A shield receiving construction method based on urban subway tunnel

By adopting detailed steps and process control in the shield receiving construction of urban subway tunnels, the problems of difficulty in determining construction conditions and leakage risks are solved, and low-cost and efficient shield receiving is achieved, protecting the environment and reducing the environment The impact on existing operating stations.

CN115467673BActive Publication Date: 2024-12-03ZHONGTIAN CONSTR GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211214571.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-09-30
Publication Date
2024-12-03
Estimated Expiration
2042-09-30

AI Technical Summary

Technical Problem

The existing shield receiving construction technology lacks visualization, which leads to difficulty in judging construction conditions, difficulty in coordination and communication between inside and outside personnel of the equipment, large workload of backfill soil cleaning, and leakage risk and a great impact on existing operating stations.

Method used

The shield receiving construction method based on urban subway tunnels is adopted, including ground connection wall breaking, mezzanine digging and support, WSS grouting reinforcement, layered chisel removal of ground connection wall steel bars and cross steel plate joints, concrete box side walls Construction, concealed tunnel backfilling and shield machine underpass ensure construction safety and environmental protection through fine steps and process control.

Benefits of technology

It improves the visualization of the received construction, reduces the risk of leakage, reduces construction costs, protects the surrounding environment, avoids the impact on existing operating stations, and minimizes the risk of damage when the cutter wheel passes through the ground wall.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115467673B_ABST
    Figure CN115467673B_ABST
Patent Text Reader

Abstract

The present invention proposes a shield receiving construction method based on an urban subway tunnel, which relates to the technical field of shield receiving construction. It includes: S1 first line ground connection wall breaking, S2 first line and second line ground connection wall 3.2m interlayer soil dark excavation and support, S3 second line ground connection wall behind WSS grouting reinforcement, S4 layered chiseling of the second line ground connection wall surface steel bars and cross steel plate joints, S5 receiving box side wall construction, S6 dark excavation tunnel and backfilling in the box, S7 shield machine under the second line and reach the receiving; the present invention is suitable for shield receiving construction with limited receiving end, high receiving leakage risk, and high ground environmental protection requirements, which can effectively prevent soil erosion outside the well, avoid leakage risk during receiving, protect the surrounding environment, and have a lower construction cost than using a steel sleeve to receive under the same risk. It can also avoid damage to the cutter when the cutterhead directly passes through the ground wall, reduce the risk of crossing, and minimize the impact on existing operating stations.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of shield receiving construction, and in particular to a shield receiving construction method based on an urban subway tunnel. Background Art

[0002] The existing technology reduces the visualization of shield receiving construction, weakens the judgment of the implementation conditions of the receiving construction, and increases the difficulty of coordination and communication between personnel inside and outside the equipment. The workload of backfill cleaning after receiving is large. Summary of the invention

[0003] The purpose of the present invention is to provide a shield receiving construction method based on an urban subway tunnel.

[0004] The embodiment of the present invention is achieved as follows:

[0005] The embodiment of the present application provides a shield receiving construction method based on an urban subway tunnel, including a first line and a second line, including the following steps:

[0006] S1, the ground connection wall of the first line is broken;

[0007] S2, underground excavation and support of 3.2m interlayer soil between the ground connection wall of the first line and the second line;

[0008] S3, WSS grouting reinforcement behind the ground connection wall of the second line;

[0009] S4, remove the surface steel bars and cross steel plate joints of the second line ground connection wall in layers;

[0010] S5, receiving box side wall construction;

[0011] S6, dark excavation of tunnel and backfilling in the box;

[0012] S7, the shield machine passes under the second line and reaches the receiving station.

[0013] In some embodiments of the present invention, in the above-mentioned step S1, during the excavation construction of the ground-connected wall at the receiving end of the first line, a pneumatic pick is used to manually excavate the concrete of the ground-connected wall surrounding the tunnel, oxygen is used to cut the steel bars of the ground-connected wall surrounding the tunnel, and a manual auxiliary crane is used to lift the concrete slag to the ground, which is then unloaded and transported to the slag dump.

