured. To avoid damage, the first connection end and the second connection end are respectively arranged on the first vertical connection pipe 33 and the second vertical connection pipe 34. In the present embodiment, the first connection end and the second connection end are respectively arranged opposite to the first horizontal connection pipe 31 and the second horizontal connection pipe 32, thereby facilitating the flow of mortar. The pouring port 35 and the exhaust port 36 are arranged on the horizontal connection pipe connecting the first vertical connection pipe 33 and the second vertical connection pipe 34, thereby facilitating checking whether the pouring is completed during pouring, and facilitating the assembly and fixed connection of the first component 1 and the second component 2 with the external plug-type assembled station connection device 3.
[0028] In this embodiment, a step surface is formed between the first connecting end and the first vertical connecting pipe 33, thereby facilitating rapid installation and positioning between the external plug-in assembled station connection device 3 and the first component 1 during installation.
[0029] In this embodiment, the protrusion is a steel bar. This facilitates the connection of the external plug-type assembled station connection device 3 with the first component 1 and the second component 2. The steel bar is easy to obtain, and the installation strength can be ensured. The cover plate 4 is connected to the connection surface of the steel bar and the second component 2, and the cover plate 4 protrudes from the connection surface of the second component 2.
[0030] Preferably, the length of the steel bar is greater than or equal to half the length of the first horizontal connecting tube or the second horizontal connecting tube 32, thereby ensuring that the external plug-type assembled station connection device 3 and the second component 2 can be reliably connected with high strength after pouring mortar.
[0031] Preferably, a cover 37 is provided on the filling port 35 and the exhaust port 36, thereby ensuring that after the mortar is poured, the external plug-type assembled station connection device 3 can be sealed and not affected by the outside world, and the mortar will not leak, further ensuring a reliable connection.
[0032] Furthermore, a waterproof layer is provided between the outer plug type assembled station connection device 3 and the first component 1 and the second component 2. Thus, the waterproof requirement is met. In this embodiment, the waterproof layer is EPDM rubber. The EPDM rubber is compacted by the deadweight of the side wall above the outer plug type assembled station connection device 3 later, so as to meet the waterproof requirement of the underground station.
[0033] In this embodiment, the first component 1 is provided with a first component connecting end 11, which is provided with threads, and the second component 2 is provided with a second component connecting end 21, thereby facilitating the connection between the first component 1 and the second component 2 and the connecting device.
[0034] The working process of the present invention is as follows: the first component connection end 11 and the outer plug type assembled station connection device 3 are screwed together. During the screwing process, the injection port 35 and the exhaust port 36 should be set on the outside of the outer plug type assembled station connection device 3 to facilitate grouting. During the assembly process of the first component 1 and the second component 2, the first component 1 and the second component 2 are first accurately positioned, and then the steel bars reserved in the second component 2 are inserted into the connection hole. After the second component connection end 21 is aligned with the connection port and inserted, the cover plate 4 enters the connection port along the slide groove. As the cover plate 4 slides in, the limit block 6 is compressed by the elastic reset device. Then, when the cover plate 4 slides over the limit block 6, the limit block 6 is between the raised portion 41 of the cover plate 4 and the second component 2, thereby completing the positioning of the outer plug type assembled station connection device 3 and the second component 2. Then, high-strength mortar is poured into the injection port 35 until slurry emerges from the exhaust port 36, and then the grouting can be stopped. The injection hole is set for grouting, and the exhaust hole is used to detect whether the interior is filled with slurry. At this time, the cover 37 can be put on. After the high-strength mortar exerts its strength, the first component 1 and the second component 2 are connected to form a whole. For the side walls of the underground station, due to the need to consider waterproofing, EPDM rubber can be used at the interface. The EPDM rubber is compacted by the self-weight pressure of the upper side wall of the external plug-type assembled station connection device 3 to meet the waterproofing requirements of the underground station. In addition, the steel bars of the first component 1 and the second component 2 need to be accurately aligned during production so that the steel bars of the two components can be inserted into the grouting sleeve after leaving the factory.
