A steel pipe grouting pile construction process with simultaneous grouting and pipe sinking

By setting a large-diameter blind plate and a grout hole at the bottom of the steel pipe pile, and simultaneously injecting cement mortar into the pipe while grouting, the existing technology solves the problem of soil sliding during the construction of steel pipe piles, and improves the efficiency of the steel pipe pile. Compression and pull-out bearing capacity, and enhances the durability and stability of the pile.

CN114411701BActive Publication Date: 2024-10-22JIANGSU OCEAN UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210037305.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-01-13
Publication Date
2024-10-22
Estimated Expiration
2042-01-13

AI Technical Summary

Technical Problem

During the construction process of existing steel pipe piles, due to pre-forming holes and then grouting, the surrounding soil easily slips into the holes, resulting in unstable pile formation and difficulty in meeting the requirements for compression and pullout bearing capacity.

Method used

The steel pipe grouting pile technology is used to sink the pipe while grouting. By setting a blind plate and a grout hole at the bottom of the steel pipe, the diameter of the blind plate is larger than the diameter of the steel pipe, forming a foundation hole larger than the diameter of the steel pipe, and cement is injected simultaneously during the pile sinking process. Mortar fills the gap between the pile body and the soil body to form a composite pile body.

Benefits of technology

It effectively prevents loose soil from falling into gaps, improves the compression and pull-out bearing capacity of steel pipe piles, forms a hard block, and enhances the durability and stability of the piles.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114411701B_ABST
    Figure CN114411701B_ABST
Patent Text Reader

Abstract

A steel pipe grouting pile forming process with grouting while sinking the pipe, wherein the steel pile body comprises a steel pipe, a pile cap for pressurizing the pile is arranged on the top of the steel pipe, a conical pile tip is arranged at the bottom of the steel pipe, a blind plate for hole forming is arranged between the conical pile tip and the steel pipe, the blind plate is arranged concentrically with the steel pipe, and the diameter of the blind plate is larger than the diameter of the steel pipe; a lateral grouting hole is arranged at the bottom of the steel pipe near the blind plate, and a grouting hole is arranged at the pile cap on the upper part of the steel pipe; as the steel pile body sinks into the foundation soil, a foundation hole larger than the diameter of the steel pipe is formed because the diameter of the blind plate is larger than the diameter of the steel pipe; cement mortar is injected into the steel pipe, and the cement mortar flows out from the grouting hole to the outside of the steel pipe to fill the gap between the steel pipe and the wall of the foundation hole; grouting is performed while sinking the pipe. The present invention can mix the cement mortar with the surrounding soil to form a hard block with a large volume, and form a composite pile body with the steel pipe pile itself, which greatly improves the compression and pull-out bearing capacity of the steel pipe pile.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of pipe pile construction, in particular to a steel pipe grouting pile forming process for sinking the pipe and grouting at the same time. Background Art

[0002] With the acceleration of urbanization, the number of construction projects in my country has also increased significantly. Due to the limited use area of ​​buildings, many projects need to be constructed in small spaces and complex geological structures. Large-diameter piles are difficult to meet construction conditions, while small-diameter piles are difficult to meet the bearing capacity requirements of the upper structure. At present, steel pipe piles are used by drilling holes with geological drilling rigs, installing steel pipes in the holes, and then using grouting pipes to press cement mortar from the bottom of the pile foundation, so that the cement mortar returns from the inside and outside of the steel pipe to the upper part, forming a steel pipe cement mortar pile body. Due to the pre-drilling and grouting, the surrounding soil is easy to slide into the hole during grouting, which is not conducive to pile formation. Summary of the invention

[0003] The technical problem to be solved by the present invention is to propose a steel pipe grouting pile forming process for improving the compressive and tensile bearing capacity by sinking the pipe and grouting at the same time, in view of the deficiencies of the prior art.

