Economic dispatch method and system for wind power power system considering reliability index

By taking into account reliability indicators and polygonal sub-regional rotating timed power outage scheme, combined with carbon trading costs and wind turbine start-up and stop costs, the unresolved problem of the relationship between power shortage and reserve capacity in the economic dispatch of the power system has been solved, and the safe operation of the system has been achieved. Cost optimization.

CN114156863BActive Publication Date: 2024-10-15ELECTRIC POWER RES INST OF EAST INNER MONGOLIA ELECTRIC POWER +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111257021.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-10-27
Publication Date
2024-10-15
Estimated Expiration
2041-10-27

AI Technical Summary

Technical Problem

Existing power system economic dispatch methods fail to effectively consider the relationship between the expected value of power shortage and system reserve capacity, and the objective function lacks carbon transaction costs, thermal power unit operating costs and wind turbine start-up and stop costs, resulting in errors between the dispatch plan and the actual project.

Method used

This paper proposes an economic dispatch method for power systems including wind power that takes into account reliability indicators. By obtaining power system reliability indicators and considering the uncertainty of wind power generation and unit failures, a polygonal sub-regional rotating timed power outage plan is formulated to determine the minimum demand reserve of the system. capacity, and establish an economic dispatch model including wind turbine start-up and stop costs and carbon emission rights trading, and optimize the objective function to reduce carbon trading costs, thermal power unit operating costs and wind turbine start-up and stop costs.

Benefits of technology

On the premise of ensuring the safe operation of the system, it reduces the impact of unplanned outages on users, reduces carbon emissions, reduces system operating costs, improves the accuracy of scheduling plans, and reduces the error between actual engineering and simulation. .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114156863B_ABST
    Figure CN114156863B_ABST
Patent Text Reader

Abstract

The present disclosure provides a method and system for economic dispatch of a wind power power system taking into account reliability indicators, comprising: obtaining a power system reliability indicator; obtaining a dispatch plan based on the obtained power system reliability indicator and a preset power system economic dispatch optimization model; wherein, when obtaining the power system reliability indicator, the uncertainty of wind power generation and unplanned shutdown of unit failures are taken into account; the power system economic dispatch optimization model takes the lowest carbon trading cost, the lowest thermal power unit operating cost and the lowest wind turbine group start-up and shutdown costs as optimization goals; the present disclosure considers the uncertainty of wind power output to establish a carbon trading cost objective function containing wind turbine group start-up and shutdown costs, which can determine a reasonable system backup capacity and reduce the impact of power outages caused by unplanned shutdowns on the user side; while ensuring the safe operation of the system, the pollution caused by carbon emissions to the environment is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of economic dispatch of power systems, and in particular, relates to an economic dispatch method and system for a wind power power system taking into account reliability indicators. Background Art

[0002] Economic dispatch of power systems refers to a dispatching method that rationally utilizes energy and equipment to ensure reliable power supply to users at the lowest power generation cost or fuel cost while meeting the requirements of safety and power quality.

[0003] The inventors of the present disclosure have found that the current economic dispatch method for power systems has the following disadvantages:

[0004] 1. When establishing the economic dispatch model, the expected value of power shortage is not considered and the relationship with the system reserve capacity is not quantified. The dispatch plan generated based on this model cannot guarantee the safe operation requirements of the system;

[0005] 2. The objective function does not include carbon trading costs, operating costs of thermal power units, and start-up and shutdown costs of wind turbines, and the error between the objective function and the actual project is large. Summary of the invention

[0006] In order to solve the above problems, the present disclosure proposes an economic dispatch method and system for a wind power system taking into account reliability indicators. The present disclosure considers the uncertainty of wind power generation and unplanned shutdown of units to establish an expected energy not supplied (EENS) reliability indicator, and formulates a polygonal regional rotation timed power outage plan based on the EENS reliability indicator to determine the minimum required reserve capacity of the system; analyzes the impact of wind power and load uncertainty on the system reserve capacity, and establishes an economic dispatch model including wind turbine start-up and shutdown costs and carbon emission rights trading; studies the relationship between system operating costs and wind power output and carbon trading prices, and analyzes the impact on the power system considering carbon emission rights trading and EENS indicators; finally, combined with a 10-unit system simulation, the correctness of the proposed model is verified.

