Welding workshop fume treatment system
By designing the flue gas treatment system in the welding workshop and using spray devices and filtering equipment to treat the flue gas, the problems of flue gas pollution and temperature instability in the welding workshop have been solved, flue gas cleaning and slag collection have been achieved, and air quality has been improved. and temperature stability.
Patent Information
- Application Number
- CN202011513888.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-12-21
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2040-12-21
AI Technical Summary
The flue gas pollution in the welding workshop is serious, affecting the health of workers, and the temperature is unstable, making it difficult to effectively handle the flue gas and slag.
A flue gas treatment system for welding workshops is designed, including flue gas hood, flue gas extraction pipe, negative pressure fan, flue gas treatment tower, spray device, filter plate, flexible filter cloth, overflow tank, closed insert plate and auxiliary The insert plate processes the flue gas through spray cleaning, filtration and cooling, and realizes the reuse of flue gas and the collection of slag materials.
Effectively cleans and cools the flue gas to ensure that the exhaust gas meets emission requirements, improves the air quality in the welding workshop, and enables the reuse of flue gas and the convenient collection of slag.
Smart Images

Figure CN112393355B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of welding workshop environment treatment, and in particular to a welding workshop fume treatment system. Background Art
[0002] Transmission towers and signal towers generally use angle steel towers. Angle steel towers have high strength and relatively low construction costs, and can effectively reduce the force of wind on them. They are widely used in the fields of power transmission and communications. In the production process of angle steel towers, there are a large number of steel components at the corners of the towers, and they are crisscrossed with each other, with a complex structure. These steel components need to be fixed to each other, and in order to ensure the connection strength of the tower corners, the steel components are directly fixed by welding. Therefore, there are relatively many welding stations in the welding workshop, and a large amount of smoke will be generated during welding, resulting in poor air quality in the welding workshop, which has a great impact on the health of welding operators; in addition, a large amount of heat will be generated during welding, resulting in a higher temperature near the welding position, and the temperature will be relatively hotter when the weather is hot; when the weather is cold, the temperature at a distance from the welding position will be relatively cold, and only the temperature near the welding position will be warmer due to the heat of welding. Summary of the invention
[0003] The purpose of the present invention is to overcome the shortcomings of the prior art and provide a welding workshop fume treatment system, which can realize the fume treatment of the welding workshop and the reuse of air, and is also convenient for collecting slag in the fume; the fume can be further cleaned and cooled by the spray device, ensuring that the exhaust gas can meet the emission requirements; the filtering effect of the fume is ensured by the filter plate and the flexible filter cloth; the spray device is supplied with water by the overflow tank, ensuring the cleanliness of the spray water, thereby ensuring the cleanliness of the spray water The invention can realize the washing effect; the connection and separation of the closed plug plate and the auxiliary plug plate are controlled by the connecting device, so as to facilitate the slag discharge operation of the slag discharge tank; the baffle plate can prevent the spray water of the spray device from directly dripping into the overflow tank, so as to ensure that the water in the overflow tank is obtained by the overflow of the water in the flue gas washing area, and thus ensure that the water volume in the flue gas washing area, the overflow tank and the spray return reaches a relative circulation balance state; the dripping speed of the spray liquid sprayed by the spray device is slowed down by the drip plate; thereby further ensuring the spray washing effect and cooling effect of the spray liquid on the air after water washing.
[0004] The technical solution adopted by the present invention is:
[0005] The fume treatment system of a welding workshop comprises a fume hood arranged on the top of each welding station in the welding workshop, the fume hoods are respectively connected with the fume exhaust pipes, the fume exhaust pipes are connected with the bottom of the fume treatment tower through the negative pressure fan A, the top of the fume treatment tower is connected with an outlet pipe through the fan B, the outlet pipe is respectively connected with the blowing pipe and the exhaust pipe through the three-way pipe A, valves are respectively provided at the connection between the blowing pipe and the exhaust pipe and the three-way pipe A, the blowing pipes are respectively connected with the blowing ports of each welding station in the welding workshop, the exhaust pipes are discharged to the outside atmosphere, and one side of the bottom of the fume treatment tower is connected with a slag discharge trough.
