A composite partition wall system and installation method thereof

By using the composite partition wall system in a narrow space and using the composite partition wall system with H-shaped steel guide rails and concave and concave and concave slot structures, the problem of wall panel installation in a narrow space is solved, and the rapid installation of wall panels and the improvement of earthquake resistance is achieved. .

CN114293831BActive Publication Date: 2024-11-08QINGDAO ZHONGKE KUNTAI TECHNICAL MATERIALS CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210047722.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-01-17
Publication Date
2024-11-08
Estimated Expiration
2042-01-17

AI Technical Summary

Technical Problem

When installing middle partition walls in a narrow space, the prior art has the problem that wall panel components are difficult to install, time-consuming and labor-intensive, and earthquake-resistant structures are difficult to meet the fortification requirements.

Method used

The composite middle partition wall system is adopted, including the middle partition wall panel connecting guide device, top anchoring device, bottom anchoring device, fork lifting device and clamping fixture, and the guide of the wall panel is achieved by using the H-shaped steel guide rail and concave and concave and convex and concave and convex groove structure. and fixed, adjust the device state through its own gravity to reduce external power demand.

Benefits of technology

It realizes rapid and simple installation of wall panels, improves production efficiency, reduces the difficulty of operation of workers, enhances construction efficiency and earthquake resistance, and saves materials and costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114293831B_ABST
    Figure CN114293831B_ABST
Patent Text Reader

Abstract

The present invention discloses a composite middle partition wall system and its installation method, including a middle partition wall panel connection guide device, a top anchor device, a bottom anchor device, and a fork lifting device and a clamping fixture for transporting the middle partition wall panel connection guide device, the middle partition wall panel connection guide device includes an H-shaped steel body, the H-shaped steel body includes two flange plates and an intermediate web portion, and the middle partition wall panel connection guide device also includes a top connection anchor plate fixed to the H-shaped steel body and the top structure and a bottom connection anchor plate fixed to the bottom structure, the present invention relates to the field of building technology. The composite middle partition wall system and its installation method make full use of the shape of the H-shaped steel guide rail to achieve the guiding and conveying effect of the H-shaped steel on the wall panel, and can also achieve the positioning and clamping effect of the H-shaped steel wing plate on the wall panel, reduce complex on-site construction, facilitate and quickly install the wall, improve production efficiency, reduce the difficulty of workers' operation, and save time and effort.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of construction, in particular to a composite middle partition wall system and an installation method thereof. Background Art

[0002] With the rapid development of cities, the inadaptability caused by external changes has inevitably appeared in the built structures or existing buildings, and it is inevitable to partially or completely transform or update some environments. Especially when the built underground structures or existing buildings need to separate the space, when the left and right ends are free ends, columns are needed to increase the stability of the wall. Especially in the narrow structure without two side support columns, the wall panel components are not easy to install in place, and the installation process requires on-site pouring or masonry of columns, which is time-consuming and labor-intensive, and the seismic structure is difficult to meet the fortification requirements. Therefore, it is necessary to provide a simple structure and easy operation of the middle partition wall system. Summary of the invention

[0003] 1. Technical issues to be solved

[0004] In view of the deficiencies in the prior art, the present invention provides a composite middle partition wall system and an installation method thereof, which overcome the drawbacks that in some current narrow structures, the left and right ends are free ends, large mechanical equipment is difficult to operate when it is necessary to separate the space, wall panel components are difficult to install in place, the installation process is time-consuming and labor-intensive, and the seismic-resistant structure is difficult to meet the defense requirements. Therefore, a composite middle partition wall system is adopted to achieve a space separation installation method with firm connection, good sealing effect and good seismic effect.

[0005] (II) Technical solution

[0006] To achieve the above objectives, the present invention is implemented through the following technical solutions: a composite middle partition wall system, including a middle partition wall panel connecting guide device, a top anchor device, a bottom anchor device, and a fork lifting device and a clamping clamp for transporting the middle partition wall panel connecting guide device.

[0007] The middle partition wall panel connecting guide device includes an H-shaped steel body, which includes two flange plates and an intermediate web portion, and the middle partition wall panel connecting guide device also includes a top connecting anchor plate fixed to the H-shaped steel body and the top structure, and a bottom connecting anchor plate fixed to the bottom structure, the top connecting anchor plate and the bottom connecting anchor plate are both welded to the H-shaped steel body, and the top connecting anchor plate and the bottom connecting anchor plate are both reserved with bolt insertion holes.

[0008] The top connecting anchor plate is square, rectangular or circular, and the bottom connecting anchor plate is square, rectangular or circular. To facilitate the middle partition wall panel to fall onto the bottom structure, the lower end of the bottom connecting anchor plate is opened into a "concave" or "H" shape.

[0009] On the upper, middle or lower part of the H-shaped steel main body in the intermediate partition wall panel connection guiding device, both sides of one flange plate are cut off, and the middle part of the flange plate in contact with the web is cut into concave-convex clamping grooves. The convex end of the supplementary flange corresponding to the concave-convex clamping grooves has vertical holes. The wall panel enters the vertical guide rail formed by the H-shaped steel main body through the notch of the concave-convex clamping grooves here and can be slidably installed up and down. The two flange plates play a role of clamping and fixing. After all the wall panels are installed, the supplementary flange is clamped to the concave-convex clamping grooves and welded firmly.

[0010] The protruding end of the concave-convex clamping groove is in the shape of an isosceles trapezoid, with a narrow outer and wide inner mode, so that the supplementary flange can be better clamped together. The widest part is just clamped tightly with the length of the vertical hole of the supplementary flange, and the narrow outer part facilitates the vertical hole of the supplementary flange to be better clamped with the concave-convex clamping groove.

[0011] The fork-lift lifting device is welded by square tubes. One end is a cross beam connecting two fork teeth. Semi-circular clamping grooves are welded on both fork teeth. The fork-lift lifting device and the clamping fixture are auxiliary devices for installing the intermediate partition wall panel connection guiding device and can be disassembled and reused after installation.

[0012] Preferably, the bottom anchoring device is a foundation bolt. During installation, it is tightened one by one corresponding to the bolt insertion holes reserved on the bottom connection anchor plate in advance. The fixing nuts of the bottom anchoring device are divided into a first nut and a second nut. During installation, the upper and lower two nuts first fix the bottom anchoring device to the bottom connection anchor plate and adjust the bottom anchoring device to the topmost position.

[0013] Preferably, the top anchoring device is an expansion bolt or a chemical bolt.

[0014] Preferably, the clamping fixture includes a fixture skeleton, a roller and a clamping bolt. The fixture skeleton is in the shape of a "C" structure, and rollers are welded on the outside of the fixture skeleton. Bolt holes are reserved at the front end of the outermost side of the fixture skeleton, so that the clamping bolt passes through the bolt holes, and then nuts are screwed on both sides of the clamping bolt respectively to tighten the fixture.

[0015] Preferably, the clamping fixture is a threaded roller with threads in the middle directly penetrating through the two flange plates of the intermediate partition wall panel connection guiding device, and plays a clamping role by tightening the clamping nuts on both sides.

[0016] Preferably, after the clamping fixture clamps the intermediate partition wall panel connection guiding device, the roller is clamped into the semi-circular clamping grooves of the two fork teeth of the fork-lift lifting device. With the increase of the lifting height, due to its own gravity, as the center of gravity moves down, the roller rolls in the semi-circular clamping grooves, and the intermediate partition wall panel connection guiding device on the left and right can be adjusted from the horizontal state to the appropriate vertical state without applying external power.

[0017] Preferably, the clamping fixture is installed above the center of gravity of the middle partition wall panel connecting guide device. During installation, the different lifting heights facilitate the adjustment of the middle partition wall panel connecting guide device from a horizontal state to a vertical state by its own gravity.

