A TBM inclined shaft construction system and construction method for a water diversion inclined shaft of a hydropower station
Through the non-rigid connection and synchronous assembly technology of the TBM inclined shaft construction system, the problem of synchronization of TBM excavation and pressure steel pipe installation in the water diversion inclined shaft of the hydropower station is solved, which improves construction safety and efficiency, simplifies the project layout, and reduces costs and risks. .
Patent Information
- Application Number
- CN202210698200.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-20
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2042-06-20
AI Technical Summary
In the existing technology, the excavation of the TBM in the inclined shaft of the hydropower station and the installation of the pressure steel pipe cannot be carried out simultaneously, resulting in difficult construction, slow speed, and poor safety. Multi-level construction increases the complexity and cost of the project.
The TBM inclined shaft construction system is adopted, including the starting device, receiving device, pushing device, stop device and relay device. Through non-rigid connection of separate work, the TBM main engine and the rear supporting system are assembled synchronously in the pressure steel pipe, using The articulated cylinder and relay cylinder realize the synchronous forward movement of the TBM main engine and the pressure steel pipe.
It has improved the safety of TBM inclined shaft construction, simplified engineering layout and design, reduced energy consumption, and improved construction efficiency. It can simultaneously carry out excavation and pressure steel pipe installation, shortening the construction period.
Smart Images

Figure CN114876470B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of construction of a water diversion inclined shaft of a hydropower station, and in particular to a TBM inclined shaft construction system and a construction method for a water diversion inclined shaft of a hydropower station. Background Art
[0002] The water diversion inclined shaft is an important structure in a hydropower station. It is characterized by steep inclination, large diameter and long length, so it is difficult to construct. The general design parameters of the water diversion inclined shaft in China are: inclination of 45° to 60°, excavation diameter of 6 to 10m, and the maximum construction length is controlled at about 400m due to the limitation of construction capacity.
[0003] At present, the high-head power station water diversion inclined shaft under construction in China adopts a multi-stage layout scheme, the cavern length is long, the adjustment guarantee design performance is poor, and the powerhouse is relatively forward, which is not conducive to reducing the length of the auxiliary caverns and exploration flat tunnels of the powerhouse. When the inclined shaft is long, it is necessary to add a middle flat section or a middle flat tunnel construction branch tunnel, which increases the project investment, prolongs the construction period, and increases the complexity of the project construction layout design. The inclined shaft excavation adopts the drilling and blasting method, the construction direction and the shape of the cave are not easy to control, the flatness of the excavated cave is poor, the problems of over-excavation and under-excavation are common, the excavation and the installation of the pressure steel pipe cannot be carried out simultaneously, the construction speed is slow, the construction period is long, and the safety is poor. The existing inclined shaft construction device announcement number CN112412478B is a tunnel inclined shaft construction system and construction method that adopts segment support, and the main machine part drives the rear matching synchronous movement, which is not suitable for the working conditions of excavation and pressure steel pipe installation simultaneously. Summary of the invention
[0004] In view of the deficiencies in the above-mentioned background technology, the present invention proposes a TBM inclined shaft construction system and construction method for a hydropower station water diversion inclined shaft, which solves the problem in the prior art that the inclined shaft TBM excavation and the pressure steel pipe installation cannot be carried out synchronously.
[0005] The technical solution of the present invention is implemented as follows: a hydropower station water diversion inclined shaft TBM inclined shaft construction system, including a starting device arranged in a lower construction branch tunnel, a receiving device arranged in an upper construction branch tunnel and a starting cavern for starting the inclined shaft TBM, the starting cavern is connected to the lower construction branch tunnel and the starting device is arranged at the intersection of the starting cavern and the lower construction branch tunnel; a jacking device and a stop device are provided at the bottom of the starting cavern; the inclined shaft TBM includes a TBM main machine, an ABS device and a rear supporting system, the ABS device is connected to the TBM main machine, and the rear supporting system is detachably connected to a pressure steel pipe used to support the inclined shaft.
