A boiler liquid level meter capable of online sewage discharge and its use method
By using two sets of pressure pipes and an online blowdown design of a differential pressure transmitter in the boiler liquid level gauge, the problem of measurement distortion caused by the pressure pipe of the differential pressure level gauge not being discharged for a long time is solved, ensuring the continuous operation of the boiler. Operation and industrial production safety and stability.
Patent Information
- Application Number
- CN202111241370.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-10-25
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2041-10-25
AI Technical Summary
If the pressure pipe of the differential pressure liquid level gauge in the boiler is not discharged for a long time, it will become clogged, resulting in distortion of the measurement value of the liquid level gauge, which may cause frequent starting of the water replenishing pump or interlocking shutdown of the boiler gas system, or even dry burning of the steam drum.
Design a boiler liquid level gauge that can discharge sewage online. It uses two sets of pressure pipes and differential pressure transmitters. By setting up a sewage valve and a balance valve, a programmable controller is used to realize online sewage discharge to ensure that the pressure pipe is always clean and avoid The level gauge signal is distorted.
It effectively avoids the blockage of the pressure pipe and the distortion of the measurement value of the liquid level gauge, prevents the water supply pump from starting frequently or the boiler gas system from shutting down, and ensures the smooth progress of industrial production.
Smart Images

Figure CN113984141B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a boiler liquid level gauge capable of online sewage discharge and a use method thereof, belonging to the technical field of liquid level gauges. Background Art
[0002] The hot water or steam generated in the boiler can directly provide the required heat energy for industrial production and people's lives, or it can be converted into mechanical energy through a steam power device, or the mechanical energy can be converted into electrical energy through a generator. Most of the boiler drum level gauges involved in control use differential pressure level gauges. The principle is to measure the static pressure difference between the variable pressure and the constant pressure, and convert the differential pressure value into an electrical signal that changes continuously with the liquid level through a differential pressure transmitter, and finally monitor it through a programmable controller.
[0003] If the pressure taking pipe of the differential pressure level gauge is not drained for a long time, it will cause blockage of the pressure taking pipe, distortion of the measured value of the level gauge, frequent startup of the water supply pump or interlocking and shutdown of the boiler gas system, and even dry burning of the steam drum.
[0004] In the actual production process, due to continuous production and other reasons, the boiler cannot be shut down and discharged according to the level meter discharge cycle. If the discharge is done online, the level meter signal will be distorted, resulting in a false drum water level. Summary of the invention
[0005] The purpose of the present invention is to provide a boiler level gauge capable of online sewage discharge and a method of using the same. By using two sets of pressure taking tubes and a differential pressure transmitter, the boiler level gauge can discharge sewage online during the production process, thereby avoiding blockage of the pressure taking tube due to long-term non-discharge of sewage from the pressure taking tube caused by continuous operation of the boiler, distortion of the measured value of the level gauge, and the like, thereby avoiding frequent starting of the make-up water pump or interlocking shutdown of the boiler gas system, and even accidents such as dry burning of the steam drum, thereby ensuring the smooth progress of industrial production and effectively solving the above-mentioned problems existing in the background technology.