[0018] The present invention also provides a method for installing a composite partition wall system, which specifically comprises the following steps:

[0019] S1. The wall panels and the connecting guide devices of the middle partition wall panels are prefabricated, welded, cut and transported to the site in advance in the factory;

[0020] S2. After arriving at the installation site, the fork lifting device is fixed on the fork tine of the forklift, and the clamping clamp fixes and clamps the middle partition wall panel connecting guide device. The rollers or threaded rollers on both sides of the clamping clamp are clamped into the semicircular arc-shaped grooves of the two fork tines of the fork lifting device. The upper end of the middle partition wall panel connecting guide device is tilted toward the crossbeam end of the fork lifting device and fixed on the forklift. The bottom anchoring device is fixed to the bottom connecting anchor plate through the first nut and the second nut respectively, and the bottom anchoring device is raised to the top, so that the middle partition wall panel connecting guide device can swing to a suitable range;

[0021] S3. The middle partition wall panel connection guide device is installed by lifting with a forklift in a small and confined space. With the change of the lifting height of the forklift, due to the effect of its own gravity, as the center of gravity is lowered, the roller or the threaded roller rolls in the semicircular groove. Without applying an external power source, the middle partition wall panel connection guide device can be slowly swung from a horizontal tilted state to a vertical state. After the middle partition wall panel connection guide device is vertical, the bottom end connected to the anchor plate corresponds to the position of the reserved bottom groove of the bottom structure;

[0022] S4. Install the top connection anchor plate first, tighten the top anchor device to the top structure and then loosen it by one and a half buckles, then loosen the two nuts of the bottom anchor device, lower the bottom anchor device to the appropriate position of the reserved bottom groove, grout the reserved bottom groove, grout the bottom anchor device and the bottom structure, tighten the top anchor device after the bottom grouting material hardens and has a certain strength, adjust the bottom anchor device after it is fully tightened, and tighten the first nut and the second nut at the same time;

[0023] S5. After the middle partition wall panel connecting guide devices on both sides of the wall panel are installed and fixed to the designated positions, the wall panel is passed through the concave and convex slots and enters the guide rail formed by the two flange plates of the middle partition wall panel connecting guide device. The two flange plates of the middle partition wall panel connecting guide device are used as guide devices and can be clamped and fixed to the wall panel;

[0024] S6. If the concave-convex slot is located at the upper part of the connecting guide device of the middle partition wall panel, install all the wall panels to the concave-convex slot from bottom to top in sequence. After the last panel is installed, the rear-filled wing panel is clamped to the concave-convex slot of the web and welded firmly. If the concave-convex slot is located in the middle part of the connecting guide device of the middle partition wall panel, install the lower wall panel first, and then install the upper wall panel after it is installed to the concave-convex slot position. The top wall panel is clamped to the top structure, and then the wall panel near the concave-convex slot is installed, and then the rear-filled wing panel is clamped to the concave-convex slot of the web and welded firmly. When the concave-convex slot is located at the lower part of the connecting guide device of the middle partition wall panel, install it in reverse gravity, install the top one first, and then fix it, and then install it in sequence until the bottom wall panel is installed, and then clamp the rear-filled wing panel to the concave-convex slot of the web and weld it firmly.

[0025] S7. After the wall panels are installed, the gaps between the wall panels and the top structure or the wall panels and the bottom structure, and between the wall panels and the flange plates of the connecting guide devices of the middle partition wall panels are grouted, and the gaps between the bottom anchor devices and the bottom structure are grouted again, which not only transfers the upper end load to the bottom anchor device to the bottom structure, which has a stabilizing effect on the foundation, but also protects the anchor bolts of the above-ground part from corrosion;

[0026] S8. After installing one set of the middle partition wall panel connecting guide device, the fork lifting device and the clamping fixture are disassembled and reused, and the next set is installed;

[0027] Preferably, the wall panel is a prefabricated middle wall panel or a lightweight partition wall decorative panel, and the thickness of the wall panel matches the distance between the two flange panels of the H-shaped steel body. The best is that the thickness of the wall panel is less than or equal to the distance between the two flange panels of the H-shaped steel body, so that the wall panel can smoothly enter the track formed by the H-shaped steel body and can pass smoothly up and down the track;

[0028] Preferably, wall panels are installed on both sides of the middle partition wall panel connecting guide device. When the installation location is wide and a section of wall panel cannot form an enclosed space, the wall panel is also installed on the other side of the H-shaped steel. After the wall panels are installed on both sides of the H-shaped steel, the rear wing plates are installed and clamped on the concave and convex grooves and welded firmly. When the bottom connecting anchor plate is square, rectangular or circular, the wall panel cannot fall completely on the bottom structure. In order to ensure the closure of the partition wall, the gap at the lower end of the wall panel is grouted. When the lower end of the bottom connecting anchor plate is opened into a "concave" or "H" shape, the wall panel can be in close contact with the bottom structure.

[0029] (III) Beneficial effects

[0030] The present invention provides a composite middle partition wall system and an installation method thereof. Compared with the prior art, the system has the following beneficial effects:

[0031] (1) The composite middle partition wall system and its installation method make full use of the shape of the H-shaped steel guide rail to realize the guiding and conveying effect of the H-shaped steel on the wall panel, and can also realize the positioning and clamping effect of the H-shaped steel wing plate on the wall panel, thereby reducing the complex construction on site, facilitating and quickly installing the wall, improving production efficiency, reducing the difficulty of workers' operation, and saving time and effort.

[0032] (2) The composite middle partition wall system and its installation method can make the wall panel better inserted into the guide groove of the H-shaped steel in the presence of upper and lower top plates and floor (ground) by cutting and filling the H-shaped steel guide rail web groove. The concave and convex shape of the web groove makes it easier to install the wing plate and also ensures a firm installation connection.

[0033] (3) The composite partition wall system and its installation method, wherein the wall panel guide device can be quickly operated and installed by a small lifting device such as a forklift, and can be used in a narrow installation space with a small overhead height.

[0034] (4) The composite middle partition wall system and its installation method, through the roller connection between the fork lifting device and the clamping fixture, assists the middle partition wall panel connecting guide device to be installed in a narrow space, and does not require the application of external power. The H-shaped steel installation state can be well adjusted by its own gravity. The auxiliary device is detachable and reusable, saving materials, and is easy to install and construct.

[0035] (5) The composite middle partition wall system and its installation method can not only clamp and position the upper and lower adjacent wall panels through the H-shaped steel positioning and connecting guide device, but also simultaneously form a good splicing effect for the left and right adjacent panels. Only a single H-shaped steel guide rail is needed on both sides, which saves space and cost.

[0036] (6) The composite middle partition wall system and its installation method use vertical H-shaped steel as a positioning and connecting guide device and fix the connecting wall panels. The installation process is simple, which can effectively enhance the construction efficiency, provide convenience for factory production, standardization and industrialization, reduce construction costs and facilitate promotion. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] Figure 1 It is an assembly front view of the partition wall positioning and connecting guide system of the present invention;

[0038] Figure 2 It is an assembly isometric view of the partition wall positioning and connecting guide system of the present invention;

[0039] Figure 3 This is a disassembled diagram of the partition wall panel connecting guide device of the present invention;

[0040] Figure 4 It is an assembly diagram of the partition wall panel connecting guide device of the present invention;

[0041] Figure 5 It is a structural schematic diagram of the concave-convex card slot of the present invention;

[0042] Figure 6 is a schematic diagram of the bottom anchoring device of the present invention;

[0043] Figure 7 is a schematic diagram of the top anchoring device of the present invention;

[0044] Figure 8 is a schematic diagram of a fork tine lifting device of the present invention;

[0045] Fig. 9 Schematic diagram of the clamping fixture of Embodiment 1-3 of the present invention;

[0046] Fig.10 This is a schematic diagram of a clamping fixture according to Embodiment 4 of the present invention;

[0047] Fig.11 It is a schematic diagram of the installation of the fork tine lifting device and the clamping fixture of Embodiment 1-3 of the present invention;

[0048] Fig.12 It is a schematic diagram of the installation of the fork tine lifting device and the clamping fixture of Example 4 of the present invention;

[0049] Fig.13 Schematic diagram of the installation of the fork lifting device and the clamping fixture of Examples 1-3 during the installation process of the present invention;

[0050] Fig.14 It is a schematic diagram of the installation of the fork tine lifting device and the clamping fixture of Example 4 during the installation process of the present invention;

[0051] Fig.15 It is an assembly perspective view of the partition wall positioning and connecting guide system during the installation process of the present invention;

[0052] Fig.16 This is a schematic diagram of the first wall panel installation during the installation process of the present invention;

[0053] Fig.17 This is a schematic diagram of the wall panel stacking installation during the installation process of the present invention;

[0054] Fig.18 This is a schematic diagram of the preparation for installation of the rear wing plate during the installation process of the present invention;

[0055] Fig.19 This is a schematic diagram of the completion of the installation of the rear wing plate during the installation process of the present invention;

[0056] Fig. 20 It is a schematic diagram of the horizontal side-by-side installation of multiple wall panels during the installation process of the present invention.

