Construction method of large-size arc-shaped parts in shield tunnel of urban railway

Through fine adjustment and monitoring technology, the problem of assembling wrong tables and grouting density control in the construction of large-sized arc parts of urban railway shield tunnels has been solved, the construction efficiency and installation quality have been improved, and the risk of concrete waste and cold joints has been reduced.

CN115199303BActive Publication Date: 2024-12-03CCCC TUNNEL ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210553203.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-05-20
Publication Date
2024-12-03
Estimated Expiration
2042-05-20

AI Technical Summary

Technical Problem

There are problems in the construction of large-size arc parts of urban railway shield tunnels, which are difficult to control the assembly platform and bottom grouting density, resulting in low installation quality of arc parts, affecting subsequent partition wall construction and track laying operations.

Method used

The fine adjustment method is used to select, lift, position and grout the arc parts, including the use of a leveler for horizontal and vertical adjustment, the grout density is monitored through pressure sensors and mud sensors, and the concrete chute structure is used to ensure concrete. accurate and continuous pouring.

Benefits of technology

Effectively control the assembly of arc parts and grouting density, improve construction efficiency, reduce the probability of concrete waste and cold joints, and ensure the stable installation of arc parts and the smooth progress of subsequent construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115199303B_ABST
    Figure CN115199303B_ABST
Patent Text Reader

Abstract

This invention discloses a construction method for large-size arc-shaped components in shield tunnels for urban railways, including: S1, selection of arc-shaped components; S2, hoisting of arc-shaped components; S3, positioning and fine-tuning of arc-shaped components; and S4, grouting of the bottom of the arc-shaped components. On the one hand, this invention achieves high construction efficiency by fine-tuning the arc-shaped components to fit the tunnel axis according to the layout points, and to fit the arc-shaped component assembly inclination angle with the longitudinal slope of the tunnel, thus controlling horizontal and vertical misalignment and facilitating bolt assembly. On the other hand, it performs grouting of the pouring joints formed between multiple arc-shaped components and tunnel segments simultaneously, ensuring high construction efficiency. Furthermore, under liquid level and stress monitoring, it ensures that the density of the grouted concrete meets requirements. This not only reduces concrete waste but also lowers the probability of cold joints during construction. In addition, the pouring process does not cause the arc-shaped components to lift, nor does it cause uneven road surface settlement during later operation, facilitating subsequent tunnel construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of shield tunnel construction, and in particular relates to a construction method for large-size arc-shaped parts in a shield tunnel of an urban railway. Background Art

[0002] In recent years, with the rapid development of urban rail transit and large underwater tunnels, the shield method has become the preferred method for urban mainstream tunnel construction due to its advantages of fast construction, no impact on ground traffic, and better control of ground settlement. Especially in the direction of large-diameter shield tunnels, with the increasing degree of prefabrication and assembly, existing shield tunnel arc parts projects have adopted a fully prefabricated structure that is faster to construct and more environmentally friendly.

[0003] Therefore, the prefabricated arc-shaped parts directly replaced the intermediate box culvert and the cast-in-place side box culvert structure, and in order to facilitate installation and construction, a through cavity was formed inside the prefabricated arc-shaped parts, and an arc-shaped opening was formed at the bottom. During installation, the bottom surface of the prefabricated arc-shaped parts was erected on the tunnel segments, and a joint was formed between the periphery of the prefabricated arc-shaped parts and the inner wall of the segments. Therefore, grouting is required to ensure the stability of the installation of the arc-shaped parts. In this way, the arc-shaped openings and the ends of the prefabricated arc-shaped parts need to be sealed, and then grouting is performed.

[0004] In short, the current construction method of large-size arc-shaped components in urban rail shield tunnels is generally divided into four parts: arc-shaped component selection, arc-shaped component hoisting, arc-shaped component positioning and fine-tuning, and arc-shaped component bottom grouting.

[0005] However, in the actual installation process, the most likely problems are: assembly misalignment control and bottom grouting density control.

[0006] Regarding the control of arc-shaped component assembly misalignment, which is mainly vertical misalignment and horizontal misalignment, the arc-shaped component is hoisted, turned over and transported to the assembly position for adjustment. When the arc-shaped component is fully adjusted and falls to the bottom, it will make the arc-shaped component connecting bolts difficult to install.

[0007] The density control of the bottom grouting is mainly about the density of the casting joint: (1) When the arc opening and the end of the prefabricated arc part are blocked, if the sealing effect is poor, it is easy to cause leakage or slurry leakage, which not only affects the density of the casting construction, but also causes waste of concrete; (2) Due to space limitations and the center alignment limitations of the prefabricated arc parts after assembly, it is difficult for the mixer truck to unload the material by the side, making it difficult for the concrete to fall accurately into the joint gap. Therefore, it is easy to have insufficient density in one casting, and if the construction is improper (such as: it is impossible to cast continuously), the concrete will be in a mess. ), will also greatly increase the probability of cold joints, which will cause cracking in the later stage and affect the installation quality of the arc parts; (3) Since the width of the gap between each arc part and the pipe segment varies greatly, the theoretical grouting volume of each gap varies greatly. It is difficult to control the grouting volume during grouting. If it is overfilled, it will cause the arc part to rise. If it is not fully filled, it will cause uneven filling, which will cause uneven settlement of the road surface in the later operation. The above two situations will cause the arc part to be misaligned in the vertical direction, affecting the subsequent construction of the middle partition wall and the subsequent track laying operation. Summary of the invention

[0008] The technical problem to be solved by the present invention is to overcome the deficiencies of the prior art and provide an improved construction method for large-size arc-shaped parts in a shield tunnel of an urban railway.

[0009] In order to solve the above technical problems, the technical solution adopted by the present invention is as follows: a construction method of a large-size arc-shaped member of a shield tunnel of an urban railway, wherein the arc-shaped member comprises an arc-shaped member having a through cavity and an arc-shaped opening, wherein the arc-shaped opening is located at the bottom of the arc-shaped member and is connected to the through cavity, and the construction method comprises:

[0010] S1, arc-shaped parts selection, which selects the order of lowering the matching arc-shaped parts according to the wedge shape of the segment;

[0011] S2. Hoisting of arc-shaped parts, including vertical hoisting and transportation and underground horizontal hoisting and transportation;

[0012] S3, positioning and fine adjustment of arc-shaped parts, wherein the positioning includes determining the centerline position, and the fine adjustment includes achieving translation of the X, Y, and Z axes or deflection around the X, Y, and Z axes, and connecting adjacent arc-shaped parts in the longitudinal direction with bolts;