[0006] The technical solution of the present invention is: a boiler liquid level gauge capable of online blowdown, comprising a steam drum, a balance cylinder, a steam phase pipe and a liquid phase pipe, wherein the steam drum and the balance cylinder are connected via the steam phase pipe and the liquid phase pipe, so that the liquid level and pressure of the steam drum and the balance cylinder are the same;
[0007] The balancing cylinder is a cylindrical container with two sets of pressure-taking pipes, namely positive pressure pipe A, negative pressure pipe A, positive pressure pipe B and negative pressure pipe B. Negative pressure pipe A and negative pressure pipe B are located in the upper part of the balancing cylinder and are connected to the balancing cylinder. The pipes are filled with soft water. The pressure-taking point is the steam pressure in the upper part of the balancing cylinder, which is called constant pressure; positive pressure pipe A and positive pressure pipe B are located at the bottom of the balancing cylinder and are connected to the balancing cylinder. The pipes are filled with soft water. The pressure-taking point is the bottom pressure in the balancing cylinder. The pressure changes with the height of the drum liquid level, which is called variable pressure; positive pressure pipe A and positive pressure pipe B merge into one place at the differential pressure transmitter and enter the positive pressure side of the differential pressure transmitter; negative pressure pipe A and negative pressure pipe B merge into one place at the differential pressure transmitter and enter the negative pressure side of the differential pressure transmitter;
[0008] Drain valves are arranged at the bottom of the positive pressure pipe A, the negative pressure pipe A, the positive pressure pipe B and the negative pressure pipe B, which are the positive pressure pipe A drain valve, the negative pressure pipe A drain valve, the positive pressure pipe B drain valve and the negative pressure pipe B drain valve respectively.
[0009] A balancing valve A is provided between the positive pressure pipe A and the negative pressure pipe A, and a balancing valve B is provided between the positive pressure pipe A and the negative pressure pipe B.
[0010] It also includes a negative pressure tube A pressure gauge and a negative pressure tube B pressure gauge, which are connected to the negative pressure tube A and the negative pressure tube B respectively.
[0011] The utility model also includes a programmable controller, and the programmable controller is connected with the differential pressure transmitter.
[0012] The method for using the above-mentioned boiler liquid level meter capable of online sewage discharge comprises the following steps:
[0013] ① In the normal operation state of the boiler, the stop valve of the negative pressure pipe A, the stop valve of the negative pressure pipe B, the stop valve of the positive pressure pipe A and the stop valve of the positive pressure pipe B are set to the fully open state, the balancing valve A and the balancing valve B are set to the closed state, the drain valve of the negative pressure pipe A, the drain valve of the positive pressure pipe A, the drain valve of the positive pressure pipe B and the drain valve of the negative pressure pipe B are set to the closed state;
[0014] ② Before the positive pressure pipe A is drained, close the stop valve of the positive pressure pipe A, open the drain valve of the positive pressure pipe A, and drain the positive pressure pipe A. After the drainage is completed, close the drain valve of the positive pressure pipe A, open the stop valve 16 of the positive pressure pipe A, and the liquid level meter returns to the operating state;
[0015] ③ Before draining the positive pressure pipe B8, close the stop valve of the positive pressure pipe B, open the drain valve of the positive pressure pipe B, drain the positive pressure pipe B, close the drain valve of the positive pressure pipe B after draining, open the stop valve of the positive pressure pipe B, and the level meter returns to the operating state;
[0016] ④Drain the negative pressure pipe A. Before draining the negative pressure pipe A, close the stop valve of the negative pressure pipe A, open the drain valve of the negative pressure pipe A, and drain the negative pressure pipe A. When the negative pressure pipe A discharges steam, close the drain valve of the negative pressure pipe A, and the drainage of the negative pressure pipe A5 is completed; close the stop valve of the positive pressure pipe A, open the balancing valve A, and the soft water in the balancing cylinder enters the negative pressure pipe A from the positive pressure pipe A through the balancing valve A. The liquid level in the negative pressure pipe A is the same as that in the balancing cylinder, slightly lower than the pressure point of the negative pressure pipe A; close the balancing valve A, open the stop valve of the positive pressure pipe A, wait for the steam condensation soft water to enter the negative pressure pipe A, observe the pressure gauge of the negative pressure pipe A, and when the pressure value is the same as that of the pressure gauge of the negative pressure pipe B, open the stop valve of the negative pressure pipe A, and the normal operation is restored;
[0017] ⑤ Drain the negative pressure pipe B. Before draining the negative pressure pipe B, close the stop valve of the negative pressure pipe B, open the drain valve of the negative pressure pipe B, and drain the negative pressure pipe B. When the negative pressure pipe B discharges steam, close the drain valve of the negative pressure pipe B, and the drainage of the negative pressure pipe B6 is completed; close the stop valve of the positive pressure pipe B, open the balancing valve B, and the soft water in the balancing cylinder enters the negative pressure pipe B from the positive pressure pipe B through the balancing valve B. The liquid level in the negative pressure pipe B is the same as that in the balancing cylinder, slightly lower than the pressure taking point of the negative pressure pipe B. Close the balancing valve B, open the stop valve of the positive pressure pipe B, wait for the steam condensation and soft water to enter the negative pressure pipe B, observe the pressure gauge of the negative pressure pipe B, and when the pressure value is the same as that of the pressure gauge of the negative pressure pipe A, open the stop valve of the negative pressure pipe B, and then return to normal operation.