[0014] In some embodiments of the present invention, in the above step S2, the outer contour of the dark tunnel excavation range is a 7300 Φ tunnel, the initial support thickness is 300 mm, the CRD method is used for excavation, four pilot tunnels are excavated, and an I-beam bulkhead and an I-beam invert are erected, and the temporary invert also serves as a working platform to facilitate the arch frame installation and shotcrete spraying operations;

[0015] Excavate the first part of the soil, spray 5cm of concrete to seal the face, erect the arch steel frame and the middle partition I-beam frame, connect them with bolts, hang steel mesh and spray concrete, remove the bottom soil, erect a temporary invert steel frame, drive the foot anchor pipe, and seal it with spray concrete;

[0016] Grouting of the anchor pipe was carried out, the second part of the soil was excavated, 5 cm of concrete was sprayed to seal the face, steel frames and I-beam frames of the middle partition were erected, and they were connected with bolts, and mesh sprayed with concrete to seal;

[0017] Excavate the third part of the soil, spray 5cm of concrete, seal the face, and erect the upper steel frame; hang a net to spray concrete, remove the bottom soil, erect a temporary invert steel frame, drive the locking anchor pipe, and spray concrete to seal;

[0018] Grouting of the anchor pipe was carried out, the fourth part of the soil was excavated, 5 cm of concrete was sprayed initially, and the tunnel face was sealed; an I-beam frame was erected and sealed with sprayed concrete;

[0019] The middle partition wall and temporary invert were demolished, and the ground-connected wall reinforcement and cross steel plate joints on the east side of the second line were removed; after the removal, C15 plain concrete was backfilled to seal the dark-excavated tunnel.

[0020] In some embodiments of the present invention, in the above-mentioned S3 step, WSS grouting is performed by drilling a hole to a predetermined depth using a double-tube drilling rig and then grouting. The slurry uses cement slurry and water glass double-liquid slurry. The two slurries are fully mixed through a slurry mixer at the end of the double tube. During grouting, electronic monitoring means are used to implement directional, quantitative, and constant pressure grouting, so that the voids or pores in the soil layer are filled with slurry and solidified, thereby changing the properties of the soil layer. Two rows of WSS grouting holes are set on both sides of the cross steel plate of the second line ground connection wall for drilling and grouting, with 50 grouting holes for a single tunnel and 100 grouting holes for a double tunnel. The reinforcement range is 3m behind the second line ground connection wall, the drilling depth is 4.2m, and grouting is performed from bottom to top in sequence.

[0021] In some embodiments of the present invention, in the above step S4, firstly, the surface concrete of the ground connection wall of the second line is chiseled off, and the surface concrete is chiseled off in sections of 0.5m from top to bottom, and the first layer of steel bars can be cut off at the same time;

[0022] After the surface concrete and the first layer of steel bars are chiseled off, the cross steel plate is chiseled off. The cross steel plate is chiseled off in layers of 0.5m from bottom to top, and the cross steel plate is cut off simultaneously. If the face condition is relatively stable, the concrete can be chiseled off in layers of 1m, and the cross steel plate is still cut off in sections of 0.5m. To ensure the stability of the second line ground connection wall, after each section of the cross steel plate is cut off, the formwork is immediately supported and poured with early-strength C15 plain concrete to proceed to the next chiseling process.

[0023] In some embodiments of the present invention, in the above step S5, the shield receiving device is received by a concrete box structure, the box structure is arranged at the bottom of the receiving end well, and the external dimensions of the concrete box structure are 8.05m long, 6m wide, and 7.82m high; the periphery is connected to the main structure by steel bars, and the depth of the steel bars embedded in the structure is not less than 20d; sand and clay are used to backfill the box, and the box is cast with C25 concrete;

[0024] The thickness of the box side wall is 400mm. The longitudinal and transverse reinforcements are HRBФ20 steel bars with a spacing of 150mm and arranged in double rows. The reinforcements are HRBФ12 steel bars, arranged @500×500mm. The main reinforcement is connected to the bottom plate structure by embedded reinforcement, and the depth of the embedded bottom plate is not less than 400mm. The horizontal reinforcement is connected to the main side wall structure by embedded reinforcement, and the depth of the embedded bottom plate is not less than 360mm. The contact surface is roughened. When welding overlap is preferred for the longitudinal main reinforcement connection, the welding length of the reinforcement is 10d for single-sided welding and 5d for double-sided welding. The overlap length of the horizontal reinforcement of the transverse side wall and the longitudinal side wall is not less than 35d.