[0006] Furthermore, the initiating device and the receiving device both include a fixed frame and an articulated frame, the articulated frame is articulated on the fixed frame, and the articulated frame is connected to the fixed frame through an articulated oil cylinder, and the articulated frame rotates through the articulated oil cylinder hinge point; a sliding frame is slidably provided on the articulated frame.
[0007] Furthermore, the TBM main machine includes a cutterhead and a box-type main beam, the cutterhead is connected to a main drive arranged on the box-type main beam, a support shoe support device is provided on the box-type main beam, and an ABS device is slidably connected to the tail of the box-type main beam.
[0008] Furthermore, the ABS device includes a front ABS device and a rear ABS device, and the rear ABS device is connected to the front ABS device through a connecting cylinder. The box-type main beam and the pressure steel pipe are provided with corresponding slag sliding channels. The pushing device includes a pushing frame, and the pushing frame is provided with a pushing cylinder; the back-stop device includes a back-stop frame, and the back-stop frame is provided with a back-stop support shoe; the back-stop frame is located in front of the pushing frame.
[0009] Furthermore, the pressure steel pipe includes a front steel pipe section and several rear steel pipe sections, the rear supporting system is arranged in the front steel pipe section, and a relay device is connected between the front steel pipe section and the rear steel pipe section and between two adjacent rear steel pipe sections; the front steel pipe section and the rear steel pipe section each include several steel pipe sections.
[0010] Furthermore, the relay device includes a primary relay frame and a secondary relay frame arranged in the pressure steel pipe, a relay cylinder is connected between the primary relay frame and the secondary relay frame, and radially arranged supporting cylinders are provided on the outer circumference of the primary relay frame and the secondary relay frame, and a boot plate is provided at the telescopic end of the supporting cylinder, and the supporting cylinder and the boot plate are telescopically extended through a slot hole opened on the pressure steel pipe.
[0011] A method for constructing a TBM inclined shaft construction system for a water diversion inclined shaft of a hydropower station, comprising the following steps:
[0012] S1: The TBM mainframe is transported to the lower construction branch tunnel and pushed onto the launching device. The launching device drives the TBM mainframe to rotate to the same angle as the inclined shaft;
[0013] S2: After transporting the rear supporting system to the lower construction branch hole and positioning the pressure steel pipe, connect the pipeline of the rear supporting system with the pipeline of the TBM host machine;
[0014] S3: The launching device pushes the TBM main engine upwards and moves it into the launching cavern and uses the support shoe support device and ABS device to assist in fixing it to prevent the TBM main engine from sliding backwards;
[0015] S4: The steel pipe section where the rear supporting system is located is placed in front of the jacking device at one time and pushed forward by the jacking device to move forward with the TBM excavation. When the jacking device reaches the right position, the stop device fixes the pressure steel pipe;
[0016] S5: After the previous steel pipe section is pushed into place, the oil cylinder of the pushing device is retracted and the next steel pipe section is connected; after the newly connected steel pipe section is connected with the previous steel pipe section, the back-stop device is disconnected from the pressure steel pipe;
[0017] S6: Repeat step S5 until the assembly of the pressure steel pipe in the entire excavation section is completed;
[0018] S7: When the length of the pressure steel pipe in the inclined shaft reaches a certain length, a relay device is installed on the pressure steel pipe. The relay device cooperates with the jacking device and the stop device to assemble the pressure steel pipe synchronously with the forward movement of the TBM;
[0019] S8: The TBM mainframe excavates to the upper construction hole, rotates the receiving device to the same inclination angle as the inclined shaft, and then connects the TBM mainframe with the receiving device;
[0020] S9: Rotate the receiving device to be parallel to the upper construction hole, dismantle the TBM host, and transport it outside the hole for storage;
[0021] S10: Use a winch to pull the pressure steel pipe carrying the rear supporting system to the upper construction hole and dismantle it;
[0022] S11: Manually connect the front and rear ends of the penstock where the relay device is located; then retract the relay device into the assembled penstock;
[0023] S12: The relay device is moved to the upper construction hole by step-by-step operation or by winch traction and dismantled.