[0018] The beneficial effects of the present invention are as follows: through the use of two sets of pressure pipes and differential pressure transmitters, the boiler level gauge can discharge sewage online during the production process, avoiding blockage of the pressure pipe due to long-term non-discharge of sewage from the pressure pipe caused by continuous operation of the boiler, distortion of the measured value of the level gauge, etc., thereby avoiding frequent starting of the water supply pump or interlocking shutdown of the boiler gas system, and even accidents such as dry burning of the steam drum, thereby ensuring the smooth progress of industrial production. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a schematic diagram of the structure of the present invention;
[0020] In the figure: steam drum 1, balancing cylinder 2, steam phase pipe 3, liquid phase pipe 4, negative pressure pipe A5, negative pressure pipe B6, positive pressure pipe A7, positive pressure pipe B8, negative pressure pipe A pressure gauge 9, negative pressure pipe B pressure gauge 10, balancing valve A11, balancing valve B12, differential pressure transmitter 13, negative pressure pipe A stop valve 14, negative pressure pipe B stop valve 15, positive pressure pipe A stop valve 16, positive pressure pipe B stop valve 17, negative pressure pipe A drain valve 18, positive pressure pipe A drain valve 19, positive pressure pipe B drain valve 20, negative pressure pipe B drain valve 21, programmable controller 22. DETAILED DESCRIPTION
[0021] In order to make the purpose, technical solutions and advantages of the invention implementation cases clearer, the technical solutions in the implementation cases of the present invention will be clearly and completely described below in conjunction with the drawings in the implementation cases. Obviously, the implementation cases described are only a small part of the implementation cases of the present invention, rather than all the implementation cases. Based on the implementation cases in the present invention, all other implementation cases obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0022] A boiler level gauge capable of online blowdown comprises a steam drum 1, a balance cylinder 2, a steam phase pipe 3 and a liquid phase pipe 4. The steam drum 1 and the balance cylinder 2 are connected via the steam phase pipe 3 and the liquid phase pipe 4, so that the liquid level and pressure of the steam drum 1 and the balance cylinder 2 are the same.
[0023] The balancing cylinder 2 is a cylindrical container, which is equipped with two sets of pressure-taking pipes, namely, the positive pressure pipe A7, the negative pressure pipe A5, the positive pressure pipe B8 and the negative pressure pipe B6. The negative pressure pipe A5 and the negative pressure pipe B6 are located in the upper half of the balancing cylinder 2, connected with the balancing cylinder 2, and the pipes are filled with soft water. The pressure-taking point is the steam pressure in the upper part of the balancing cylinder 2, which is called constant pressure; the positive pressure pipe A7 and the positive pressure pipe B8 are located at the bottom of the balancing cylinder 2, connected with the balancing cylinder 2, and the pipes are filled with soft water. The pressure-taking point is the bottom pressure in the balancing cylinder 2. The pressure changes with the liquid level of the steam drum 1, which is called variable pressure; the positive pressure pipe A7 and the positive pressure pipe B8 merge into one place at the differential pressure transmitter 13 and enter the positive pressure side of the differential pressure transmitter 13; the negative pressure pipe A5 and the negative pressure pipe B6 merge into one place at the differential pressure transmitter 13 and enter the negative pressure side of the differential pressure transmitter 13;
[0024] Drain valves are arranged at the bottom of the positive pressure pipe A7, the negative pressure pipe A5, the positive pressure pipe B8 and the negative pressure pipe B6, which are respectively the positive pressure pipe A drain valve 19, the negative pressure pipe A drain valve 18, the positive pressure pipe B drain valve 20 and the negative pressure pipe B drain valve 21.
