A kind of electroosmotic waterproof wall for foundation pit in water-rich area and its construction method
By installing an electropermeable wall at the bottom of the foundation pit and using an electric field water-stop curtain to prevent groundwater infiltration, the problem of waste of groundwater resources in traditional waterproofing methods is solved, and effective waterproofing and groundwater resource protection are achieved in water-rich areas.
Patent Information
- Application Number
- CN202011582432.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-12-28
- Publication Date
- 2024-10-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Traditional foundation pit waterproofing methods require continuous pumping and drainage of groundwater in water-rich areas, resulting in waste of groundwater resources, high energy consumption, and excessive surface settlement, affecting surrounding buildings.
An electro-osmotic wall is used, including several electro-osmotic plates and electro-osmotic blocks. The conductive plates form an electric field water-stopping curtain at the bottom of the foundation pit, which is energized and waterproof. After a power outage, the groundwater flow is restored and the groundwater resources are protected.
Effectively prevent groundwater from seeping into foundation pits, avoid excessive pumping, protect groundwater resources, adapt to complex geological conditions, reduce energy consumption and costs, and reduce surface subsidence.
Smart Images

Figure CN112681351B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to an electro-osmosis waterproof wall for a foundation pit in a water-rich area and a construction method thereof. Background Art
[0002] In traditional water-rich pressure-bearing areas, waterproofing is generally done by setting up water-stop curtains on the side walls of the foundation pit, combining the water-stop curtains with support, separating the groundwater within the foundation pit from the groundwater system outside the foundation pit, forming an independent water zone, and using precipitation wells to pump and drain water during the precipitation process. However, in areas with more groundwater, karst fissure water is often widely distributed, the karst channels at the bottom of the foundation pit are complex, and sometimes the waterproof layer is thin, resulting in poor waterproofing effect at the bottom of the foundation pit. In order to achieve the effect of precipitation at the bottom of the foundation pit, the traditional water-stop curtain needs to combine the water-stop curtain with precipitation inside and outside the foundation pit at the same time to form a hydraulic slope to meet the groundwater level below the bottom of the foundation pit to meet the construction requirements. However, this method requires continuous pumping of groundwater, which causes a huge waste of groundwater resources and brings huge hidden dangers to some areas that need groundwater protection. In addition, continuous pumping of groundwater requires a lot of energy and will lead to excessive waste of groundwater resources. In the process of excessive pumping of groundwater, it will cause excessive surface settlement and have a great impact on surrounding buildings. Summary of the invention
[0003] The purpose of the present invention is to provide an electro-osmosis waterproof wall for foundation pits in water-rich areas and a construction method thereof, so as to overcome the disadvantage that the existing foundation pits use a precipitation method of continuously extracting groundwater, which causes a huge waste of groundwater resources.
[0004] To achieve the above-mentioned purpose, the present invention provides an electro-osmotic waterproof wall for foundation pits in water-rich areas, comprising: an electro-osmotic wall, which includes a plurality of electro-osmotic plates, wherein the plurality of electro-osmotic plates are arranged at intervals at the bottom of the foundation pit to be excavated, each of the electro-osmotic plates includes a plurality of electro-osmotic blocks spliced with each other, each of the electro-osmotic blocks includes a frame and two conductive plates, wherein one conductive plate is respectively provided at the top and the bottom of the frame, wherein the conductive plate located at the top of the frame is an anode plate, and the other conductive plate is a cathode plate; and a power supply device, which is electrically connected to the electro-osmotic wall through a transmission line.
[0005] Preferably, in the above technical solution, each of the electro-osmosis blocks is connected to the transmission line, and the transmission line includes an anode transmission line and a cathode transmission line. The anode plate of each electro-osmosis block is connected to the anode transmission line, and the cathode plate is connected to the cathode transmission line, and each of the electro-osmosis blocks is connected to the power supply device through the anode transmission line and the cathode transmission line.
[0006] Preferably, in the above technical solution, each of the electro-osmosis blocks is provided with a plurality of evenly distributed water-permeable holes.
[0007] Preferably, in the above technical solution, the frame of each electroosmosis block is a rectangular parallelepiped frame structure.
[0008] Preferably, in the above technical solution, the frame of each electro-osmosis block is a concrete structure.