[0024] The working process of the relay device in step S7 is as follows: the first-level relay frame is recovered, the second-level relay frame is held tight against the cave wall, the relay oil cylinder between the first-level relay frame and the second-level relay frame is extended, and the pressure steel pipe where the first-level relay frame is located is pushed forward by one stroke; the first-level relay frame is held tight against the cave wall, the second-level relay frame is recovered, the relay oil cylinder between the first-level relay frame and the second-level relay frame is recovered, and the pressure steel pipe where the second-level relay frame is located is pulled forward by one stroke.
[0025] The beneficial effects of the present invention are as follows:
[0026] 1. The TBM mainframe and the rear supporting system of the present invention adopt a non-rigidly connected separate working mode. The TBM rear supporting system is located in the pressure steel pipe and is pushed forward by a jacking device and a relay device, which reduces the weight of the TBM mainframe towing forward and improves the safety of TBM inclined shaft upward construction.
[0027] 2. The TBM construction method of the present invention optimizes the traditional multi-stage inclined shaft construction into a straight tunnel, reduces the construction of the middle flat section or the middle flat tunnel branch tunnel, reduces the complexity of the engineering construction layout design, optimizes the layout of the water diversion system, shortens the length of the water diversion system, reduces the amount of engineering civil engineering, and is conducive to improving the regulation of the hydropower station to ensure the design performance.
[0028] 3. The TBM construction method of the present invention can realize automated mechanized excavation, greatly reduce labor intensity, reduce energy consumption, save costs, and at the same time, its equipment construction is stable, efficient, effectively controls stratum disturbance, and reduces construction risks. The overall structural design of the present invention is reasonable, and TBM excavation and pressure steel pipe installation can be carried out simultaneously, which fills the gap of TBM excavation of water diversion inclined shafts, and can shorten the inclined shaft construction period as a whole, which is conducive to the early operation of the power station to generate economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] In order to more clearly illustrate the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings in the following description are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying any creative work.
[0030] Figure 1 It is a schematic diagram of the overall structure of the present invention.
[0031] Figure 2 It is a top view schematic diagram of the ABS on the TBM main machine of the present invention.
[0032] Figure 3 It is a cross-sectional schematic diagram of the rear supporting system of the present invention.
[0033] Figure 4 It is a cross-sectional schematic diagram of the relay device of the present invention.
[0034] Figure 5 This is a schematic diagram of the launch and reception of the inclined shaft TBM. DETAILED DESCRIPTION
[0035] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0036] like Figure 1As shown, embodiment 1 is a TBM inclined shaft construction system for a water diversion inclined shaft of a hydropower station, comprising a starting device 1 arranged in a lower construction branch tunnel 100, a receiving device 2 arranged in an upper construction branch tunnel 200, and a starting cavern 300 for starting the inclined shaft TBM3. The tunnel excavated by the inclined shaft TBM3 is an inclined shaft, and the inclined shaft is used to connect the upper construction branch tunnel and the lower construction branch tunnel. The starting cavern 300 is connected with the lower construction branch tunnel 100 and the starting device 1 is arranged at the intersection of the starting cavern 300 and the lower construction branch tunnel 100; the starting device is used for starting the TBM main machine 31. A jacking device 5 and a stop device 6 are provided at the bottom of the starting cavern 300; the jacking device is used for jacking the pressure steel pipe 4 and the TBM, so that they can be excavated forward and synchronously assembled with the pressure steel pipe. A steel pipe support 8 is provided between the pressure steel pipe 4 and the inclined shaft tunnel. The inclined shaft TBM 3 includes a TBM mainframe 31, an ABS device 32 and a rear supporting system 33. The ABS device 32 is connected to the TBM mainframe 31, and the rear supporting system 33 is detachably connected to the pressure steel pipe 4 used to support the inclined shaft. The tail of the TBM mainframe is suspended in the pressure steel pipe, and the TBM excavation construction is separated from the steel pipe jacking operation, thereby improving the construction efficiency.
