Prestressed anchoring device for concrete bridge and construction method thereof
By designing a prestressed anchoring device, the tensioning process of carbon fiber cloth is simplified by using a rectangular frame and jack system, the problems of complex structure and troublesome construction of carbon fiber cloth tensioning anchors in the prior art are solved, and efficient carbon fiber cloth fixing and bridges are achieved. Reinforcement effect.
Patent Information
- Application Number
- CN202110144634.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-02-02
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2041-02-02
AI Technical Summary
The existing carbon fiber cloth tension anchors have complex structures and are troublesome to construct, making it difficult to ensure the tensile strength and construction efficiency of carbon fiber cloth, resulting in poor bridge reinforcement effect.
A prestressed anchoring device for concrete bridges is designed, including a rectangular frame assembly, a fixing part and a tensioning part. The carbon fiber cloth is clamped through a clamping cloth shaft and a fixed base, and the tensioning top plate is pushed to move along the length of the rectangular frame by using a jack. Until the carbon fiber cloth is tensioned in place and tightened to the bridge construction surface to ensure effective fixation and tension of the carbon fiber cloth.
Simplified the tensioning process of carbon fiber cloth, improved the construction efficiency and clamping of carbon fiber cloth, ensured the maximum strength effect of carbon fiber cloth, solved the instability caused by uneven construction surfaces, and improved the quality and efficiency of bridge reinforcement. .
Smart Images

Figure CN112942145B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of concrete bridge reinforcement, and in particular to a prestressed anchoring device for a concrete bridge and a construction method thereof. Background Art
[0002] Reinforced concrete bridges account for a large proportion of existing bridges in my country, but their technical conditions are poor. On the one hand, due to the low design standards, except for the bridges built according to the design standards announced by the Ministry of Communications in 1972 and 1982, which can basically meet the recent traffic, most of the bridges built before that, especially in the late 1950s and 1960s, have been subjected to vehicle loads exceeding the design load for a long time; on the other hand, due to problems in bridge design, construction, maintenance, management, surrounding environment, and unexpected disasters suffered by bridges during use, such as earthquakes, floods, and accidental collisions, the existing reinforced concrete bridges have insufficient bearing capacity, a sharp decline in technical conditions, or aging, damage, cracks, etc., which has caused an increase in dangerous bridges and an increasing impact on driving. This has turned bridges into the bottleneck of highway transportation, seriously affecting the smooth flow of the entire route, and has also become a frequent site for traffic accidents.
[0003] Cracking of reinforced concrete bridges is a common phenomenon. The use of carbon fiber cloth to reinforce them is widely used in civil engineering. Carbon fiber cloth reinforcement has the advantages of high strength, high efficiency, convenient construction, high construction efficiency, no increase in structural deadweight and cross-sectional size, wide application and corrosion resistance. Pasting carbon fiber cloth on the outer surface of concrete will not destroy the original structural form, but also improve the bending, shear and compressive strength of the cross-section of concrete components. In addition, it can also have a certain restraining effect on the generation and development of cracks. When pasting carbon fiber cloth, it is necessary to ensure stability, accuracy and uniformity, so that the carbon fiber cloth is not wrinkled or folded, and the extension is smooth and smooth. However, the existing carbon fiber cloth tensioning anchor structure is relatively complex, and the construction is troublesome. It is difficult to ensure the tensile strength of the carbon fiber cloth and efficient bridge reinforcement work. Therefore, it is urgent to design a new technical solution to comprehensively solve the problems existing in the existing technology. Summary of the invention
[0004] The purpose of the present invention is to provide a prestressed anchoring device for concrete bridges and a construction method thereof, which can effectively solve the problems of complex structure, troublesome construction, difficulty in ensuring that the tensile strength of the carbon fiber cloth is fully utilized, and low construction efficiency of the existing carbon fiber cloth tensioning anchor.