[0006] A further improvement of the present invention is that the bottom of the slag trough is lower than the bottom of the flue gas treatment tower, the bottom of the flue gas treatment tower is inclined downward in the direction facing the slag trough, and extends to be connected to the bottom of the slag trough, and a closed plug plate is provided on the tower wall of the flue gas treatment tower facing the slag trough and within the height range of the trough wall of the slag trough, and the closed plug plate is reciprocated between the flue gas treatment tower and the slag trough by a hydraulic piston cylinder, the hydraulic piston cylinder is located on the side of the slag trough facing away from the flue gas treatment tower, the piston rod end of the hydraulic piston cylinder is fixedly connected with an auxiliary plug plate matching the closed plug plate, the side wall of the auxiliary plug plate facing the closed plug plate is connected and fixed to the corresponding side wall of the closed plug plate through a plug plate connecting device, and the connecting device controls the connection and separation of the closed plug plate and the auxiliary plug plate.
[0007] A further improvement of the present invention is that horizontal supporting bars of closed plug plates are respectively provided in the flue gas treatment tower, corresponding to the side walls facing and facing away from the slag discharge trough; a partition vertical plate is provided on the side wall on the side facing away from the slag discharge trough in the flue gas treatment tower, above the horizontal supporting bars; the bottom of the partition vertical plate is sealed and fixedly connected to the side wall via a connecting cross plate; the two side walls of the partition vertical plate are respectively sealed and fixedly connected to the corresponding side walls of the flue gas treatment tower; an overflow trough is formed between the partition vertical plate and the side wall and the adjacent side wall; a flue gas water washing zone is formed at the lower part of the flue gas treatment tower, located outside the partition vertical plate; a spray device is also provided on the top of the flue gas treatment tower; the liquid inlet pipe of the spray device is connected to the bottom of the overflow trough through a liquid pump A; the outlet end of the flue gas extraction pipe is connected to the side wall of the flue gas treatment tower within the range of the flue gas water washing zone, and extends into the flue gas water washing zone.
[0008] A further improvement of the present invention is that a filter plate and a flexible filter cloth are fixedly provided in the flue gas water washing area, above the outlet end of the flue gas exhaust pipe, from bottom to top, and the flexible filter cloth is fixedly connected to the corresponding position on the top of the partition plate.
[0009] A further improvement of the present invention is that the filter plates include the coarse filter plate, the medium filter plate and the fine filter plate from bottom to top, the coarse filter plate is provided with one layer, the medium filter plate is provided with multiple layers, and the fine filter plate is provided with one layer.
[0010] A further improvement of the present invention is that the coarse filter plate is a curved plate, the surface of the curved plate is provided with protrusions and depressions distributed at intervals, and a plurality of filter holes are evenly distributed on the top of the protrusions.
[0011] A further improvement of the present invention is that adjacent protrusions and depressions are connected by smooth transition.
[0012] A further improvement of the present invention is that the middle filter plate is a wire mesh plate, the fine filter plate is a mesh plate, and the diameter of the mesh B of the mesh plate is smaller than the diameter of the mesh A of the wire mesh plate.
[0013] A further improvement of the present invention is that the flexible filter cloth is a gauze mesh.
[0014] A further improvement of the present invention is that a gap is provided between the bottom of the side wall of the flue gas treatment tower facing the slag trough and the corresponding position of the tower bottom, and the bottom of the trough wall of the flue gas treatment tower facing the slag trough is lower than the closed plug plate.
[0015] A further improvement of the present invention is that the slag discharge trough is connected with the flue gas water washing zone through a liquid pump B, and the pipe mouth A of the liquid suction pipe of the liquid pump B is located at the bottom of the side wall of the slag discharge trough corresponding to the flue gas treatment tower facing the slag discharge trough; the pipe mouth B of the liquid discharge pipe of the liquid pump B is located in the flue gas water washing zone, within the range between the closed plug plate and the filter plate.
