Rotating assembled foundation treatment steel pipe pile and construction method
Through the sectional installation and post-groughening reinforcement of rotary assembled steel pipe piles, the technical problem that steel pipe piles cannot directly enter the foundation is solved, and convenient steel pipe pile construction and good foundation reinforcement effect are achieved.
Patent Information
- Application Number
- CN202210643804.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-09
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2042-06-09
AI Technical Summary
When steel pipe piles are used for foundation settlement, longer steel pipe piles cannot directly enter directly below the foundation, resulting in construction difficulties or unsatisfactory reinforcement effect.
Steel pipe piles are processed using rotary assembled foundation, including three-section steel pipe bodies (semi-cylindrical arc and quarter-cylindrical arc), V-shaped grooves and insert block structures. Steel is gradually installed through segmented rotation and welding. Pipe piles and post-gritten reinforcement after construction is completed.
It realizes the convenient installation of steel pipe piles and good foundation reinforcement effect, improving the convenience of construction and the overall holding capacity of the foundation.
Smart Images

Figure CN114855769B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of construction safety equipment, and in particular to a rotary assembled foundation treatment steel pipe pile and a construction method. Background Art
[0002] The current solution for the reinforcement of the foundation of independent shops often uses steel pipe piles for foundation treatment, which requires the steel pipe piles to be completed in advance before the next process can be carried out. Steel pipe pile construction is currently also used as a way to reinforce the foundation when the foundation settles. At this time, the longer steel pipe piles cannot directly enter the bottom of the foundation, resulting in the inability to construct or the reinforcement effect is not ideal. Summary of the invention
[0003] The present invention provides a rotary assembled foundation treatment steel pipe pile and a construction method to solve the technical problem that when steel pipe piles are used for foundation reinforcement treatment during foundation settlement, longer steel pipe piles cannot directly enter directly under the foundation.
[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is: a rotating assembled foundation treatment steel pipe pile, including three sections of steel pipe bodies, namely a first steel pipe body and two sections of second steel pipe bodies; the first steel pipe body is a semi-cylindrical arc steel pipe, the curvature of the first steel pipe body is 180°, the second steel pipe body is a quarter-cylindrical arc steel pipe, the curvature of the second steel pipe body is 90°, the three sections of steel pipe bodies have the same height, and the three sections of steel pipe bodies are spliced into a complete cylindrical hollow pipe body; the top of the three sections of steel pipe bodies are provided with a V-shaped groove, and the bottom is provided with a V-shaped plug, and the V-shaped plug matches the V-shaped groove.
[0005] Furthermore, the height of the first steel tube body and the second steel tube body is 500 mm, and the diameters are both 5 mm.
[0006] A construction method for a rotary assembled steel pipe pile for foundation treatment comprises the following steps:
[0007] S1. Press the first steel tube body into the ground using a jack, and then rotate the first steel tube body 180 degrees;
[0008] S2, then install a section of the second steel tube body, and weld the second steel tube body to the first steel tube body firmly;
[0009] S3, then installing another section of the second steel pipe body, and welding the second steel pipe body, the first steel pipe body and another section of the second steel pipe body together to form a complete steel pipe, and using a jack to press the complete steel pipe into the ground;
[0010] S4, then reinsert another first steel pipe body above the first complete steel pipe section pressed into the ground, insert the V-shaped plug at the bottom end of the upper steel pipe body into the V-shaped groove at the top end of the adjacent lower steel pipe body, and repeat the above steps S1-S3 to install the next section of steel pipe until several sections of steel pipe are assembled in sections in sequence to the designed length of the steel pipe pile;
[0011] S5. After the construction is completed, post-grouting is used in the assembled steel pipe piles to reinforce them so that the soil inside the steel pipe and the bearing layer at the bottom of the pile form a whole.
[0012] Compared with the prior art, the present invention has the following beneficial effects:
[0013] The rotary assembled foundation treatment steel pipe pile of the present invention is mainly used for a reinforcement scheme of using steel pipe piles to treat the foundation when the local foundation settlement is large after the main structure is completed. The rotary assembled steel pipe pile has a good foundation reinforcement effect, is convenient to construct, and is easy to operate. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a schematic diagram of the structure of the first steel tube body.
[0015] Figure 2 Schematic diagram of the structure of the second steel tube body.
[0016] Figure 3 This is a schematic diagram of the construction orientation of steel pipe piles and foundation.
[0017] Figure 4 Schematic diagram of steel pipe pile construction steps.
[0018] The following are marked in the figure:
[0019] 1-first steel tube body, 2-second steel tube body, 3-V-shaped groove, 4-V-shaped plug block, 5-foundation. DETAILED DESCRIPTION
[0020] The present invention is further described below in conjunction with specific embodiments. Example
[0021] like Figure 1-3As shown, a rotary assembled foundation treatment steel pipe pile includes three sections of steel pipe bodies, namely a first steel pipe body 1 and two sections of second steel pipe bodies 2; the first steel pipe body 1 is a section of semi-cylindrical arc steel pipe, the arc of the first steel pipe body 1 is 180°, the second steel pipe body 2 is a quarter-cylindrical arc steel pipe, the arc of the second steel pipe body 2 is 90°, the three sections of steel pipe bodies have the same height, and the three sections of steel pipe bodies are spliced to form a complete cylindrical hollow pipe body; the top of the three sections of steel pipe bodies is provided with a V-shaped groove 3, and the bottom is provided with a V-shaped plug 4, and the V-shaped plug 4 matches the V-shaped groove 3. In this way, the V-shaped plug 4 of the square steel pipe body is inserted into the adjacent lower V-shaped groove 3. In this way, the steel pipe is easy to rotate.