[0005] In order to solve the above technical problems, the present invention adopts the following technical solutions:
[0006] A prestressed anchoring device for a concrete bridge comprises a frame assembly installed on a bridge construction surface, a fixing portion, a tensioning portion, and a carbon fiber cloth located between the fixing portion and the tensioning portion and closely attached to the bridge construction surface;
[0007] The frame assembly is a rectangular frame, and waist-shaped through holes are opened on both sides of the rectangular frame along its length direction. The tensioning part is located inside the rectangular frame and is slidably arranged along the length direction of the rectangular frame through the waist-shaped through holes; the fixing part is anchored on the bridge construction surface on the extension line of the rectangular frame length;
[0008] The fixing part and the tensioning part both include a clamping assembly, and the clamping assembly includes a cloth clamping shaft and a fixed base. Two cloth clamping shafts are provided, and the two cloth clamping shafts are spliced along their axial direction to form a cylinder, and the end of the carbon fiber cloth is clamped at the junction of the two cloth clamping shafts; the fixed base is located at both ends of the two cloth clamping shafts, clamps the two spliced cloth clamping shafts and limits the circumferential rotation of the two cloth clamping shafts, and an anchor hole for anchoring on the bridge construction surface is also provided on the fixed base;
[0009] The tensioning part also includes a tensioning top plate, which is installed on a side of the clamping assembly of the tensioning part close to the fixed part. A jack is installed between the tensioning top plate and the inner side of the rectangular frame. The jack pushes the tensioning top plate to move away from the fixed part. The tensioning top plate drives the clamping assembly of the tensioning part to move along the length direction of the rectangular frame until the carbon fiber cloth is tensioned into place; the fastening anchor bolt passes through the anchor hole of the fixed base of the tensioning part to anchor the tensioned clamping assembly of the tensioning part to the bridge construction surface.
[0010] Preferably, support legs for anchoring the bridge are provided at the four corners of the rectangular frame on the side close to the bridge construction surface, and the support legs support the rectangular frame to form a gap between the bridge construction surface and the rectangular frame; the two cloth clamping shafts of the tensioning part are located in the gap, and the two ends of the two cloth clamping shafts extend outside the rectangular frame, and the two ends of the cloth clamping shafts are respectively inserted into the fixed base and fixed to the bridge construction surface through the fixed base.
[0011] Preferably, a balancing through hole is opened in the tensioned top plate along the width direction of the rectangular frame for use with the waist-shaped through hole, a balancing shaft is inserted in the balancing through hole, and both ends of the balancing shaft extend into the corresponding waist-shaped through hole, and the balancing shaft drives the tensioned top plate to move along the length direction of the rectangular frame.
[0012] Preferably, the fixed base includes a base body and anchoring wing plates arranged on both sides of the base body for connecting to the bridge construction surface, and the anchor holes are opened on the anchoring wing plates; a square through hole is opened at the connection between the base body and the two cloth clamping shafts, the two cloth clamping shafts have the same shape, and square limit blocks are provided at both ends of the two cloth clamping shafts, and the square limit blocks are accommodated in the square through hole after the two cloth clamping shafts are spliced.
[0013] Preferably, a connecting hole is further provided on the square limiting block, and a connecting bolt for connecting the two cloth clamping shafts is inserted into the connecting hole.
[0014] Preferably, grooves for preventing the jack from shifting are provided on the tensioning top plate and the surface of the rectangular frame that contacts the jack.
[0015] Preferably, a fixing device is provided on the side of the tensioning top plate away from the jack, and the fixing device includes a fixing screw whose axial direction is consistent with the length direction of the rectangular frame. One end of the fixing screw is fixed to the tensioning top plate, and the other end passes through the rectangular frame, and the end is screwed with a flange nut.