[0013] S4, bottom grouting of the arc-shaped member, including: B1, opening plugging, including plugging of the bottom opening of the arc-shaped member and plugging of the end of the arc-shaped member, and the arc-shaped member forms a casting joint with two sides open between the pipe segment; B2, pouring of concrete, which injects concrete from one open side. In particular, fine adjustment includes: 1) leveling machine fine adjustment, which uses a leveling machine located in the through cavity and moves. After the arc-shaped member is roughly in place, the leveling machine is used to perform horizontal and vertical fine adjustment. At the same time, when the leveling machine is walking and working, the support point Not on the arc-shaped part, and the leveling machine has a ±5° steering function; 2) Horizontal misalignment control, first use a square tube with the same width as the arc-shaped part, put a level ruler on the top of the square tube, and work together to find the horizontal point for assembling the arc-shaped parts of the formed tunnel, then use the surveying team to lay out the arc-shaped part assembly axis point, and assemble and fit the axis of the formed tunnel according to the laid-out point; 3) Vertical misalignment control, when two adjacent ring arc-shaped parts are vertically misaligned, the arc-shaped part assembly inclination angle is adjusted in time to fit the longitudinal slope of the formed tunnel by padding the bottom of the arc-shaped part with a steel plate;

[0014] In B1, when the bottom opening is sealed, each arc-shaped opening sealing device is provided with a pressure sensor, a joint is formed between each arc-shaped member and the pipe segment, a plurality of the joints constitute the casting joint, and a mud sensor is provided in the casting joint; in the casting of B2, density detection needs to be carried out simultaneously, wherein the density detection includes: 1) grouting liquid level monitoring, which obtains the liquid level information of the poured concrete through the mud sensor and controls the grouting amount; 2) stress monitoring, which compares the data value N1 of the pressure sensor with the pressure value N2 calculated at the position of the sensor, wherein |(N1-N2) / N2|≤5%, grouting is required.

[0015] Preferably, the shield tunneling construction is advanced based on the tunnel design axis. The axis of the formed tunnel is different from the design axis. The shield machine advances in a serpentine manner. The vertical and curve radii are difficult to control and are consistent with the design axis and the curve. The positioning in S3 includes the following steps:

[0016] (1) The surveying team lays out the arc-shaped parts assembly axis points;

[0017] (2) During the assembly process, use a level to check again whether the arc is level at the top of the arc;

[0018] (3) Use the wedge shape of the arc part to fit the turning radius.

[0019] Furthermore, before the lifting of S2, the following steps are also included: 1) cleaning up debris. Before assembling the arc-shaped parts, it is necessary to clear the debris at the assembly position and the bottom of the connection surface with the upper arc-shaped part; 2) surface treatment of the arc-shaped parts, and at the same time, gluing a 5±2mm thick rubber sheet on one side of the arc-shaped parts in the direction of the large curve.

[0020] In the S2 hoisting, adjust the height of the flatbed truck that transports the arc-shaped part so that the C-type crane can grab the arc-shaped part. After the height adjustment is completed, lower and translate the hoist to the bottom of the arc-shaped part. After preliminary alignment, lift the hoist so that it is just stuck on the arc-shaped part. When it is in place, the proximity switch will give a signal. The operator can tighten the clamp and lift the arc-shaped part. After the arc-shaped part touches the limit switch, it can be translated. After the C-type crane grabs the arc-shaped part, move the arc-shaped part crane forward to the assembly position so that the arc-shaped part is erected and in place.

[0021] Furthermore, before the lifting of S2, the following steps are also included: 1) cleaning up debris. Before assembling the arc-shaped parts, it is necessary to clear the debris at the assembly position and the bottom of the connection surface with the upper arc-shaped part; 2) surface treatment of the arc-shaped parts, and at the same time, gluing a 5±2mm thick rubber sheet on one side of the arc-shaped parts in the direction of the large curve.

[0022] Preferably, in the lifting of S2, the height of the flatbed truck transporting the arc-shaped part is adjusted so that the C-type crane can grab the arc-shaped part. After the height adjustment is completed, the lifting device is lowered and translated to the bottom of the arc-shaped part. After preliminary alignment, the lifting device is lifted so that it is just stuck on the arc-shaped part. After it is in place, the proximity switch will give a signal, and the operator can tighten the clamp and lift the arc-shaped part. After the arc-shaped part touches the limit switch, it can be translated. After the C-type crane grabs the arc-shaped part, it moves the arc-shaped part crane forward to the assembly position so that the arc-shaped part is erected and in place.

[0023] According to a specific implementation and preferred aspect of the present invention, in B2 2), the force value F at the bottom opening of each arc-shaped member is obtained by a pressure sensor. 1 …F N , and obtain F 平 , and then calculate according to the following formula:

[0024] F=0.22γ c t 0 β 1 β 2 V 1 / 2 Formula 1

[0025] In formula 1, F is the pressure of the newly poured concrete on the plugging device, unit: kN / m 2 ; γ c is the gravity density of concrete, unit: kN / m 3 ; V is the pouring speed of concrete, unit: m / h; t 0 Initial setting time of newly poured concrete, unit: h, β 1 is the correction coefficient of admixture effect, and is 1.0~1.2; β 2is the correction coefficient of concrete slump, and is 0.85 to 1.15; respectively calculate the pressure value at the bottom opening of each arc-shaped member, and obtain the average value F 压 , and|(F 平 -F 压 ) / F 压 |≤5%, if the ratio exceeds 5%, grouting is required. The required density can be obtained by force value comparison.

[0026] Furthermore, the pressure sensor obtains the maximum pressure value Fmax at the bottom opening of the arc-shaped member. If (Fmax-F 压 ) / F 压 >30%, it means that the pressure sensor is damaged, and the Fmax data is discarded to obtain the F 平 .

[0027] According to a specific implementation and preferred aspect of the present invention, the mud sensors are divided into multiple groups and are spaced apart along the length direction of the shield tunnel, wherein each group of mud sensors corresponds to a pouring section, and after the grouting of each pouring section is completed, the grouting of the next pouring section is continued until the grouting of the pouring joint is completed, and after all the grouting is completed, F is obtained. 平 and F 压 The pouring is carried out in a step-by-step manner to avoid erroneous instructions from the mud sensor, which affects the grouting efficiency. In addition, the force value is obtained after all the grouting of the pouring joints is completed, thereby ensuring the accuracy of the monitoring results.

[0028] Preferably, each group of mud sensors has multiple mud sensors, two of which are located on both sides of the pouring section, and the remaining mud sensors are located between the two mud sensors, and each mud sensor is set on the bottom surface of the arc-shaped member or / and the arc-shaped surface of the pipe segment, and after multiple mud sensors are in contact with concrete, the grouting of the corresponding pouring section is stopped. The direct benefit of this is to avoid over-grouting, but this measure can only observe the overall pouring liquid level and cannot detect the local density.

[0029] Furthermore, density detection also includes radar detection, in which the poured concrete is scanned by radar and imaged to detect the density of the grouting, further verifying the quality of the grouting and ensuring the quality of the grouting.

[0030] According to another specific implementation and preferred aspect of the present invention, when the slump is less than 30 mm, β 2 Take 0.85~0.95; when the slump is 30~90mm, β 2 Take 1.0~1.1; when the slump is 90~150mm, β 2 Take 1.10~1.15, because slump directly affects the fluidity of grouting concrete.

[0031] According to another specific implementation and preferred aspect of the present invention, the pressure value of F can also be calculated by the following formula:

[0032] F=γ c H Formula 2

[0033] In formula 2, H is the total height from the concrete pressure calculation position to the top surface of the newly poured concrete, in meters, γ c is the gravity density of concrete, unit: kN / m 3 The data obtained by using Formula 2 can further verify the results of Formula 1, thereby ensuring that the grouting density meets actual needs.