[0007] In order to achieve the above object, the present invention is implemented through the following technical solutions:

[0008] In a first aspect, the present disclosure provides a method for economic dispatch of a wind power system taking into account reliability indicators, comprising:

[0009] Obtain power system reliability indicators;

[0010] Obtain a dispatching plan based on the obtained power system reliability index and the preset power system economic dispatching optimization model;

[0011] Among them, when obtaining the reliability index of the power system, the uncertainty of wind power generation and the unplanned shutdown of unit failures are taken into account; the power system economic dispatch optimization model takes the lowest carbon trading cost, the lowest operating cost of thermal power units and the lowest start-up and shutdown cost of wind turbine groups as optimization goals.

[0012] Furthermore, the power system reliability index is an expected value of power shortage. After the expected value of power shortage is obtained, the reliability index of the expected value of power shortage is standardized according to the total load loss value and the power outage time.

[0013] Furthermore, based on the reliability index of the expected value of power shortage, a polygonal regional rotational timed power outage plan is formulated to determine the system's minimum required spare capacity; the area affected by the fault is divided into multiple areas by polygons, and the power outage time is determined according to the proportion of each area's load to the total lost load. The sum of the rotational power outage time in each area is the unit fault maintenance time.

[0014] Furthermore, the content of determining the relationship between the expected value of power shortage and the reserve capacity by adopting the polygonal regional rotation timed power outage scheme includes:

[0015] The outage capacity is determined based on the power generation capacity of the outage units, the spare capacity that can be provided by the outage units and the total spare capacity provided by the system;

[0016] The total power loss is determined by the product of the outage capacity and the length of maintenance time;

[0017] The total power loss is distributed to multiple areas respectively. The distribution principle is to distribute in proportion to the expected value of power shortage, and the total power loss in different areas is obtained.

[0018] Calculate the reliability index of the expected value of power shortage in each area based on the probability of occurrence of the fault scenario;

[0019] According to the relationship between the reliability index of the expected value of power shortage in each area and the acceptable expected value of power shortage, the relationship between the reserve and the expected value of power shortage is determined to obtain the minimum reserve capacity required in each area;

[0020] The sum of the reserves in all areas is the minimum total reserve required by the system.

[0021] Furthermore, the probability of occurrence of the fault scenario is determined based on the normal units, faulty units and the forced outage rate of the units.

[0022] Furthermore, when determining the reserve capacity, the load and wind power output forecast errors are considered.

[0023] Furthermore, the constraints of the power system economic dispatch optimization model include output constraints, power balance constraints, ramp constraints, continuous start-stop constraints and reliability constraints.

[0024] In a second aspect, the present disclosure further provides an economic dispatch system for a wind power system taking into account reliability indicators, comprising a data acquisition module and a dispatch scheme generation module;

[0025] The data acquisition module is configured to: obtain power system reliability indicators;

[0026] The dispatching scheme generating module is configured to: obtain a dispatching scheme according to the obtained power system reliability index and the preset power system economic dispatching optimization model;

[0027] Among them, when obtaining the reliability index of the power system, the uncertainty of wind power generation and the unplanned shutdown of unit failures are taken into account; the power system economic dispatch optimization model takes the lowest carbon trading cost, the lowest operating cost of thermal power units and the lowest start-up and shutdown cost of wind turbine groups as optimization goals.

[0028] In a third aspect, the present disclosure further provides a computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the steps of the method for economic dispatch of a wind power system taking into account reliability indicators as described in the first aspect.

[0029] In a fourth aspect, the present disclosure further provides an electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, the steps of the method for economic dispatch of a wind power system taking into account reliability indicators as described in the first aspect are implemented.

