A construction method for on-site assembly of prefabricated segmental pier bodies
Through the on-site assembly method of prefabricated segment pier body and pier cap, combined with steel mesh, sleeve and micro-expanded concrete, the safety risks and quality control problems in bridge pier construction are solved, construction efficiency and quality are improved, and construction efficiency and quality are reduced. Construction cost.
Patent Information
- Application Number
- CN202210782564.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-07-05
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2042-07-05
AI Technical Summary
There are problems in the construction of bridge piers with high safety risks, difficult quality control, low construction efficiency and difficult insulation measures.
The prefabricated segmented pier body and pier cap are used to implement segmented construction and construction by combining centralized prefabricated field, prefabricated pedestals, using reinforced mesh, sleeves and lifting parts, mold drop technology and micro-expanded concrete. Combination assembly.
It improves the quality and efficiency of pier construction, reduces safety risks, ensures the curing effect and quality control of concrete, and shortens the construction period.
Smart Images

Figure CN115142348B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of bridge engineering construction, and in particular relates to a construction method for on-site assembly of a prefabricated segment pier body. Background Art
[0002] With the continuous construction of my country's transportation infrastructure, the transportation network is becoming more and more dense. Bridge projects are widely used because they occupy less land.
[0003] A bridge pier is a structure located in the middle of a bridge and supporting the upper structures of two adjacent spans. Its function is to reliably and effectively transmit the load from the upper structure to the foundation. The bridge pier plays an important supporting role in the overall structure of the bridge. The construction method of the bridge pier body usually adopts the method of on-site formwork cast-in-place concrete. This method has a relatively large safety risk. There are great safety risks in the process of formwork erection and demolition. The concrete casting process is also prone to safety risks such as formwork explosion. The maintenance quality of the pier body is often difficult to control, which brings certain hidden dangers to the quality of the pier body. Since the formwork can only be removed after the pier body reaches the demolding strength, the turnover time of the pier body formwork is increased, which reduces the construction efficiency of the bridge pier. If the work is rushed, a large amount of formwork needs to be invested, which increases the construction cost. When the temperature drops, the insulation measures for the pier body are more difficult, and the insulation effect is not good, which will bring certain hidden dangers to the quality of the pier body. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a construction method for on-site assembly of prefabricated segmental pier bodies. This construction method can overcome the above-mentioned difficulties or problems, improve the pier body construction efficiency, ensure construction quality, and reduce safety risks.
[0005] In order to achieve the above purpose, this method proposes the following construction technical solutions:
[0006] The segmental pier body and pier cap are prefabricated in a centralized prefabrication yard. Prefabricated pedestals are set up in the prefabrication yard. The number of pedestals is determined according to the construction progress and the maintenance time of the segmental pier body.
[0007] The structure of the segmental pier body: The lower surface of the segmental pier body is provided with a groove that is recessed into the segmental pier body. The distance between the outer edges of the four sides of the groove and the outer edges of the four sides of the segmental pier body is 20 cm, and the depth of the groove is 20 cm. There is a boss extending upward on the upper surface of the segmental pier body. The distance between the outer edges of the boss and the outer edges of the segmental pier body is 20 cm, and the height of the boss is 20 cm. The four corners of the boss of the segmental pier body are pre-embedded with lifting parts, and the four corners of the groove are provided with reserved holes for installing lifting parts corresponding to the positions of each lifting part, which are used for the lifting of the segmental pier body, and also include four reserved holes for installing I-beams that run through the entire segmental pier body. There is a steel mesh inside the segmental pier body.
[0008] The construction method of the segmental pier body is as follows: prefabricate the bottom mold of the segmental pier body pedestal, and there is a boss extending upward on the bottom mold. The distance between the outer edges of the four sides of the boss and the outer edges of the four sides of the bottom mold is 20cm, and the height of the boss is 20cm. Four steel plates extending upward are set at the four corners of the boss. The positions of the steel plates are consistent with the positions of the four reserved holes for installing the hanging parts. The height of the steel plates is 2-5mm higher than the height of the embedded hanging parts exposed outside the segmental pier body, and the width is 2-4mm more than the width of the embedded hanging parts.