[0034] According to another specific implementation and preferred aspect of the present invention, the arc-shaped opening blocking device is located in the through cavity and blocks the arc-shaped opening of the arc-shaped member, and comprises:

[0035] An arc-shaped blocking plate, comprising an arc-shaped plate body which is attached to the inner wall of the bottom of the through cavity and covers the arc-shaped opening;

[0036] A sealing member extending along the periphery of the arc-shaped opening and attached to the bottom surface of the arc-shaped plate body;

[0037] A top support member, comprising a support frame installed on the top surface of the arc-shaped plate body, a support rod installed on the support frame, and a top support foot installed on the support rod, wherein the support frame comprises a support rod arranged parallel to or / and intersecting with the arc-shaped opening, there are multiple support rods, and the multiple support rods are distributed between the support rod and the top inner wall of the through cavity with the arc-shaped opening as a reference interval, the top support foot corresponds to the support rod one by one, and can be detached from or supported on the top inner wall of the through cavity by movement and adjustment along the length direction of the support rod;

[0038] The pressure sensors are arranged on the arc-shaped sealing plate and are evenly spaced and distributed in the circumferential direction of the arc-shaped opening.

[0039] Here, by covering and fitting the arc plate body and the seal, and taking the arc opening as a reference, the uniform top support provided inside can enhance the sealing effect of the arc opening, provide the necessary conditions for high-quality pouring, and avoid waste of concrete. At the same time, there is no need to embed or post-process the arc parts, and disassembly and assembly can be carried out in a small space.

[0040] Preferably, the support rods include a plurality of arc-shaped support rods extending along the length direction of the arc-shaped opening, and a plurality of connecting support rods arranged horizontally between each two adjacent arc-shaped support rods, wherein the plurality of arc-shaped support rods and the plurality of connecting support rods intersect to form a network area to cover the arc-shaped opening, and the pressure sensor is arranged at the position of the support rod. In this way, the uniform supporting force is further ensured, the pouring quality is ensured, and the pressure is also easily obtained.

[0041] According to a specific implementation and preferred aspect of the present invention, there are two arc-shaped support rods, which are installed parallel to each other on both sides of the arc-shaped opening, the connecting support rod is horizontally arranged between the two arc-shaped support rods, and the support rod is installed on the connecting support rod and / or the arc-shaped support rod. The rod-shaped structure is optimized to further facilitate on-site installation.

[0042] Preferably, there are four support rods, which are distributed at four corners around the circumference of the arc-shaped opening, and the top support feet are installed on the top of the support rods. The arc fits and the support rods abut against each other to ensure the sealing effect.

[0043] Specifically, each support rod is vertically mounted on the arc-shaped support rod from the lower end, and the upper end extends toward the inner wall of the top of the through cavity.

[0044] According to another specific implementation and preferred aspect of the present invention, each support rod can be adjusted and extended along its length direction, so that the arc-shaped opening corresponding to the through cavity can be blocked according to the height of different through cavities.

[0045] Preferably, the top support member further comprises two reinforcing rods extending along the width direction of the arc-shaped opening, wherein each of the reinforcing rods connects the support rods located at both sides of the arc-shaped opening to ensure that the top support is firm.

[0046] Preferably, the arc plate body is an arc steel plate, and its shape is similar to that of the arc opening, so as to simplify the sealing structure and also facilitate the alignment of the centers of the arc steel plate and the arc opening.

[0047] Preferably, the top support foot comprises a support foot body, a support foot rod, and an adjustment part, wherein the adjustment part is operated to cause the support foot rod to pass through or retract from the support foot body. Under the movement of the support foot rod, the support is implemented to complete high-quality blocking.

[0048] In addition, the sealing member is a rubber pad and is aligned with the outer contour of the arc-shaped plate body, thereby ensuring a good sealing effect and being easy to implement.

[0049] According to another specific implementation and preferred aspect of the present invention, a concrete chute structure is used for grouting in S2, and the concrete chute structure comprises:

[0050] A base, comprising a chassis frame and a support frame arranged on the chassis frame;

[0051] A concrete chute, comprising a chute body forming a long strip-shaped discharge channel, the chute body having a discharge port and a feed port, and the chute body is installed on the support frame in an inclined manner with the feed port at the top and the discharge port at the bottom, wherein the discharge port extends inwardly from top to bottom;

[0052] The discharge baffle is set up at the discharge port of the chute body by flipping around a pivot extending in the width direction of the chute body, and the discharge baffle has an open state and an intercepting state. When in the open state, the concrete pushes the discharge baffle to flip upward around the pivot, and is unloaded from the opening formed by the discharge baffle and the discharge port to the slit of the prefabricated arc-shaped parts and pipe segments, and the size of the opening is proportional to the flow rate of concrete; when in the intercepting state, the discharge baffle flips around the pivot under its own weight and closes the opening. Through the cooperation of the concrete chute and the discharge baffle, not only can the concrete of the mixer truck be accurately and continuously guided and unloaded to the slot to be poured, but the unloading flow rate is controllable, reducing the probability of insufficient density and cold joints during pouring, improving the installation quality of the arc-shaped parts, but also avoiding the waste of concrete and reducing the subsequent cleaning workload.

[0053] Preferably, the support frame can be telescopically arranged up and down, and the chute body is hinged to the top of the support frame from the bottom. In this way, the unloading of concrete at different heights can be satisfied by adjusting the support frame up and down.

[0054] According to a specific implementation and preferred aspect of the present invention, the support frame includes two sets of telescopic support rods spaced apart along the length direction of the chute body, wherein the two sets of telescopic support rods can be raised and lowered to adjust the height and / or angle of the chute body. That is, when they are raised and lowered at the same time, the height can be adjusted, and the tilt angle of the chute body can be changed when the lifting height is inconsistent, thereby meeting the use needs under different working conditions and enhancing the practicality of the concrete chute structure.

[0055] Preferably, each group of telescopic support rods is telescopically adjusted synchronously, wherein each group of telescopic support rods is composed of at least two telescopic support rods, and are spaced apart and distributed along the width direction of the chute body, so that the support is more stable.

[0056] According to another specific implementation and preferred aspect of the present invention, the chute body includes an inclined chute bottom plate and chute side plates extending upward from both sides of the chute bottom plate, wherein a discharge channel with an open top is formed between the chute bottom plate and the two side chute side plates, and the upper part of the discharge channel forms a feed port and the lower part forms a discharge port. Such a chute body structure is very easy to process and shape, and the concrete flow in the discharge channel can be visually observed, which is convenient for pouring construction.

[0057] Preferably, there are two pivots, which are respectively located on both sides of the discharge baffle, wherein each pivot is rotatably connected to the corresponding side plate of the trough, and when in the intercepting state, the discharge baffle is laid on the lower end of the trough bottom plate from the bottom, which is convenient for assembly and can effectively control the flow of poured concrete.

[0058] Furthermore, the pivot is located at the upper part of the discharge baffle, which is more conducive to the flipping operation of the discharge baffle.