[0025] A balancing valve A11 is provided between the positive pressure pipe A7 and the negative pressure pipe A5, and a balancing valve B12 is provided between the positive pressure pipe A7 and the negative pressure pipe B6.
[0026] It also includes a negative pressure tube A pressure gauge 9 and a negative pressure tube B pressure gauge 10, which are connected to the negative pressure tube A5 and the negative pressure tube B6 respectively.
[0027] It also includes a programmable controller 22, which is connected to the differential pressure transmitter 13. The signal of the pressure transmitter 13 is transmitted to the programmable controller 22, and is converted into the required liquid level signal after calculation and range setting.
[0028] The method for using the above-mentioned boiler level gauge capable of online sewage discharge comprises the following steps:
[0029] ① In the normal operation state of the boiler, the negative pressure pipe A stop valve 14, the negative pressure pipe B stop valve 15, the positive pressure pipe A stop valve 16 and the positive pressure pipe B stop valve 17 are set to the fully open state, the balancing valve A11 and the balancing valve B12 are set to the closed state, the negative pressure pipe A drain valve 18, the positive pressure pipe A drain valve 19, the positive pressure pipe B drain valve 20 and the negative pressure pipe B drain valve 21 are set to the closed state;
[0030] ② Before the positive pressure pipe A7 is drained, close the positive pressure pipe A stop valve 16, open the positive pressure pipe A drain valve 19, and drain the positive pressure pipe A7. After the drainage is completed, close the positive pressure pipe A drain valve 19, open the positive pressure pipe A stop valve 16, and the liquid level meter returns to the operating state;
[0031] ③ Before the positive pressure pipe B8 is drained, close the positive pressure pipe B stop valve 17, open the positive pressure pipe B drain valve 20, and drain the positive pressure pipe B8. After the drainage is completed, close the positive pressure pipe B drain valve 20, open the positive pressure pipe B stop valve 17, and the liquid level meter returns to the operating state;
[0032] ④Drain the negative pressure pipe A5. Before draining the negative pressure pipe A5, close the stop valve 14 of the negative pressure pipe A, open the drain valve 18 of the negative pressure pipe A, and drain the negative pressure pipe A5. When the negative pressure pipe A5 discharges steam, close the drain valve 18 of the negative pressure pipe A, and the drainage of the negative pressure pipe A5 is completed; close the stop valve 16 of the positive pressure pipe A, open the balancing valve A11, and the soft water in the balancing cylinder enters the negative pressure pipe A5 from the positive pressure pipe A7 through the balancing valve A11. The liquid level in the negative pressure pipe A5 is the same as that in the balancing cylinder 2, slightly lower than the pressure point of the negative pressure pipe A5; close the balancing valve A11, open the stop valve 16 of the positive pressure pipe A, wait for the steam to condense and the soft water to enter the negative pressure pipe A5, observe the pressure gauge 9 of the negative pressure pipe A, and when the pressure value is the same as that of the pressure gauge of the negative pressure pipe B6, open the stop valve 14 of the negative pressure pipe A, and the normal operation is restored;
[0033] ⑤ Drain the negative pressure pipe B6. Before draining the negative pressure pipe B6, close the stop valve 15 of the negative pressure pipe B, open the drain valve 21 of the negative pressure pipe B, and drain the negative pressure pipe B6. When the negative pressure pipe B6 discharges steam, close the drain valve 21 of the negative pressure pipe B, and the drainage of the negative pressure pipe B6 is completed; close the stop valve of the positive pressure pipe B8, open the balancing valve B12, and the soft water in the balancing cylinder enters the negative pressure pipe B6 from the positive pressure pipe B8 through the balancing valve B12. The liquid level in the negative pressure pipe B6 is the same as that in the balancing cylinder 2, slightly lower than the pressure point of the negative pressure pipe B6. Close the balancing valve B12, open the stop valve 17 of the positive pressure pipe B, wait for the steam to condense and the soft water to enter the negative pressure pipe B6, observe the pressure gauge 10 of the negative pressure pipe B, and when the pressure value is the same as that of the pressure gauge 9 of the negative pressure pipe A, open the stop valve 15 of the negative pressure pipe B, and then the normal operation is restored.