[0016] A further improvement of the present invention is that a vent pipe is provided in the side wall of the flue gas treatment tower facing the slag discharge trough, and a matching socket is provided on the trough wall of the flue gas treatment tower facing the slag discharge trough corresponding to the closed plug plate, the vent pipe comprises a vent pipe unit A and a vent pipe unit B, the lower pipe opening A of the vent pipe unit A extends from the side wall at the lower position of the closed plug plate, the upper pipe opening A of the vent pipe unit A is connected with the socket from the bottom of the socket, the upper pipe opening B of the vent pipe unit B extends outward from the side wall at the upper position of the slag discharge trough, the lower pipe opening B of the vent pipe unit B is connected with the socket from the top of the socket, the closed plug plate is provided with a vent pipe unit C corresponding to the vent pipe, and when the closed plug plate is fully inserted into the flue gas treatment tower, the vent pipe unit C is respectively connected with the vent pipe unit A and the vent pipe unit B, so that the vent pipes are connected.
[0017] A further improvement of the present invention is that the outlet end of the flue gas extraction pipe located in the flue gas water washing area is connected and fixed with an outlet nozzle, the outlet nozzle is located above the closed plug plate, the outlet direction of the outlet nozzle is upward, and the outlet nozzle is a spherical surface with multiple outlet holes evenly distributed on the spherical surface.
[0018] A further improvement of the present invention is that a baffle A is fixedly connected inside the flue gas treatment tower, on the side wall corresponding to the bottom connection of the partition plate, and above the overflow tank. The two ends of the baffle A are respectively sealed and fixedly connected to the side walls of the flue gas treatment tower connected to both sides of the partition plate. The baffle A is inclined downward along the side facing the flue gas water washing area, and the bottom end of the baffle A is located within the range of the flue gas water washing area.
[0019] A further improvement of the present invention is that the baffle A is provided with multiple rows of ventilation holes, and a baffle B is respectively provided on the top surface of the baffle A and above each row of ventilation holes, and the baffle B is inclined downward along the side facing the flue gas water washing area, and the bottom edge of the baffle B is respectively located on the side of the corresponding ventilation hole facing the flue gas water washing area, and the slope of the baffle B is smaller than the slope of the baffle A.
[0020] A further improvement of the present invention is that a plurality of drip plates are provided in the flue gas treatment tower between the spray device and the partition plate.
[0021] A further improvement of the present invention is that the height difference between the spray device and the topmost dripping plate is equal to the height difference between two adjacent dripping plates.
[0022] A further improvement of the present invention is that a slot matching the closed plug plate is formed between the bottom of the partition vertical plate and the horizontal shoulder strips provided on the corresponding side panels of the flue gas treatment tower.
[0023] A further improvement of the present invention is that the liquid inlet pipe is pre-buried and fixed in the side wall of the flue gas treatment tower, and the liquid inlet pipe is also connected to an external water inlet device through a three-way pipe B.
[0024] A further improvement of the present invention is that when the hydraulic piston rod is fully extended out of the hydraulic piston cylinder, the auxiliary plug plate closes the notch of the slag discharge trough, and the closing plug plate is fully inserted into the flue gas treatment tower through the auxiliary plug plate; when the hydraulic piston rod is fully retracted into the hydraulic piston cylinder, the auxiliary plug plate is completely separated from the slag discharge trough, and at this time, when the closing plug plate is fixed to the auxiliary plug plate through the connecting device, the closing plug plate closes the notch of the slag discharge trough.
[0025] A further improvement of the present invention is that the air blowing pipe is connected and communicated with the air blowing port through a blowing manifold, and a heating device is provided on the blowing manifold, and the heating device heats the air passing through the blowing manifold.
[0026] The beneficial effects of the present invention are:
[0027] First, the welding workshop fume treatment system of the present invention can realize the fume treatment of the welding workshop and the reuse of air, and is also convenient for collecting slag in the fume.