[0059] Specifically, the trough side plates on both sides are arranged in parallel and perpendicular to the trough bottom plate, the two sides of the discharge baffle plate are matched with the inner wall gap of the trough side plates, and the feed port and the discharge port are arranged symmetrically. The molding is convenient and obstacles to the flipping movement of the discharge baffle plate can be avoided.

[0060] According to another specific implementation and preferred aspect of the present invention, a detachable counterweight module is also provided on the discharge baffle, so that the opening can be closed at any time according to the on-site construction conditions to meet the on-site construction needs.

[0061] In addition, a universal pulley is provided at the bottom of the chassis frame to facilitate the shifting and pouring of the concrete chute structure along the length of the tunnel.

[0062] Due to the implementation of the above technical solution, the present invention has the following advantages compared with the prior art:

[0063] On the one hand, the present invention implements horizontal and vertical misalignment control through fine adjustment so that the arc-shaped parts are assembled and fitted to the axis of the formed tunnel according to the layout points, and the arc-shaped parts assembly inclination angle is fitted to the longitudinal slope of the formed tunnel, thereby facilitating bolt assembly; on the other hand, the grouting of the casting joints formed between multiple arc-shaped parts and pipe segments is implemented at one time, which has high construction efficiency, and under liquid level monitoring and stress monitoring, it can ensure that the density of the concrete after grouting meets the requirements, and at the same time, not only the waste rate of concrete is reduced, but also the probability of cold joints during construction is reduced. In addition, the arc-shaped parts will not be lifted during pouring, and uneven road surface settlement will not be caused in later operations, which is convenient for subsequent tunnel construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0064] Figure 1 is a schematic structural diagram of the arc-shaped member of this embodiment 1;

[0065] Figure 2 It is a schematic flow chart of the construction method of large-size arc-shaped parts in the shield tunnel of the urban railway in this embodiment 1;

[0066] Figure 3 for Figure 1 Schematic diagram of the process of mid-bottom grouting;

[0067] Figure 4 is a schematic diagram of the arc-shaped opening blocking device of Example 1 in a blocking state;

[0068] Figure 5 This is a schematic structural diagram of the arc-shaped opening blocking device of this embodiment 1;

[0069] Figure 6 for Figure 5 A schematic diagram of the main view;

[0070] Figure 7 for Figure 6 An enlarged top view of (top support omitted);

[0071] Figure 8 for Figure 6 Schematic diagram of an enlarged upward view;

[0072] Fig. 9 Schematic diagram of the structure of the concrete chute of Example 1 (the discharge baffle is in an open state);

[0073] Fig.10 It is a front view schematic diagram of the concrete chute structure of this embodiment 1 (the discharge baffle is in the intercepting state);

[0074] Wherein: 1. arc-shaped member; 10. through cavity; 11. arc-shaped opening; 2. arc-shaped blocking plate; 20. arc-shaped plate body; 3. sealing member; 4. top support member; 40. support frame; 400. frame rod; a. arc-shaped support rod; b. connecting support rod; 41. support rod; 42. top support foot; 420. support foot body; 421. support foot rod; 422. adjustment part; 43. reinforcing rod; A1. base; A10. chassis frame; A11. support frame; 110. telescopic support rod; A2. concrete chute; A20. chute body; 20a. discharge port; 20b. feed port; 200. trough bottom plate; 201. trough side plate; A3. discharge baffle; s. pivot; A4. counterweight module; A5. universal pulley. DETAILED DESCRIPTION

[0075] In order to make the above-mentioned purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are described in detail below in conjunction with the accompanying drawings. In the following description, many specific details are set forth to facilitate a full understanding of the present application. However, the present application can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without violating the connotation of the present application, so the present application is not limited by the specific embodiments disclosed below.

[0076] Example 1

[0077] like Figure 1 As shown, the arc-shaped member includes an arc-shaped member 1 having a through cavity 10 and an arc-shaped opening 11 , wherein the arc-shaped opening 11 is located at the bottom of the arc-shaped member 1 and communicates with the through cavity 10 .

[0078] Combination Figure 2 As shown, the construction method of large-size arc-shaped parts of urban rail shield tunnels includes:

[0079] S1, arc-shaped parts selection, which selects the order of lowering the matching arc-shaped parts according to the wedge shape of the segment;

[0080] S2. Hoisting of arc-shaped parts, including vertical hoisting and transportation and underground horizontal hoisting and transportation;

[0081] S3, positioning and fine adjustment of arc-shaped parts, wherein the positioning includes determining the centerline position, and the fine adjustment includes achieving translation of the X, Y, and Z axes or deflection around the X, Y, and Z axes, and connecting adjacent arc-shaped parts in the longitudinal direction with bolts;

[0082] S4. Grouting at the bottom of the arc-shaped part.

[0083] Specifically, the applicant breaks down the above steps as follows:

[0084] 1. Vertical and horizontal lifting and transportation in limited space

[0085] (1) Selection of arc parts

[0086] The average width of the arc parts is 2m, and the wedge amount is 50mm. The arc parts correspond to the longitudinal seams of the pipe segments one by one. Therefore, before assembling the arc parts, it is necessary to understand the trend of the pipe segments and select the order of lowering the arc parts according to the wedge amount of the pipe segments. At the same time, the arc parts have different models at special mileages. Before construction, the "Arc Part Assembly Arrangement Table" should be arranged according to the design documents and drawings.

[0087] Before transporting curved parts, check repeatedly according to the wedge quantity and mileage, and load them after confirming that they are correct and checking that there is no surface damage.

[0088] (2) Vertical transportation

[0089] The vertical transportation of this project is mainly carried out by two 55T gantry cranes placed in the arc-shaped parts yard, and forklifts are used for auxiliary construction.

[0090] (3) Horizontal lifting and transportation underground

[0091] The arc-shaped parts are transported horizontally by an electric double-head flatbed truck. The materials are transported to the underground vehicle through two lifting holes and then transported horizontally to the working surface.

[0092] 2. Measurement and positioning of arc parts

[0093] The shield tunneling construction is carried out based on the tunnel design axis. The axis of the formed tunnel is different from the design axis. The shield machine generally advances in a serpentine manner, and the vertical and curve radii are difficult to control to be consistent with the design axis and curve. Therefore, the arc-shaped parts assembly and positioning should be carried out according to the following steps:

[0094] (1) The surveying team lays out the arc-shaped parts assembly axis points. Assembly according to the laid-out points can better fit the axis of the formed tunnel, reduce the use of staggered platforms to re-fit the axis when it deviates from the axis, and reduce horizontal misalignment.

[0095] (2) During the assembly process, use a level to check again at the top of the arc to see if it is level.

[0096] (3) Use the wedge shape of the arc part to fit the turning radius.