[0030] Compared with the prior art, the present invention has the following beneficial effects:

[0031] 1. This disclosure considers the uncertainty of wind power output and establishes a carbon trading cost objective function that includes the start-up and shutdown costs of wind turbines, which can determine a reasonable system backup capacity and reduce the impact of power outages caused by unplanned outages on the user side; while ensuring the safe operation of the system, it reduces the pollution caused by carbon emissions to the environment;

[0032] 2. Aiming at the randomness of unplanned outage of units and wind power output and load changes, the present invention derives the relationship between the reliability index and reserve of the expected energy not supplied EENS and proposes a polygonal regional rotation timed power outage scheme;

[0033] 3. This paper proposes an expected value indicator for power shortage and quantifies its relationship with the system's spare capacity. On this basis, an economic dispatch model is established. The simulation example shows that the expected value of power shortage defined in this paper leads to an increase in system operating costs, but the quantified polygonal regional rotation timed power outage scheme can ensure the safe operation requirements of the system.

[0034] 4. This disclosure takes into account carbon trading costs, operating costs of thermal power units, and start-up and shutdown costs of wind turbine groups when constructing the economic dispatch objective function; example simulation shows that adding carbon trading costs and start-up and shutdown costs of wind turbine groups to the objective function can reduce the error between system simulation and actual engineering. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] The drawings in the specification that constitute a part of this embodiment are used to provide a further understanding of this embodiment. The schematic embodiments of this embodiment and their descriptions are used to explain this embodiment and do not constitute improper limitations on this embodiment.

[0036] Figure 1 This is a schematic diagram of a hexagonal area rotating timed power outage scheme according to Embodiment 1 of the present disclosure;

[0037] Figure 2 is the approximate probability distribution of the prediction error interval of Example 1 of the present disclosure;

[0038] Figure 3 The wind power prediction data of Embodiment 1 of the present disclosure;

[0039] Figure 4 The load forecast data of Embodiment 1 of the present disclosure;

[0040] Figure 5 The unit output without considering the carbon trading model in Example 1 of the present disclosure;

[0041] Figure 6 The unit output under the carbon trading model in Example 1 of the present disclosure;

[0042] Figure 7 The unit combination taking into account wind power output of Embodiment 1 of the present disclosure;

[0043] Figure 8 A graph showing the relationship between the wind turbine output and the system power generation and operation cost in Embodiment 1 of the present disclosure;

[0044] Fig. 9 A relationship diagram between the system power generation operation cost and the carbon trading price in Example 1 of the present disclosure;

[0045] Fig.10 This is the impact of the EENS reliability index on the system spare capacity in Example 1 of the present disclosure. DETAILED DESCRIPTION

[0046] The present disclosure is further described below in conjunction with the accompanying drawings and embodiments.

[0047] It should be noted that the following detailed descriptions are illustrative and are intended to provide further explanation of the present application. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present application belongs.

[0048] Embodiment 1:

[0049] This embodiment provides an economic dispatch method for wind power power system taking into account reliability index. For the unplanned outage of units and the randomness of wind power output and load changes, the relationship between the reliability index and reserve of the expected energy not supplied EENS is derived and a polygonal regional rotation timed power outage scheme is proposed. The carbon trading cost objective function including the start-up and shutdown costs of wind turbines is established considering the uncertainty of wind power output. The results show that this method can determine a reasonable system reserve capacity and reduce the impact of power outages caused by unplanned outages on the user side. This method reduces the pollution caused by carbon emissions to the environment while ensuring the safe operation of the system.

[0050] 1.EENS ​​reliability index

[0051] In this embodiment, the indicators of power system reliability include expected load not supplied (ELNS), lost load probability (LOLP), expected power shortage, etc. The expected power shortage refers to the power shortage of the power system due to the forced shutdown of the unit. First, the expected power shortage EENS is standardized by the reliability indicator, namely (expected energy not supplied ratio) EENSR, and the standardization is as follows:

[0052]

[0053] Where: EENSR is the expected proportion of insufficient power; LR is the total load loss value; TB is the power outage time.