[0009] The segmental pier body steel mesh is tied to the bottom form of the prefabricated segmental pier body pedestal. The distance between the segmental pier body steel mesh and the segmental pier body side form is the thickness of the protective layer required by the design drawings. The steel mesh can prevent the cracking of concrete. Four sleeves with the same height as the segmental pier body are installed on the boss of the bottom form. The cross section of the sleeve is rectangular. The length and width of the bottom section of the sleeve are 1-2mm smaller than the length and width of the upper section, so that the sleeve has a chamfered platform structure, which is convenient for the removal of the sleeve after the concrete pouring is completed. A ring handle is set on the top of the sleeve for lifting the sleeve handle when removing it. After the sleeve is installed in place, two layers of well-shaped steel bars are set up to locate the position of the sleeve. The sleeve is installed in the hole formed in the middle of the two layers of well-shaped steel bars. The upper well-shaped steel bars and the lower well-shaped steel bars are welded to the segmental pier body steel mesh, so that the sleeve can be positioned.
[0010] The four pre-buried hanging parts are welded to the steel mesh of the segment pier body through positioning steel bars. The hanging parts are U-shaped, and hanging holes are set at the upper ends of the hanging parts.
[0011] After the segmental pier body steel mesh, sleeves, and hoisting parts are installed, the segmental pier body side formwork is erected. A 20cm high boss formwork with four sides reduced inward by 20cm is installed on the top of the segmental pier body side formwork. A truss is installed at the position of the segmental pier body side formwork corresponding to the boss formwork, and the boss formwork is installed and fixed by the truss by dropping the formwork. After the formwork is erected, the segmental pier body concrete is poured. When the concrete strength reaches the hoisting requirements, the side formwork is removed and the segmental pier body is hoisted to the maintenance area for maintenance.
[0012] The height of the segmental pier body is divided into standard segments and non-standard segments. The heights of standard segments are 2m, 1.5m and 1m respectively. The height of non-standard segments is the overall height of the pier body minus the height of the standard segment. According to the designed height of the pier body, standard and non-standard segments are used to assemble the pier body.
[0013] Structure of the pier cap: a lower groove recessed into the interior of the pier cap is provided on the lower surface of the pier cap, the distance between the outer edges of the four sides of the lower groove and the outer edges of the four sides of the pier cap is 20 cm, and the depth of the lower groove is 20 cm; four lifting parts are embedded in the four corners of the upper surface of the pier cap, and reserved holes for installing the lifting parts are provided at the four corners of the lower groove on the lower surface of the pier cap corresponding to the positions of the four lifting parts, and two upper grooves recessed into the interior of the pier cap are also provided on the upper surface of the pier cap, the depth of the upper groove is 5 cm, and the width of the upper groove is 5-10 cm wider than the pad stone at the top of the pier. After assembly, the two upper grooves are located at the pad stone at the top of the pier, and each upper groove is provided with two reserved holes for installing I-beams that run through the entire pier cap; the positions of the four reserved holes for installing lifting parts at the four corners of the lower groove on the lower surface of the pier cap correspond to the positions of the four lifting parts embedded in the four corners of the boss of the segmental pier body; the positions of the four reserved holes for installing I-beams correspond to the positions of the four reserved holes for installing I-beams of the segmental pier body.
[0014] The construction method of the pier cap is: use the pedestal bottom formwork of the prefabricated segmental pier body, tie the pier cap steel mesh on the pedestal bottom formwork, and the distance between the pier cap steel mesh and the segmental pier body side formwork is the thickness of the protective layer required by the design drawings. Four sleeves with the same height as the segmental pier body are installed on the boss of the bottom formwork. The cross section of the sleeve is rectangular. The length and width of the sleeve bottom section are 1-2mm smaller than the length and width of the upper section, so that the sleeve has a chamfered platform structure. A ring handle is set on the top of the sleeve. After the sleeve is installed in place, two layers of well-shaped steel bars are set up to locate the position of the sleeve. The sleeve is installed in the hole formed in the middle of the two layers of well-shaped steel bars. The upper well-shaped steel bars and the lower well-shaped steel bars are welded to the steel mesh. Four pre-buried hanging parts are welded to the pier cap steel mesh through positioning steel bars. The hanging parts are U-shaped, and hanging holes are set at the upper ends of the hanging parts.