[0057] In the figure, 1-top structure, 2-middle partition wall panel connecting guide device, 21-concave and convex groove, 22-rear wing plate, 23-bottom connection anchor plate, 24-top connection anchor plate, 3-wall panel, 4-bottom structure, 41-reserved bottom groove, 5-fork tooth lifting device, 51-semicircular groove, 6-top anchor device, 7-bottom anchor device, 71-first nut, 72-second nut, 8-clamping clamp, 81-clamping bolt, 82-roller, 82'-threaded roller, 83-clamping nut. DETAILED DESCRIPTION

[0058] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0059] See also Figure 1-20 The embodiments of the present invention provide four technical solutions: a composite middle partition wall system and an installation method thereof, specifically including the following embodiments:

[0060] Example 1

[0061] A composite middle partition wall system, comprising a middle partition wall panel connecting guide device 2, a top anchoring device 6, a bottom anchoring device 7, and a fork lifting device 5 and a clamping fixture 8 for transporting the middle partition wall panel connecting guide device 2;

[0062] The middle partition wall panel connecting guide device 2 includes an H-shaped steel body, the H-shaped steel body includes two flange plates and a middle web portion, and the middle partition wall panel connecting guide device 2 also includes a top connecting anchor plate 24 fixed to the H-shaped steel body and the top structure 1, and a bottom connecting anchor plate 23 fixed to the bottom structure 4, the top connecting anchor plate 24 and the bottom connecting anchor plate 23 are both welded to the H-shaped steel body, and the top connecting anchor plate 24 and the bottom connecting anchor plate 23 are both reserved with bolt insertion holes;

[0063] The top connecting anchor plate 24 is square, rectangular or circular, and the bottom connecting anchor plate 23 is square, rectangular or circular. To facilitate the middle partition wall panel to fall onto the bottom structure 4, the lower end of the bottom connecting anchor plate 23 is opened into a "concave" or "H" shape;

[0064] In the middle partition wall panel connection guiding device 2, both sides of the upper part of the H-shaped steel main body are cut off one flange plate, and the middle part of the flange plate in contact with the web is cut into concave-convex clamping grooves 21. The convex end of the supplementary flange plate 22 corresponding to the concave-convex clamping grooves 21 has a vertical hole. The wall panel 3 enters the vertical guide rail formed by the H-shaped steel main body through the notch of the concave-convex clamping grooves 21 here and can be slidably installed up and down. The two flange plates play a role of clamping and fixing. After the wall panel 3 is completely installed, the supplementary flange plate 22 is clamped to the concave-convex clamping grooves 21 and welded firmly;

[0065] The protruding end of the concave-convex clamping grooves 21 is in an isosceles trapezoid shape, with a narrow outer and wide inner mode, so that the supplementary flange plate 22 can be better clamped together. The widest part is just clamped tightly with the length of the vertical hole of the supplementary flange plate 22, and the narrow outer part facilitates the vertical hole of the supplementary flange plate 22 to be better clamped to the concave-convex clamping grooves 21;

[0066] The fork-lift device 5 is welded by square tubes. One end is a cross beam connecting two fork teeth. Semi-circular arc-shaped clamping grooves 51 are welded on both fork teeth. The fork-lift device 5 and the clamping fixture 8 are auxiliary devices for installing the middle partition wall panel connection guiding device 2 and can be disassembled and reused after installation.

[0067] In the embodiment of the present invention, the bottom anchoring device 7 is a foundation bolt. During installation, it is tightened one by one corresponding to the bolt insertion holes reserved on the bottom connection anchor plate 23 in advance. The fixing nuts of the bottom anchoring device 7 are divided into a first nut 71 and a second nut 72. During installation, the upper and lower two nuts first fix the bottom anchoring device 7 to the bottom connection anchor plate 23 and adjust the bottom anchoring device 7 to the topmost position.

[0068] In the embodiment of the present invention, the top anchoring device 6 is an expansion bolt.

[0069] As Fig.10 shown, in Embodiment 1 of the present invention, the clamping fixture 8 includes a fixture skeleton, a roller 82 and a clamping bolt 81. The fixture skeleton is in a "C" shape structure, and the roller 82 is welded on the outside of the fixture skeleton. A bolt hole is reserved at the outermost front end of the fixture skeleton, so that the clamping bolt 81 passes through the bolt hole, and then nuts are respectively screwed on both sides of the clamping bolt 81 to tighten the fixture.

[0070] In the embodiment of the present invention, after the clamping fixture 8 clamps the middle partition wall panel connection guiding device 2, the roller 82 is clamped into the semi-circular arc-shaped clamping grooves 51 of the two fork teeth of the fork-lift device 5. With the increase of the lifting height, due to its own gravity, as the center of gravity is lowered, the roller 82 rolls in the semi-circular arc-shaped clamping grooves 51, and without applying external power, the left and right middle partition wall panel connection guiding devices 2 can be adjusted from a horizontal state to a suitable vertical state.

[0071] In the embodiment of the present invention, the clamping fixture 8 is installed at a position above the center of gravity of the middle partition wall panel connecting guide device 2. During installation, the middle partition wall panel connecting guide device 2 can be adjusted from a horizontal state to a vertical state by its own gravity through different lifting heights.

[0072] The embodiment of the present invention further provides a method for installing a composite middle partition wall system, which specifically includes the following steps:

[0073] S1, the wall panels 3 and the middle partition wall panel connecting guide device 2 are prefabricated, welded, cut and transported to the site in advance in the factory;

[0074] S2. After arriving at the installation site, the fork lifting device 5 is fixed on the fork tine of the forklift, and the clamping clamp 8 is fixed to clamp the middle partition wall panel connecting guide device 2. The rollers 82 on both sides of the clamping clamp are clamped into the semicircular arc-shaped clamping grooves 51 of the two fork tines of the fork lifting device 5. The upper end of the middle partition wall panel connecting guide device 2 is inclined toward the crossbeam end of the fork lifting device 5 and fixed on the forklift. The bottom anchoring device 7 is fixed to the bottom connecting anchor plate 23 by the first nut 71 and the second nut 72 respectively, and the bottom anchoring device 7 is moved to the top, so that the middle partition wall panel connecting guide device 2 can swing to a suitable range.

[0075] S3. Install the middle partition wall panel connecting guide device 2 by lifting with a forklift in a small and confined space. With the change of the lifting height of the forklift, due to its own gravity, as the center of gravity is lowered, the roller 82 rolls in the semicircular slot 51. Without applying an external power source, the middle partition wall panel connecting guide device 2 can be slowly swung from a horizontal tilted state to a vertical state. After the middle partition wall panel connecting guide device 2 is vertical, the bottom end connected to the anchor plate 23 corresponds to the position of the reserved bottom slot 41 of the bottom structure 4.