[0054] This embodiment discusses three situations. The first is that the system's backup capacity is greater than the power generation capacity of the shutdown unit; the second is that the power generation capacity of the shutdown unit is greater than the system's backup capacity; the third is that the power generation capacity of the shutdown unit is equal to the backup capacity. This embodiment controls the EENS within a certain range for the second situation, and finally quantifies the system's minimum required backup. Assuming that the current system has N units running and only one unit is shut down or no unit is shut down, there are a total of N+1 fault scenarios. Among them, the EENS caused by the shutdown capacity of unit i under scenario S can be handled by the polygonal regional rotation timed power outage solution of this embodiment.

[0055] 2. Polygonal area rotation timed power outage plan

[0056] In this embodiment, the polygonal regional rotating timed power outage scheme is proposed for the demand side, and its purpose is to minimize the economic impact caused by excessive power outages on the high-load areas within the power outage range. Since most of the central areas of urban areas belong to key load areas, the power outage range of this embodiment does not involve this area. The area affected by the fault is divided into n equal parts by polygons, and the divided areas are A1, A2...An. A1, A2...An, each area has an asymmetric load, and the power outage time is determined according to the proportion of the load in each area to the total load loss. The sum of the rotating power outage time in each area is the unit fault maintenance time TB. The advantage of this scheme not only takes into account the losses caused by large-scale power outages to the user side, but also takes into account the number of power outage areas divided according to different power loss amounts. The following uses a typical hexagon as a demonstration model to study the relationship between EENS and spare capacity, as shown in Figure 1 As shown, it is a hexagon divided into six equal parts, among which B1, B2...B6 are the urban center, and A1, A2...A6 are the areas with rotating power outages.

[0057] Then the outage capacity caused by the outage failure of unit i in scenario S is:

[0058] P r,s =P i,s +R i,s -R all (2)

[0059] Where: P r,s is the power outage capacity; P i,s is the power generation capacity of the shutdown unit i; R i,s R is the spare capacity that can be provided by the shutdown unit i; all The total spare capacity provided to the system.

[0060] The total power loss defined in this embodiment is the product of the unit outage capacity and the maintenance time, that is:

[0061]

[0062] Where: L An Area A in the power outage range n The load

[0063] Distribute the total power loss to A 1 ,A 2 ……A 6 In the region, the total power loss in different regions is recorded as The principle of allocation is to allocate in proportion to EENSR. The proportional power loss in area 1 is:

[0064]

[0065] Where: The expected value of the acceptable power shortage in area 1.

[0066] Substituting formula (2) and (3) into formula (4) yields:

[0067]

[0068] Where: The minimum required spare capacity for area 1.

[0069] Simulate the N+1 scenario Calculate and sum to get the EENS of area 1 1 value:

[0070]

[0071] Where: β s is the probability of occurrence of fault scenario S, and the formula is as follows:

[0072]

[0073] Where: i ks is a normal unit in scenario S; i os is the faulty unit in scenario S; F ios is the forced outage rate of the unit.

[0074] Formula (5)(6)(7) is combined to get:

[0075]

[0076] According to the reliability index We can get:

[0077]

[0078] Substituting into formula (1) and rearranging it, we can get:

[0079]

[0080] In order to meet the relationship between the reserve and the expected value of power shortage, the minimum reserve capacity required in area 1 is for:

[0081]

[0082] The method for calculating the minimum reserve capacity of the remaining power outage areas is the same as above. Finally, the sum of the reserves of all areas is the minimum total reserve required by the system, that is,

[0083]

[0084] 3. Reserve capacity considering load and wind power output forecast errors

[0085] (1) Load forecasting model:

[0086] L' R =L+ξ L (13)

[0087] Where: L' R is the actual load; L is the predicted load; ξ L is the load forecast deviation. L Generally, it follows that the expectation is 0 and the variance is δ L 2 A normally distributed random variable. Figure 2 As shown in the figure, the continuous load forecast error is approximately discretized into M probability intervals, and the middle value of the interval corresponds to the load forecast error value, that is,

[0088]

[0089] Where: μ M,t The mean of load forecast error; ε M,t is the standard deviation of the interval width.