[0016] The construction method of the above-mentioned prestressed anchoring device for concrete bridge comprises the following steps:
[0017] S1. Pre-treat the bridge construction surface, clamp one end of the carbon fiber cloth between the two cloth clamping shafts of the fixing part, rotate the cloth clamping shaft at least one circle along the circumference of the cloth clamping shaft to fix the carbon fiber cloth on the cloth clamping shaft, then install fixed bases at both ends of the cloth clamping shaft, and anchor the fixed bases on the bridge construction surface;
[0018] S2. Clamp the other end of the carbon fiber cloth between the two cloth clamping shafts of the tensioning part, rotate the cloth clamping shaft at least one circle along the circumference to fix the carbon fiber cloth on the cloth clamping shaft, then install fixed bases at both ends of the cloth clamping shaft, place the tensioning top plate on the fixed base, and finally install the rectangular frame on the assembled clamping assembly and the tensioning top plate;
[0019] S3. Straighten the carbon fiber cloth, anchor the rectangular frame assembled in step S2 on the bridge construction surface, and then install a jack between the tensioning top plate near the fixed part and the rectangular frame. The jack pushes the tensioning top plate to move away from the fixed part, and the tensioning top plate drives the clamping assembly of the tensioning part to move, thereby tensioning the carbon fiber cloth;
[0020] S4. After the carbon fiber cloth is tensioned in place, the fixed base of the tensioning part is anchored to the bridge construction surface. After the tensioning is completed, the carbon cloth is brushed with glue, and then the fixed part, rectangular frame and tensioning top plate are removed.
[0021] The prestressed anchoring device for concrete bridges provided in the above technical solution is provided with a frame assembly, a fixing part and a tensioning part, and the carbon fiber cloth is fixed between the tensioning part and the fixing part. In order to ensure the clamping of the carbon fiber cloth, two cloth clamping shafts spliced into a cylinder are provided, and the two cloth clamping shafts are clamped by a fixed base, so that the structure is simple and the carbon fiber cloth can be effectively fixed. When in use, one end of the carbon fiber cloth is firstly wound around the cloth clamping shaft of the fixing part, and fixed to the bridge construction surface by the fixed base, and then the other end of the carbon fiber cloth is wound around the cloth clamping shaft of the movable part, and the fixed base is installed, and finally a jack is provided between the tensioning top plate and the frame assembly, and the tensioning top plate is pushed by the jack to move along the length direction of the rectangular frame until the carbon fiber cloth is tensioned in place, and the movable part is fixed to the bridge construction surface to realize the tensioning of the carbon fiber cloth, and then the laying of the carbon fiber cloth is completed, and the maximum strength effect of the carbon fiber cloth is effectively exerted.
[0022] For bridge construction surfaces that are not flat enough, if surface contact is used, it may cause unstable connection. In order to solve this problem, the present invention arranges support legs on the side of the rectangular frame close to the bridge construction surface, and uses the support legs at the four corners to contact the bridge construction surface, which can effectively avoid the problem of unstable surface contact caused by the low flatness of the bridge construction surface.
[0023] In order to better cooperate with the rectangular frame, the present invention opens a balancing through hole in the tensioning top plate, and a balancing shaft is inserted in the balancing through hole. The balancing shaft is located in the waist-shaped through hole of the rectangular frame, driving the tensioning top plate to move along the length direction of the rectangular frame. The structure is simple to manufacture and highly detachable, and is extremely convenient for disassembly after the construction is completed. Similarly, a square through hole is opened on the base body of the fixed base, and square limit blocks are set at both ends of the cloth clamping shaft. When the two cloth clamping shafts are spliced, the square limit blocks are accommodated in the square through hole, and the square through hole is used to clamp them while limiting the rotation of the cloth clamping shaft along its circumferential direction, effectively fixing the carbon fiber cloth clamped in the cloth clamping shaft, and preparing for subsequent tensioning and pasting.