[0076] S4, first install the top connection anchor plate 24, tighten the top anchor device 6 to the top structure 1 and then loosen it by one and a half buckles, then loosen the two nuts of the bottom anchor device 7, adjust the bottom anchor device 7 down to the appropriate position of the reserved bottom groove 41, grout the reserved bottom groove 41, grout the bottom anchor device 7 and the bottom structure 4, tighten the top anchor device 6 after the bottom grouting material hardens and has a certain strength, and then adjust the bottom anchor device 7 after it is fully tightened, and tighten the first nut 71 and the second nut 72 at the same time;

[0077] S5. After the middle partition wall panel connecting guide device 2 on both sides of the wall panel 3 is installed and fixed to the designated position, the wall panel 3 is passed through the concave-convex slot 21 and enters the guide rail formed by the two flange plates of the middle partition wall panel connecting guide device 2. The two flange plates of the middle partition wall panel connecting guide device 2 are used as guide devices to clamp and fix the wall panel;

[0078] S6. If the concave-convex groove 21 is located at the upper part of the connecting guide device 2 of the middle partition wall panel, all the wall panels 3 are sequentially installed from bottom to top to the concave-convex groove 21. After the last panel is installed, the wing plate 22 is clamped to the concave-convex groove 21 of the web plate and welded firmly.

[0079] S7. After the wall panel 3 is installed, the gaps between the wall panel 3 and the top structure 1 or the wall panel 3 and the bottom structure 4, and between the wall panel 3 and the flange plate of the intermediate partition wall panel connecting guide device 2 are grouted, and the gap between the bottom anchor device 7 and the bottom structure 4 is grouted again, so that the upper end load is transferred to the bottom anchor device 7 to the bottom structure 4, which has a stabilizing effect on the foundation, and also protects the anchor bolts of the above-ground part from corrosion;

[0080] S8, after installing a set of middle partition wall panel connecting guide device 2, the fork lifting device 5 and the clamping fixture 8 are disassembled and reused, and the next set is installed;

[0081] In the embodiment of the present invention, the wall panel 3 is a prefabricated middle wall panel or a lightweight partition wall decorative panel, and the thickness of the wall panel 3 matches the distance between the two flange panels of the H-shaped steel body. The best is that the thickness of the wall panel 3 is less than or equal to the distance between the two flange panels of the H-shaped steel body, so that the wall panel can smoothly enter the track formed by the H-shaped steel body and can pass smoothly up and down the track;

[0082] In the embodiment of the present invention, wall panels 3 are installed on both sides of the middle partition wall panel connecting guide device 2. When the installation location is wide and a section of wall panel cannot form an enclosed space, the wall panel 3 is also installed on the other side of the H-shaped steel. After the wall panels 3 are installed on both sides of the H-shaped steel, the rear wing plates 22 are installed and clamped on the concave and convex grooves 21 and welded firmly. When the bottom end connecting anchor plate 23 is square, rectangular or circular, the wall panel 3 cannot completely fall on the bottom structure 4. In order to ensure the closure of the partition wall, the gap at the lower end of the wall panel 3 is grouted. When the lower end of the bottom end connecting anchor plate 23 is opened into a "concave" or "H" shape, the wall panel 3 can be in close contact with the bottom structure 4.

[0083] Example 2

[0084] A composite middle partition wall system, comprising a middle partition wall panel connecting guide device 2, a top anchoring device 6, a bottom anchoring device 7, and a fork lifting device 5 and a clamping fixture 8 for transporting the middle partition wall panel connecting guide device 2;

[0085] The middle partition wall panel connecting guide device 2 includes an H-shaped steel body, the H-shaped steel body includes two flange plates and a middle web portion, and the middle partition wall panel connecting guide device 2 also includes a top connecting anchor plate 24 fixed to the H-shaped steel body and the top structure 1, and a bottom connecting anchor plate 23 fixed to the bottom structure 4, the top connecting anchor plate 24 and the bottom connecting anchor plate 23 are both welded to the H-shaped steel body, and the top connecting anchor plate 24 and the bottom connecting anchor plate 23 are both reserved with bolt insertion holes;

[0086] The top connecting anchor plate 24 is square, rectangular or circular, and the bottom connecting anchor plate 23 is square, rectangular or circular. To facilitate the middle partition wall panel to fall onto the bottom structure 4, the lower end of the bottom connecting anchor plate 23 is opened into a "concave" or "H" shape;

[0087] The middle part of the H-shaped steel body in the middle partition wall panel connecting guide device 2 is cut off from both sides of a flange plate, and the middle part of the flange plate in contact with the web plate is cut into a concave-convex groove 21, and the convex end of the rear-added flange plate 22 corresponding to the concave-convex groove 21 has a vertical hole, and the wall panel 3 enters the vertical guide rail formed by the H-shaped steel body through the notch of the concave-convex groove 21, and can be slid up and down for installation. The two flange plates play a role of clamping and fixing. After all the wall panels 3 are installed, the rear-added flange plate 22 is clamped to the concave-convex groove 21 and welded firmly;

[0088] The protruding end of the concave-convex slot 21 is an isosceles trapezoid, which is narrow outside and wide inside, so that the rear wing plate 22 can be better clamped together. The widest part is just the length of the vertical hole of the rear wing plate 22, and the narrow outside facilitates the vertical hole of the rear wing plate 22 to better clamp the concave-convex slot 21;

[0089] The fork tine lifting device 5 is welded from a square tube, one end of which is a crossbeam connecting two fork tines. Semicircular arc grooves 51 are welded on both fork tines. The fork tine lifting device 5 and the clamping fixture 8 are auxiliary devices for installing the middle partition wall panel connecting guide device 2, and can be disassembled and reused after installation.

[0090] In the embodiment of the present invention, the bottom anchoring device 7 is a foundation bolt, which is pre-tightened one by one to the bolt insertion hole reserved in the bottom connecting anchor plate 23 during installation, and the fixing nut of the bottom anchoring device 7 is divided into a first nut 71 and a second nut 72. During installation, the upper and lower nuts first fix the bottom anchoring device 7 to the bottom connecting anchor plate 23, and adjust the bottom anchoring device 7 to the top.

[0091] In the embodiment of the present invention, the top anchoring device 6 is a chemical bolt.

[0092] In the embodiment of the present invention, the clamping fixture 8 includes a fixture skeleton, a roller 82 and a clamping bolt 81. The fixture skeleton has a "C" - shaped structure, and the roller 82 is welded to the outside of the fixture skeleton. A bolt hole is reserved at the outermost front end of the fixture skeleton, so that the clamping bolt 81 passes through the bolt hole, and then nuts are screwed on both sides of the clamping bolt 81 respectively to tighten the fixture.

[0093] In the embodiment of the present invention, after the clamping fixture 8 clamps the middle partition wall panel connection guiding device 2, the roller 82 is stuck into the semi - circular arc - shaped clamping grooves 51 of the two forks of the fork - tooth lifting device 5. With the increase of the lifting height, due to its own gravity, as the center of gravity descends, the roller 82 rolls in the semi - circular arc - shaped clamping grooves 51. Without applying external power, the left - and - right middle partition wall panel connection guiding devices 2 can be adjusted from a horizontal state to a suitable vertical state.

[0094] In the embodiment of the present invention, the clamping fixture 8 is installed at a position above the center of gravity of the middle partition wall panel connection guiding device 2. During installation, by different lifting heights, it is convenient for the middle partition wall panel connection guiding device 2 to be adjusted from a horizontal state to a vertical state by its own gravity.