[0025] The side walls are assembled with 15mm thick wooden formwork, 45×90mm wooden beams and Φ48×3.5mm double steel pipes. The side walls use Φ48×3.5mm double steel pipes as the main ribs, arranged horizontally with a spacing of 1200mm; 45×90mm wooden beams are used as secondary ribs, arranged vertically with a spacing of 150mm; Φ48×3.5mm steel pipes are used as the support system, the wall formwork is equipped with diagonal braces, and horizontal tie rods and scissor braces are set between the wall formworks; the external wall formwork uses φ14 water-stop tie screws, and the horizontal and vertical arrangements are both 600mm.

[0026] In some embodiments of the present invention, the above step S6 further includes:

[0027] S61, backfilling between the first line ground wall and the second line ground wall in layers with C15 plain concrete;

[0028] S62: After the initial setting of the concrete, backfill sand in the box to 1m above the tunnel vault. Backfill clay above 1m and compact it. The thickness of the clay backfill must ensure that the water and soil pressure in the pit is greater than the water and soil pressure outside the pit.

[0029] In some embodiments of the present invention, the above step S7 further includes:

[0030] S71, before the TBM arrives, calculate the distance from the top of the shield cutterhead to the end continuous wall through actual measurement; when the TBM arrives at this distance, it enters the excavation state, monitors the ground settlement twice a day, and takes measures such as grouting based on the monitoring data; when the TBM reaches the 50th ring, it stops advancing, arranges surveyors to conduct continuous measurement, and rechecks the tunnel axis, and manually measures the TBM posture. After the measurement and re-measurement are correct, recheck the tunnel axis and shield posture, and carry out shield excavation construction based on the measurement results;

[0031] S72, the shield machine passes under the second line station. The shield machine passes under the second line station in operation at a distance of 47.25m to 3.2m from the receiving tunnel gate. The length is 44.05m, and the shield machine enters the excavation section.

[0032] S73, shield cutting and grinding the underground continuous wall on the east side of the second line. When the shield cutting and grinding the second layer of the underground continuous wall, the soil pressure should be established to the theoretical calculated soil pressure to prevent the shield from over-excavation and causing the settlement of the second line structure; at the same time, during the excavation process, the excavation parameters should be adjusted dynamically in real time according to the construction monitoring;

[0033] S74, the parameters for tunneling are set as the advancement speed <5mm / min, the total thrust <10000kN; the cutter head speed <1.2rpm; in order to prevent the shield machine from falling when exiting the tunnel, the shield machine head is required to be 20mm~30mm higher than the axis; the excavation parameters in the box are set as the advancement speed <5mm / min, the total thrust <5000kN; depending on the actual thrust size, the cutter head speed is controlled at 0.5~1.0rpm in principle, not exceeding this value;

[0034] S75, grouting and sealing. To ensure smooth reception of the shield machine, the shield tail of the shield machine is left 35cm inside the side wall of the main body of the first line, and double-liquid grouting and sealing rings are started. The grouting volume of each ring is controlled according to the grouting pressure, which is about 0.35Mpa. The grouting volume is not less than 180% to 250% of the gap between the pipe segment and the tunnel door;

[0035] S76, the box body is removed and the shield machine is disassembled. The grouting and sealing of the tunnel gate is completed. After the grouting effect is checked and meets the requirements, the shield continues to advance. After the shield machine arrives at the box, it breaks down the side walls of the box body and the construction platform, cleans and backfills sand and soil, empties the debris in the soil bin, and carries out shield hoisting and dismantling construction.