[0015] After the steel mesh, sleeves, and hoisting parts are installed, the side formwork of the segmental pier cap is erected. The truss is installed on the side formwork of the pier cap, and the upper groove formwork is installed and fixed by the truss by dropping the formwork. After the formwork is erected, concrete pouring begins. When the concrete strength reaches the hoisting requirements, the side formwork is removed and the pier cap is hoisted to the maintenance area for maintenance.
[0016] During the construction of the cap on site, a boss matching the groove at the bottom of the segmental pier is set at the pier body position, and four steel plates are embedded on the boss. The positions of the four embedded steel plates are respectively consistent with the positions of the four reserved holes for installing I-beams in the segmental pier body. Two "J"-shaped steel bars are welded at the bottom of the steel plate, and the steel bars are embedded in the cap concrete.
[0017] Weld the I-beams to the four steel plates embedded in the cap boss (the width of the I-beam is 2-4cm smaller than the width of the sleeve). The height of the I-beam is also segmented, and the height of each segment is 5-10cm higher than the installed segment pier. After the first section of the I-beam is welded on the embedded steel plate, the first segment pier is lifted by the lifting parts at the segment pier boss, and the I-beams are inserted into the four reserved holes for installing the I-beams on the segment pier, and the cap boss is inserted into the groove at the bottom of the segment pier. The first segment pier is installed. Weld the second section of the I-beam to the first section of the I-beam. After the welding is completed, hoist the second segment pier. Similarly, the second section of the I-beam is inserted into the four reserved holes for installing the I-beams on the second segment pier, and the boss of the first segment pier is inserted into the groove at the bottom of the second segment pier. The second section is installed. Repeat the above sequence until the segment pier is installed to the design elevation. The top elevation of the I-beam is 1-2 cm higher than the bottom of the groove on the upper surface of the pier cap.
[0018] Finally, the pier cap is installed in the same way as the segmental pier body. After the pier cap is installed in place, pour micro-expansive concrete with a grade one level higher than the pier body concrete into the reserved hole for installing the I-beam. When the micro-expansive concrete is poured to the bottom elevation of the pier cap groove, it is covered and cured. When the strength of the micro-expansive concrete reaches the design requirements, two longitudinal I-beams are welded and connected with two steel plates. Pad stone steel bars are welded on the two steel plates and tied. After the tying is completed, the pad stone side formwork is erected to pour the pad stone concrete and cure until the strength reaches the design requirements. The entire pier body construction is completed.
[0019] The advantages of the present invention are as follows: since the pier body is centrally prefabricated in a prefabrication yard, the construction quality of the pier body can be effectively improved, the quality control of concrete can be in place, and the occurrence of common concrete quality problems can be reduced or avoided. The maintenance measures in the prefabrication yard can be effectively implemented to ensure the maintenance effect of the concrete. According to the construction progress of the foundation on site, the segmental pier body can be prefabricated in advance, which improves the construction efficiency and shortens the construction period. It avoids the use of a supporting formwork system on site and reduces safety risks. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is a schematic diagram of the main structure of the segmental pier body in the present invention;
[0021] Figure 2 It is a schematic diagram of the top view structure of the segmental pier body in the present invention;
[0022] Figure 3 It is a schematic diagram of the main structure of the pier cap in the present invention;
[0023] Figure 4 It is a schematic diagram of the top view of the pier cap in the present invention. DETAILED DESCRIPTION
[0024] The segmental pier body 1 and pier cap 2 are centrally prefabricated in a prefabrication yard. Prefabricated pedestals are set up in the prefabrication yard. The number of pedestals is determined according to the construction progress and the maintenance time of the segmental pier body.