[0034] In actual application, it is assumed that the boiler is in normal operation, the negative pressure pipe A stop valve 14, the negative pressure pipe B stop valve 15, the positive pressure pipe A stop valve 16, and the positive pressure pipe B stop valve 17 are all fully open, the balancing valve A11 and the balancing valve B12 are closed, the negative pressure pipe A drain valve 18, the positive pressure pipe A drain valve 19, the positive pressure pipe B drain valve 20, and the negative pressure pipe B drain valve 21 are closed.
[0035] Positive pressure pipe A7 drainage method: Before draining the positive pressure pipe A7, close the positive pressure pipe A stop valve 16. Since the pressure of positive pressure pipe B8 is the same as that of positive pressure pipe A7, there is no deviation in the force on the positive pressure side of the differential pressure transmitter 13, and the true value of the liquid level is not affected. At this time, open the positive pressure pipe A drainage valve 19 to drain the positive pressure pipe A7. After the drainage is completed, close the positive pressure pipe A drainage valve 19, open the positive pressure pipe A stop valve 16, and the level meter returns to the operating state.
[0036] Positive pressure pipe B8 drainage method: Before positive pressure pipe B8 drainage, close positive pressure pipe B stop valve 17. Since the pressure of positive pressure pipe A7 is the same as that of positive pressure pipe B8, there is no deviation in the force on the positive pressure side of the differential pressure transmitter 13, and the true value of the liquid level is not affected. At this time, open the positive pressure pipe B drainage valve 20 to drain the positive pressure pipe B8. After drainage, close the positive pressure pipe B drainage valve 20, open the positive pressure pipe B stop valve 17, and the level meter returns to the operating state.
[0037] Negative pressure pipe A5 sewage discharge method: Before the negative pressure pipe A5 sewage discharge, close the negative pressure pipe A stop valve 14. Since the pressure of the negative pressure pipe A5 is the same as that of the negative pressure pipe B6, there is no deviation in the force on the positive pressure side of the differential pressure transmitter 13, and the true value of the liquid level is not affected. At this time, open the negative pressure pipe A sewage discharge valve 18 to discharge the negative pressure pipe A5. When the negative pressure pipe A5 discharges steam, close the negative pressure pipe A sewage discharge valve 18, and the negative pressure pipe A5 sewage discharge is completed. At this time, there is no steam condensed soft water in the negative pressure pipe A5, and the steam pressure on the upper part of the balance cylinder 2 cannot be accurately measured. It takes a long time to wait for the negative pressure pipe A5 to be filled with condensed water. To avoid long waiting, close the positive pressure pipe A stop valve 16, open the balance valve A11, and the soft water in the balance cylinder 2 enters the negative pressure pipe A5 from the positive pressure pipe A7 through the balance valve A11. The liquid level in the negative pressure pipe A5 is the same as that of the balance cylinder 2, slightly lower than the pressure point of the negative pressure pipe A5. Close the balance valve A11, open the stop valve 16 of the positive pressure pipe A, and wait for the steam condensation soft water to enter the negative pressure pipe A5. Observe the pressure gauge 9 of the negative pressure pipe A. When the pressure value is the same as that of the pressure gauge 10 of the negative pressure pipe B, it proves that the negative pressure pipe A5 is full of condensed water. Open the stop valve 14 of the negative pressure pipe A, and the normal operation is restored.