[0097] 3. Arc Parts Assembly

[0098] (1) The arc parts are in place

[0099] a) Clean up the debris. Before assembling the arc parts, you need to clean up the debris at the assembly position and at the bottom of the connection surface with the upper arc part;

[0100] b) Surface treatment of arc-shaped parts. According to the assembly plan requirements and actual conditions, a 5mm thick nitrile cork rubber sheet is glued on one side of the arc-shaped part in the direction of the large curve to achieve a fit with the axis of the formed tunnel;

[0101] c) Adjust the height of the flatbed truck that transports the curved part so that the C-type crane can grab the curved part; after the height adjustment is completed, lower and translate the spreader to the bottom of the curved part, and after preliminary alignment, lift the spreader so that it is just stuck on the curved part; after it is in place, the proximity switch will give a signal, and the operator can tighten the clamp and lift the curved part. After the curved part touches the limit switch, it can be translated;

[0102] d) Move the arc-shaped crane forward. After the C-type crane grabs the arc-shaped part, move the arc-shaped crane forward to the assembly position to ensure that there is enough space for the arc-shaped part to stand upright;

[0103] e) To erect the arc-shaped member, first lower the arc-shaped member horizontally to a certain height and stop, then slowly lower the two sets of steel wire ropes connected to the bottom of the arc-shaped member to slowly erect the arc-shaped member. During this process, the height of the arc-shaped member and the distance from the upper arc-shaped member can be adjusted simultaneously to ensure that the arc-shaped member is roughly in place.

[0104] (2) Assembly accuracy control

[0105] a) Leveling machine fine adjustment

[0106] After the arc is roughly in place, the arc leveling equipment developed by the company is used to fine-tune the horizontal and vertical directions. The equipment can achieve translation in the X, Y, and Z directions; and rotation around the X, Y, and Z directions. When the whole machine is moving and working, the support point is not on the arc to avoid secondary displacement of the installed arc. The whole machine can achieve ±5° steering and can perform micro-steering inside the arc.

[0107] b) Horizontal misalignment control

[0108] In the early stage, an aluminum alloy square tube with the same width as the arc part is used (the square tube must be straight), and a level ruler is placed on the top of the square tube to find the horizontal point for assembling the arc parts of the formed tunnel. After that, the surveying team is used to lay out the arc part assembly axis point. The assembly according to the laid out points can better fit the axis of the formed tunnel, reduce the deviation from the axis, and re-fit the axis by staggering to reduce horizontal staggering.

[0109] During the assembly process, use a level ruler to check whether the arc is level again at the top of the arc. When assembling arcs of horizontal and vertical curve segments, the gap can be adjusted by sticking a thin plate (such as nitrile cork board) on the long side of the arc outside the curve to achieve fitting of the curve radius.

[0110] c) Vertical misalignment control

[0111] When two adjacent ring arcs are vertically misaligned, the arc assembly inclination angle is adjusted in time to fit the longitudinal slope of the formed tunnel by padding the bottom of the arc with steel plates. At the same time, the assembly quality of the segment is ensured and the misalignment of the bottom of the segment is reduced.

[0112] (3) Bolt connection

[0113] After the arc parts are fine-tuned, the adjacent arc parts are connected longitudinally, and the adjacent prefabricated arc components are connected using 6 M36 arc bolts.

[0114] 4. Grouting at the bottom of the curved part

[0115] In order to fill the gap between the bottom of the arc-shaped member and the pipe segment, the bottom of every five arc-shaped members is grouted, and the grouting material is C40 self-compacting fine stone concrete.

[0116] (1) Before grouting, the lower opening of the arc part and the end of the arc part need to be blocked to prevent grout leakage. The lower opening of the arc part is closed with the company's self-developed steel formwork.

[0117] (2) After the arc-shaped part is opened and the ends are closed, grouting is carried out through the gap between the pipe segment and the arc-shaped part. The grouting material is C40 self-compacting fine stone concrete. The grouting surface covers the arc segment of the arc-shaped part with a thickness of 60-100 mm. The theoretical grouting volume of each ring is 0.72-1.2 m3.

[0118] Due to the limited space in the tunnel and the difficulty in pouring, the company independently developed a portable arc-shaped piece pouring auxiliary equipment to assist grouting, which not only avoids concrete waste, but also allows continuous pouring and avoids the formation of cold joints that affect the stability of the bottom of the arc-shaped piece.

[0119] Combination Figure 3 As shown, the bottom grouting process for installing the arc-shaped components of the large-diameter shield tunnel of this embodiment includes the following steps:

[0120] S1, opening plugging, which includes plugging the bottom opening (shaped opening 11) of the arc-shaped member 1 and plugging the end of the arc-shaped member 1, and the arc-shaped member 1 forms a casting joint with two sides open between the two sides and the pipe segment;

[0121] S2. Concrete pouring: concrete is injected from the open side.

[0122] Specifically, in S1, when the bottom opening is sealed, the arc-shaped opening sealing device is located in the through cavity 10 and seals the arc-shaped opening 11 of the arc-shaped member. In this example, the arc-shaped opening sealing device includes an arc-shaped sealing plate 2, a sealing member 3, a top support member 4, and a pressure sensor.

[0123] Specifically, the arc-shaped blocking plate 2 includes an arc-shaped plate body 20 which is attached to the inner wall of the bottom of the through cavity 10 and covers the arc-shaped opening 11 .

[0124] The arc plate body 20 is an arc-shaped steel plate, and its shape is similar to that of the arc-shaped opening 11. This facilitates the simplification of the blocking structure and also facilitates the alignment of the centers of the arc-shaped steel plate and the arc-shaped opening.

[0125] Combination Figure 4 As shown, the top support member 4 includes a support frame 40 installed on the top surface of the arc-shaped plate body 20, a support rod 41 installed on the support frame 40, a top support foot 42 installed on the support rod 41, and a reinforcing rod 43.

[0126] The support frame 40 includes a support rod 400 arranged parallel to and intersecting the arc-shaped opening, wherein the support rod 400 includes two arc-shaped support rods a extending along the length direction of the arc-shaped opening and a connecting support rod b horizontally arranged between the two arc-shaped support rods a.

[0127] The two arc-shaped support rods a and the connecting support rod b intersect to form a grid area to cover the arc-shaped opening. In this way, the top support force is further ensured to be uniform and the pouring quality is ensured.

[0128] Two arc-shaped support rods a are installed parallel to each other on both sides of the arc-shaped opening, the connecting support rod b is horizontally arranged between the two arc-shaped support rods a, and the support rod 41 is installed on the arc-shaped support rod a. The rod-shaped structure is optimized to further facilitate on-site installation.

[0129] In this example, there are four support rods 41, which are distributed at four corners around the circumference of the arc-shaped opening, so as to ensure the sealing effect by coordinating the arc-shaped fit and the support rods.

[0130] The top support leg 42 is installed on the top of the support rod 41. The top support leg 42 corresponds to the support rod 41 one by one, and can be moved and adjusted along the length direction of the support rod 41 to be detached from or supported on the inner wall of the top of the through cavity.

[0131] Specifically, the pressure sensors correspond to the support rods one by one and are arranged at the bottom of the arc-shaped steel plate where the support rods are located.

[0132] Combination Figure 5 and Figure 6 As shown, specifically, each support rod 41 is vertically mounted on the arc-shaped support rod a from the lower end, and the upper end extends toward the inner wall of the top of the through cavity.

[0133] Each support rod 41 can be adjusted and extended along its length direction. In this way, the arc-shaped opening corresponding to the through cavity can be blocked according to the height of the through cavity.