[0036] Compared with the prior art, the embodiments of the present invention have at least the following advantages or beneficial effects:

[0037] Effect 1: The present invention is suitable for shield receiving construction with limited receiving end, high receiving leakage risk and high ground environmental protection requirements. It establishes a water and soil pressure difference inside and outside the well, effectively prevents soil and water loss outside the well, avoids leakage risk during receiving, and protects the surrounding environment.

[0038] Effect 2: Compared with using steel sleeves to receive construction costs under the same risk, the cost is lower;

[0039] Effect three: The use of dark excavation construction can avoid damage to the cutter when the cutterhead directly passes through the ground wall, reduce the risk of crossing, and minimize the impact on existing operating stations. BRIEF DESCRIPTION OF THE DRAWINGS

[0040] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.

[0041] Figure 1 This is a schematic diagram of the initial support of a dark-excavated tunnel according to an embodiment of the present invention;

[0042] Figure 2 This is a schematic diagram of the first step of pilot tunnel excavation support according to an embodiment of the present invention;

[0043] Figure 3 This is a schematic diagram of the second step of pilot tunnel excavation and support according to an embodiment of the present invention;

[0044] Figure 4 This is a schematic diagram of the third step of pilot tunnel excavation and support according to an embodiment of the present invention;

[0045] Figure 5 This is a schematic diagram of the fourth step of pilot tunnel excavation and support according to an embodiment of the present invention;

[0046] Figure 6 This is a schematic diagram of dismantling the middle partition wall and temporary invert and backfilling according to an embodiment of the present invention;

[0047] Figure 7 It is a schematic diagram of the connection between the primary support steel frame and the temporary middle partition wall invert according to an embodiment of the present invention;

[0048] Figure 8 This is a schematic diagram of I-beam connection according to an embodiment of the present invention;

[0049] Fig. 9 This is a schematic diagram of the WSS grouting hole arrangement according to an embodiment of the present invention;

[0050] Fig.10 This is a schematic diagram of the longitudinal section of the WSS grouting hole position according to an embodiment of the present invention;

[0051] Fig.11 This is a schematic diagram of the surface steel bars of the ground-connected wall on the east side of the second line in an embodiment of the present invention before and after being removed;

[0052] Fig.12This is a schematic diagram of layered breaking of a cross steel plate according to an embodiment of the present invention;

[0053] Fig.13 Receive a concrete box layout diagram for an embodiment of the present invention;

[0054] Fig.14 This is a first layout diagram of a support for receiving a concrete box side wall formwork according to an embodiment of the present invention;

[0055] Fig.15 The second layout diagram of the support for receiving the side wall formwork of the concrete box according to the embodiment of the present invention;

[0056] Fig.16 This is a schematic diagram of the first step of the box body according to an embodiment of the present invention. DETAILED DESCRIPTION

[0057] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0058] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0059] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0060] In the description of the embodiments of the present invention, it should be noted that if the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. appear, the orientation or position relationship indicated is based on the orientation or position relationship shown in the drawings, or the orientation or position relationship in which the product of the invention is usually placed when in use. It is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as a limitation on the present invention. In addition, if the terms "first", "second", "third", etc. appear, they are only used to distinguish the description and cannot be understood as indicating or implying relative importance.

[0061] In addition, the terms "horizontal", "vertical", "overhanging" and the like do not mean that the components must be absolutely horizontal or overhanging, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.

[0062] In the description of the embodiments of the present invention, if the term "plurality" appears, it means at least 2.

[0063] In the description of the embodiments of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal connection of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0064] Example

[0065] S1, removal of the ground connection wall of the first line:

[0066] During the excavation of the ground-connected wall at the receiving end of the first line, pneumatic picks were used to manually excavate the concrete of the tunnel enclosure ground-connected wall, oxygen was used to cut the steel bars of the enclosure ground-connected wall, and a manual auxiliary crane was used to lift the concrete slag to the ground, which was then unloaded and transported to the slag dump.