[0024] Finally, in order to improve the connection stability and accuracy of the two spliced cloth clamping shafts, the present invention opens a connection hole in the square limit block of the cloth clamping shaft, aligns and tightens the two cloth clamping shafts through connecting bolts, and further improves the clamping degree of the carbon fiber cloth; in addition, in order to prevent the jack from shifting during use, grooves are opened on the tensioning top plate and the rectangular frame, which can effectively ensure the construction stability and safety. In order to further improve the balance and stability of the tensioning top plate, the present invention also sets a fixing screw and a flange nut on the side of the tensioning top plate away from the jack to prevent the tensioning top plate from shifting and increase the stability of the tensioning process. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 This is a schematic structural diagram of the prestressed anchoring device for a concrete bridge according to the present invention;
[0026] Figure 2 It is a structural schematic diagram of the frame assembly and the tensioning part of the present invention;
[0027] Figure 3 It is a schematic diagram of the structure of the clamping assembly of the present invention;
[0028] Figure 4 It is a structural schematic diagram of the tensioned top plate of the present invention.
[0029] In the figure: 1. rectangular frame; 11. waist-shaped through hole; 12. supporting leg; 13. gap; 2. tensioning part; 21. tensioning top plate; 211. balancing through hole; 212. balancing shaft; 22. fixing screw; 221. flange nut; 3. carbon fiber cloth; 4. fixing part; 5. clamping assembly; 51. cloth clamping shaft; 511. square limit block; 512. connecting hole; 513. connecting bolt; 52. base body; 521. square through hole; 522. anchoring wing plate; 523. anchor hole; 6. groove. DETAILED DESCRIPTION
[0030] In order to make the purpose and advantages of the present invention more clearly understood, the present invention is specifically described below in conjunction with embodiments. It should be understood that the following text is only used to describe one or several specific embodiments of the present invention, and does not strictly limit the scope of protection of the specific claims of the present invention.
[0031] Example 1
[0032] The technical solution adopted in this embodiment is as follows Figures 1 to 4 As shown, a prestressed anchoring device for a concrete bridge includes a frame assembly installed at the bottom of the bridge, a fixing portion 4, a tensioning portion 2, and a carbon fiber cloth 3 located between the fixing portion 4 and the tensioning portion 2 and close to the construction surface of the bridge.
[0033] Specifically, the fixing part 4 and the tensioning part 2 each include: Figure 3The clamping assembly 5 shown in the figure comprises a cloth clamping shaft 51 and a fixed base, wherein two cloth clamping shafts 51 are provided, and the two cloth clamping shafts 51 are spliced along their axial direction to form a cylinder, and the ends of the carbon fiber cloth 3 are clamped at the joint of the two cloth clamping shafts 51; the fixed base is located at both ends of the two cloth clamping shafts 51, clamps the two spliced cloth clamping shafts 51 and limits the circumferential rotation of the two cloth clamping shafts 51, and an anchor hole 523 for anchoring to the bridge construction surface is also provided on the fixed base; the fixed base comprises a base body 52 and anchoring wing plates 522 provided on both sides of the base body 52 and used to connect to the bridge construction surface, and the anchor hole 523 is provided on the anchoring wing plates 522; a square through hole 521 is provided at the joint of the base body 52 and the two cloth clamping shafts 51, and the two cloth clamping shafts 51 have the same shape, and square limit blocks 51 are provided at both ends thereof. 1. After the two cloth clamping shafts 51 are spliced, the square limit block 511 is accommodated in the square through hole 521; the square limit block 511 is also provided with a connecting hole 512, and a connecting bolt 513 for connecting the two cloth clamping shafts 51 is inserted in the connecting hole 512; when the fixing part is constructed, the carbon fiber cloth is first clamped between the two cloth clamping shafts, and then the spliced cloth clamping shafts are rotated for one and a half weeks, and the connecting bolt 513 is inserted into the connecting hole 512 at the same time. The connecting bolt and the connecting hole are used in combination to not only align the cloth clamping shafts, but also to fasten the two cloth clamping shafts. Here, both ends of the connecting bolt do not exceed the two end surfaces of the connecting hole. Then, the square through hole of the fixing base is aligned with the square limit block and inserted, and the chemical anchor is inserted into the anchor hole 523 on the anchor wing plate 522, and the entire fixing part is installed on the bridge construction surface.