[0134] The top support foot 42 includes a support foot body 420, a support foot rod 421, and an adjustment portion 422, wherein the adjustment portion 422 is operated (for example, the adjustment portion 422 is directly turned to the adjustment portion 422, and the support foot rod 421 is screwed in or out through the threaded cooperation between the support foot body 420 and the support foot body 420), and the support foot rod 421 passes through or retracts from the support foot body 420. Under the movement of the support foot rod, the support is implemented to complete high-quality plugging.

[0135] There are two reinforcing rods 43 extending along the width direction of the arc-shaped opening, wherein each reinforcing rod 43 connects the support rods 41 located on both sides of the arc-shaped opening to ensure that the top support is firm.

[0136] Combination Figure 7 and Figure 8 As shown, the sealing member 3 extends along the periphery of the arc-shaped opening and fits on the bottom surface of the arc-shaped plate body 20 .

[0137] Specifically, the sealing member 3 is a rubber pad and is aligned with the outer contour of the arc-shaped plate body, thereby ensuring a good sealing effect and being easy to implement.

[0138] A joint is formed between each arc-shaped member and the pipe segment, and a plurality of joints constitute a casting joint, and a mud sensor is arranged in the casting joint.

[0139] The mud sensors are divided into multiple groups and are spaced along the length of the shield tunnel. Each group of mud sensors corresponds to a pouring section. After each pouring section is grouted, the grouting of the next pouring section is continued until the grouting of the pouring joint is completed. The pouring is carried out in a step-by-step manner to avoid erroneous instructions from the mud sensors, which affects the grouting efficiency.

[0140] Preferably, each group of mud sensors has multiple mud sensors, two of which are located on both sides of the pouring section, and the remaining mud sensors are located between the two mud sensors, and each mud sensor is set on the bottom surface of the arc-shaped member or / and the arc-shaped surface of the pipe segment, and after multiple mud sensors are in contact with concrete, the grouting of the corresponding pouring section is stopped. The direct benefit of this is to avoid over-grouting, but this measure can only observe the overall pouring liquid level and cannot detect the local density.

[0141] During the pouring of S2, it is necessary to perform density detection simultaneously, wherein the density detection includes: 1) grouting liquid level monitoring, which obtains the liquid level information of the poured concrete through the mud sensor to control the grouting amount; 2) stress monitoring, which obtains the force value F at the bottom opening of each arc-shaped member through the pressure sensor. 1 …F N , and obtain F 平 , and then calculate according to the following formula:

[0142] F=0.22γ c t 0 β 1 β 2 V 1 / 2 Formula 1

[0143] In formula 1, F is the pressure of the newly poured concrete on the plugging device, unit: kN / m 2 ; γ c is the gravity density of concrete, unit: kN / m 3 ; V is the pouring speed of concrete, unit: m / h; t 0 Initial setting time of newly poured concrete, unit: h, β 1 is the correction coefficient of admixture effect, and is 1.0~1.2; β 2 is the correction coefficient of concrete slump, and is 0.85 to 1.15; respectively calculate the pressure value at the bottom opening of each arc-shaped member, and obtain the average value F 压 , and|(F 平 -F 压 ) / F 压 |≤5%. If the ratio exceeds 5%, grouting is required.

[0144] Specifically, γ c , V, t 0 , β 1 , β 2 All of them are known, therefore, the value of F pressure can be easily obtained. Then, by comparing the measured and calculated values, the pressure of concrete at the casting joint on the curved steel plate can be determined to obtain the density.

[0145] In the above formula 1, t 0 =200 / (T+15), and T is the temperature of concrete pouring. Once the initial setting time is uncertain, it can be obtained through this formula, which is convenient for pressure detection.

[0146] When the slump is less than 30 mm, β 2 Take 0.85; when the slump is 30-90mm, β 2 Take 1.0; when the slump is 90-150mm, β 2Take 1.15 because slump directly affects the fluidity of grouting concrete.

[0147] As for admixtures, there must be admixtures in the concrete, otherwise it will easily solidify and cannot be transported. Therefore, β 2 Take 1.2.

[0148] At the same time, density detection also includes 3) radar detection, in which the poured concrete is scanned by radar and imaged to detect the density of grouting, further verifying the quality of grouting and ensuring the quality of grouting.

[0149] In addition, the pressure sensor obtains the maximum pressure value Fmax at the bottom opening of the arc-shaped member. If (Fmax-F 压 ) / F 压 >30%, it means that the pressure sensor is damaged, and the Fmax data is discarded to obtain the F 平 In this way, obviously erroneous data can be eliminated to ensure the accuracy of the data obtained.

[0150] Combination Fig. 9 and Fig.10 As shown, the concrete chute structure for grouting includes a base A1, a concrete chute A2, and a discharge baffle A3.

[0151] The base A1 includes a chassis frame A10 and a support frame A11 disposed on the chassis frame A10.

[0152] The concrete chute A2 includes a chute body A20 forming a long strip-shaped discharge channel, the chute body A20 has a discharge port 20a and a feed port 20b, and the chute body A20 is installed on the support frame A11 at an angle with the feed port 20b at the top and the discharge port 20a at the bottom, wherein the discharge port 20a extends inwardly from top to bottom.

[0153] In this example, the chute body A20 includes an inclined chute bottom plate 200 and chute side plates 201 extending upward from both sides of the chute bottom plate 200, wherein a discharge channel with an open top is formed between the chute bottom plate 200 and the chute side plates 201 on both sides, and the upper part of the discharge channel forms a feed port 20b, and the lower part forms a discharge port 20a. Such a chute body structure is very easy to process and shape, and the flow rate of concrete in the discharge channel can be visually observed, which is convenient for pouring construction.

[0154] Specifically, the two sides of the tank side plates 201 are arranged in parallel and perpendicular to the tank bottom plate 200, the two sides of the discharge baffle A3 are matched with the inner wall gap of the tank side plates 201, and the feed port 20b and the discharge port 20a are arranged symmetrically. The molding is convenient and the turning movement of the discharge baffle can be avoided to form obstacles.

[0155] The discharge baffle A3 is flipped and mounted on the discharge port 20a of the chute body A20 by a pivot s extending in the width direction of the chute body A20.

[0156] There are two pivots s, which are respectively located on both sides of the discharge baffle A3, wherein each pivot s is rotatably connected to the corresponding side trough side plate 201. When in the intercepting state, the discharge baffle A3 is laid on the lower end of the trough bottom plate 200 from the bottom, which is convenient for assembly and can effectively control the flow of poured concrete.

[0157] Specifically, the pivot s is located at the upper part of the unloading baffle A3, which is more conducive to the flipping operation of the unloading baffle A3.

[0158] In this example, the unloading baffle A3 has an open state and an intercepting state. When in the open state, the concrete pushes the unloading baffle A3 to flip upward around the pivot s, and is unloaded from the opening formed by the unloading baffle A3 and the unloading port 20a to the grooves of the prefabricated arc parts and the pipe segments, and the size of the opening is proportional to the flow rate of concrete; when in the intercepting state, the unloading baffle flips around the pivot under its own weight and closes the opening.