[0095] The embodiment of the present invention also provides an installation method for a composite middle partition wall system, which specifically includes the following steps:

[0096] S1. The wall panel 3 and the middle partition wall panel connection guiding device 2 are prefabricated, welded and cut in the factory in advance, and then transported to the site;

[0097] S2. After arriving at the installation site, the fork - tooth lifting device 5 is fixed on the fork teeth of the forklift, the clamping fixture 8 is fixed to clamp the middle partition wall panel connection guiding device 2, the rollers 82 on both sides of the clamping fixture are stuck into the semi - circular arc - shaped clamping grooves 51 of the two forks of the fork - tooth lifting device 5. The upper end of the middle partition wall panel connection guiding device 2 inclines towards the cross - beam end of the fork - tooth lifting device 5 and is fixed on the forklift. The bottom anchoring device 7 is respectively fixed on the bottom connecting anchor plate 23 through the first nut 71 and the second nut 72, and the bottom anchoring device 7 reaches the topmost end so that the middle partition wall panel connection guiding device 2 can swing within a suitable range;

[0098] S3. In a narrow and enclosed space, through the lifting of the forklift, the middle partition wall panel connection guiding device 2 is installed. Due to the change of the lifting height of the forklift, due to its own gravity, as the center of gravity descends, the roller 82 rolls in the semi - circular arc - shaped clamping grooves 51. Without applying an external power source, the middle partition wall panel connection guiding device 2 can be slowly swung from a horizontal inclined state to a vertical state. After the middle partition wall panel connection guiding device 2 is vertical, the bottom connecting anchor plate 23 exactly corresponds to the position of the reserved bottom groove 41 of the bottom structure 4.

[0099] S4, first install the top connection anchor plate 24, tighten the top anchor device 6 to the top structure 1 and then loosen it by one and a half buckles, then loosen the two nuts of the bottom anchor device 7, adjust the bottom anchor device 7 down to the appropriate position of the reserved bottom groove 41, grout the reserved bottom groove 41, grout the bottom anchor device 7 and the bottom structure 4, tighten the top anchor device 6 after the bottom grouting material hardens and has a certain strength, and then adjust the bottom anchor device 7 after it is fully tightened, and tighten the first nut 71 and the second nut 72 at the same time;

[0100] S5. After the middle partition wall panel connecting guide device 2 on both sides of the wall panel 3 is installed and fixed to the designated position, the wall panel 3 is passed through the concave-convex slot 21 and enters the guide rail formed by the two flange plates of the middle partition wall panel connecting guide device 2. The two flange plates of the middle partition wall panel connecting guide device 2 are used as guide devices to clamp and fix the wall panel;

[0101] S6. If the concave-convex groove 21 is located in the middle of the middle partition wall panel connecting guide device 2, first install the lower wall panel 3, and then install the upper wall panel 3 after it is installed to the concave-convex groove 21. The uppermost wall panel 3 is clamped with the top structure 1. Then, after installing the wall panel 3 near the concave-convex groove 21, clamp the rear wing plate 22 to the web concave-convex groove 21 and weld it firmly.

[0102] S7. After the wall panel 3 is installed, the gaps between the wall panel 3 and the top structure 1 or the wall panel 3 and the bottom structure 4, and between the wall panel 3 and the flange plate of the intermediate partition wall panel connecting guide device 2 are grouted, and the gap between the bottom anchor device 7 and the bottom structure 4 is grouted again, so that the upper end load is transferred to the bottom anchor device 7 to the bottom structure 4, which has a stabilizing effect on the foundation, and also protects the anchor bolts of the above-ground part from corrosion;

[0103] S8, after installing a set of middle partition wall panel connecting guide device 2, the fork lifting device 5 and the clamping fixture 8 are disassembled and reused, and the next set is installed;

[0104] In the embodiment of the present invention, the wall panel 3 is a prefabricated middle wall panel or a lightweight partition wall decorative panel, and the thickness of the wall panel 3 matches the distance between the two flange panels of the H-shaped steel body. The best is that the thickness of the wall panel 3 is less than or equal to the distance between the two flange panels of the H-shaped steel body, so that the wall panel can smoothly enter the track formed by the H-shaped steel body and can pass smoothly up and down the track;

[0105] In the embodiment of the present invention, wall panels 3 are installed on both sides of the middle partition wall panel connecting guide device 2. When the installation location is wide and a section of wall panel cannot form an enclosed space, the wall panel 3 is also installed on the other side of the H-shaped steel. After the wall panels 3 are installed on both sides of the H-shaped steel, the rear wing plates 22 are installed and clamped on the concave and convex grooves 21 and welded firmly. When the bottom end connecting anchor plate 23 is square, rectangular or circular, the wall panel 3 cannot completely fall on the bottom structure 4. In order to ensure the closure of the partition wall, the gap at the lower end of the wall panel 3 is grouted. When the lower end of the bottom end connecting anchor plate 23 is opened into a "concave" or "H" shape, the wall panel 3 can be in close contact with the bottom structure 4.

[0106] Example 3

[0107] A composite middle partition wall system, comprising a middle partition wall panel connecting guide device 2, a top anchoring device 6, a bottom anchoring device 7, and a fork lifting device 5 and a clamping fixture 8 for transporting the middle partition wall panel connecting guide device 2;

[0108] The middle partition wall panel connecting guide device 2 includes an H-shaped steel body, the H-shaped steel body includes two flange plates and a middle web portion, and the middle partition wall panel connecting guide device 2 also includes a top connecting anchor plate 24 fixed to the H-shaped steel body and the top structure 1, and a bottom connecting anchor plate 23 fixed to the bottom structure 4, the top connecting anchor plate 24 and the bottom connecting anchor plate 23 are both welded to the H-shaped steel body, and the top connecting anchor plate 24 and the bottom connecting anchor plate 23 are both reserved with bolt insertion holes;

[0109] The top connecting anchor plate 24 is square, rectangular or circular, and the bottom connecting anchor plate 23 is square, rectangular or circular. To facilitate the middle partition wall panel to fall onto the bottom structure 4, the lower end of the bottom connecting anchor plate 23 is opened into a "concave" or "H" shape;

[0110] The lower part of the H-shaped steel body in the middle partition wall panel connecting guide device 2 is cut off from both sides of a flange plate, and the middle part of the flange plate in contact with the web plate is cut into a concave-convex groove 21, and the convex end of the rear-filled flange plate 22 corresponding to the concave-convex groove 21 has a vertical hole, and the wall panel 3 enters the vertical guide rail formed by the H-shaped steel body through the notch of the concave-convex groove 21, and can be slid up and down for installation. The two flange plates play a role of clamping and fixing. After all the wall panels 3 are installed, the rear-filled flange plate 22 is clamped to the concave-convex groove 21 and welded firmly;

[0111] The protruding end of the concave-convex slot 21 is an isosceles trapezoid, which is narrow outside and wide inside, so that the rear wing plate 22 can be better clamped together. The widest part is just the length of the vertical hole of the rear wing plate 22, and the narrow outside facilitates the vertical hole of the rear wing plate 22 to better clamp the concave-convex slot 21;

[0112] The fork tooth lifting device 5 is welded by square tubes. One end is a cross beam that connects two fork teeth. Semi-circular grooves 51 are welded on both fork teeth. The fork tooth lifting device 5 and the clamping fixture 8 are auxiliary devices for installing the middle partition wall panel connection guiding device 2 and can be disassembled and reused after installation.

[0113] In the embodiment of the present invention, the bottom anchoring device 7 is an anchor bolt. During installation, it is tightened one by one in advance into the bolt insertion holes reserved on the bottom connection anchor plate 23. And the fixing nuts of the bottom anchoring device 7 are divided into a first nut 71 and a second nut 72. During installation, the upper and lower nuts first fix the bottom anchoring device 7 to the bottom connection anchor plate 23, and the bottom anchoring device 7 is adjusted to the topmost position.

[0114] In the embodiment of the present invention, the top anchoring device 6 is an expansion bolt.

[0115] In the embodiment of the present invention, as Fig.10 In Case 1, the clamping fixture 8 includes a fixture skeleton, rollers 82 and clamping bolts 81. The fixture skeleton has a "C" - shaped structure, and rollers 82 are welded on the outer side of the fixture skeleton. Bolt holes are reserved at the outermost front end of the fixture skeleton, so that the clamping bolts 81 pass through the bolt holes, and then nuts are screwed on both sides of the clamping bolts 81 respectively to tighten the fixture.

[0116] In the embodiment of the present invention, after the clamping fixture 8 clamps the middle partition wall panel connection guiding device 2, the rollers 82 are stuck into the semi-circular grooves 51 of the two fork teeth of the fork tooth lifting device 5. With the increase of the lifting height, due to its own gravity, as the center of gravity moves down, the rollers 82 roll in the semi-circular grooves 51, and without applying external power, the left and right middle partition wall panel connection guiding devices 2 can be adjusted from a horizontal state to a proper vertical state.