[0090] (2) Wind power output prediction model:

[0091] P R =P W,j +ξ W (15)

[0092] Where: P R is the actual load; P W,j is the predicted output of wind turbine j; W is the wind power prediction deviation. W Generally, it follows that the expectation is 0 and the variance is δ W 2 Normally distributed random variable.

[0093] The wind power forecast error processing method is the same as the load forecast error processing method, and the middle value of the interval corresponds to the wind power forecast error value, that is,

[0094]

[0095] In this embodiment, the load prediction error ξ L It is regarded as a "negative output" multi-state unit, and each interval represents a state. There is no "unit failure" in the load, so the forced outage rate is considered to be 0. The difference is that the wind power prediction error ξ W The equivalent multi-state unit has unit failures, so the forced outage rate is not 0. Then formula (2) becomes:

[0096]

[0097] Where: is the faulty fan unit n ok The original planned contribution; For normal wind turbines n sj The predicted output deviation.

[0098] The scene probability in formula (7) changes as follows:

[0099]

[0100] Where: F l,s is the state probability of prediction deviation in load failure scenario S; F j,s is the state probability of wind turbine j in fault scenario S.

[0101] Substituting formula (1)(14)(16)(17)(18) into (4)(6), we can obtain the minimum required reserve when wind power is connected to the system at time t.

[0102] 4. Objective Function

[0103] The objective function in this embodiment consists of three parts: carbon trading cost F ct , the operating cost of thermal power units F g , wind turbine group start-up and shutdown costs F w The objective function is expressed as follows

[0104] minF=min(F ct +F g +F w ) (19)

[0105] (1) Carbon trading costs:

[0106] At present, there are two main ways to allocate carbon trading quotas: one is free allocation; the other is paid allocation through auction. In order to promote the better development of the carbon trading market and encourage power generation companies to actively participate, it is most appropriate for the carbon trading market to adopt free initial carbon emission rights allocation and use the baseline method to determine the carbon trading quota.

[0107] Carbon trading costs refer to the government allocating carbon trading quotas to enterprises with emission sources. Enterprises choose to sell the remaining allocated quotas or purchase excess quotas in the carbon emission market based on their actual emissions, which results in economic gains or losses for the enterprises. This is called carbon trading costs.

[0108] The calculation formula for carbon trading costs is as follows:

[0109]

[0110]

[0111]

[0112] Where: K pt is the carbon trading price; E pt is the total carbon emissions in period T; E qt is the carbon emission quota in the corresponding period; N t is the total number of thermal power units; δ i is the carbon emission intensity per unit of electricity of conventional thermal power unit i; P G,it is the power generation plan of the i-th thermal power unit at time t; T is the total number of dispatching time periods; η is the unit power emission allocation t / (MW.h), η is determined by the “regional power grid baseline emission factor” issued by the National Development and Reform Commission; P Dt It is the total power generation of each unit in the system within the unit time period t.

[0113] Thermal power unit operating cost: The operating cost of thermal power units includes coal consumption cost and start-up and shutdown cost, namely

[0114]

[0115] Where: u it is the start / stop status of the i-th thermal power unit at time t, u it =1 indicates that the unit is in operation state, u it =0 indicates that the unit is in shutdown state; a i , b i 、c i is the coal consumption cost coefficient of the i-th thermal power unit; S it is the start-up and shutdown cost of the i-th thermal power unit at time t, and the formula is as follows:

[0116]

[0117] t ih =T i,off +t ic (25)

[0118] Where: is the hot start cost of the i-th unit at time t; is the cold start cost of the i-th unit at time t; T i,off is the minimum continuous shutdown time of the i-th unit; t i,off is the actual continuous shutdown time of the i-th unit; t ih is the intermediate variable; tic is the cold start time of the i-th unit.

[0119] Wind turbine startup and shutdown costs:

[0120] Taking into account the deviation of wind power forecast, in this embodiment, all wind turbines are regarded as one wind turbine group to simplify the calculation, and the start-up and shutdown costs of wind turbines generated in two time periods are calculated. The formula is as follows:

[0121]

[0122] Where: S w is the startup cost of a single wind turbine; p N(t) is the probability of wind power fluctuation error at time t after discretization; P o The capacity of a single wind turbine.