[0037] The launching device 1 and the receiving device 2 described in this embodiment both include a fixed frame 1-1 and an articulated frame 1-2. The fixed frame 1-1 of the launching device 1 is fixed in the launching tunnel below the lower construction branch tunnel 100; the fixed frame of the receiving device 2 is fixed at the bottom of the upper construction branch tunnel 200. The articulated frame 1-2 is hinged on the fixed frame 1-1, and the articulated frame 1-2 is connected to the fixed frame 1-1 through an articulated oil cylinder 1-3. The articulated frame 1-2 rotates through the articulated oil cylinder 1-3 articulation point to adjust the angle of the articulated frame 1-2. A sliding frame 1-4 is slidably provided on the articulated frame 1-2. The sliding frame can slide relative to the articulated frame under the action of the oil cylinder or the traction device, and is used for the launching and receiving of the TBM.
[0038] like Figure 2As shown, Example 2 is a TBM inclined shaft construction system for a water diversion inclined shaft of a hydropower station. On the basis of Example 1, the TBM main machine 31 includes a cutter disc 31-1 and a box-type main beam 31-2. The box-type main beam 31-2 can adopt an existing Kai-type structure, that is, it includes an inner Kai and an outer Kai. In this embodiment, the inner Kai is of an extended design. The cutter disc 31-1 is connected to the main drive arranged on the box-type main beam 31-2, and the main drive provides the power for the rotation of the cutter disc. The box-type main beam 31-2 is provided with a shoe support device 31-3; the shoe support device can adopt the shoe support device on the existing TBM, which is used to support the TBM main machine 31 and also provide the power for the TBM to advance forward. The ABS device 32 is slidably connected to the tail of the box-type main beam 31-2 to prevent the TBM main machine from sliding backward. The ABS device is connected to the rear supporting system through a pipeline. The ABS device is in a normally open state (tightening the tunnel wall state), and can be operated to a closed state (shoe recovery, non-tightening the tunnel wall) through the operation of the main control room.
[0039] Specifically, the ABS device 32 includes a front ABS device 321 and a rear ABS device 322, and the rear ABS device 322 is connected to the front ABS device 321 via a connecting cylinder 323. Both the front ABS device 321 and the rear ABS device 322 can use a gripper device similar to that on an existing TBM, which is in a normally open state (tightening the tunnel wall state) and can be operated to a closed state (gripper retracted, not tightening the tunnel wall) through the operation of the main control room.
[0040] In this embodiment, the box-type main beam 31-2 and the pressure steel pipe 4 are provided with corresponding slag sliding channels 9 for slag sliding operation. Specifically, the TBM host chute can directly transfer the slag to the chute in the steel pipe and then continue to slide down to the bottom foundation pit slag receiving device.
[0041] Furthermore, the pushing device 5 includes a pushing frame 51, on which a pushing cylinder is provided; the anti-retreat device 7 includes an anti-retreat frame 71, on which an anti-retreat support boot is provided; the anti-retreat frame 71 is located in front of the pushing frame 51 and is fixed on the wall of the inclined shaft, and the anti-retreat support boot on the anti-retreat frame 71 can be extended and retracted relative to the steel pipe, and the anti-retreat support boot holds the steel pipe tightly when extended to prevent the steel pipe from slipping; when the steel pipe moves forward under the action of the pushing cylinder, the anti-retreat support boot retracts to release the steel pipe.