[0117] In the embodiment of the present invention, the clamping fixture 8 is installed at a position above the center of gravity of the middle partition wall panel connection guiding device 2. During installation, by different lifting heights, it is convenient for the middle partition wall panel connection guiding device 2 to be adjusted from a horizontal state to a vertical state by its own gravity.

[0118] The embodiment of the present invention also provides an installation method for a composite middle partition wall system, which specifically includes the following steps:

[0119] S1. The wall panel 3 and the middle partition wall panel connection guiding device 2 are prefabricated, welded and cut in the factory in advance and then transported to the site;

[0120] S2. After arriving at the installation site, the fork lifting device 5 is fixed on the fork tine of the forklift, and the clamping clamp 8 is fixed to clamp the middle partition wall panel connecting guide device 2. The rollers 82 on both sides of the clamping clamp are clamped into the semicircular arc-shaped clamping grooves 51 of the two fork tines of the fork lifting device 5. The upper end of the middle partition wall panel connecting guide device 2 is inclined toward the crossbeam end of the fork lifting device 5 and fixed on the forklift. The bottom anchoring device 7 is fixed to the bottom connecting anchor plate 23 by the first nut 71 and the second nut 72 respectively, and the bottom anchoring device 7 is moved to the top, so that the middle partition wall panel connecting guide device 2 can swing to a suitable range.

[0121] S3. Install the middle partition wall panel connecting guide device 2 by lifting with a forklift in a small and confined space. With the change of the lifting height of the forklift, due to its own gravity, as the center of gravity is lowered, the roller 82 rolls in the semicircular slot 51. Without applying an external power source, the middle partition wall panel connecting guide device 2 can be slowly swung from a horizontal tilted state to a vertical state. After the middle partition wall panel connecting guide device 2 is vertical, the bottom end connected to the anchor plate 23 corresponds to the position of the reserved bottom slot 41 of the bottom structure 4.

[0122] S4, first install the top connection anchor plate 24, tighten the top anchor device 6 to the top structure 1 and then loosen it by one and a half buckles, then loosen the two nuts of the bottom anchor device 7, adjust the bottom anchor device 7 down to the appropriate position of the reserved bottom groove 41, grout the reserved bottom groove 41, grout the bottom anchor device 7 and the bottom structure 4, tighten the top anchor device 6 after the bottom grouting material hardens and has a certain strength, and then adjust the bottom anchor device 7 after it is fully tightened, and tighten the first nut 71 and the second nut 72 at the same time;

[0123] S5. After the middle partition wall panel connecting guide device 2 on both sides of the wall panel 3 is installed and fixed to the designated position, the wall panel 3 is passed through the concave-convex slot 21 and enters the guide rail formed by the two flange plates of the middle partition wall panel connecting guide device 2. The two flange plates of the middle partition wall panel connecting guide device 2 are used as guide devices to clamp and fix the wall panel;

[0124] S6. When the concave-convex groove 21 is located at the lower part of the connecting guide device 2 of the middle partition wall panel, install it by the counter-gravity method, install the top one first, then fix it, and then install it in sequence until the bottom wall panel 3 is installed, then clamp the rear wing plate 22 to the concave-convex groove 21 of the web plate and weld it firmly;

[0125] S7. After the wall panel 3 is installed, the gaps between the wall panel 3 and the top structure 1 or the wall panel 3 and the bottom structure 4, and between the wall panel 3 and the flange plate of the intermediate partition wall panel connecting guide device 2 are grouted, and the gap between the bottom anchor device 7 and the bottom structure 4 is grouted again, so that the upper end load is transferred to the bottom anchor device 7 to the bottom structure 4, which has a stabilizing effect on the foundation, and also protects the anchor bolts of the above-ground part from corrosion;

[0126] S8, after installing a set of middle partition wall panel connecting guide device 2, the fork lifting device 5 and the clamping fixture 8 are disassembled and reused, and the next set is installed;

[0127] In the embodiment of the present invention, the wall panel 3 is a prefabricated middle wall panel or a lightweight partition wall decorative panel, and the thickness of the wall panel 3 matches the distance between the two flange panels of the H-shaped steel body. The best is that the thickness of the wall panel 3 is less than or equal to the distance between the two flange panels of the H-shaped steel body, so that the wall panel can smoothly enter the track formed by the H-shaped steel body and can pass smoothly up and down the track;

[0128] In the embodiment of the present invention, wall panels 3 are installed on both sides of the middle partition wall panel connecting guide device 2. When the installation location is wide and a section of wall panel cannot form an enclosed space, the wall panel 3 is also installed on the other side of the H-shaped steel. After the wall panels 3 are installed on both sides of the H-shaped steel, the rear wing plates 22 are installed and clamped on the concave and convex grooves 21 and welded firmly. When the bottom end connecting anchor plate 23 is square, rectangular or circular, the wall panel 3 cannot completely fall on the bottom structure 4. In order to ensure the closure of the partition wall, the gap at the lower end of the wall panel 3 is grouted. When the lower end of the bottom end connecting anchor plate 23 is opened into a "concave" or "H" shape, the wall panel 3 can be in close contact with the bottom structure 4.

[0129] Example 4

[0130] A composite middle partition wall system, comprising a middle partition wall panel connecting guide device 2, a top anchoring device 6, a bottom anchoring device 7, and a fork lifting device 5 and a clamping fixture 8 for transporting the middle partition wall panel connecting guide device 2;

[0131] The middle partition wall panel connecting guide device 2 includes an H-shaped steel body, the H-shaped steel body includes two flange plates and a middle web portion, and the middle partition wall panel connecting guide device 2 also includes a top connecting anchor plate 24 fixed to the H-shaped steel body and the top structure 1, and a bottom connecting anchor plate 23 fixed to the bottom structure 4, the top connecting anchor plate 24 and the bottom connecting anchor plate 23 are both welded to the H-shaped steel body, and the top connecting anchor plate 24 and the bottom connecting anchor plate 23 are both reserved with bolt insertion holes;

[0132] The top connecting anchor plate 24 is square, rectangular or circular, and the bottom connecting anchor plate 23 is square, rectangular or circular. To facilitate the middle partition wall panel to fall onto the bottom structure 4, the lower end of the bottom connecting anchor plate 23 is opened into a "concave" or "H" shape;

[0133] The upper part of the H-shaped steel body in the middle partition wall panel connecting guide device 2 is cut off from both sides of a flange plate, and the middle part of the flange plate in contact with the web plate is cut into a concave-convex groove 21, and the convex end of the rear-filled flange plate 22 corresponding to the concave-convex groove 21 has a vertical hole, and the wall panel 3 enters the vertical guide rail formed by the H-shaped steel body through the notch of the concave-convex groove 21, and can be slid up and down for installation. The two flange plates play a role of clamping and fixing. After all the wall panels 3 are installed, the rear-filled flange plate 22 is clamped to the concave-convex groove 21 and welded firmly;

[0134] The protruding end of the concave-convex slot 21 is an isosceles trapezoid, which is narrow outside and wide inside, so that the rear wing plate 22 can be better clamped together. The widest part is just the length of the vertical hole of the rear wing plate 22, and the narrow outside facilitates the vertical hole of the rear wing plate 22 to better clamp the concave-convex slot 21;

[0135] The fork tine lifting device 5 is welded from a square tube, one end of which is a crossbeam connecting two fork tines. Semicircular arc grooves 51 are welded on both fork tines. The fork tine lifting device 5 and the clamping fixture 8 are auxiliary devices for installing the middle partition wall panel connecting guide device 2, and can be disassembled and reused after installation.

[0136] In the embodiment of the present invention, the bottom anchoring device 7 is a foundation bolt, which is pre-tightened one by one to the bolt insertion hole reserved in the bottom connecting anchor plate 23 during installation, and the fixing nut of the bottom anchoring device 7 is divided into a first nut 71 and a second nut 72. During installation, the upper and lower nuts first fix the bottom anchoring device 7 to the bottom connecting anchor plate 23, and adjust the bottom anchoring device 7 to the top.