[0067] S2, excavation and support:

[0068] Dark excavation construction:

[0069] The underground excavation method is used to construct the 3.2m interval between the station main enclosure ground ties and the second line transfer node enclosure ground ties. During this period, the underground ties of the first line receiving tunnel gate need to be broken. The outer contour of the underground excavation tunnel excavation range is a Ф7300 tunnel with an initial support thickness of 300mm. The CRD method is used for excavation, and 4 pilot holes are excavated. The I-beam middle partition and I-beam invert are erected in time. The temporary invert also serves as an operating platform to facilitate the installation of the arch frame and shotcrete operations. In order to ensure the clearance size of the tunnel, under-excavation is strictly prohibited.

[0070] After the excavation is completed, the C25 concrete is sprayed to 5cm, and then the steel frame is erected, the locking anchor rods are set, the 150×150mmФ8 steel mesh is hung, and the C25 concrete is sprayed to the designed thickness. After the excavation is completed, the initial support construction should be organized as soon as possible so that the initial support structure can be closed into a ring as soon as possible to ensure construction safety.

[0071] It should be noted that:

[0072] (1) Before excavation, drill holes on the excavation surface to understand the ground conditions ahead and whether there is sand inclusion or water gushing. The excavation depth for each cycle is 0.5m. After each excavation is completed, the initial support operation is immediately carried out. During excavation construction, the excavation depth must not exceed the cycle depth to ensure construction safety.

[0073] (2) Considering the need for initial support and tunnel convergence, the excavation section should be widened by 50 mm outside the design contour line to ensure the clearance size for subsequent shield advancement.

[0074] (3) Considering the safety of initial support, the supporting steel arch frames at both ends of the dark-excavated tunnel are embedded in the ground-connected walls of the first and second lines to a depth of 0.15m, the dark-excavated tunnel is 3.2m, the initial support length is 3.5m, and each support is 0.5m per arch, for a total of 7 arches. For details, see Figure 1 shown.

[0075] (4) After each cycle of shotcrete spraying, before entering the next earthwork excavation, advance exploration holes are first drilled to verify the reinforcement effect and whether there is water or sand gushing from the stratum to ensure the safety of subsequent excavation.

[0076] (5) To ensure the safety of excavation construction, on-site construction workers, safety officers and construction teams implement a 24-hour shift work system, and promptly handle any problems found to ensure on-site safety.

[0077] (6) Measures to prevent water and sand flow and drainage on the excavation surface:

[0078] ① When water and sand flow occurs in the excavation face, double-fast cement is used for sealing, and light well points are used for drainage.

[0079] ② Set up a 0.3m×0.3m drainage ditch at the bottom of the tunnel and a light well point at the entrance. The well depth is 0.5m below the excavation surface and the precipitation depth is 0.5m below the excavation surface to ensure waterless construction on the excavation surface.

[0080] The specific excavation steps and methods are described as follows:

[0081] 1. Pilot tunnel excavation support, such as Figure 2 As shown:

[0082] (1) Excavate the first part of the soil and spray 5 cm of concrete to seal the tunnel face;

[0083] (2) Erect the arch steel frame and the middle bulkhead I-beam frame and connect them with bolts;

[0084] (3) Shotcrete with steel mesh;

[0085] (4) Clear the bottom soil, erect a temporary invert steel frame, install locking anchor pipes, and seal with sprayed concrete.

[0086] 2. Pilot tunnel excavation support, such as Figure 3 As shown:

[0087] (1) Grouting of locking anchor pipe;

[0088] (2) Excavate the second part of the soil and initially spray 5 cm of concrete to seal the tunnel face;

[0089] (3) Erect the steel frame and the I-beam frame of the middle partition and connect them with bolts;

[0090] (4) Sealing with mesh sprayed concrete.

[0091] 3. Pilot tunnel excavation support, such as Figure 4 As shown:

[0092] (1) Excavate the third part of the soil, spray 5 cm of concrete, and seal the tunnel face;

[0093] (2) Erecting the upper steel frame;

[0094] (3) Grid shotcrete;

[0095] (4) Clear the bottom soil, erect a temporary invert steel frame, install locking anchor pipes, and seal with sprayed concrete.