[0042] like Figure 3As shown, Example 3 is a TBM inclined shaft construction system for a water diversion inclined shaft of a hydropower station. On the basis of Example 2, the pressure steel pipe 4 described in this embodiment includes a front steel pipe section and a plurality of rear steel pipe sections. The rear supporting system 33 is arranged in the front steel pipe section. A relay device 6 is connected between the front steel pipe section and the rear steel pipe section and between two adjacent rear steel pipe sections; the front steel pipe section and the rear steel pipe section each include a plurality of steel pipe sections. When the inclined shaft is long and the jacking device 5 cannot provide sufficient jacking force, a relay device 6 is added between the corresponding two sections of the steel pipe, and the pressure steel pipe is moved forward in sections in cooperation with the jacking device. The number of relay devices can be set as needed. During the construction process, the relay devices operate in sequence from top to bottom according to the use position.
[0043] In this embodiment, each relay device 6 includes a primary relay frame 61 and a secondary relay frame 62 arranged in the pressure steel pipe 4, and a relay cylinder 63 is connected between the primary relay frame 61 and the secondary relay frame 62. The outer circumferences of the primary relay frame 61 and the secondary relay frame 62 are provided with support cylinders 64 arranged radially, and the telescopic ends of the support cylinders 64 are provided with boot plates 65. The support cylinders 64 and the boot plates 65 are telescopically extended through slots provided on the pressure steel pipe 4. Taking a relay device 6 as an example, the primary relay device is retracted, and the connecting cylinder is extended to move the pressure steel pipe in front of the relay device forward by one stroke. After the stroke is in place, the primary relay device is extended to hold the cave wall tightly, and the secondary relay device is retracted, and the connecting cylinder is retracted to move the secondary relay device forward by one stroke. According to the above method, the pressure steel pipe is stepped forward in sections and orderly.
[0044] like Figure 4 As shown, Example 4: A method for constructing a TBM inclined shaft construction system for a water diversion inclined shaft of a hydropower station described in Example 3, the steps are as follows:
[0045] S1: The TBM mainframe 31 is transported to the lower construction branch hole and pushed to the starting device, and the starting device drives the TBM mainframe 31 to rotate to the same angle as the inclined shaft (position 1 in the figure). Specifically, the TBM is transported to the lower construction branch hole in the form of parts and components, and assembled using lifting equipment such as gantry cranes or truck cranes. After the mainframe is assembled, it is pushed to the starting device and firmly fixed to the sliding parts of the starting device.
[0046] S2: After transporting the rear supporting system 33 to the lower construction branch hole and positioning the pressure steel pipe, connect the pipeline of the rear supporting system with the pipeline of the TBM main machine. Specifically, transport the rear supporting components to the lower construction branch hole, connect them with the pressure steel pipe according to the designed sequence, and connect the auxiliary equipment in each section of the pressure steel pipe with an extension pipeline. After the rear supporting system and the pressure steel pipe are positioned, connect the rear supporting system with the TBM main machine.
[0047] S3: The launching device pushes the TBM main engine upwards and moves it into the launching cavern and uses the support shoe support device 31-3 and the ABS device 32 to assist in fixing it to prevent the TBM main engine from sliding backwards;
[0048] S4: The steel pipe section where the rear supporting system is located is placed in front of the jacking device 5 at one time and is pushed forward by the jacking device 5 to move forward with the TBM excavation. When the jacking device has reached the right stroke, the stop device fixes the pressure steel pipe;
[0049] S5: After the previous steel pipe section is pushed into place, the oil cylinder of the pushing device is retracted and the next steel pipe section is connected; after the newly connected steel pipe section is connected to the previous steel pipe section (usually by welding), the anti-retraction device is disconnected from the pressure steel pipe;
[0050] S6: Repeat step S5 until the assembly of the pressure steel pipe 4 in the entire excavation section is completed;
[0051] S7: When the length of the pressure steel pipe in the inclined shaft reaches a certain length, a relay device is set between the two steel pipe sections of the pressure steel pipe. The relay device cooperates with the jacking device 5 and the stop device 6 to assemble the pressure steel pipe synchronously with the forward movement of the TBM. The working process of the relay device is as follows: the first relay frame 61 is recovered, the second relay frame 62 holds the cave wall tightly, and the relay cylinder 63 between the first relay frame 61 and the second relay frame 62 is extended to push the pressure steel pipe where the first relay frame 61 is located forward by one stroke; the first relay frame 61 holds the cave wall tightly, the second relay frame 62 is recovered, and the relay cylinder 63 between the first relay frame 61 and the second relay frame 62 is recovered, and the pressure steel pipe where the second relay frame 62 is located is pulled forward by one stroke.