[0123] (2) Constraints:

[0124] 1) Output constraints

[0125]

[0126]

[0127] 2) Power balance constraints

[0128]

[0129] Where: K is the number of wind turbines; P L,t is the load of the system in period t.

[0130] 3) Climbing constraints

[0131] -R di ≤P G,it -P G,i(t-1) ≤R ui (30)

[0132] Where: R di and R ui is the descending and ascending ramp rate of unit i, with a time interval of 1 hour.

[0133] 4) Continuous start-stop constraints

[0134]

[0135]

[0136] Where: T i,on It is the minimum continuous running time of the unit.

[0137] 5) Reliability constraints

[0138] Considering the wind power and load forecast errors, the failure scenario probability of formula (18) is introduced to obtain the reliability constraint, that is,

[0139] Rall ≥R req (33)

[0140] 5. Example Analysis

[0141] (1) Example parameters:

[0142] The wind power economic dispatch model is a mixed integer nonlinear programming problem. In this embodiment, the nonlinear programming problem is converted into a linear programming problem for easy solution. In the RTS-96 test system, 10 thermal power units are retained and 200 wind turbines with a single unit capacity of 2.5MW are added. The carbon emission intensity per unit of electricity of the 10 thermal power units is 0.98, 0.97, 0.97, 1.21, 1.15, 1.21, 0.88, 1.13, 1.17, and 0.42, respectively.

[0143] The average carbon trading price is 59.29 yuan / t, the highest price is 77 yuan / t and the lowest price is 48 yuan / t. Wind power forecast data is obtained from the literature. Figure 3 , load forecast data can be found at Figure 4 .

[0144] (2) Simulation results:

[0145] like Figure 5 The figure shows the impact of carbon trading on the output of thermal power units without taking into account wind power output. Figure 5 Without considering the carbon trading model, Figure 6 To consider the carbon trading model. Figure 5 and Figure 6 It can be seen from the two figures that due to the large capacity and long start-stop time of G1 and G2 units, the unit output does not change under the two models. Figure 5 and Figure 6 In both figures, the output of G6 and G7 units changes at 10-14. Figure 6 Starting from 10 o'clock, the G6 unit with a carbon emission intensity of 1.21 was shut down and replaced by the G7 unit with a carbon emission intensity of 0.88 to generate electricity, with a total replacement output of 360MW. Figure 6 From 14:00 to 17:00, G4, G5, and G6 changed significantly. The G4 and G5 units, whose carbon emission intensities were 1.21 and 1.15 respectively, reduced their output as the load decreased after 14:00, and were replaced by the G3 unit, with a total replacement output of 410MW. The total emissions of the model without considering the carbon trading cost are very high, causing serious damage to the environment. In the model considering the carbon trading cost, low-emission intensity units are used to replace high-emission intensity units under the premise of meeting the constraints. This not only complies with environmentally friendly policies, but also enables enterprises to obtain benefits in the carbon trading market, thereby reducing the system's power generation and operation costs.

[0146] Depend on Figure 5 , Figure 6 and Figure 7 It can be seen that the access to wind power has a great impact on the combination of thermal power units, which is mainly reflected in the downward trend of the overall output of the units. This is also the advantage of clean energy in reducing the consumption of primary energy. Before the access to wind power system, G1 and G2 are fully powered all day and cannot provide backup, but after the access to wind power, G1 and G2 can provide 220MW, 150MW, and 95MW of backup capacity in the 1, 5, 23 and other periods with less load respectively; G3, G4, and G5 can also provide certain backup in multiple periods; while the output of G6, G8, and G10 units is 0MW.