[0028] Secondly, the welding workshop fume treatment system of the present invention can further clean the fume through the spray device and cool the fume, thereby ensuring that the waste gas can meet the emission requirements.
[0029] Thirdly, the welding workshop fume treatment system of the present invention ensures the fume filtering effect through the filter plate and the flexible filter cloth.
[0030] Fourthly, the welding workshop fume treatment system of the present invention supplies water to the spray device through the overflow tank, thereby ensuring the cleanliness of the spray water and further ensuring the cleaning effect of the spray water.
[0031] Fifth, the welding workshop fume treatment system of the present invention controls the connection and disconnection of the closed plug plate and the auxiliary plug plate through the connecting device, thereby facilitating the slag discharge operation of the slag discharge trough.
[0032] Sixth, the welding workshop fume treatment system of the present invention, through the action of the baffle, prevents the spray water of the spray device from dripping directly into the overflow tank, thereby ensuring that the water in the overflow tank is obtained by the overflow of water from the fume water washing area, thereby ensuring that the amount of water returned from the fume water washing area, the overflow tank and the spray reaches a relative circulation balance state.
[0033] Seventh, the welding workshop fume treatment system of the present invention reduces the dripping speed of the spray liquid sprayed by the spray device through the action of the drip plate, thereby further ensuring the spray cleaning effect and cooling effect of the spray liquid on the air after water washing. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] Figure 1 It is a top view schematic diagram of the present invention.
[0035] Figure 2 It is an enlarged schematic diagram of the front cross-section of the flue gas treatment tower of the present invention.
[0036] Figure 3 It is an enlarged schematic diagram of the front cross-section of the buffer substrate. DETAILED DESCRIPTION
[0037] Combination Figure 1~Figure 3 It can be seen that the fume treatment system of the welding workshop includes a fume hood 1 arranged on the top of each welding station in the welding workshop, the fume hood 1 is respectively connected to the fume exhaust pipe 2, the fume exhaust pipe 2 is connected to the bottom of the fume treatment tower 3 through a negative pressure fan A, the top of the fume treatment tower 3 is connected to an outlet pipe 4 through a fan B, the outlet pipe 4 is respectively connected to the blowing pipe 5 and the exhaust pipe 6 through a three-way pipe A, valves are respectively provided at the connection between the blowing pipe 5 and the exhaust pipe 6 and the three-way pipe A, the blowing pipe 5 is respectively connected to the blowing port 8 of each welding station in the welding workshop, the exhaust pipe 6 is discharged to the outside atmosphere, and a slag discharge trough 7 is connected to one side of the bottom of the fume treatment tower 3.
[0038] The bottom of the slag trough 7 is lower than the bottom of the flue gas treatment tower 3. The bottom 21 of the flue gas treatment tower 3 is inclined downward in the direction facing the slag trough 7 and extends to the bottom of the slag trough 7. A closed plug plate 22 is provided on the tower wall of the flue gas treatment tower 3 facing the slag trough 7 and within the height range of the trough wall of the slag trough 7. The closed plug plate 22 reciprocates between the flue gas treatment tower 3 and the slag trough 7 through a hydraulic piston cylinder 23. The hydraulic piston cylinder 23 is located on the side of the slag trough 7 facing away from the flue gas treatment tower 3. The piston rod end of the hydraulic piston cylinder 23 is fixedly connected with an auxiliary plug plate 24 matching the closed plug plate 22. The side wall of the auxiliary plug plate 24 facing the closed plug plate 22 is connected and fixed to the corresponding side wall of the closed plug plate 22 through a plug plate connecting device. The connecting device controls the connection and separation of the closed plug plate 22 and the auxiliary plug plate 24.