[0159] At the same time, a detachable counterweight module A4 is also provided on the discharge baffle A3. In this way, the opening can be closed at any time according to the on-site construction conditions to meet the needs of on-site construction. For example, when the construction needs to be moved, the mixer truck stops unloading and can be directly moved, and at this time the opening can be closed to prevent the concrete in the discharge channel from leaking out.

[0160] In addition, considering the adjustment of angle and height, in this example, the support frame A11 can be telescopically arranged up and down, and the chute body A20 is hinged from the bottom to the top of the support frame A11. In this way, the up and down adjustment of the support frame can meet the unloading of concrete at different heights.

[0161] Specifically, the support frame A11 includes two sets of telescopic support rods 110 respectively close to the feed port 20b and the discharge port 20a, wherein the two sets of telescopic support rods 110 can be raised and lowered to adjust the height and / or angle of the chute body A20. That is, when they are raised and lowered at the same time, the height can be adjusted, and the tilt angle of the chute body can be changed when the lifting height is inconsistent, thereby meeting the use needs under different working conditions and enhancing the practicality of the concrete chute structure.

[0162] Each group of telescopic support rods 110 is telescopically adjusted synchronously, wherein each group of telescopic support rods 110 is composed of at least two telescopic support rods, and are spaced apart along the width direction of the chute body A20, so that the support is more stable.

[0163] In addition, a universal pulley A5 is provided at the bottom of the chassis frame A10 to facilitate the displacement and pouring of the concrete chute structure along the length direction of the tunnel.

[0164] Therefore, in the pouring of concrete of S2, a concrete chute structure is used for unloading, which not only avoids concrete waste, but also allows continuous pouring and avoids the occurrence of cold joints that affect the stability of the bottom of the arc-shaped part.

[0165] Example 2

[0166] The opening plugging and bottom grouting adopted in this embodiment are basically the same as those in Embodiment 1, except that:

[0167] The pressure value of F can also be calculated by the following formula:

[0168] F=γ c H Formula 2

[0169] In formula 2, H is the total height from the concrete pressure calculation position to the top surface of the newly poured concrete, in meters, γ c is the gravity density of concrete, unit: kN / m 3 The data obtained by using Formula 2 can further verify the results of Formula 1, thereby ensuring that the grouting density meets actual needs.

[0170] In summary, the bottom grouting of the present invention has the following advantages:

[0171] 1. Grouting the casting joints formed between multiple arc-shaped parts and pipe segments at one time has high construction efficiency. Under liquid level monitoring and stress monitoring, it can ensure that the density of concrete after grouting meets the requirements. At the same time, it not only reduces the waste rate of concrete, but also reduces the probability of cold joints during construction. In addition, the arc-shaped parts will not be lifted during pouring, nor will it cause uneven settlement of the road surface in the later operation. Therefore, the arc-shaped parts will not be misaligned in the vertical direction, which is convenient for the construction of subsequent tunnels;

[0172] 2. By comparing the calculated and measured data, the pressure value information can be accurately obtained, and the high-quality grouting at the bottom of the arc-shaped part can be ensured through various verifications (such as radar scanning) and the improvement of grouting measures. Moreover, the construction methods adopted are gradually promoted, and the pressure value is considered as a whole, so that the monitoring results are accurate and the grouting operation is convenient;

[0173] 3. Through the covering and fitting of the arc plate body and the sealing member, and taking the arc opening as the reference, the uniform top support provided inside can enhance the sealing effect of the arc opening, provide the necessary conditions for high-quality pouring, and avoid the waste of concrete. At the same time, it can be disassembled and assembled in a small space without pre-embedding or post-processing of the arc parts. In addition, the top support is easy to disassemble and assemble, and can also be retracted, so as to meet the installation needs of different working conditions (for example: different heights of the through cavity), and the pressure sensor can obtain the pressure value more accurately;

[0174] 4. Through the cooperation of the concrete chute and the unloading baffle, during a pouring process, not only can the concrete of the mixer truck be accurately and continuously unloaded to the slot to be poured, but the unloading flow rate is controllable, which reduces the probability of insufficient density and cold joints during pouring, improves the installation quality of arc parts, and at the same time, reduces the waste of concrete and the subsequent cleaning workload. In addition, the angle, height and position of the concrete chute can be adjusted to meet the needs of on-site pouring.

[0175] The key points of quality control in this construction method are arc-shaped component assembly misalignment control, bolt connection control and arc-shaped component bottom grouting density control.

[0176] 1. Control of arc-shaped parts assembly misalignment

[0177] There are two types of misalignment control for arc-shaped parts assembly: vertical misalignment and horizontal misalignment. The arc-shaped parts are hoisted, turned over and transported to the assembly position for adjustment. When the arc-shaped parts are fully adjusted and fall to the bottom, it will make it difficult to install the arc-shaped parts connecting bolts. Generally, when it is adjusted to the basic level, the bolts are inserted first and then fine-tuned. Adjust to a vertical and horizontal misalignment of less than 10mm.

[0178] 2. Control of grouting density at the bottom of the arc part

[0179] (1) After the arc-shaped parts are installed in place, concrete is used to fill the bottom. The concrete mix ratio should meet the "Ordinary Concrete Mix Ratio Design Code" JGJ55-2011.

[0180] (2) Before assembling the curved parts, the hand holes and caulking of the bottom pipe segments must be processed first. Prevent debris from forming in the hand holes and pipe segment seams, which may affect the mortar filling effect at the bottom. The hand hole processing includes: bolt holes, assembly positioning pin holes, and secondary grouting holes. The hand holes and caulking are sealed with sulphoaluminate micro-expansive cement. After sealing, check whether there is any leakage in the pipe segments at the bottom. If there is any leakage, it should be handled in time.

[0181] (3) The slump of C40 self-compacting fine stone concrete backfilled at the bottom of the arc-shaped member should be between ±180 mm, and ensure that all the gaps in the bottom layer of the arc-shaped member are filled.

[0182] (4) Select 8 points at the bottom of the arc to measure the gap distance, calculate the gap volume, and compare it with the original standard volume. The actual grouting volume must be greater than the theoretical grouting volume.

[0183] 3. Bolt connection

[0184] When temporary steel gaskets are used to temporarily fix the bottom of the arc-shaped part, they must be placed evenly and symmetrically and must be temporarily fixed firmly to prevent the arc-shaped part from sliding when the shield trolley is unevenly stressed during movement. Bolt tensioning should be tightened symmetrically and gradually multiple times. Bolt warning force should be implemented according to design requirements. Failure of bolt connection should be handled as a quality accident.

[0185] The above detailed description of the present invention is intended to enable persons familiar with the art to understand the contents of the present invention and implement them, but it does not limit the protection scope of the present invention. Any equivalent changes or modifications made according to the spirit of the present invention should be included in the protection scope of the present invention.