[0034] like Figure 2 As shown, the frame assembly of this embodiment is a rectangular frame 1, and waist-shaped through holes 11 are opened on both sides of the rectangular frame 1 along its length direction. The tensioning part 2 is located on the inner side of the rectangular frame 1 and is slidably arranged along the length direction of the rectangular frame 1 through the waist-shaped through holes 11; the fixing part 4 is anchored on the bridge construction surface on the length extension line of the rectangular frame 1; in order to avoid the problem of unstable installation caused by the unevenness of the bridge construction surface, this embodiment is provided with support legs 12 for anchoring the bridge at the four corners of the rectangular frame 1 on the side close to the bridge construction surface, and the support legs 12 support the rectangular frame 1 to form a gap 13 between the bridge construction surface and the rectangular frame 1; the two cloth clamping shafts 51 of the tensioning part 2 are located in the gap 13, and the two ends of the two cloth clamping shafts 51 extend to the outside of the rectangular frame 1, and the two ends of the cloth clamping shafts 51 are respectively inserted into the fixed base, and fixed to the bridge construction surface through the fixed base; this can effectively solve the problem of uneven construction surface, and the point contact of the four corners makes the contact between the rectangular frame and the bridge construction surface more stable and accurate.
[0035] Combination Figure 1 and Figure 4The tensioning part 2 also includes a tensioning top plate 21. A balancing through hole 211 is provided in the tensioning top plate 21 along the width direction of the rectangular frame 1 to cooperate with the waist-shaped through hole 11. A balancing shaft 212 is inserted into the balancing through hole 211. Both ends of the balancing shaft 212 extend into the corresponding waist-shaped through hole 11. The balancing shaft 212 drives the tensioning top plate 21 to move along the length direction of the rectangular frame 1. The tensioning top plate 21 is specifically installed on the anchoring wing plate 522 on one side of the tensioning part fixed base near the fixed part 4, and can be inserted by bolts or directly prevented thereon. A jack is installed between the plate 21 and the inner side of the rectangular frame 1, and a groove 6 is provided on the tensioning top plate 21 and the surface of the rectangular frame 1 in contact with the jack to prevent the jack from shifting. The jack pushes the tensioning top plate 21 to move away from the fixed part 4, and the tensioning top plate 21 drives the clamping assembly 5 of the tensioning part 2 to move along the length direction of the rectangular frame 1 until the carbon fiber cloth 3 is tensioned to the set value; the chemical anchor bolt passes through the anchor hole 523 of the fixed base of the tensioning part 2, and anchors the tensioned clamping assembly 5 of the tensioning part 2 to the bridge construction surface. In addition, in order to prevent the tensioning top plate from shifting and improve the tensioning stability, a fixing screw 22 is provided on the side of the tensioning top plate 21 away from the jack, and its axial direction is consistent with the length direction of the rectangular frame. One end of the fixing screw 22 is fixed on the tensioning top plate 21, and the other end passes through the rectangular frame, and a flange nut 221 is screwed on the end. A through hole slightly larger than the fixing screw is provided on the rectangular frame. The fixing screw also slides in the through hole and can be tightened by the flange nut to achieve stability and prevent displacement.
[0036] The prestressed anchoring device for concrete bridges of this embodiment has a simple structure and is easy to use. All components are detachably connected, which is convenient for carrying and disassembly after construction. At the same time, a cloth clamping shaft is used to clamp the carbon fiber cloth over a large area, effectively solving the problems of complex structure, troublesome construction, difficulty in ensuring the tensile strength of the carbon fiber cloth, and low construction efficiency of the existing carbon fiber cloth tensioning anchor.