[0052] S8: The TBM mainframe excavates to the upper construction hole, rotates the receiving device to the same inclination angle as the inclined shaft, and then connects the TBM mainframe with the receiving device;
[0053] S9: Rotate the receiving device to be parallel to the upper construction hole (position A in the figure), dismantle the TBM host, and transport it outside the hole for storage;
[0054] S10: Use a winch to pull the pressure steel pipe carrying the rear supporting system to the upper construction hole and dismantle it;
[0055] S11: Manually connect the front and rear ends of the penstock where the relay device is located; then retract the relay device into the assembled penstock;
[0056] S12: The relay device is moved to the upper construction hole by step-by-step operation or by winch traction and dismantled.
[0057] During TBM excavation, the slag generated by excavation flows through the cutter head slag chute and the inner chute to the pressure steel pipe slag channel, and then slides to the bottom foundation pit. The slag falling into the foundation pit can be transferred to the slag transport truck through the slag transfer belt conveyor and transported out of the hole.
[0058] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A TBM inclined shaft construction system for a water diversion inclined shaft of a hydropower station, characterized by: The invention comprises a launching device (1) arranged in a lower construction branch hole (100), a receiving device (2) arranged in an upper construction branch hole (200), and a launching cavern (300) for launching an inclined shaft TBM (3); the launching cavern (300) is connected to the lower construction branch hole (100), and the launching device (1) is arranged at the intersection of the launching cavern (300) and the lower construction branch hole (100); a jacking device (5) and a stop device (7) are arranged at the bottom of the launching cavern (300); the inclined shaft TBM (3) comprises a TBM host (31), an ABS device (32) and a rear supporting system (33); the ABS device (32) is connected to the TBM host (31), and the rear supporting system (33) is detachably connected to a pressure steel pipe (4) for supporting the inclined shaft; The originating device (1) and the receiving device (2) both comprise a fixed frame (1-1) and an articulated frame (1-2); the articulated frame (1-2) is articulated on the fixed frame (1-1), and the articulated frame (1-2) is connected to the fixed frame (1-1) via an articulated oil cylinder (1-3); the articulated frame (1-2) rotates via the articulated oil cylinder (1-3) articulation point; a sliding frame (1-4) is slidably provided on the articulated frame (1-2); The TBM main machine (31) comprises a cutterhead (31-1) and a box-type main beam (31-2), the box-type main beam (31-2) being provided with a support shoe support device (31-3), and the ABS device (32) being slidably connected to the rear of the box-type main beam (31-2); The pressure steel pipe (4) comprises a front steel pipe section and a plurality of rear steel pipe sections, the rear supporting system (33) is arranged in the front steel pipe section, and a relay device (6) is connected between the front steel pipe section and the rear steel pipe section, and between two adjacent rear steel pipe sections; the front steel pipe section and the rear steel pipe section each comprise a plurality of steel pipe sections.
2. The hydropower station diversion inclined shaft TBM inclined shaft construction system according to claim 1 is characterized by: The cutter disc (31-1) is connected to a main drive arranged on a box-type main beam (31-2).
3. The hydropower station diversion inclined shaft TBM inclined shaft construction system according to claim 1 is characterized by: The ABS device (32) comprises a front ABS device (321) and a rear ABS device (322), and the rear ABS device (322) is connected to the front ABS device (321) via a connecting oil cylinder (323).
4. The hydropower station diversion inclined shaft TBM inclined shaft construction system according to claim 1 is characterized by: Corresponding slag sliding channels are provided in the box-type main beam (31-2) and the pressure steel pipe (4).