[0022] Furthermore, the height of the first steel tube body 1 and the second steel tube body 2 is 500 mm, and the diameter is 5 mm. The diameter of the steel tube body is adjusted according to the design requirements. The length of the steel pipe pile is determined by the design. For example, if the total length of the steel pipe pile after assembly is 20 m, it is divided into 40 sections for segmented assembly construction.
[0023] The height of the first steel tube body 1 and the second steel tube body 2 can also be designed to be 1000 mm or 1500 mm according to requirements.
[0024] A construction method for a rotary assembled steel pipe pile for foundation treatment comprises the following steps (eg Figure 4 shown):
[0025] S1, press the first steel tube body 1 into the ground using a jack, and then rotate the first steel tube body 1 180 degrees;
[0026] S2, then install a section of the second steel tube body 2, and weld the second steel tube body 2 to the first steel tube body 1 firmly;
[0027] S3. Then install another section of the second steel pipe body 2, and weld the second steel pipe body 2, the first steel pipe body 1 and another section of the second steel pipe body 2 together to form a complete steel pipe, and use a jack to press the complete steel pipe into the ground; the side of the steel pipe is welded by manual arc welding.
[0028] S4, then reinsert another first steel pipe body 1 above the first complete steel pipe section pressed into the ground, insert the V-shaped plug 4 at the bottom end of the upper steel pipe body into the V-shaped groove 3 at the top end of the adjacent lower steel pipe body, and repeat the above steps S1-S3 to install the next section of steel pipe until several sections of steel pipe are sequentially assembled in sections to the designed length of the steel pipe pile;
[0029] S5. After the construction is completed, the prefabricated steel pipe pile is reinforced by post-grouting so that the soil inside the steel pipe and the bearing layer at the bottom of the pile form a whole, thereby achieving the effect of foundation treatment.
[0030] During the construction of steel pipe piles, due to the mechanical action of the jack, the friction between the steel pipe and the surrounding soil side wall will cause the soil to be squeezed, and the steel pipe will exert lateral pressure on the surrounding soil, thereby causing the displacement of the soil side wall. The soil density of the hole wall is reduced. The inside of the steel pipe pile will also cause compression deformation of the soil, affecting the bearing capacity of the steel pipe pile. In order to improve the bearing capacity of the steel pipe pile and form an effective integral force-bearing structure at the bottom and inside of the steel pipe pile, a grouting pipe is pre-buried inside the steel pipe pile in advance. The grouting effect is that the cement slurry enters the gap between the soil and the soil layer to form a splitting force layer. In particular, after grouting at the bottom of the pile body, the soil around the pile body and the bottom of the pile is pre-pressed by the deadweight of the pile body, returning to or approaching its original stress state, thereby greatly improving the bite performance between the pile and the soil. The diameter of the grouting pipe is 20mm, and a cast iron pipe with a wall thickness of 2mm is used. The end of the grouting pipe is 300mm away from the bottom of the steel pipe pile. The grouting liquid is configured with P32.5 ordinary Portland cement. Grouting should be stopped when the grouting volume is not less than 2t, and can be stopped only when the grouting volume is less than 2t and the grouting pressure reaches 2MPa.
Claims
1. A construction method for rotating assembled steel pipe piles for foundation treatment, characterized in that: A rotary assembled foundation treatment steel pipe pile comprises three sections of steel pipe bodies, namely a first steel pipe body (1) and two sections of second steel pipe bodies (2); the first steel pipe body (1) is a section of semi-cylindrical arc-shaped steel pipe, the arc of the first steel pipe body (1) is 180°, the second steel pipe body (2) is a quarter-cylindrical arc-shaped steel pipe, the arc of the second steel pipe body (2) is 90°, the three sections of steel pipe bodies have the same height, and the three sections of steel pipe bodies are spliced to form a complete cylindrical hollow pipe body; the top ends of the three sections of steel pipe bodies are provided with V-shaped grooves (3), and the bottom ends are provided with V-shaped plugs (4), and the V-shaped plugs (4) match the V-shaped grooves (3); the rotary assembled foundation treatment steel pipe pile is suitable for use in strengthening the foundation when local foundation settlement is treated after the main structure is completed; The construction method includes the following steps: S1. Press the first steel tube body (1) into the ground using a jack, and then rotate the first steel tube body (1) 180 degrees; S2, then installing a section of a second steel tube body (2), and firmly welding the second steel tube body (2) to the first steel tube body (1); S3, then installing another section of the second steel tube body (2), and welding the second steel tube body (2) with the first steel tube body (1) and another section of the second steel tube body (2) to form a complete steel tube, and using a jack to press the complete steel tube into the ground; S4, then reinsert another first steel pipe body (1) above the first complete steel pipe section pressed into the ground, insert the V-shaped plug (4) at the bottom end of the upper steel pipe body into the V-shaped groove (3) at the top end of the adjacent lower steel pipe body, and repeat the above steps S1-S3 to install the next section of steel pipe until several sections of steel pipe are sequentially assembled in sections to the designed length of the steel pipe pile; S5. After the construction is completed, post-grouting is used in the assembled steel pipe piles to reinforce them so that the soil inside the steel pipe and the bearing layer at the bottom of the pile form a whole.
2. The construction method of a rotary assembled steel pipe pile for foundation treatment according to claim 1, characterized in that: The first steel tube body (1) and the second steel tube body (2) have a height of 500 mm and a diameter of 5 mm.