[0038] Negative pressure pipe B6 drainage method: Before the negative pressure pipe B6 is drained, close the negative pressure pipe B stop valve 15. Since the pressure of the negative pressure pipe B6 is the same as that of the negative pressure pipe A5, there is no deviation in the force on the positive pressure side of the differential pressure transmitter 13, and the true value of the liquid level is not affected. At this time, open the negative pressure pipe B drain valve 21 to drain the negative pressure pipe B6. When the negative pressure pipe B6 discharges steam, close the negative pressure pipe B drain valve 21, and the negative pressure pipe B6 is drained. At this time, there is no steam condensed soft water in the negative pressure pipe B6, and the steam pressure on the upper part of the balance cylinder 2 cannot be accurately measured. It takes a long time to wait for the negative pressure pipe B6 to be filled with condensed water. To avoid long waiting, close the positive pressure pipe B stop valve 17, open the balance valve B12, and the soft water in the balance cylinder 2 enters the negative pressure pipe B6 from the positive pressure pipe B8 through the balance valve B12. The liquid level in the negative pressure pipe B6 is the same as that of the balance cylinder 2, slightly lower than the pressure point of the negative pressure pipe B6. Close the balancing valve B12, open the stop valve 17 of the positive pressure pipe B, wait for the steam condensed soft water to enter the negative pressure pipe B6, observe the pressure gauge 10 of the negative pressure pipe B, when the pressure value is the same as that of the pressure gauge 9 of the negative pressure pipe A, it proves that the negative pressure pipe B6 is full of condensed water, open the stop valve 15 of the negative pressure pipe B, and then return to normal operation.
Claims
1. A boiler level gauge that can discharge waste water online. Features: The steam drum (1) comprises a steam drum (1), a balance cylinder (2), a steam phase pipe (3) and a liquid phase pipe (4), wherein the steam drum (1) and the balance cylinder (2) are connected via the steam phase pipe (3) and the liquid phase pipe (4), so that the liquid level and pressure of the steam drum (1) and the balance cylinder (2) are the same; The balancing cylinder (2) is a cylindrical container, and is provided with two sets of pressure-taking pipes, namely, a positive pressure pipe A (7), a negative pressure pipe A (5), a positive pressure pipe B (8), and a negative pressure pipe B (6). The negative pressure pipe A (5) and the negative pressure pipe B (6) are located in the upper part of the balancing cylinder (2), are connected to the balancing cylinder (2), are filled with soft water, and the pressure-taking point is the steam pressure in the upper part of the balancing cylinder (2), which is called constant pressure; the positive pressure pipe A (7) and the positive pressure pipe B (8) are located in the upper part of the balancing cylinder (2). ) bottom, connected to the balance cylinder (2), the tube is filled with soft water, the pressure point is the pressure at the bottom of the balance cylinder (2), the pressure changes with the liquid level of the drum (1), and is called variable pressure; the positive pressure tube A (7) and the positive pressure tube B (8) merge into one place at the differential pressure transmitter (13) and enter the positive pressure side of the differential pressure transmitter (13); the negative pressure tube A (5) and the negative pressure tube B (6) merge into one place at the differential pressure transmitter (13) and enter the negative pressure side of the differential pressure transmitter (13); Drain valves are provided at the bottom of the positive pressure pipe A (7), the negative pressure pipe A (5), the positive pressure pipe B (8) and the negative pressure pipe B (6), which are respectively the positive pressure pipe A drain valve (19), the negative pressure pipe A drain valve (18), the positive pressure pipe B drain valve (20) and the negative pressure pipe B drain valve (21); A balancing valve A (11) is provided between the positive pressure pipe A (7) and the negative pressure pipe A (5), and a balancing valve B (12) is provided between the positive pressure pipe A (7) and the negative pressure pipe B (6); It also includes a negative pressure pipe A pressure gauge (9) and a negative pressure pipe B pressure gauge (10), which are connected to the negative pressure pipe A (5) and the negative pressure pipe B (6) respectively.