[0037] Example 2
[0038] This embodiment is a construction method of a prestressed anchoring device for a concrete bridge according to embodiment 1, comprising the following steps:
[0039] S1. Pre-treat the bridge construction surface, clamp one end of the carbon fiber cloth between two cloth clamping shafts of the fixing part, rotate the cloth clamping shafts one and a half times in the circumferential direction to fix the carbon fiber cloth on the cloth clamping shafts, then install fixed bases at both ends of the cloth clamping shafts, and anchor the fixed bases on the bridge construction surface through chemical anchor bolts;
[0040] S2. Clamp the other end of the carbon fiber cloth between the two cloth clamping shafts of the tensioning part, rotate the cloth clamping shaft one and a half times in the circumferential direction to fix the carbon fiber cloth on the cloth clamping shaft, then install fixed bases at both ends of the cloth clamping shaft, place the tensioning top plate on the anchor wing plate of the fixed base, and finally install the rectangular frame on the assembled clamping assembly and the tensioning top plate;
[0041] S3. Straighten the carbon fiber cloth, anchor the rectangular frame assembled in step S2 on the bridge construction surface, and then install a jack between the tensioning top plate near the fixed part and the rectangular frame. The jack pushes the tensioning top plate to move away from the fixed part, and the tensioning top plate drives the clamping assembly of the tensioning part to move, thereby tensioning the carbon fiber cloth;
[0042] S4. After the carbon fiber cloth is tensioned into place, tighten the flange nut and anchor the fixed base of the tensioning part to the bridge construction surface. After the tensioning is completed, brush glue on the carbon cloth, and then remove the fixed part, rectangular frame and tensioning top plate.
[0043] The construction method of this embodiment stretches the clamped carbon fiber cloth to ensure that the carbon fiber cloth is maintained in a prestressed state of a set value to exert the maximum strength effect; in addition, the length of the two ends of the carbon fiber cloth clamped by the cloth clamping shaft is also short, which can effectively avoid the waste of the carbon fiber cloth; finally, all the used parts can be removed after the carbon fiber cloth is pasted, with a high degree of reuse, which can save a lot of construction costs.
[0044] The implementation modes of the present invention are described in detail above in conjunction with the embodiments, but the present invention is not limited to the above-mentioned implementation modes. For ordinary technicians in this technical field, after knowing the contents recorded in the present invention, they can make several equivalent changes and substitutions thereto without departing from the principle of the present invention, and these equivalent changes and substitutions should also be regarded as belonging to the protection scope of the present invention.
Claims
1. A prestressed anchoring device for a concrete bridge, Features: It includes a frame assembly installed on the bridge construction surface, a fixing part, a tensioning part, and a carbon fiber cloth located between the fixing part and the tensioning part and close to the bridge construction surface; The frame assembly is a rectangular frame, and waist-shaped through holes are opened on both sides of the rectangular frame along its length direction. The tensioning part is located inside the rectangular frame and is slidably arranged along the length direction of the rectangular frame through the waist-shaped through holes; the fixing part is anchored on the bridge construction surface on the extension line of the rectangular frame length; The fixing part and the tensioning part both include a clamping assembly, and the clamping assembly includes a cloth clamping shaft and a fixed base. Two cloth clamping shafts are provided, and the two cloth clamping shafts are spliced along their axial direction to form a cylinder, and the end of the carbon fiber cloth is clamped at the junction of the two cloth clamping shafts; the fixed base is located at both ends of the two cloth clamping shafts, clamps the two spliced cloth clamping shafts and limits the circumferential rotation of the two cloth clamping shafts, and an anchor hole for anchoring on the bridge construction surface is also provided on the fixed base; The tensioning part also includes a tensioning top plate, which is installed on a side of the clamping assembly of the tensioning part close to the fixed part. A jack is installed between the tensioning top plate and the inner side of the rectangular frame. The jack pushes the tensioning top plate to move away from the fixed part. The tensioning top plate drives the clamping assembly of the tensioning part to move along the length direction of the rectangular frame until the carbon fiber cloth is tensioned in place. The fastening anchor bolt passes through the anchor hole of the fixed base of the tensioning part to anchor the tensioned clamping assembly of the tensioning part to the bridge construction surface. The four corners of the rectangular frame on the side close to the bridge construction surface are all provided with support legs for anchoring the bridge, and the support legs support the rectangular frame, forming a gap between the bridge construction surface and the rectangular frame; the two cloth clamping shafts of the tensioning part are located in the gap, and the two ends of the two cloth clamping shafts extend outside the rectangular frame, and the two ends of the cloth clamping shafts are respectively inserted into the fixed base and fixed on the bridge construction surface through the fixed base; A balancing through hole is opened in the tensioned top plate along the width direction of the rectangular frame for use with the waist-shaped through hole. A balancing shaft is inserted in the balancing through hole, and both ends of the balancing shaft extend into the corresponding waist-shaped through hole. The balancing shaft drives the tensioned top plate to move along the length direction of the rectangular frame.