[0039] In the flue gas treatment tower 3, horizontal supporting bars with closed plug plates 22 are respectively provided corresponding to the side walls facing and facing away from the slag discharge trough 7. A partition vertical plate 11 is provided on the side wall of the flue gas treatment tower 3 facing away from the slag discharge trough 7 and above the horizontal supporting bars. The bottom of the partition vertical plate 11 is sealed and fixedly connected to the side wall via a connecting cross plate. The two side walls of the partition vertical plate 11 are sealed and fixedly connected to the corresponding side walls of the flue gas treatment tower 3 respectively. An overflow trough 13 is formed between the partition vertical plate 11 and the side wall and the adjacent side wall. A flue gas water washing area 12 is formed at the lower part of the flue gas treatment tower 3 and located outside the partition vertical plate 11. A spray device 14 is also provided on the top of the flue gas treatment tower 3. The liquid inlet pipe 15 of the spray device 14 is connected to the bottom of the overflow trough 13 through a liquid pump A16. The gas outlet end of the flue gas exhaust pipe 2 is connected to the side wall of the flue gas treatment tower 3 located within the range of the flue gas water washing area 12 and extends into the flue gas water washing area 12.
[0040] In the flue gas washing area 12 , above the outlet end of the flue gas exhaust pipe 2 , a filter plate and a flexible filter cloth 33 are fixedly arranged in sequence from bottom to top, and the flexible filter cloth 33 is fixedly connected to the corresponding position on the top of the partition vertical plate 11 .
[0041] The filter plates include the coarse filter plate 30, the middle filter plate 31 and the fine filter plate 32 from bottom to top. The coarse filter plate 30 has one layer, the middle filter plate 31 has multiple layers, and the fine filter plate 32 has one layer.
[0042] The coarse filter plate 30 is a curved plate, and the surface of the curved plate is provided with protrusions 36 and depressions 35 distributed at intervals, and a plurality of filter holes 37 are evenly distributed on the top of the protrusions 36 .
[0043] Adjacent protrusions 36 and recesses 35 are connected by smooth transition.
[0044] The middle filter plate 31 is a wire mesh plate, and the fine filter plate 32 is a mesh plate. The diameter of the mesh B of the mesh plate is smaller than the diameter of the mesh A of the wire mesh plate.
[0045] The flexible filter cloth 33 is a gauze mesh.
[0046] A gap is arranged between the bottom of the side wall of the flue gas treatment tower 3 facing the slag trough 7 and the corresponding position of the tower bottom 21 , and the bottom of the flue gas treatment tower 33 facing the slag trough 7 is lower than the closed plug plate 22 .
[0047] The slag trough 7 is connected to the flue gas water washing zone 12 through a liquid pump B29, and a pipe mouth A27 of a liquid suction pipe of the liquid pump B29 is located at the bottom of the side wall of the slag trough 7 corresponding to the flue gas treatment tower 3 facing the slag trough 7; a pipe mouth B28 of a liquid discharge pipe of the liquid pump B29 is located in the flue gas water washing zone 12, within the range between the closed plug plate 22 and the filter plate.
[0048] A vent pipe 26 is provided in the side wall of the flue gas treatment tower 3 facing the slag trough 7, and a matching socket is provided on the trough wall of the flue gas treatment tower 3 facing the slag trough 7 corresponding to the closed plug plate 22. The vent pipe 26 includes a vent pipe unit A and a vent pipe unit B. The lower pipe opening A of the vent pipe unit A extends from the side wall at the lower position of the closed plug plate 22, and the upper pipe opening A of the vent pipe unit A is connected with the socket from the bottom of the socket. The upper pipe opening B of the vent pipe unit B extends outward from the side wall at the upper position of the slag trough 7, and the lower pipe opening B of the vent pipe unit B is connected with the socket from the top of the socket. The closed plug plate 22 is provided with a vent pipe unit C corresponding to the vent pipe 26. When the closed plug plate 22 is fully inserted into the flue gas treatment tower 3, the vent pipe unit C is respectively connected with the vent pipe unit A and the vent pipe unit B, so that the vent pipe 26 is connected.
[0049] The outlet end of the flue gas exhaust pipe 2 located in the flue gas water washing area 12 is connected and fixed with an outlet nozzle 20, which is located above the closed plug plate 22. The outlet direction of the outlet nozzle 20 is upward, and the outlet nozzle 20 is a spherical surface with multiple outlet holes evenly distributed on the spherical surface.