[0147] Table 1 is a comparison of the system reserve capacity and demand reserve capacity before and after the access of wind power. It can be seen from the table that the access of wind power will lead to an increase in the two reserve capacities. This is because the access of wind power will reduce the output of thermal power units and convert part of the output of the original thermal power units into the system's reserve capacity; but the uncertainty of wind power output and unit failures will lead to an increase in EENS, and thus the demand reserve will also increase. However, the difference between the demand reserve and the reserve capacity before and after the access of wind power in the 7th and 13th periods is not much, which is mainly due to the fact that only three thermal power units were put into production at 7 o'clock and were restricted by the limit of reserve capacity. From the above example analysis, it can be obtained that after the access of wind power, both types of system reserves are increasing, but the difference between the two types of reserves before and after the access of the system is significantly different, so coordinating the relationship between the two types of reserves plays an important role in the safe operation of the system.

[0148] Table 1 Comparison of demand reserve and reserve capacity before and after wind power access

[0149]

[0150] Figure 8 It represents the relationship between the system power generation and operation cost, wind power output fluctuation and carbon trading price within a year. Figure 8 It can be seen from the figure that wind turbines generate more power in spring and autumn, which is closely related to the natural climate of a certain area. When the wind power penetration rate is high, thermal power units can reduce their output and put the excess emissions into the carbon trading market to make a profit. Fig. 9 The power generation and operation cost of the medium-sized system is about 60,000 to 70,000 yuan / day less in spring and autumn than in other seasons. Fig. 9 It can also be seen that the operating cost of power generation in autumn is lower than that in spring. The main reason is that the carbon trading price in autumn is higher than that in spring, so the company's profit in the carbon trading market increases. Figure 8As can be seen from the above, the power generation cost is 2.27 million yuan per day for most of the year. From the above calculation example, it can be seen that the system power generation operation cost is related to the output of the wind turbine, and is less affected by the carbon trading price, but the carbon emission quota factor allocated to the carbon emission source cannot be ignored. For enterprises that have been allocated carbon emission quotas, if the actual carbon emission quotas of the enterprise are sufficient, they can make profits by selling the excess quotas. If the quotas are insufficient, they need to purchase, which increases the operating costs.

[0151] As can be seen from Table 2, with the increase of wind power grid penetration rate, the start-up and shutdown costs of wind power also increase, but when the wind power grid penetration rate increases from 20% to 30%, the increase of wind power start-up and shutdown costs slows down. The main reason is that the wind power grid penetration rate increases, but the start-up and shutdown frequency of wind turbines decreases. As can be seen from Table 2, the start-up and shutdown costs of wind power can be ignored at low penetration rates. The system operation cost decreases with the increase of wind power grid penetration, but the degree of cost reduction is affected by the wind power grid penetration limit.

[0152] Table 2 Relationship between wind power start-up and shutdown costs and wind power grid access rate

[0153]

[0154] from Fig.10 It can be seen that the required reserve capacity of each unit in the system is increasing when the EENS index is considered compared with that when the EENS is not considered, with the maximum increase of 32MW and the minimum increase of 6MW, a total increase of 427MW. Although the consideration of EENS in the study of this embodiment will increase the system operating cost, it enhances the reliability of the system.

[0155] From Table 3, it can be seen that the system operation cost considering EENS increases by 11.58% compared with that not considering EENS. The reason is that the economic dispatch considering the reliability index of EENS leads to an increase in demand reserve, thereby sacrificing economy to improve system reliability, resulting in an increase in system operation cost.

[0156] Table 3 Impact of EENS reliability index on system operation cost

[0157]

[0158] Embodiment 2:

[0159] This embodiment provides an economic dispatch system for a wind power system taking into account reliability indicators, including a data acquisition module and a dispatch scheme generation module;

[0160] The data acquisition module is configured to: obtain power system reliability indicators;

[0161] The dispatching scheme generating module is configured to: obtain a dispatching scheme according to the obtained power system reliability index and the preset power system economic dispatching optimization model;

[0162] Among them, when obtaining the reliability index of the power system, the uncertainty of wind power generation and the unplanned shutdown of unit failures are taken into account; the power system economic dispatch optimization model takes the lowest carbon trading cost, the lowest operating cost of thermal power units and the lowest start-up and shutdown cost of wind turbine groups as optimization goals.