[0025] See also Figure 1 and Figure 2 , The structure of the segmental pier body: The lower surface of the segmental pier body 1 is provided with a groove 11 recessed into the segmental pier body, the distance between the outer edges of the four sides of the groove and the outer edges of the four sides of the segmental pier body is 20 cm, and the depth of the groove is 20 cm. There is a boss 12 extending upward on the upper surface of the segmental pier body, the distance between the outer edges of the boss and the outer edges of the segmental pier body is 20 cm, and the height of the boss is 20 cm; the four corners of the boss of the segmental pier body are respectively embedded with lifting parts 13, and the four corners of the groove are respectively provided with reserved holes 14 for installing lifting parts corresponding to the positions of each lifting part, which are used for the lifting of the segmental pier body, and also include four reserved holes 15 for installing I-beams that run through the entire segmental pier body. There is a steel mesh inside the segmental pier body.
[0026] The construction method of the segmental pier body is as follows: prefabricate the bottom mold of the segmental pier body pedestal, and there is a boss extending upward on the bottom mold. The distance between the outer edges of the four sides of the boss and the outer edges of the four sides of the bottom mold is 20cm, and the height of the boss is 20cm. Four steel plates extending upward are set at the four corners of the boss. The positions of the steel plates are consistent with the positions of the four reserved holes for installing the hanging parts. The height of the steel plates is 2-5mm higher than the height of the embedded hanging parts exposed outside the segmental pier body, and the width is 2-4mm more than the width of the embedded hanging parts.
[0027] The segmental pier body steel mesh is tied to the bottom form of the prefabricated segmental pier body pedestal. The distance between the segmental pier body steel mesh and the segmental pier body side form is the thickness of the protective layer required by the design drawings. The steel mesh can prevent the cracking of concrete. Four sleeves with the same height as the segmental pier body are installed on the boss of the bottom form. The cross section of the sleeve is rectangular. The length and width of the bottom section of the sleeve are 1-2mm smaller than the length and width of the upper section, so that the sleeve has a chamfered platform structure, which is convenient for the removal of the sleeve after the concrete pouring is completed. A ring handle is set on the top of the sleeve for lifting the sleeve handle when removing it. After the sleeve is installed in place, two layers of well-shaped steel bars are set up to locate the position of the sleeve. The sleeve is installed in the hole formed in the middle of the two layers of well-shaped steel bars. The upper well-shaped steel bars and the lower well-shaped steel bars are welded to the segmental pier body steel mesh, so that the sleeve can be positioned.
[0028] The four pre-buried hanging parts are welded to the steel mesh of the segment pier body through positioning steel bars. The hanging parts are U-shaped, and hanging holes are set at the upper ends of the hanging parts.
[0029] After the segmental pier body steel mesh, sleeves, and hoisting parts are installed, the segmental pier body side formwork is erected. A 20cm high boss formwork with four sides reduced inward by 20cm is installed on the top of the segmental pier body side formwork. A truss is installed at the position of the segmental pier body side formwork corresponding to the boss formwork, and the boss formwork is installed and fixed by the truss by dropping the formwork. After the formwork is erected, the segmental pier body concrete is poured. When the concrete strength reaches the hoisting requirements, the side formwork is removed and the segmental pier body is hoisted to the maintenance area for maintenance.
[0030] The height of the segmental pier body is divided into standard segments and non-standard segments. The heights of standard segments are 2m, 1.5m and 1m respectively. The height of non-standard segments is the overall height of the pier body minus the height of the standard segment. According to the designed height of the pier body, standard and non-standard segments are used to assemble the pier body.