[0096] 4. Pilot tunnel excavation support, such as Figure 5 As shown:

[0097] (1) Grouting of locking anchor pipe;

[0098] (2) Excavate the fourth part of the soil, spray 5 cm of concrete, and seal the tunnel face;

[0099] (3) Erecting the I-beam frame;

[0100] (4) Mesh shotcrete.

[0101] 5. Remove the middle partition and temporary invert, backfill and seal. Figure 6 As shown:

[0102] (1) After the excavation is completed, the ground-connected wall reinforcement and cross steel plate joints on the east side of the second line are removed;

[0103] (2) After the construction is completed, the middle partition and temporary invert will be removed;

[0104] (3) Backfill C15 plain concrete to seal the tunnel.

[0105] Support construction:

[0106] Fabrication of steel frame, middle partition and inverted arch I-beam:

[0107] (1) The steel frame, middle partition and invert are made of 22ɑ I-beams and transported to the site for installation.

[0108] (2) The I-beams are accurately processed and have smooth arcs. The welding meets the requirements of the specifications. The steel frame is welded symmetrically on both sides, and the center of the steel frame coincides with the axis.

[0109] (3) After processing, the I-beam frame should be assembled for trial to check for distortion. The joints of each frame should be interchangeable. The error along the tunnel perimeter contour should be ±3 cm, and the plane warping should be less than 2 cm.

[0110] Steel frame installation:

[0111] (1) Before installing the arch steel frame, the loose slag and other debris under the arch foot should be removed, and the over-excavated part should be padded with concrete blocks.

[0112] (2) The steel frame is assembled on the excavation working surface. 260×260×16mm steel plates are welded between each section of the steel frame and holes are drilled. Bolt connections are used during installation. Figure 7-8 shown.

[0113] (3) Concrete blocks are used to wedge the steel frame and soil layer, and then shotcrete is sprayed to compact the steel frame and soil layer.

[0114] (4) The steel frames are welded together with C22 (threaded steel bars) longitudinal connecting steel bars, and the circumferential spacing of the connecting steel bars is 1.0m.

[0115] (5) The steel frame must be accurately positioned, paying attention to the elevation and center line to prevent positional deviations in various directions such as "leaning forward and backward, high on the left and low on the right, left front and right back".

[0116] (6)Quality standards:

[0117] Allowable error of steel frame assembly

[0118] A. Peripheral assembly tolerance: ±30mm.

[0119] B plane warping: less than 20mm.

[0120] The allowable error of steel frame installation is shown in Table 1.

[0121] position Midline Elevation Tilt Left and right arch foot elevation Left and right steel frame mileage synchronization Allowable error 2cm +2cm, -0 ≤2° ±2cm ±5cm

[0122] Table 1

[0123] Shotcrete:

[0124] The initial support shotcrete of the tunnel adopts dry shotcrete technology. The shotcrete is mixed centrally at the mortar mixing station in the construction site of the first line, transported to the construction site, and shotcreted using a dry concrete shotcrete machine. After the tunnel excavation is completed, 5cm thick concrete is first shot to seal the rock surface, then anchor rods are installed, steel frames are erected, and steel meshes are hung. The initial shotcrete rock surface is cleaned and then shot again to the designed thickness.

[0125] Construction control points:

[0126] (1) The raw materials of shotcrete can only be used after they have passed the inspection. The accelerator should be properly stored to prevent moisture and deterioration. The water-cement ratio of the mixture should be strictly controlled, and the working condition of the accelerator injection should be checked frequently. The rebound rate and actual mix ratio of the concrete should be checked in time during the spraying process. The rebound rate of shotcrete: the side wall should not be greater than 15%, and the arch should not be greater than 25%.

[0127] (2) The construction must be carried out promptly after tunnel excavation. It is strictly forbidden to use potentially alkali-active aggregates for shotcrete. The thickness of shotcrete should be pre-embedded with thickness control marks to strictly control the thickness of shotcrete.