[0035] In summary, the embodiment of the present invention provides an external plug type assembled station connection device 3, wherein the external plug type assembled station connection device 3, the first component 1 and the second component 2 are connected through the external plug type assembled station connection device 3, the external plug type assembled station connection device 3 connects the first component 1 and the second component 2 on both sides of the prefabricated assembly, and high-strength mortar can be poured into the connecting pipe body through the pouring port 35. When the high-strength mortar fills the connecting pipe body, mortar will flow out of the exhaust port 36, which makes it easy to determine that the pouring is completed. When the mortar pouring is completed, the external plug type assembled station connection device 3 is connected to the first component 1 and the second component 2, and the integrity of the components is good. The nodes connected in this way have stronger seismic resistance than the nodes connected by tongue and groove and plug-in. The use of high-strength mortar poured into the connecting pipe body can ensure that there is still a gripping force on the outside of the plug-in part, thereby enhancing the stress strength of the node. At the same time, due to the early strength effect of the mortar, compared with the cast-in-place node, the construction time of the node in this embodiment can be shortened, meeting the requirements of rapid assembly of the prefabricated station, and the cover plate 4 is arranged at the bottom of the protrusion of the second component 2. When the protrusion of the second component 2 is inserted into the connecting port, the cover plate 4 is sealed at the end of the connecting port, which is convenient for subsequent grouting, and the cover plate 4 is arranged on the protrusion, which enhances the strength of the cover plate 4 and avoids the mortar in the external plug-type prefabricated station connecting device 3 from flowing out due to damage to the cover plate 4, further ensuring the reliable connection between the first component 1 and the second component 2, thereby ensuring the strength of the prefabricated station.
[0036] In the description of the present invention, it is necessary to understand that the orientations or positional relationships indicated by terms such as “upper”, “lower”, “left”, “right”, “top”, “bottom”, “inside” and “outside” are based on the orientations or positional relationships shown in the accompanying drawings and are only for the convenience of describing the present invention and simplifying the description. They do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0037] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present invention. These improvements and substitutions should also be regarded as the scope of protection of the present invention.
Claims
1. An external plug-in type assembled station connection device, the assembled station comprises a plurality of first components and a second component, characterized in that: The connecting pipe body comprises a first connecting end and a second connecting end, the first member is provided with a connecting end, the connecting end of the first member is provided with a thread, the first connecting end is connected to the connecting end of the first member through the thread, the second connecting end is provided with a connecting port adapted to the second member, the second member is provided with a protrusion, the bottom of the protrusion is provided with a cover plate, the protrusion is inserted into the connecting port, the cover plate is provided at the end of the connecting port, and the connecting pipe body is provided with a filling port and an exhaust port in sequence; The connection port is provided with a slide groove for the cover plate to slide, the slide groove is provided with a limit block, the bottom of the limit block is provided with an elastic reset device, and the cover plate is provided with at least one protrusion extending outward along the circumferential direction of the cover plate; The connecting pipe body comprises a first horizontal connecting pipe and a second horizontal connecting pipe arranged in parallel in the horizontal direction, and a first vertical connecting pipe and a second vertical connecting pipe arranged in the vertical direction, the first horizontal connecting pipe, the second horizontal connecting pipe, the first vertical connecting pipe and the second vertical connecting pipe are interconnected to form a square shape, the first connecting end and the second connecting end are respectively arranged on the first vertical connecting pipe and the second vertical connecting pipe, and the infusion port and the exhaust port are arranged on the horizontal connecting pipe connecting the first vertical connecting pipe and the second vertical connecting pipe; A step surface is formed between the first connecting end and the first vertical connecting pipe; A waterproof layer is provided between the external plug-type assembled station connection device and the first component and the second component.
2. The external plug-type assembled station connection device according to claim 1 is characterized in that: The protruding portion is a steel bar, the cover plate is connected to the connecting surface of the steel bar and the second component, and the cover plate is arranged to protrude from the connecting surface of the second component.
3. The external plug-type assembled station connection device according to claim 2 is characterized in that: The length of the steel bar is greater than or equal to half the length of the first horizontal connecting pipe or the second horizontal connecting pipe.
4. The external plug-type assembled station connection device according to claim 1 is characterized in that: The filling port and the exhaust port are both provided with covers.