[0009] A construction method for an electroosmotic waterproof wall for a foundation pit in a water-rich area comprises the following steps:
[0010] (1) Construction preparation: Conduct geological surveys to find out the geological conditions and groundwater distribution of the foundation pit to be excavated and its surroundings, and prepare electroosmotic blocks in advance;
[0011] (2) Excavation of working wells: Excavate working wells at fixed points at a certain distance around the foundation pit where there is no groundwater distribution;
[0012] (3) Installing the electro-osmotic wall: At the bottom of each working well, the electro-osmotic blocks of each electro-osmotic plate are pushed into the bottom of the foundation pit one by one by a pipe jacking machine. After all the electro-osmotic plates are installed in place, a transmission line is used to pass through the corresponding working well to connect all the electro-osmotic plates to the power supply device;
[0013] (4) Excavation of foundation pit: Before excavation of the foundation pit, backfill all working pits and set up water-stop curtains on the side walls of the foundation pit. Then, with the electro-osmosis wall energized, excavate the foundation pit and make a foundation pit floor plate at the bottom of the foundation pit to seal the bottom of the foundation pit. Finally, disconnect the power supply of the electro-osmosis wall.
[0014] Compared with the prior art, the present invention has the following beneficial effects:
[0015] 1. The electro-osmotic wall of the present invention comprises a plurality of electro-osmotic plates, which are arranged at intervals at the bottom of a foundation pit to be excavated. When the foundation pit is excavated, electricity can be turned on for waterproofing. The formed electric field waterproof curtain can cover the entire foundation pit, and can effectively prevent groundwater from seeping into the foundation pit. It can also play a waterproofing effect even in places where the electro-osmotic wall is not laid, avoiding excessive pumping of groundwater. After power failure, the intervals between the electro-osmotic plates can allow groundwater to flow, restore the flow direction of groundwater, and effectively protect groundwater resources. It can adapt to various complex geological conditions and environmental conditions, especially under geological conditions where pressurized water and karst fissure water are relatively abundant, the waterproofing effect is particularly significant.
[0016] 2. The frame of each electro-osmosis block of the present invention is a concrete structure, which improves the overall strength of the electro-osmosis block and ensures its strength index during the jacking operation. After being buried in the soil at the bottom of the foundation pit, it can bear the upper water pressure and upper soil pressure to ensure the normal operation of the electro-osmosis wall.
[0017] 3. The construction method of the electro-osmotic wall of the present invention is simple and convenient. Before the foundation pit is excavated, the electro-osmotic wall is installed first. During the excavation of the foundation pit, the electro-osmotic wall remains energized and waterproof, preventing external groundwater from entering the foundation pit and keeping the groundwater below the designed elevation. After the construction at the bottom of the foundation pit is completed, the power supply is stopped to restore the original fluidity of the groundwater and protect the groundwater resources. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic structural diagram of the electro-osmotic waterproof wall for foundation pits in water-rich areas according to the present invention.
[0019] Figure 2 According to the present invention Figure 1 Section view along line AA.
[0020] Figure 3 Schematic diagram of the structure of the electroosmosis block according to the present invention.
[0021] Figure 4 According to the present invention Figure 3 Schematic top view of .
[0022] Description of main reference numerals:
[0023] 1- ground, 2- groundwater level, 3- water-stop curtain, 4- groundwater level after precipitation, 5- groundwater level in foundation pit, 6- electro-osmosis plate, 7- working well, 8- cathode transmission line, 9- anode transmission line, 10- power supply device, 11- foundation pit, 12- water-permeable hole, 13- conductive plate, 14- frame. DETAILED DESCRIPTION
[0024] The specific implementation modes of the present invention are described in detail below in conjunction with the accompanying drawings, but it should be understood that the protection scope of the present invention is not limited by the specific implementation modes.
[0025] Unless explicitly stated otherwise, throughout the specification and claims, the term “comprise” or variations such as “include” or “comprising”, etc., will be understood to include the stated elements or components but not to exclude other elements or components.
[0026] Figures 1 to 4 The schematic diagram of the structure of an electroosmotic waterproof wall for a foundation pit in a water-rich area according to a preferred embodiment of the present invention is shown, and the electroosmotic waterproof wall includes an electroosmotic wall and a power supply device 10. Figure 1 and Figure 4The electro-osmotic wall includes a plurality of electro-osmotic plates 6, which are arranged at intervals at the bottom of a foundation pit 11 to be excavated. Each electro-osmotic plate 6 includes a plurality of electro-osmotic blocks spliced together. Each electro-osmotic block includes a frame 14 and two conductive plates 13. A conductive plate 13 is respectively provided at the top and the bottom of the frame 14, wherein the conductive plate 13 located at the top of the frame 14 is an anode plate, and the other conductive plate 13 is a cathode plate. The power supply device 10 is connected to the electro-osmotic wall through a transmission line to supply power to the electro-osmotic wall. The electro-osmotic wall of the present invention can be energized for waterproofing when the foundation pit 11 is excavated. The formed electric field water-stopping curtain can cover the entire foundation pit 11, and can effectively prevent groundwater from seeping into the foundation pit 11. It can also play a water-stopping effect even in places where the electro-osmotic wall is not laid, so as to reduce the groundwater level 5 in the foundation pit to below the design elevation, that is, after the electro-osmotic wall is energized, the groundwater level 5 in the foundation pit can be reduced to the groundwater level 4 after precipitation, and the groundwater level 4 after precipitation is located below the design elevation, avoiding excessive pumping of groundwater; after power failure, the gaps between the electro-osmotic plates 6 can be used for groundwater flow, restoring the groundwater flow direction, effectively protecting groundwater resources, and being able to adapt to various complex geological conditions and environmental conditions, especially under geological conditions where pressurized water and karst fissure water are relatively abundant, the effect is particularly significant.