[0163] Embodiment 3:

[0164] This embodiment provides a computer-readable storage medium on which a computer program is stored. When the program is executed by a processor, the steps of the economic dispatch method of a wind power system taking into account reliability indicators described in Example 1 are implemented.

[0165] Embodiment 4:

[0166] This embodiment provides an electronic device, including a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the program, the steps of the economic dispatch method for a wind power system taking into account reliability indicators described in Example 1 are implemented.

[0167] The above description is only a preferred embodiment of the present embodiment and is not intended to limit the present embodiment. For those skilled in the art, the present embodiment may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present embodiment shall be included in the protection scope of the present embodiment.

Claims

1. An economic dispatch method for a wind power system taking into account reliability indicators, characterized in that: include: Obtain power system reliability indicators; Obtain a dispatching plan based on the obtained power system reliability index and the preset power system economic dispatching optimization model; Among them, when obtaining the reliability index of the power system, the uncertainty of wind power generation and the unplanned shutdown of unit failure are taken into account; the power system economic dispatch optimization model takes the lowest carbon trading cost, the lowest operating cost of thermal power units and the lowest start-up and shutdown cost of wind turbine groups as optimization goals; The reliability index of the power system is an expected value of power shortage. After the expected value of power shortage is obtained, the reliability index of the expected value of power shortage is standardized according to the total load loss value and the power outage time; Based on the reliability index of the expected value of power shortage, a polygonal regional rotation timed power outage plan is formulated to determine the minimum required spare capacity of the system; the area affected by the fault is divided into multiple areas by polygons, and the power outage time is determined according to the proportion of the load in each area to the total load loss. The sum of the rotation power outage time in each area is the unit fault maintenance time; The content of determining the relationship between the expected value of power shortage and the reserve capacity using the polygonal regional rotation timed power outage plan includes: The outage capacity is determined based on the power generation capacity of the outage units, the spare capacity that can be provided by the outage units and the total spare capacity provided by the system; The total power loss is determined by the product of the outage capacity and the length of maintenance time; The total power loss is distributed to multiple areas respectively. The distribution principle is to distribute in proportion to the expected value of power shortage, and the total power loss in different areas is obtained. Calculate the reliability index of the expected value of power shortage in each area based on the probability of occurrence of the fault scenario; According to the relationship between the reliability index of the expected value of power shortage in each area and the acceptable expected value of power shortage, the relationship between the reserve and the expected value of power shortage is determined to obtain the minimum reserve capacity required in each area; The sum of the reserves in all areas is the minimum total reserve required by the system.

2. The economic dispatch method for wind power power system taking into account reliability index according to claim 1, characterized in that: The probability of occurrence of the fault scenario is determined based on the normal units, faulty units and the forced outage rate of the units.

3. The economic dispatch method for wind power power system taking into account reliability index according to claim 1, characterized in that: When determining the reserve capacity, the load and wind power output forecast errors are taken into account.

4. The economic dispatch method for wind power power system taking into account reliability index according to claim 1, characterized in that: The constraints of the power system economic dispatch optimization model include output constraints, power balance constraints, ramp constraints, continuous start-stop constraints and reliability constraints.

5. An economic dispatch system for a wind power system taking into account reliability indicators, characterized in that: Applying the method as described in any one of claims 1 to 4, specifically comprising a data acquisition module and a scheduling scheme generation module; The data acquisition module is configured to: obtain power system reliability indicators; The dispatching scheme generating module is configured to: obtain a dispatching scheme according to the obtained power system reliability index and the preset power system economic dispatching optimization model; Among them, when obtaining the reliability index of the power system, the uncertainty of wind power generation and the unplanned shutdown of unit failures are taken into account; the power system economic dispatch optimization model takes the lowest carbon trading cost, the lowest operating cost of thermal power units and the lowest start-up and shutdown cost of wind turbine groups as optimization goals.

6. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, the economic dispatch method for a wind power system taking into account reliability indicators as described in any one of claims 1 to 4 is implemented.

7. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the program, the economic dispatch method for a wind power system taking into account reliability indicators as described in any one of claims 1 to 4 is implemented.