[0137] In the embodiment of the present invention, the top anchoring device 6 is an expansion bolt or a chemical bolt.

[0138] like Fig.10 As shown, in Embodiment 4 of the present invention, the clamping fixture 8 is a threaded roller 82' with threads in the middle that directly penetrates the two flanges of the middle partition wall panel connecting guide device 2, and plays a clamping role by tightening the clamping nuts 83 on both sides.

[0139] In the embodiment of the present invention, after the clamping fixture 8 clamps the middle partition wall panel connecting guide device 2, the roller 82 is clamped into the semicircular groove 51 of the two fork teeth of the fork tooth lifting device 5. By increasing the lifting height, due to the effect of its own gravity, the threaded roller 82' rolls in the semicircular groove 51 as the center of gravity is lowered. Without applying external power, the left and right middle partition wall panel connecting guide devices 2 can be adjusted from a horizontal state to a suitable vertical state.

[0140] In the embodiment of the present invention, the clamping fixture 8 is installed at a position above the center of gravity of the middle partition wall panel connecting guide device 2. During installation, the middle partition wall panel connecting guide device 2 can be adjusted from a horizontal state to a vertical state by its own gravity through different lifting heights.

[0141] The embodiment of the present invention further provides a method for installing a composite middle partition wall system, which specifically includes the following steps:

[0142] S1, the wall panels 3 and the middle partition wall panel connecting guide device 2 are prefabricated, welded, cut and transported to the site in advance in the factory;

[0143] S2. After arriving at the installation site, the fork lifting device 5 is fixed on the fork tine of the forklift, and the clamping clamp 8 is fixed to clamp the middle partition wall panel connecting guide device 2. The threaded rollers 82' on both sides of the clamping clamp are clamped into the semicircular arc-shaped clamping grooves 51 of the two fork tines of the fork lifting device 5. The upper end of the middle partition wall panel connecting guide device 2 is tilted toward the crossbeam end of the fork lifting device 5 and fixed on the forklift. The bottom anchoring device 7 is fixed to the bottom connecting anchor plate 23 by the first nut 71 and the second nut 72 respectively, and the bottom anchoring device 7 is moved to the top, so that the middle partition wall panel connecting guide device 2 can swing to a suitable range.

[0144] S3. Install the middle partition wall panel connecting guide device 2 by lifting with a forklift in a small and confined space. With the change of the lifting height of the forklift, due to its own gravity, the threaded roller 82' rolls in the semicircular slot 51 as the center of gravity is lowered. Without applying an external power source, the middle partition wall panel connecting guide device 2 can be slowly swung from a horizontal tilted state to a vertical state. After the middle partition wall panel connecting guide device 2 is vertical, the bottom end connected to the anchor plate 23 corresponds to the position of the reserved bottom slot 41 of the bottom structure 4.

[0145] S4, first install the top connection anchor plate 24, tighten the top anchor device 6 to the top structure 1 and then loosen it by one and a half buckles, then loosen the two nuts of the bottom anchor device 7, adjust the bottom anchor device 7 down to the appropriate position of the reserved bottom groove 41, grout the reserved bottom groove 41, grout the bottom anchor device 7 and the bottom structure 4, tighten the top anchor device 6 after the bottom grouting material hardens and has a certain strength, and then adjust the bottom anchor device 7 after it is fully tightened, and tighten the first nut 71 and the second nut 72 at the same time;

[0146] S5. After the middle partition wall panel connecting guide device 2 on both sides of the wall panel 3 is installed and fixed to the designated position, the wall panel 3 is passed through the concave-convex slot 21 and enters the guide rail formed by the two flange plates of the middle partition wall panel connecting guide device 2. The two flange plates of the middle partition wall panel connecting guide device 2 are used as guide devices to clamp and fix the wall panel;

[0147] S6. If the concave-convex groove 21 is located at the upper part of the connecting guide device 2 of the middle partition wall panel, all the wall panels 3 are sequentially installed from bottom to top to the concave-convex groove 21. After the last panel is installed, the wing plate 22 is clamped to the concave-convex groove 21 of the web plate and welded firmly.

[0148] S7. After the wall panel 3 is installed, the gaps between the wall panel 3 and the top structure 1 or the wall panel 3 and the bottom structure 4, and between the wall panel 3 and the flange plate of the intermediate partition wall panel connecting guide device 2 are grouted, and the gap between the bottom anchor device 7 and the bottom structure 4 is grouted again, so that the upper end load is transferred to the bottom anchor device 7 to the bottom structure 4, which has a stabilizing effect on the foundation, and also protects the anchor bolts of the above-ground part from corrosion;

[0149] S8, after installing a set of middle partition wall panel connecting guide device 2, the fork lifting device 5 and the clamping fixture 8 are disassembled and reused, and the next set is installed;

[0150] In the embodiment of the present invention, the wall panel 3 is a prefabricated middle wall panel or a lightweight partition wall decorative panel, and the thickness of the wall panel 3 matches the distance between the two flange panels of the H-shaped steel body. The best is that the thickness of the wall panel 3 is less than or equal to the distance between the two flange panels of the H-shaped steel body, so that the wall panel can smoothly enter the track formed by the H-shaped steel body and can pass smoothly up and down the track;

[0151] In the embodiment of the present invention, wall panels 3 are installed on both sides of the middle partition wall panel connecting guide device 2. When the installation location is wide and a section of wall panel cannot form an enclosed space, the wall panel 3 is also installed on the other side of the H-shaped steel. After the wall panels 3 are installed on both sides of the H-shaped steel, the rear wing plates 22 are installed and clamped on the concave and convex grooves 21 and welded firmly. When the bottom end connecting anchor plate 23 is square, rectangular or circular, the wall panel 3 cannot completely fall on the bottom structure 4. In order to ensure the closure of the partition wall, the gap at the lower end of the wall panel 3 is grouted. When the lower end of the bottom end connecting anchor plate 23 is opened into a "concave" or "H" shape, the wall panel 3 can be in close contact with the bottom structure 4.

[0152] Meanwhile, the contents not described in detail in this specification belong to the prior art known to those skilled in the art.

[0153] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0154] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A composite middle partition wall system, characterized in that: it includes a middle partition wall panel connection guiding device (2), a top anchoring device (6), a bottom anchoring device (7), and a fork-lift device (5) and a clamping fixture (8) for transporting the middle partition wall panel connection guiding device (2); The middle partition wall panel connection guiding device (2) includes an H-shaped steel main body, the H-shaped steel main body includes two flange plates and an intermediate web part, and the middle partition wall panel connection guiding device (2) also includes a top connection anchor plate (24) fixed to the top structure (1) and a bottom connection anchor plate (23) fixed to the bottom structure (4). The top connection anchor plate (24) and the bottom connection anchor plate (23) are both welded to the H-shaped steel main body, and the top connection anchor plate (24) and the bottom connection anchor plate (23) both have bolt insertion holes reserved; The top connection anchor plate (24) is rectangular or circular, and the bottom connection anchor plate (23) is rectangular or circular. To facilitate the middle partition wall panel to fall onto the bottom structure (4), the lower end of the bottom connection anchor plate (23) is open in a "concave" or "H" shape; On the upper, middle or lower part of the H-shaped steel main body of the middle partition wall panel connection guiding device (2), both sides of one flange plate are cut off, and the middle part of the flange plate in contact with the web is cut into a concave-convex card slot (21). The convex end of the supplementary flange plate (22) corresponding to the concave-convex card slot (21) has a vertical hole. The wall panel (3) enters the vertical guide rail formed by the H-shaped steel main body through the notch of the concave-convex card slot (21) and can be slid up and down for installation. The two flange plates play a role of clamping and fixing. After the wall panel (3) is completely installed, the supplementary flange plate (22) is clamped to the concave-convex card slot (21) and welded firmly; The protruding end of the concave-convex card slot (21) is an isosceles trapezoid, in the mode of being narrow outside and wide inside, so that the supplementary flange plate (22) can be clamped together. The widest part just clamps tightly with the length of the vertical hole of the supplementary flange plate (22), and being narrow outside facilitates the vertical hole of the supplementary flange plate (22) to be clamped to the concave-convex card slot (21); The fork-lift device (5) is welded by square tubes, one end is a cross beam connecting two forks, and semi-circular arc-shaped card slots (51) are welded on both forks. The fork-lift device (5) and the clamping fixture (8) are auxiliary devices for installing the middle partition wall panel connection guiding device (2) and can be disassembled and reused after installation; The clamping fixture (8) includes a fixture skeleton, a roller (82) and a clamping bolt (81). The fixture skeleton is in a "C" shape structure, and rollers (82) are welded on the outer side of the fixture skeleton. A bolt hole is reserved at the outermost front end of the fixture skeleton, so that the clamping bolt (81) passes through the bolt hole, and then nuts are screwed on both sides of the clamping bolt (81) respectively to tighten the fixture; The clamping fixture (8) is a threaded roller (82') with threads in the middle directly penetrating through the two flange plates of the middle partition wall panel connection guiding device (2), and clamping is achieved by tightening the clamping nuts (83) on both sides.