[0031] See also Figure 3 and Figure 4 The structure of the pier cap 2 is as follows: a lower groove 21 is provided on the lower surface of the pier cap, which is recessed into the interior of the pier cap. The distance between the outer edges of the four sides of the lower groove and the outer edges of the four sides of the pier cap is 20 cm, and the depth of the lower groove is 20 cm; four hanging parts 22 are respectively embedded in the four corners of the upper surface of the pier cap, and reserved holes 23 for installing hanging parts are respectively provided at the four corners of the lower groove on the lower surface of the pier cap corresponding to the positions of the four hanging parts. The upper surface of the pier cap is also provided with two upper grooves 24 recessed into the interior of the pier cap, and the depth of the upper grooves is 5cm, the width of the upper groove is 5-10cm wider than the pad stone at the top of the pier. After assembly, the two upper grooves are located at the pad stone at the top of the pier, and each upper groove is provided with two reserved holes 25 for installing I-beams that run through the entire pier cap; the positions of the four reserved holes for installing lifting parts at the four corners of the lower groove on the lower surface of the pier cap respectively correspond to the positions of the four lifting parts pre-buried at the four corners of the segment pier body boss; the positions of the four reserved holes for installing I-beams correspond to the positions of the four reserved holes for installing I-beams of the segment pier body.
[0032] The construction method of the pier cap is: use the pedestal bottom formwork of the prefabricated segmental pier body, tie the pier cap steel mesh on the pedestal bottom formwork, and the distance between the pier cap steel mesh and the segmental pier body side formwork is the thickness of the protective layer required by the design drawings. Four sleeves with the same height as the segmental pier body are installed on the boss of the bottom formwork. The cross section of the sleeve is rectangular. The length and width of the sleeve bottom section are 1-2mm smaller than the length and width of the upper section, so that the sleeve has a chamfered platform structure. A ring handle is set on the top of the sleeve. After the sleeve is installed in place, two layers of well-shaped steel bars are set up to locate the position of the sleeve. The sleeve is installed in the hole formed in the middle of the two layers of well-shaped steel bars. The upper well-shaped steel bars and the lower well-shaped steel bars are welded to the steel mesh. Four pre-buried hanging parts are welded to the pier cap steel mesh through positioning steel bars. The hanging parts are U-shaped, and hanging holes are set at the upper ends of the hanging parts.
[0033] After the steel mesh, sleeves and hoisting parts are installed, the side formwork of the pier cap is erected. The truss is installed on the side formwork of the pier cap, and the upper groove formwork is installed and fixed by the truss by dropping the formwork. After the formwork is erected, concrete pouring begins. When the concrete strength reaches the hoisting requirements, the side formwork is removed and the pier cap is hoisted to the maintenance area for maintenance.
[0034] During the construction of the cap on site, a boss matching the groove at the bottom of the segmental pier is set at the pier body position, and four steel plates are embedded on the boss. The positions of the four embedded steel plates are respectively consistent with the positions of the four reserved holes for installing I-beams in the segmental pier body. Two "J"-shaped steel bars are welded at the bottom of the steel plate, and the steel bars are embedded in the cap concrete.
[0035] Weld the I-beams to the four steel plates embedded in the cap boss (the width of the I-beam is 2-4cm smaller than the width of the sleeve). The height of the I-beam is also segmented, and the height of each segment is 5-10cm higher than the installed segment pier. After the first section of the I-beam is welded on the embedded steel plate, the first segment pier is lifted by the lifting parts at the segment pier boss, and the I-beams are inserted into the four reserved holes for installing the I-beams on the segment pier, and the cap boss is inserted into the groove at the bottom of the segment pier. The first segment pier is installed. Weld the second section of the I-beam to the first section of the I-beam. After the welding is completed, hoist the second segment pier. Similarly, the second section of the I-beam is inserted into the four reserved holes for installing the I-beams on the second segment pier, and the boss of the first segment pier is inserted into the groove at the bottom of the second segment pier. The second section is installed. Repeat the above sequence until the segment pier is installed to the design elevation. The top elevation of the I-beam is 1-2 cm higher than the bottom of the groove on the upper surface of the pier cap.