[0004] The technical problem to be solved by the present invention is achieved through the following technical scheme: a steel pipe grouting pile forming process with pipe sinking and grouting, comprising a steel pile body, which is characterized by:

[0005] The steel pile body includes a steel pipe, a pile cap is provided on the top of the steel pipe for pile sinking under pressure, a conical pile tip is provided at the bottom of the steel pipe, a blind plate for hole forming is provided between the conical pile tip and the steel pipe, the blind plate is concentrically arranged with the steel pipe, and the diameter of the blind plate is larger than the diameter of the steel pipe; a lateral grouting hole is provided at the bottom of the steel pipe near the blind plate, and a grouting hole is provided at the pile cap on the upper part of the steel pipe;

[0006] The steps for pile sinking are as follows:

[0007] (1) Sink the conical pile tip into the foundation soil and connect the grouting hole to the grouting machine through the grouting pipe;

[0008] (2) Apply pressure to the pile cap through equipment to carry out pipe sinking operation. While the steel pile body is sinking, the grouting machine injects cement mortar into the steel pipe pile through the grouting port;

[0009] (3) As the steel pile body sinks into the foundation soil, a foundation hole larger than the diameter of the steel pipe is formed because the diameter of the blind plate is larger than the diameter of the steel pipe;

[0010] As the amount of cement mortar injected into the steel pipe increases, the cement mortar flows out from the slurry outlet to the outside of the steel pipe to quickly fill the gap between the steel pipe and the base hole wall;

[0011] (4) Grouting should be performed while the pipe is being sunk, and the injection volume and speed of cement mortar should be controlled to match the speed of sinking the pipe, so as to fill the base hole without overflowing.

[0012] (5) Sink the pipe to the designed elevation depth, ensuring that the inside and outside of the steel pipe are filled with cement mortar. The steel pipe is evenly wrapped with cement mortar, and the grouting is completed.

[0013] The technical problem to be solved by the present invention can be further achieved by the following technical solution: the diameter of the blind plate is 50 mm to 200 mm larger than the diameter of the steel pipe.

[0014] The technical problem to be solved by the present invention can be further achieved by the following technical solution: two slurry outlet holes are provided, which are symmetrically arranged on both sides of the steel pipe.

[0015] The technical problem to be solved by the present invention can be further achieved by the following technical solution: the slurry outlet hole is set at 50 mm away from the blind plate.

[0016] The technical problem to be solved by the present invention can be further achieved by the following technical solution: a circle of enclosure is provided around the slurry outlet, the enclosure is fixedly connected to the blind plate downward, and the outer wall diameter of the enclosure is less than or equal to the diameter of the blind plate.

[0017] Compared with the prior art, the blind plate connecting the pile body and the pile tip at the bottom of the steel pipe of the present invention has a diameter larger than the steel pipe pile body. During the pile sinking process, a base hole larger than the diameter of the steel pipe is formed in the soil. Cement mortar is injected simultaneously while the steel pipe is sinking the pile, which can timely fill the gap formed between the pile body and the surrounding soil when the pile body sinks, effectively preventing the soil around the pile from loosely falling into the gap. The present invention can mix cement mortar with the surrounding soil to form a large hard block, and form a composite pile body with the steel pipe pile itself, greatly improving the compression and pull-out bearing capacity of the steel pipe pile. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the steel pipe grouting pile formation of the present invention. DETAILED DESCRIPTION

[0019] The specific technical solutions of the present invention are further described below. To make the purpose, technical solutions and advantages of the embodiments of the present invention clearer and to facilitate those skilled in the art to further understand the present invention, the technical solutions in the embodiments of the present invention will be clearly and completely described below in combination with the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of them, and do not constitute a limitation on the rights thereof. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work are within the scope of protection of the present invention.

[0020] A steel pipe grouting pile construction process with simultaneous grouting while sinking the pipe.

[0021] The accompanying drawing is a schematic diagram of the steel pipe grouting pile of the present invention, comprising a steel pile body, the steel pile body comprising a steel pipe 6, a pile cap 3 for pressurizing the pile is provided on the top of the steel pipe, a conical pile tip 1 is provided at the bottom of the steel pipe, a blind plate 8 for hole forming is provided between the conical pile tip and the steel pipe, the blind plate is concentrically arranged with the steel pipe, and the diameter of the blind plate is larger than the diameter of the steel pipe; a lateral grouting hole 5 is provided at the bottom of the steel pipe near the blind plate, and a grouting hole 2 is provided at the pile cap on the upper part of the steel pipe;

[0022] The steps for pile sinking are as follows:

[0023] (1) Sink the conical pile tip into the foundation soil and connect the grouting hole to the grouting machine through the grouting pipe;

[0024] (2) Apply pressure to the pile cap through equipment to carry out pipe sinking operation. While the steel pile body is sinking, the grouting machine injects cement mortar into the steel pipe pile through the grouting port;

[0025] (3) As the steel pile body sinks into the foundation soil, a foundation hole 4 larger than the diameter of the steel pipe is formed because the diameter of the blind plate is larger than the diameter of the steel pipe;

[0026] As the amount of cement mortar injected into the steel pipe increases, the cement mortar flows out from the slurry outlet to the outside of the steel pipe to quickly fill the gap between the steel pipe and the base hole wall;

[0027] (4) Grouting should be performed while the pipe is being sunk, and the injection volume and speed of cement mortar should be controlled to match the speed of sinking the pipe, so as to fill the base hole without overflowing.