[0027] refer to Figures 1 to 4 Preferably, each electro-osmosis block is connected to a transmission line, and the transmission line includes an anode transmission line 9 and a cathode transmission line 8. The anode plate of each electro-osmosis block is connected to the anode transmission line 9, and the cathode plate is connected to the cathode transmission line 8. Each electro-osmosis block is connected to the power supply device 10 through the anode transmission line 9 and the cathode transmission line 8, that is, each electro-osmosis block is connected to the anode transmission line 9 and the cathode transmission line 8, and is connected to the power supply device 10 through the anode transmission line 9 and the cathode transmission line 8, so as to facilitate the individual control of the power on and off of each electro-osmosis block.
[0028] refer to Figure 3 and Figure 4 Preferably, the frame 14 of each electroosmosis block is a rectangular frame structure to facilitate the installation of the electroosmosis block, and the frame 14 of each electroosmosis block is a concrete structure, that is, the two conductive plates 13 of each electroosmosis block are symmetrically arranged up and down, and the edges of the rectangular block surrounded by the two conductive plates 13 are cast in concrete to improve the overall strength of the electroosmosis block and ensure its strength index during the jacking operation. After being buried in the soil, it can bear the upper water pressure and the upper soil pressure to ensure the normal operation of the electroosmosis wall.
[0029] refer to Figure 3 and Figure 4Preferably, each electro-osmosis block is provided with a number of evenly distributed water holes 12, that is, each electro-osmosis block is provided with water holes 12 on the upper and lower conductive plates 13, so as to facilitate the circulation of groundwater. After the construction of the foundation pit 11 is completed, the power supply of the electro-osmosis wall is disconnected to further improve the fluidity of the groundwater, restore the groundwater to its original flow direction, and avoid damaging the groundwater resources.
[0030] refer to Figures 1 to 4 , a construction method for electroosmotic waterproof wall of foundation pit in water-rich area, comprising the following steps:
[0031] (1) Construction preparation: Conduct geological surveys to ascertain the geological conditions and groundwater distribution of the foundation pit 11 to be excavated and its surroundings, determine the approximate depth of the groundwater level 3, and set the specific depth of the bottom plate to be waterproofed according to the foundation pit construction design drawing, that is, according to actual needs, and pre-fabricate the electro-osmosis blocks according to the foundation pit construction design drawing.
[0032] (2) Excavation of working well 7: A fixed point is set at a certain distance around the foundation pit 11 where there is no groundwater distribution, and the working well 7 is excavated at the fixed point.
[0033] (3) Installing the electro-osmotic wall: At the bottom of each working well 7, the electro-osmotic blocks of each electro-osmotic plate 6 are pushed into the bottom of the foundation pit 11 one by one by a pipe jacking machine. After all the electro-osmotic plates 6 are installed in place, a transmission line is used to pass through the corresponding working well 7 to connect all the electro-osmotic plates 6 to the power supply device 10.
[0034] (4) Excavation of foundation pit 11: Before excavating foundation pit 11, backfill all working wells 7. During the backfilling process, pay attention to the protection of the power transmission lines and compact the backfill soil in accordance with regulations. Set a water-stop curtain 3 on the side wall of foundation pit 11 to form a closed space with the electro-osmotic wall at the bottom. Then, when the electro-osmotic wall is energized, excavate foundation pit 11, make a foundation pit floor plate at the bottom of foundation pit 11, seal the bottom of foundation pit 11, and finally disconnect the power supply of electro-osmotic wall.
[0035] refer to Figures 1 to 4 Preferably, in step (2), when excavating the working well 7 along the periphery of the foundation pit 11, lining and support should be promptly applied in the working well 7 to prevent the working well 7 from collapsing. The diameter of the excavated working well 7 is not less than 2m, and the distance between two adjacent working wells 7 is not less than 20m.