2. A boiler level gauge capable of online sewage discharge according to claim 1, Features: It also includes a programmable controller (22), which is connected to the differential pressure transmitter (13).
3. A method for using a boiler level gauge capable of online sewage discharge according to claim 1 or 2, Features The following steps are involved: ① In the normal operation state of the boiler, the stop valve (14) of the negative pressure pipe A, the stop valve (15) of the negative pressure pipe B, the stop valve (16) of the positive pressure pipe A and the stop valve (17) of the positive pressure pipe B are set to the fully open state, the balancing valve A (11) and the balancing valve B (12) are set to the closed state, the drain valve (18) of the negative pressure pipe A, the drain valve (19) of the positive pressure pipe A, the drain valve (20) of the positive pressure pipe B and the drain valve (21) of the negative pressure pipe B are set to the closed state; ② Drain the positive pressure pipe A (7). Before draining the positive pressure pipe A (7), close the positive pressure pipe A stop valve (16), open the positive pressure pipe A drain valve (19), and drain the positive pressure pipe A (7). After draining, close the positive pressure pipe A drain valve (19), open the positive pressure pipe A stop valve (16), and the level gauge returns to the operating state. ③ Drain the positive pressure pipe B (8). Before draining the positive pressure pipe B (8), close the positive pressure pipe B stop valve (17), open the positive pressure pipe B drain valve (20), and drain the positive pressure pipe B (8). After draining, close the positive pressure pipe B drain valve (20), open the positive pressure pipe B stop valve (17), and the liquid level meter returns to the operating state. ④ The negative pressure pipe A (5) is drained. Before the negative pressure pipe A (5) is drained, the stop valve (14) of the negative pressure pipe A is closed and the drain valve (18) of the negative pressure pipe A is opened to drain the negative pressure pipe A (5). When the negative pressure pipe A (5) is discharged with steam, the drain valve (18) of the negative pressure pipe A is closed and the drain of the negative pressure pipe A (5) is completed. The stop valve (16) of the positive pressure pipe A is closed and the balancing valve A (11) is opened. The soft water in the balancing cylinder (2) flows from the positive pressure pipe A (7) through the balancing valve A (11) enters the negative pressure pipe A (5), and the liquid level in the negative pressure pipe A (5) is the same as that in the balance cylinder (2), and is slightly lower than the pressure point of the negative pressure pipe A (5); close the balance valve A (11), open the stop valve (16) of the positive pressure pipe A, wait for the steam condensation soft water to enter the negative pressure pipe A (5), observe the pressure gauge (9) of the negative pressure pipe A, and when the pressure value is the same as that of the pressure gauge (10) of the negative pressure pipe B, open the stop valve (14) of the negative pressure pipe A, and the normal operation state is restored; ⑤ Drain the negative pressure pipe B (6). Before draining the negative pressure pipe B (6), close the stop valve (15) of the negative pressure pipe B and open the drain valve (21) of the negative pressure pipe B to drain the negative pressure pipe B (6). When the negative pressure pipe B (6) discharges steam, close the drain valve (21) of the negative pressure pipe B to complete the drainage of the negative pressure pipe B (6). Close the stop valve (17) of the positive pressure pipe B and open the balancing valve B (12). The soft water in the balancing cylinder (2) flows from the positive pressure pipe B (8) through the balancing valve. B (12) enters the negative pressure pipe B (6). The liquid level in the negative pressure pipe B (6) is the same as that in the balance cylinder (2), slightly lower than the pressure point of the negative pressure pipe B (6). Close the balance valve B (12), open the stop valve (17) of the positive pressure pipe B, wait for the steam condensation soft water to enter the negative pressure pipe B (6), observe the pressure gauge (10) of the negative pressure pipe B, and when the pressure value is the same as that of the pressure gauge (9) of the negative pressure pipe A, open the stop valve (15) of the negative pressure pipe B, and the normal operation state is restored.
Citation Information
Patent Citations
Boiler liquid level meter capable of discharging sewage on line
CN216348961U