[0128] (3) The spraying surface should be carefully checked before spraying, and any loose soil should be dealt with in time. The sprayer should be placed in a safe area and as close to the spraying site as possible to facilitate communication between the operator and the sprayer and adjust the working air pressure at any time.

[0129] (4) After the spraying is completed, the bonding between the sprayed concrete and the rock surface should be checked. This can be done by tapping with a hammer. At the same time, the flatness and cross section should be measured, and this cross section should be compared with the excavated cross section to confirm whether the thickness of the sprayed concrete meets the design and specification requirements. If there are hollows or shelling, they should be chiseled out in time, rinsed clean and re-sprayed, or filled with grouting.

[0130] (5) When spraying the lower part of the side wall, the rebound material during the spraying of the upper section needs to be cleaned up to prevent the rebound material from being drawn into the lower spray layer to form a "honeycomb" and reduce the support strength.

[0131] (6) Check the ejector elbow, feed pipe and pipe joints regularly and deal with any problems promptly. When the pipe is blocked, the main machine must be shut down before any treatment can be carried out.

[0132] (7) After the spraying is completed, the main machine should be turned off first, and then the metering pump, vibrating rod and air valve should be turned off in turn, and then the residue in the machine and the conveying pipeline should be cleaned with clean water.

[0133] (8) During winter construction of shotcrete, anti-freeze and heat preservation measures should be taken at the work site of the shotcrete injection machine; the air temperature in the work area and the temperature of the mixture entering the sprayer should not be lower than 5°C.

[0134] S3, WSS grouting reinforcement behind the ground connection wall of the second line:

[0135] WSS grouting is the process of grouting after drilling to a predetermined depth using a double-tube drilling rig. The slurry is a double-liquid slurry of cement slurry and water glass. The two slurries are fully mixed through the slurry mixer at the end of the double tube. Electronic monitoring means are used for directional grouting. Quantitative and constant pressure grouting fills the voids or pores in the soil layer with slurry and solidifies, changing the properties of the soil layer. This project mainly sets up two rows of WSS grouting holes on both sides of the cross steel plate of the second line ground connection wall for drilling and grouting. There are 50 grouting holes for a single portal and 100 grouting holes for double portals. The reinforcement range is 3m behind the second line ground connection wall. The drilling depth is about 4.2m, and grouting is done from bottom to top. Figure 9-10 shown.

[0136] Measures to ensure grouting quality:

[0137] (1) Drilling:

[0138] ① Arrange holes; Arrange holes strictly according to the construction design drawings and conduct verification.

[0139] ② Drilling rig positioning: accurate positioning, aligning with the hole position, drilling at the designed angle, the drill bit position error ≤ 20mm. The allowable deviation of the drill rod angle is no more than 1°.

[0140] ③ Drilling: Closely observe the drilling scale and overflow and water discharge. When water gushing occurs, stop drilling immediately, inject grout to stop water first, and then analyze the cause. Drilling can only be continued after confirming the water-stopping effect.

[0141] (2) The metering tools for ingredients must be inspected and qualified and ingredients must be mixed according to the designed formula.

[0142] (3) Grouting should be carried out according to the designed grouting procedure. The amount of grouting must be accurate, the grouting pressure and direction must be strictly controlled, and it must be operated by a dedicated person. When the pressure suddenly rises or the grout overflows from the hole wall or the ground, the grouting should be stopped immediately. Measures should be taken to solve the problem and ensure the grouting amount.

[0143] (4) After grouting is completed, the grouting holes should be sealed to ensure that there is no grout overflow or leakage. After reaching the age, horizontal core drilling should be carried out to verify the reinforcement effect, and appropriate grouting should be added according to the reinforcement effect to ensure construction quality.

[0144] (5) A dedicated person is responsible for the operation records of each process.

[0145] (6) Construction inspection and monitoring should be strengthened throughout the grouting process to prevent ground overflow and ground subsidence in the construction area.