Claims

1. A construction method for a large-size arc-shaped member in a shield tunnel of an urban railway, wherein the arc-shaped member has a through cavity and an arc-shaped opening, wherein the arc-shaped opening is located at the bottom of the arc-shaped member and communicates with the through cavity, characterized in that: S1, arc-shaped parts selection, which selects the order of lowering the matching arc-shaped parts according to the wedge shape of the segment; S2. Hoisting of arc-shaped parts, including vertical hoisting and transportation and underground horizontal hoisting and transportation; S3, positioning and fine adjustment of arc parts, the positioning includes determining the centerline position, the fine adjustment includes achieving X, Y, Z axis translation or deflection around the X, Y, Z axis direction, and bolts are used to connect adjacent arc parts in the longitudinal direction; at the same time, the fine adjustment includes: 1) leveling machine fine adjustment, which uses a leveling machine located inside the through cavity to move. After the arc parts are roughly in place, the leveling machine is used to adjust the horizontal and vertical directions. At the same time, when the leveling machine is walking and working, the support point is not on the arc parts, and the leveling machine has a ±5° steering; 2) horizontal misalignment control, which first uses a square tube with the same width as the arc parts, puts a level ruler on the top of the square tube, and cooperates to find the horizontal point of the lower structure assembly of the formed tunnel, and then uses the surveying team to lay out the axis point of the lower structure assembly , according to the layout points, the axis of the formed tunnel is assembled and fitted; 3) vertical misalignment control, when the two adjacent ring arc parts are vertically misaligned, the arc part assembly inclination angle is adjusted in time to fit the longitudinal slope of the formed tunnel by padding the steel plate at the bottom of the arc part; the shield excavation construction is carried out based on the tunnel design axis as the standard. There is a difference between the axis of the formed tunnel and the design axis. The shield machine moves forward in a serpentine manner. The vertical and curve radii are difficult to control to be perpendicular to the design axis and the curve is consistent. The positioning in S3 includes the following steps: (1) the surveying team lays out the axis point of the substructure assembly; (2) during the assembly process, the level ruler is used to check whether the substructure is horizontal again at the top of the substructure; (3) the wedge volume of the substructure itself is used to achieve the fitting of the substructure to the turning radius; S4, bottom grouting of the arc-shaped member, which includes: B1, opening plugging, which includes plugging of the bottom opening of the arc-shaped member and plugging of the end of the arc-shaped member, and the arc-shaped member forms a casting joint open on both sides between the two sides and the pipe segment; B2, pouring of concrete, which injects concrete from one open side. In B1, when the bottom opening is plugged, each arc-shaped opening plugging device used is provided with a pressure sensor, and a joint is formed between each arc-shaped member and the pipe segment. Multiple pieces of the joints constitute the casting joint, and a mud sensor is set in the casting joint; in the pouring of B2, it is necessary to perform density detection simultaneously, wherein the density detection includes: 1) grouting liquid level monitoring, which obtains the liquid level information of the poured concrete through the mud sensor to control the grouting amount; 2) stress monitoring, which compares the data value N1 measured by the pressure sensor with the pressure value N2 calculated at the position of the sensor, wherein |(N1-N2) / N2|≤5%, grouting is required.

2. The construction method for large-size arc-shaped parts of shield tunnels for urban railroads according to claim 1 is characterized by: Before the lifting of S2, the following steps are also included: 1) cleaning of debris. Before the arc-shaped parts are assembled, the debris at the assembly position and the bottom of the connection surface with the lower structure of the upper block need to be cleared; 2) surface treatment of the arc-shaped parts, and at the same time, a 5±2mm thick rubber sheet is glued on one side of the large curve direction of the lower structure.

3. The construction method of large-size arc-shaped parts for shield tunnels of urban railroads according to claim 2 is characterized by: During the hoisting of S2, the height of the flatbed truck transporting the arc-shaped part is adjusted so that the C-type crane can grab the arc-shaped part. After the height adjustment is completed, the hoist is lowered and translated to the bottom of the arc-shaped part. After preliminary alignment, the hoist is lifted so that it is just stuck on the arc-shaped part. When it is in place, the proximity switch will give a signal, and the operator can tighten the clamp and lift the arc-shaped part. After the arc-shaped part touches the limit switch, it can be translated. After the C-type crane grabs the arc-shaped part, the lower structure crane is moved forward to the assembly position to make the arc-shaped part upright and in place.

4. The construction method of large-size arc-shaped parts for shield tunnels of urban railroads according to claim 1 is characterized by: In B2 2), the force values ​​F1, F2, ..., F at the bottom opening of each arc-shaped member are obtained by a pressure sensor. N , and obtain F 平 , and then calculate according to the following formula: F=0.22γ c t0β1β2V 1 / 2 formula 1 In formula 1, F is the pressure of the newly poured concrete on the plugging device, unit: kN / m 2 ; γ c is the gravity density of concrete, unit: kN / m 3 ; V is the pouring speed of concrete, in units of m / h; t0 is the initial setting time of newly poured concrete, in units of h, β1 is the correction coefficient for the influence of admixtures, and is 1.0 to 1.2; β2 is the correction coefficient for the slump of concrete, and is 0.85 to 1.15; calculate the pressure value at the bottom opening of each of the arc-shaped members, and obtain the average value F 压 , and |(F 平 -F 压 ) / F 压 |≤5%. If the ratio exceeds 5%, grouting is required.

5. The construction method of large-size arc-shaped parts for shield tunnels of urban railroads according to claim 4 is characterized by: The pressure sensor obtains the maximum pressure value Fmax at the bottom opening of the arc. If (Fmax-F 压 ) / F 压 >30%, it means that the pressure sensor is damaged, and the Fmax data is discarded to obtain the F 平 .

6. The construction method for large-size arc-shaped parts of shield tunnels for urban railroads according to claim 5 is characterized by: The mud sensors are divided into multiple groups and are spaced apart along the length of the shield tunnel, wherein each group of mud sensors corresponds to a pouring section. After each pouring section is grouted, the grouting of the next pouring section is continued until the grouting of the pouring joint is completed. After all grouting is completed, F is obtained. 平 and F 压 The value of .

7. The construction method for large-size arc-shaped parts of shield tunnels for urban railroads according to claim 6 is characterized by: Each group of mud sensors has multiple ones, two of which are located on both sides of the casting section, and the remaining mud sensors are located between the two mud sensors, and each mud sensor is arranged on the bottom surface of the arc-shaped member and / or the arc-shaped surface of the pipe segment, and after multiple mud sensors are in contact with concrete, the grouting of the corresponding casting section is stopped.

8. The construction method of large-size arc-shaped parts for shield tunnels of urban railroads according to claim 1 is characterized by: The density detection also includes 3) radar detection, in which the poured concrete is scanned by radar and imaged to detect the grouting density; in formula 1, t0=200 / (T+15), and T is the temperature when the concrete is poured; when the slump is less than 30mm, β2 is 0.85-0.95; when the slump is 30-90mm, β2 is 1.0-1.1; when the slump is 90-150mm, β2 is 1.10-1.

15.

9. The construction method for large-size arc-shaped parts of shield tunnels for urban railroads according to any one of claims 1 to 3, 7 and 8, characterized in that: The pressure value F of the newly poured concrete on the plugging device can also be calculated by the following formula: F=γ c H Formula 2 In formula 2, H is the total height from the concrete pressure calculation position to the top surface of the newly poured concrete, in meters, γ c is the gravity density of concrete, unit: kN / m 3 .