2. A composite middle partition wall system according to claim 1, characterized in that: The bottom anchoring device (7) is a foundation bolt, which is pre-tightened one by one to the bolt insertion holes reserved in the bottom connecting anchor plate (23) during installation, and the fixing nut of the bottom anchoring device (7) is divided into a first nut (71) and a second nut (72). During installation, the upper and lower nuts first fix the bottom anchoring device (7) to the bottom connecting anchor plate (23), and adjust the bottom anchoring device (7) to the top.

3. A composite partition wall system according to claim 1, Features: The top anchoring device (6) is an expansion bolt or a chemical bolt.

4. A composite partition wall system according to claim 1, Features: After the clamping clamp (8) clamps the middle partition wall panel connecting guide device (2), the roller (82) is clamped into the semicircular arc-shaped grooves (51) of the two fork teeth of the fork tooth lifting device (5). As the lifting height increases, due to the effect of its own gravity, the roller (82) rolls in the semicircular arc-shaped grooves (51) as the center of gravity is lowered. Without applying external power, the left and right middle partition wall panel connecting guide devices (2) can be adjusted from a horizontal state to a suitable vertical state.

5. A composite partition wall system according to claim 1, Features: The clamping fixture (8) is installed at a position above the center of gravity of the middle partition wall panel connecting guide device (2). During installation, the middle partition wall panel connecting guide device (2) can be adjusted from a horizontal state to a vertical state by its own gravity by lifting at different heights.

6. A method for installing the composite partition wall system according to any one of claims 1 to 5, Features: The specific steps include: S1, the wall panels (3) and the intermediate partition wall panel connecting guide device (2) are prefabricated, welded, cut and transported to the site in advance in the factory; S2. After arriving at the installation site, the fork lifting device (5) is fixed on the fork tine of the forklift, and the clamping clamp (8) is used to clamp the middle partition wall panel connecting guide device (2). The rollers (82) or threaded rollers (82') on both sides of the clamping clamp are clamped into the semicircular arc-shaped clamping grooves (51) of the two fork tines of the fork lifting device (5). The upper end of the middle partition wall panel connecting guide device (2) is tilted toward the cross beam end of the fork lifting device (5) and fixed on the forklift. The bottom anchoring device (7) is fixed to the bottom connecting anchor plate (23) by means of the first nut (71) and the second nut (72), and the bottom anchoring device (7) is raised to the top, so that the middle partition wall panel connecting guide device (2) can swing to a suitable range. S3. The middle partition wall panel connecting guide device (2) is installed in a small and confined space by lifting with a forklift. As the lifting height of the forklift changes, due to the effect of its own gravity, as the center of gravity is lowered, the roller (82) or the threaded roller (82') rolls in the semicircular slot (51). Without applying an external power source, the middle partition wall panel connecting guide device (2) can be slowly swung from a horizontal tilted state to a vertical state. After the middle partition wall panel connecting guide device (2) is vertical, the bottom end connected to the anchor plate (23) corresponds to the position of the reserved bottom slot (41) of the bottom structure (4); S4, first install the top connection anchor plate (24), tighten the top anchor device (6) to the top structure (1) and then loosen it by one and a half buckles, then loosen the two nuts of the bottom anchor device (7), adjust the bottom anchor device (7) down to a suitable position of the reserved bottom groove (41), grout the reserved bottom groove (41), grout the bottom anchor device (7) and the bottom structure (4), tighten the top anchor device (6) after the bottom grouting material hardens to a certain strength, and after it is fully tightened, adjust the bottom anchor device (7) and tighten the first nut (71) and the second nut (72) at the same time; S5. After the middle partition wall panel connecting guide devices (2) on both sides of the wall panel (3) are installed and fixed to the designated positions, the wall panel (3) is passed through the concave-convex slot (21) and enters the guide rail formed by the two flange plates of the middle partition wall panel connecting guide device (2). The two flange plates of the middle partition wall panel connecting guide device (2) are used as guide devices to clamp and fix the wall panel; S6. If the concave-convex groove (21) is located at the upper part of the middle partition wall panel connecting guide device (2), all wall panels (3) are installed from bottom to top to the concave-convex groove (21). After the last panel is installed, the wing plate (22) is clamped on the web concave-convex groove (21) and welded firmly. If the concave-convex groove (21) is located in the middle part of the middle partition wall panel connecting guide device (2), the lower wall panel (3) is installed first, and after it is installed to the concave-convex groove (21), the upper wall panel (3) is installed. The uppermost wall panel (3) is then installed. The wall panel (3) is clamped to the top structure (1), and then the wall panel (3) near the concave-convex groove (21) is installed, and then the rear wing panel (22) is clamped to the web concave-convex groove (21) and welded firmly; when the concave-convex groove (21) is located at the lower part of the middle partition wall panel connecting guide device (2), it is installed in a counter-gravity method, the top one is installed first, and then fixed, and then installed in sequence until the bottom wall panel (3) is installed, and then the rear wing panel (22) is clamped to the web concave-convex groove (21) and welded firmly; S7. After the wall panel (3) is installed, the gaps between the wall panel (3) and the top structure (1) or between the wall panel (3) and the bottom structure (4), and between the wall panel (3) and the flange plate of the intermediate partition wall panel connecting guide device (2) are grouted, and the gap between the bottom anchor device (7) and the bottom structure (4) is grouted again, so as to transfer the upper end load to the bottom anchor device (7) to the bottom structure (4) and protect the anchor bolts on the ground from corrosion; S8. After installing one set of the middle partition wall panel connecting guide device (2), the fork tooth lifting device (5) and the clamping fixture (8) are disassembled and reused, and the next set is installed.

7. The method for installing a composite partition wall system according to claim 6, Features: The wall panel (3) is a prefabricated middle wall panel or a lightweight partition wall decorative panel, and the thickness of the wall panel (3) matches the distance between the flange panels on both sides of the H-shaped steel body.

8. The method for installing a composite partition wall system according to claim 7, Features: Wall panels (3) are installed on both sides of the middle partition wall panel connecting guide device (2). When the location to be installed is wide and a section of wall panel cannot form a closed space, the wall panel (3) is also installed on the other side of the H-shaped steel. After the wall panels (3) are installed on both sides of the H-shaped steel, the rear wing plates (22) are installed and clamped on the concave and convex clamping grooves (21) and welded firmly. When the bottom connecting anchor plate (23) is rectangular or circular, the wall panel (3) cannot completely fall onto the bottom structure (4). In order to ensure the sealing of the partition wall, the gap at the lower end of the wall panel (3) is grouted. When the lower end of the bottom connecting anchor plate (23) is opened into a "concave" or "H" shape, the wall panel (3) can be closely contacted with the bottom structure (4).