[0036] Finally, the pier cap is installed in the same way as the segmental pier body. After the pier cap is installed in place, pour micro-expansive concrete with a grade one level higher than the pier body concrete into the reserved hole for installing the I-beam. When the micro-expansive concrete is poured to the bottom elevation of the pier cap groove, it is covered and cured. When the strength of the micro-expansive concrete reaches the design requirements, two longitudinal I-beams are welded and connected with two steel plates. Pad stone steel bars are welded on the two steel plates and tied. After the tying is completed, the pad stone side formwork is erected to pour the pad stone concrete and cure until the strength reaches the design requirements. The entire pier body construction is completed.
[0037] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A construction method for on-site assembly of prefabricated segmental pier bodies, characterized by: The segmental pier body and pier cap are prefabricated in a centralized prefabrication yard, and a prefabrication pedestal is set up in the prefabrication yard; The structure of the segmental pier body: the lower surface of the segmental pier body is provided with a groove recessed into the segmental pier body, the distance between the outer edges of the four sides of the groove and the outer edges of the four sides of the segmental pier body is 20cm, the depth of the groove is 20cm, and the upper surface of the segmental pier body is provided with a boss extending upward, the distance between the outer edges of the boss and the outer edges of the segmental pier body is 20cm, and the height of the boss is 20cm; the four corners of the boss of the segmental pier body are respectively embedded with lifting parts, and the four corners of the groove are respectively provided with reserved holes for installing lifting parts corresponding to the positions of each lifting part, and also include four reserved holes for installing I-beams that run through the entire segmental pier body; there is a steel mesh inside the segmental pier body; The construction method of the segmental pier body is as follows: prefabricate the bottom mold of the segmental pier body pedestal, and there is a boss extending upward on the bottom mold. The distance between the outer edges of the four sides of the boss and the outer edges of the four sides of the bottom mold is 20 cm, and the height of the boss is 20 cm; four steel plates extending upward are respectively set at the four corners of the boss, and the positions of the steel plates are consistent with the positions of the four reserved holes for installing the hanging parts. The height of the steel plates is 2-5 mm higher than the height of the embedded hanging parts exposed outside the segmental pier body, and the width is 2-4 mm more than the width of the embedded hanging parts; The segmental pier body steel mesh is tied on the bottom form of the prefabricated segmental pier body pedestal, and the distance between the segmental pier body steel mesh and the segmental pier body side form is the thickness of the protective layer; four sleeves with the same height as the segmental pier body are installed on the boss of the bottom form, and the cross section of the sleeve is rectangular. The length and width of the bottom cross section of the sleeve are 1-2mm smaller than the length and width of the upper cross section. A ring handle is set on the top of the sleeve. After the sleeve is installed in place, upper and lower layers of well-shaped steel bars are set to locate the position of the sleeve. The sleeve is installed in the hole formed in the middle of the two layers of well-shaped steel bars. The upper well-shaped steel bars and the lower well-shaped steel bars are welded to the segmental pier body steel mesh; The four pre-buried hanging parts are welded to the steel mesh of the segment pier body through positioning steel bars; After the segmental pier body steel mesh, sleeves and hoisting parts are installed, the segmental pier body side formwork is erected; a 20cm high boss formwork with four sides reduced by 20cm inward is installed on the top of the segmental pier body side formwork; a truss is installed at the position of the segmental pier body side formwork corresponding to the boss formwork, and the boss formwork is installed and fixed by the truss in a drop formwork manner; after the formwork is erected, the segmental pier body concrete is poured; when the concrete strength reaches the hoisting requirements, the side formwork is removed and the segmental pier body is maintained; The structure of the pier cap: a lower groove recessed into the interior of the pier cap is provided on the lower surface of the pier cap, the distance between the outer edges of the four sides of the lower groove and the outer edges of the four sides of the pier cap is 20 cm, and the depth of the lower groove is 20 cm; four hanging parts are respectively embedded in the four corners of the upper surface of the pier cap, and reserved holes for installing hanging parts are respectively provided at the four corners of the lower groove on the lower surface of the pier cap