[0036] refer to Figures 1 to 4Preferably, in step (3), each electro-osmotic block is connected to a power transmission line. When each electro-osmotic block of the electro-osmotic plate 6 is installed one by one from the bottom of the working well 7 to the bottom of the foundation pit 11, the power transmission line of each electro-osmotic block is distributed along the installation hole of the pipe jacking machine. After all the electro-osmotic blocks are installed, the power transmission lines of all the electro-osmotic blocks are extended through the corresponding working wells 7 to the ground 1 to facilitate connection with the power supply device 10, and then the installation holes are blocked; wherein, the pushing pressure of the pipe jacking machine is not greater than 100T, and the pushing speed is not greater than 5mm / min.
[0037] By adopting the electro-osmotic waterproof wall and the construction method thereof of the present invention, the electro-osmotic wall at the bottom of the foundation pit 11 can be energized for drainage, and there is no need to continuously pump out groundwater, thereby reducing energy consumption and costs, preventing large-scale surface subsidence, and improving safety performance. After the electro-osmotic wall is disconnected from power supply, the gaps between the electro-osmotic plates 6 and the water-permeable holes 12 on the electro-osmotic plates 6 can be used for groundwater flow, thereby restoring the original flow direction of the groundwater and protecting groundwater resources. This has significant advantages in areas with high demand for groundwater protection.
[0038] The foregoing description of specific exemplary embodiments of the present invention is for the purpose of illustration and demonstration. These descriptions are not intended to limit the present invention to the precise form disclosed, and it is clear that many changes and variations can be made based on the above teachings. The purpose of selecting and describing the exemplary embodiments is to explain the specific principles of the present invention and its practical application, so that those skilled in the art can realize and utilize various different exemplary embodiments of the present invention and various different selections and changes. The scope of the present invention is intended to be limited by the claims and their equivalents.
Claims
1. An electroosmotic waterproof wall for foundation pits in water-rich areas. It is characterized in that include: An electroosmotic wall, comprising a plurality of electroosmotic plates, wherein the plurality of electroosmotic plates are arranged at intervals at the bottom of a foundation pit to be excavated, wherein each of the electroosmotic plates comprises a plurality of electroosmotic blocks spliced together, wherein each of the electroosmotic blocks comprises a frame and two conductive plates, wherein one conductive plate is disposed at the top and the bottom of the frame, respectively, wherein the conductive plate at the top of the frame is an anode plate, and the other conductive plate is a cathode plate; and A power supply device, which is electrically connected to the electro-osmotic wall via a transmission line; Wherein, each of the electro-osmosis blocks is connected to the transmission line, and the transmission line includes an anode transmission line and a cathode transmission line. The anode plate of each electro-osmosis block is connected to the anode transmission line, and the cathode plate is connected to the cathode transmission line. Each of the electro-osmosis blocks is connected to the power supply device through the anode transmission line and the cathode transmission line. Wherein, each of the electro-osmotic blocks is provided with a plurality of evenly distributed water-permeable holes.
2. The electroosmotic waterproof wall for foundation pit in water-rich areas according to claim 1, It is characterized in that The frame of each electroosmosis block is a rectangular parallelepiped frame structure.
3. The electroosmotic waterproof wall for foundation pit in water-rich areas according to claim 1, It is characterized in that The frame of each electro-osmosis block is a concrete structure.
4. A construction method for the electroosmotic waterproof wall of a foundation pit in a water-rich area as claimed in claim 1, It is characterized in that The following steps are involved: (1) Construction preparation: Conduct geological surveys to find out the geological conditions and groundwater distribution of the foundation pit to be excavated and its surroundings, and prepare electroosmotic blocks in advance; (2) Excavation of working wells: Excavate working wells at fixed points at a certain distance around the foundation pit where there is no groundwater distribution; (3) Installing the electro-osmotic wall: At the bottom of each working well, the electro-osmotic blocks of each electro-osmotic plate are pushed into the bottom of the foundation pit one by one by a pipe jacking machine. After all the electro-osmotic plates are installed in place, a transmission line is used to pass through the corresponding working well to connect all the electro-osmotic plates to the power supply device; (4) Excavation of foundation pit: Before excavation of the foundation pit, backfill all working pits and set up water-stop curtains on the side walls of the foundation pit. Then, with the electro-osmosis wall energized, excavate the foundation pit and make a foundation pit floor plate at the bottom of the foundation pit to seal the bottom of the foundation pit. Finally, disconnect the power supply of the electro-osmosis wall.