[0028] (5) Sink the pipe to the designed elevation depth, ensuring that the inside and outside of the steel pipe are filled with cement mortar. The steel pipe is evenly wrapped with cement mortar, and the grouting is completed.

[0029] The diameter of the blind plate is 50mm-200mm larger than the diameter of the steel pipe. The specific size depends on the geological conditions.

[0030] There are two slurry outlet holes, which are symmetrically arranged on both sides of the steel pipe.

[0031] The slurry outlet hole is set at 50mm away from the blind plate.

[0032] A circle of enclosure plates 7 is arranged around the pulp outlet, and the enclosure plates are fixedly connected to the blind plate downwards, and the outer wall diameter of the enclosure plates is less than or equal to the diameter of the blind plate.

[0033] The uniform coating of cement mortar inside and outside can provide support and protection for the steel pipe pile body, and the durability and stability of the pile are improved; the gap formed by the expanded diameter of the pile tip and the sinking of the blind plate can expand the steel pipe pile body, provide good friction force around the pile soil, and effectively improve the bearing capacity of the pile. After the cement mortar is wrapped, a uniform and continuous outer wall is formed on the outside of the steel pipe, which improves the durability of the steel pipe and provides effective support for the bearing capacity of the pile.

[0034] Steel pipe grouting piles are mainly composed of steel pipes and cement mortar inside and outside the steel pipes. After the cement mortar solidifies, the two work together to improve the bearing capacity of the pile body. At the same time, the cement mortar can also protect the steel pipe from corrosion in the surrounding environment and extend the life of the steel pipe. The pile has the advantages of small pile diameter, strong penetration, high bearing capacity per unit area of ​​the cross section, and convenient construction. It has a good balance in both construction and bearing capacity.

Claims

1. A steel pipe grouting pile construction process with grouting while sinking the pipe, comprising a steel pile body, characterized in that: The steel pile body includes a steel pipe, a pile cap is provided on the top of the steel pipe for pressurizing the pile, a conical pile tip is provided at the bottom of the steel pipe, a blind plate for hole forming is provided between the conical pile tip and the steel pipe, the blind plate is concentrically arranged with the steel pipe, and the diameter of the blind plate is larger than the diameter of the steel pipe; A lateral grouting hole is provided at the bottom of the steel pipe near the blind plate, and a grouting hole is provided at the pile cap on the upper part of the steel pipe; a circle of enclosure is provided around the grouting hole, the enclosure is fixedly connected to the blind plate downward, and the outer wall diameter of the enclosure is less than or equal to the diameter of the blind plate; The steps for pile sinking are as follows: (1) sink the conical pile tip into the foundation soil, and connect the grouting hole to the grouting machine through the grouting pipe; (2) Apply pressure to the pile cap through equipment to carry out pipe sinking operation. While the steel pile body is sinking, the grouting machine injects cement mortar into the steel pipe pile through the grouting port; (3) As the steel pile body sinks into the foundation soil, a foundation hole larger than the diameter of the steel pipe is formed because the diameter of the blind plate is larger than the diameter of the steel pipe; as the amount of cement mortar injected into the steel pipe increases, the cement mortar flows out from the slurry outlet to the outside of the steel pipe to quickly fill the gap between the steel pipe and the wall of the foundation hole; (4) Grouting is performed while sinking the pipe, and the injection volume and speed of cement mortar are controlled to match the speed of sinking the pipe, so as to fill the base hole without overflowing; (5) Sink the pipe to the designed elevation depth, ensuring that the inside and outside of the steel pipe are filled with cement mortar. The steel pipe is evenly wrapped with cement mortar, and the grouting is completed.

2. The steel pipe grouting pile forming process with sinking pipe and grouting as claimed in claim 1 is characterized by: The diameter of the blind plate is 50mm-200mm larger than the diameter of the steel pipe.

3. The steel pipe grouting pile forming process with sinking pipe and grouting as claimed in claim 1 is characterized by: There are two slurry outlet holes, which are symmetrically arranged on both sides of the steel pipe.

4. The steel pipe grouting pile forming process with sinking pipe and grouting as claimed in claim 1 is characterized by: The slurry outlet hole is set at 50mm away from the blind plate.