corresponding to the positions of the four hanging parts, and two upper grooves recessed into the interior of the pier cap are also provided on the upper surface of the pier cap, the depth of the upper groove is 5 cm, and the width of the upper groove is 5-10 cm wider than the pad stone at the top of the pier. After assembly, the two upper grooves are located at the pad stone at the top of the pier, and each upper groove is provided with two reserved holes for installing I-beams that run through the entire pier cap; the positions of the four reserved holes for installing hanging parts at the four corners of the lower groove on the lower surface of the pier cap correspond to the positions of the four hanging parts embedded in the four corners of the boss of the segmental pier body; the positions of the four reserved holes for installing I-beams correspond to the positions of the four reserved holes for installing I-beams on the segmental pier body; The construction method of the pier cap is as follows: use the pedestal bottom formwork of the prefabricated segmental pier body, tie the pier cap steel mesh on the pedestal bottom formwork, and the distance between the pier cap steel mesh and the segmental pier body side formwork is the thickness of the protective layer; install four sleeves with the same height as the segmental pier body on the boss of the bottom formwork, the sleeve has a rectangular cross-section, the length and width of the sleeve bottom cross-section are 1-2mm smaller than the length and width of the upper cross-section, and a ring handle is set on the top of the sleeve. After the sleeve is installed in place, two layers of well-shaped steel bars are set up to locate the position of the sleeve, and the sleeve is installed in the hole formed in the middle of the two layers of well-shaped steel bars. The upper well-shaped steel bars and the lower well-shaped steel bars are welded to the steel mesh; four pre-buried hoisting parts are respectively welded to the pier cap steel mesh through positioning steel bars; After the steel mesh, sleeve and hoisting parts are installed, the side formwork of the pier cap is erected; the truss is installed on the side formwork of the pier cap, and the upper groove formwork is installed and fixed by the truss by dropping the formwork; after the formwork is erected, concrete pouring begins; when the concrete strength reaches the hoisting requirements, the side formwork is removed and the pier cap is maintained; During the construction of the cap on site, a boss matching the groove at the bottom of the segmental pier is set at the pier body position, and four steel plates are embedded on the boss. The positions of the four embedded steel plates are respectively consistent with the positions of the four reserved holes for installing I-beams in the segmental pier body; Two "X"-shaped steel bars are welded at the bottom of the steel plate, and the steel bars are embedded in the concrete of the cap; The I-beams are welded to the four steel plates pre-embedded on the boss of the cap respectively. The height of the I-beams is also segmented, and the height of each section is 5-10cm higher than the height of the installed segmental pier. After the first section of the I-beam is welded on the pre-embedded steel plate, the first segmental pier body is hoisted by the hoisting parts at the boss of the segmental pier body, and the I-beams are respectively inserted into the four reserved holes for installing the I-beams on the segmental pier body, and the boss of the cap is inserted into the groove at the bottom of the segmental pier body, and the first segmental pier body is installed. The second section of the I-beam is welded to the first section of the I-beam. After the welding is completed, the second segmental pier body is hoisted, and the second section of the I-beam is also inserted into the four reserved holes for installing the I-beams on the second segmental pier body, and the boss of the first segmental pier body is inserted into the groove at the bottom of the second segmental pier body, and the second section is installed. Repeat the above sequence until the segmental pier body is installed to the design elevation, and the top elevation of the I-beam is 1-2cm higher than the bottom of the groove on the upper surface of the pier cap. Finally, the pier cap is installed. The installation method of the pier cap and the segmental pier body is the same. After the pier cap is in place, pour the micro-expansive concrete with a grade one grade higher than the pier body concrete into the reserved hole for installing the I-beam. When the micro-expansive concrete is poured to the bottom elevation of the pier cap groove, it is covered and cured. When the strength of the micro-expansive concrete reaches the design requirement, two longitudinal I-beams are welded and connected with two steel plates respectively, and the pad stone steel bars are welded on the two steel plates. The pad stone steel bars are tied. After the tying is completed, the pad stone side formwork is erected to pour the pad stone concrete and cure until the strength reaches the requirement and the entire pier body construction is completed.