[0050] A baffle A17 is fixedly connected inside the flue gas treatment tower 3, on the side wall corresponding to the bottom connection of the partition plate 11, and above the overflow tank 13. The two ends of the baffle A17 are respectively sealed and fixedly connected to the side walls of the flue gas treatment tower 3 connected to both sides of the partition plate 11. The baffle A17 is inclined downward along the side facing the flue gas water washing area 12, and the bottom end of the baffle A17 is located within the range of the flue gas water washing area 12.
[0051] The baffle A17 is provided with multiple rows of ventilation holes 18, and baffles B19 are respectively provided on the top surface of the baffle A17 and above each row of ventilation holes 18. The baffles B19 are inclined downward along the side facing the flue gas water washing zone 12, and the bottom edges of the baffles B19 are respectively located on the side of the corresponding ventilation holes 18 facing the flue gas water washing zone 12, and the slope of the baffle B19 is smaller than the slope of the baffle A17.
[0052] A plurality of drip plates 34 are provided in the flue gas treatment tower 3 between the spray device 14 and the partition plate 11 .
[0053] The height difference between the spray device 14 and the topmost drip plate 34 is equal to the height difference between two adjacent drip plates 34 .
[0054] A slot 25 matching the closed plug plate 22 is formed between the bottom of the partition vertical plate 11 and the horizontal beams provided on the corresponding side panels of the flue gas treatment tower 3.
[0055] The liquid inlet pipe 15 is pre-buried and fixed in the side wall of the flue gas treatment tower 3, and the liquid inlet pipe 15 is also connected to an external water inlet device through a three-way pipe B.
[0056] When the hydraulic piston rod is fully extended out of the hydraulic piston cylinder 23, the auxiliary plug plate 24 closes the notch of the slag trough 7, and the closing plug plate 22 is fully inserted into the flue gas treatment tower 3 through the auxiliary plug plate 24; when the hydraulic piston rod is fully retracted into the hydraulic piston cylinder 23, the auxiliary plug plate 24 is completely separated from the slag trough 7. At this time, when the closing plug plate 22 is fixed to the auxiliary plug plate 24 through the connecting device, the closing plug plate 22 closes the notch of the slag trough 7.
[0057] The air blowing pipe 5 is connected and communicated with the air blowing port 8 through the air blowing manifold 9 . The air blowing manifold 9 is provided with a heating device 10 . The heating device 10 heats the air passing through the air blowing manifold 9 .
[0058] When the present application is used, first, the closing plug plate 22 is fixed to the auxiliary plug plate 24 through the connecting device, and then the hydraulic piston rod of the hydraulic piston cylinder 23 together with the auxiliary plug plate 24 and the closing plug plate 22 are retracted into the hydraulic piston cylinder 23 to the maximum stroke. At this time, the closing plug plate 22 closes the slag discharge trough 7; then the exhaust pipe 6 is connected to the exhaust pipe 4 of the flue gas treatment tower 3, and then the water of the external water inlet device is sprayed into the flue gas treatment tower 3 from the spray device 14 through the liquid pump A16; when the liquid level in the flue gas water washing area 12 of the flue gas treatment tower 3 reaches the top of the partition plate 11, the water in the flue gas water washing area 12 begins to overflow into the overflow tank 13, and when the liquid in the overflow tank 13 When the surface reaches half the height of the overflow tank 13; then the liquid pump A16 closes the external water inlet device, and connects the spray device 14 with the water in the overflow tank 13 through the liquid inlet pipe 15 for cyclic spraying; the welding fume generated by the welding station at the corresponding position of the fume hood 1 is sucked out by the negative pressure fan A, and then introduced into the fume treatment tower 3, and the fume is evenly discharged through the air outlet nozzle 20; the fume located in the fume water washing area 12 is filtered in multiple layers through the coarse filter plate 30, the medium filter plate 31, the fine filter plate 32 and the flexible filter cloth 33 in turn, so that the solid particles in the fume are blocked, and the clean air leaves the fume water washing area 12 and continues to move upward; and