2. The prestressed anchoring device for concrete bridge according to claim 1, Features: The fixed base includes a base body and anchor wing plates arranged on both sides of the base body for connecting to the bridge construction surface, and the anchor holes are opened on the anchor wing plates; a square through hole is opened at the connection between the base body and the two cloth clamping shafts, the two cloth clamping shafts have the same shape, and square limit blocks are arranged at both ends, and the square limit blocks are accommodated in the square through hole after the two cloth clamping shafts are spliced.
3. The prestressed anchoring device for concrete bridge according to claim 2, Features: The square limit block is also provided with a connecting hole, in which a connecting bolt for connecting two cloth clamping shafts is inserted.
4. The prestressed anchoring device for concrete bridge according to claim 1, Features: The tensioning top plate and the rectangular frame are both provided with grooves on the surface in contact with the jack to prevent the jack from shifting.
5. The prestressed anchoring device for concrete bridge according to claim 1, Features: A fixing device is provided on the side of the tensioning top plate away from the jack, and the fixing device includes a fixing screw whose axial direction is consistent with the length direction of the rectangular frame. One end of the fixing screw is fixed to the tensioning top plate, and the other end passes through the rectangular frame, and the end is screwed with a flange nut.
6. A construction method for the prestressed anchoring device for a concrete bridge as claimed in claim 1, It is characterized in that The following steps are involved: S1. Pre-treat the bridge construction surface, then clamp one end of the carbon fiber cloth between two cloth clamping shafts of the fixing part, rotate the cloth clamping shaft at least one circle along the circumference of the cloth clamping shaft to fix the carbon fiber cloth on the cloth clamping shaft, and finally install fixed bases at both ends of the cloth clamping shaft, and anchor the fixed bases on the bridge construction surface; S2. Clamp the other end of the carbon fiber cloth between the two cloth clamping shafts of the tensioning part, rotate the cloth clamping shaft at least one circle along the circumference to fix the carbon fiber cloth on the cloth clamping shaft, then install fixed bases at both ends of the cloth clamping shaft, install the tensioning top plate on the fixed base, and finally install the rectangular frame on the assembled clamping assembly and the tensioning top plate; S3. Straighten the carbon fiber cloth, anchor the rectangular frame assembled in step S2 on the bridge construction surface, and then install a jack between the tensioning top plate near the fixed part and the rectangular frame. The jack pushes the tensioning top plate to move away from the fixed part, and the tensioning top plate drives the clamping assembly of the tensioning part to move, thereby tensioning the carbon fiber cloth; S4. After the carbon fiber cloth is tensioned in place, the fixed base of the tensioning part is anchored to the bridge construction surface. After the tensioning is completed, the carbon cloth is brushed with glue, and then the fixed part, rectangular frame and tensioning top plate are removed.