5. The hydropower station diversion inclined shaft TBM inclined shaft construction system according to claim 1 is characterized by: The pushing device (5) comprises a pushing frame (51) on which a pushing oil cylinder is provided; the stopping device (7) comprises a stopping frame (71) on which a stopping shoe is provided; the stopping frame (71) is located in front of the pushing frame (51).
6. The hydropower station water diversion inclined shaft TBM inclined shaft construction system according to claim 1, characterized in that: The relay device (6) comprises a primary relay frame (61) and a secondary relay frame (62) arranged in a pressure steel pipe (4); a relay oil cylinder (63) is connected between the primary relay frame (61) and the secondary relay frame (62); a support oil cylinder (64) is arranged radially on the outer circumference of each of the primary relay frame (61) and the secondary relay frame (62); a shoe plate (65) is provided at the telescopic end of the support oil cylinder (64); and the support oil cylinder (64) and the shoe plate (65) are telescopically movable through slots provided on the pressure steel pipe (4).
7. A method for constructing a TBM inclined shaft construction system for a water diversion inclined shaft of a hydropower station according to any one of claims 1 to 6, characterized in that: Here are the steps: S1: The TBM mainframe (31) is transported to the lower construction branch tunnel and pushed onto the launching device, and the launching device drives the TBM mainframe (31) to rotate to the same angle as the inclined shaft; S2: After transporting the rear supporting system (33) to the lower construction branch hole and positioning the pressure steel pipe, connect the pipeline of the rear supporting system with the pipeline of the TBM main machine; S3: The launching device pushes the TBM main engine upwards and moves it into the launching cavern and uses a support shoe support device (31-3) and an ABS device (32) to assist in fixing the main engine of the TBM to prevent it from sliding backwards; S4: The steel pipe section where the rear supporting system is located is placed in front of the jacking device (5) and is pushed forward by the jacking device (5) to move forward along with the TBM excavation. When the jacking device has reached the right position, the stop device fixes the pressure steel pipe; S5: After the previous steel pipe section is pushed into place, the oil cylinder of the pushing device is retracted and the next steel pipe section is connected; after the newly connected steel pipe section is connected with the previous steel pipe section, the back-stop device is disconnected from the pressure steel pipe; S6: repeat step S5 until the assembly of the pressure steel pipe (4) in the entire excavation section is completed; S7: When the length of the pressure steel pipe in the inclined shaft reaches a certain length, a relay device is arranged on the pressure steel pipe, and the relay device cooperates with the jacking device (5) and the stop device (7) to assemble the pressure steel pipe synchronously with the forward movement of the TBM; S8: The TBM mainframe excavates to the upper construction hole, rotates the receiving device to the same inclination angle as the inclined shaft, and then connects the TBM mainframe with the receiving device; S9: Rotate the receiving device to be parallel to the upper construction hole, dismantle the TBM host, and transport it outside the hole for storage; S10: Use a winch to pull the pressure steel pipe carrying the rear supporting system to the upper construction hole and dismantle it; S11: Manually connect the front and rear ends of the penstock where the relay device is located; then retract the relay device into the assembled penstock; S12: The relay device is moved to the upper construction hole by step-by-step operation or by winch traction and dismantled.
8. The method for constructing a TBM inclined shaft construction system for a water diversion inclined shaft of a hydropower station according to claim 7, characterized in that: The working process of the relay device in step S7 is as follows: the first relay frame (61) is retracted, the second relay frame (62) is supported against the cave wall, and the relay oil cylinder (63) between the first relay frame (61) and the second relay frame (62) is extended to push the pressure steel pipe where the first relay frame (61) is located forward by one stroke; the first relay frame (61) is supported against the cave wall, the second relay frame (62) is retracted, and the relay oil cylinder (63) between the first relay frame (61) and the second relay frame (62) is retracted to pull the pressure steel pipe where the second relay frame (62) is located forward by one stroke.