passes through the spray device 1 4 is sprayed to cool down, thereby excluding the flue gas treatment tower 3; after the solid particles in the flue gas are blocked, they gradually settle to the tower bottom 21 due to gravity, and continue to fall downward along the tower bottom 21 to the bottom of the slag trough 7; when there is a lot of slag material accumulated at the bottom of the slag trough 7, the hydraulic piston rod of the hydraulic piston cylinder 23, together with the auxiliary plug plate 24 and the closed plug plate 22, extends to the maximum stroke. At this time, the closed plug plate 22 divides the flue gas treatment tower 3 into two parts, the upper part of the closed plug plate 22 can still be used for normal water washing of the flue gas, and the area below the closed plug plate 22 in the flue gas treatment tower 3 is tightly connected to the slag trough 7; finally, by connecting The device disengages the closed plug plate 22 from the auxiliary plug plate 24, and drives the auxiliary plug plate 24 to retreat to the maximum stroke through the hydraulic piston rod of the hydraulic piston cylinder 23, thereby facilitating the slag discharge from the slag discharge trough 7; when discharging slag, it is necessary to first pump out the water in the slag discharge trough 7, and through the action of the liquid pump B29, the water on the top surface of the slag discharge trough 7 is pumped to the flue gas water washing area 12 located above the closed plug plate 22 in the flue gas treatment tower 3, and the area below the closed plug plate 22 in the flue gas treatment tower 3 is also connected to the outside atmosphere through the ventilation pipe 26, so that the water in the treatment tower 3 connected to the slag discharge trough 7 can be smoothly pumped away; after the water in the slag discharge trough 7 is pumped out, the slag in the slag discharge trough 7 can be directly dug out.During use, after the blowing pipe 5 is connected to the outlet pipe 4 of the flue gas treatment tower 3, the clean air treated by the flue gas treatment tower 3 can also be blown to the welding station in the welding workshop, thereby ensuring the air quality of the welding workshop; when the temperature in the welding workshop is low, the air passing through the blowing manifold 9 can also be heated by the heating device 10, and then warm air can be blown out.
Claims
1. Welding workshop fume treatment system, characterized by: The invention comprises a fume hood (1) arranged on the top of each welding station in a welding workshop, wherein the fume hood (1) is respectively connected to a fume exhaust pipe (2), wherein the fume exhaust pipe (2) is connected to the bottom of a fume treatment tower (3) through a negative pressure fan A, wherein an air outlet pipe (4) is arranged on the top of the fume treatment tower (3) through a fan B, wherein the air outlet pipe (4) is respectively connected to an air blowing pipe (5) and an exhaust pipe (6) through a three-way pipe A, wherein valves are respectively arranged at the connection points between the air blowing pipe (5) and the exhaust pipe (6) and the three-way pipe A, wherein the air blowing pipe (5) is respectively connected to an air blowing port (8) of each welding station in the welding workshop, wherein the exhaust pipe (6) is discharged to the outside atmosphere, and wherein one side of the bottom of the fume treatment tower (3) is connected to a slag discharge trough (7); The bottom of the slag discharge trough (7) is lower than the bottom of the flue gas treatment tower (3); the bottom (21) of the flue gas treatment tower (3) is inclined downward in a direction facing the slag discharge trough (7) and extends to the bottom of the slag discharge trough (7); a closed plug plate (22) is provided on the tower wall of the flue gas treatment tower (3) facing the slag discharge trough (7) and within the height range of the trough wall of the slag discharge trough (7); the closed plug plate (22) is connected between the flue gas treatment tower (3) and the slag discharge trough (7) by a hydraulic piston cylinder (23). ), the hydraulic piston cylinder (23) being located on a side of the slag discharge trough (7) facing away from the flue gas treatment tower (3), the piston rod end of the hydraulic piston cylinder (23) being fixedly connected to an auxiliary plug plate (24) matching the closed plug plate (22), the side wall of the auxiliary plug plate (24) facing the closed plug plate (22) being connected and fixed to the corresponding side wall of the closed plug plate (22) via a plug plate connecting device, the connecting device controlling the connection and separation of the closed plug plate (22) and the auxiliary plug plate (24); The flue gas treatment tower (3) is provided with horizontal bars of closed plug plates (22) on the side walls facing and facing away from the slag discharge trough (7), and a partition plate (11) is provided on the side wall facing away from the slag discharge trough (7) of the flue gas treatment tower (3) above the horizontal bars. The bottom of the partition plate (11) is sealed and fixedly connected to the side wall via a connecting cross plate, and the two side walls of the partition plate (11) are sealed and fixedly connected to the corresponding side walls of the flue gas treatment tower (3). The partition plate (11) is connected to the side wall and the corresponding side wall. An overflow tank (13) is formed between adjacent side walls, a flue gas water washing zone (12) is formed in the lower part of the flue gas treatment tower (3) and located outside the partition vertical plate (11), a spray device (14) is also provided at the top of the flue gas treatment tower (3), a liquid inlet pipe (15) of the spray device (14) is connected to the bottom of the overflow tank (13) through a liquid pump A (16), and an outlet end of the flue gas extraction pipe (2) is connected to the side wall of the flue gas treatment tower (3) located within the flue gas water washing zone (12) and extends into the flue gas water washing zone (12); A filter plate and a flexible filter cloth (33) are fixedly arranged in sequence from bottom to top in the flue gas water washing area (12), located above the gas outlet end of the flue gas extraction pipe (2), and the flexible filter cloth (33) is fixedly connected to a corresponding position on the top of the partition vertical plate (11); A plurality of drip plates (34) are provided in the flue gas treatment tower (3) between the spray device (14) and the partition stand (11).
2. The welding workshop fume treatment system according to claim 1, characterized in that: The outlet end of the smoke exhaust pipe (2) located in the smoke water washing area (12) is connected to and fixed with an outlet nozzle (20), the outlet nozzle (20) is located above the closed plug plate (22), the outlet direction of the outlet nozzle (20) is upward, and the outlet nozzle (20) is a spherical surface with a plurality of outlet holes evenly distributed on the surface of the spherical surface.
3. The welding workshop fume treatment system according to claim 1, characterized in that: A baffle A (17) is fixedly connected inside the flue gas treatment tower (3), on a side wall corresponding to the bottom of the partition vertical plate (11), and located above the overflow tank (13); both ends of the baffle A (17) are respectively sealed and fixedly connected to the side walls of the flue gas treatment tower (3) connected to both sides of the partition vertical plate (11); the baffle A (17) is tilted downward along a side facing the flue gas water washing zone (12), and the bottom end of the baffle A (17) is located within the range of the flue gas water washing zone (12).
4. The welding workshop fume treatment system according to claim 1, characterized in that: A slot (25) matching the closed plug plate (22) is formed between the bottom of the partition upright plate (11) and the horizontal beams provided on the corresponding side panels of the flue gas treatment tower (3).
5. The welding workshop fume treatment system according to claim 1, characterized in that: The liquid inlet pipe (15) is pre-buried and fixed in the side wall of the flue gas treatment tower (3), and the liquid inlet pipe (15) is also connected to an external water inlet device through a three-way pipe B.
6. The welding workshop fume treatment system according to claim 1, characterized in that: When the hydraulic piston rod is fully extended out of the hydraulic piston cylinder (23), the auxiliary plug plate (24) closes the notch of the slag discharge groove (7), and the closing plug plate (22) is fully inserted into the flue gas treatment tower (3) through the auxiliary plug plate (24); when the hydraulic piston rod is fully retracted into the hydraulic piston cylinder (23), the auxiliary plug plate (24) is completely separated from the slag discharge groove (7), and at this time, when the closing plug plate (22) is fixed to the auxiliary plug plate (24) through the connecting device, the closing plug plate (22) closes the notch of the slag discharge groove (7).