[0146] (7) Anti-collapse measures:

[0147] ① When drilling, drill strictly in accordance with technical specifications and related requirements. If collapse is likely to occur, use the follow-pipe method to ensure the quality of the drilling.

[0148] ② When drilling, the drilling water must not be directly sprayed onto the hole wall.

[0149] (8) When drilling, if the drill is stuck or the hole collapses, grouting should be performed before drilling. When drilling, the drilling record should be filled in carefully. The hole should be cleaned after drilling.

[0150] (9) Control measures for hole opening angle control and grouting inclined hole construction:

[0151] ① Before drilling, accurately measure the drilling position and drilling angle according to the requirements of the drawing. To ensure the accuracy of the drilling direction, use an inclinometer to measure the deviation of the borehole during the drilling process, and constantly check and correct it during the drilling process.

[0152] ② Measure the inclination of the hole frequently when drilling. If the error exceeds the limit, it should be corrected in time. If the hole still exceeds the limit, it should be sealed and re-drilled in situ.

[0153] S4, remove the surface steel bars and cross steel plate joints of the second line ground connection wall in layers:

[0154] After excavation and support to the ground-connected wall on the east side of the second line and WSS grouting reinforcement, the ground-connected wall on the east side of the second line began to be broken. The ground-connected wall of the second line was broken with reference to the ground-connected wall of the first line, mainly to break the surface steel bars and cross steel plate joints, retain the second layer of ground-connected wall steel bars, and later directly excavate and break them by the shield machine to remove the steel bars.

[0155] Construction technology for breaking the ground-connected wall of the second line:

[0156] First, remove the surface concrete of the second line ground connection wall. The surface concrete is removed in sections of 0.5m from top to bottom, and the first layer of steel bars can be cut off at the same time.

[0157] After the surface concrete and the first layer of steel bars are removed, the cross steel plate is removed. The cross steel plate is removed in layers of 0.5m from bottom to top, and the cross steel plate is cut off simultaneously. If the face is relatively stable, the concrete can be removed in layers of 1m, and the cross steel plate is still cut off in sections of 0.5m. To ensure the stability of the ground connection wall of the second line, the formwork is immediately cast with early-strength C15 plain concrete after each section of the cross steel plate is cut off, and the next removal process is entered. Figure 11-12 shown.

[0158] Safety control measures for chiseling out cross steel plates:

[0159] When the cross steel plate joint of the ground-connected wall is removed, at least two anti-surge devices are now configured to deal with sudden gushing situations. The anti-surge device is made of 6mm steel plate and angle steel, with a length of 1m, a width of 0.6m, and a height of 0.05m. Two ball valve pipes are welded in the middle of the anti-surge device, and holes are opened on the four sides of the device. When water and sand gushing occurs, expansion bolts are inserted through the four holes to fix it to the ground-connected wall to achieve the anti-surge effect.

[0160] S5, receiving box side wall construction:

[0161] The shield receiving device adopts a concrete box structure, which is set at the bottom of the receiving end well. The external dimensions of the concrete box structure are 8.05m long, 6m wide and 7.82m high. The surrounding area is connected to the main structure with steel bars, and the depth of the steel bars embedded in the structure is not less than 20d. Sand and clay are used to backfill the box, and the box is cast with C25 concrete. Fig.13 shown.

[0162] Side wall structure construction:

[0163] (1) Steel bar connection:

[0164] The thickness of the box side wall is 400mm. Both longitudinal and transverse reinforcements are HRBФ20 steel bars, with a spacing of 150mm and arranged in double rows. The reinforcement is HRBФ12 steel bars, arranged @500×500mm. The main reinforcement is connected to the bottom plate structure by embedded reinforcement, and the depth of the embedded bottom plate is not less than 400mm. The horizontal reinforcement is connected to the main side wall structure by embedded reinforcement, and the depth of the embedded bottom plate is not less than 360mm. The contact surface is roughened. When welding overlap is preferred for the longitudinal main reinforcement connection, the welding length of the reinforcement is 10d for single-sided welding and 5d for double-sided welding. The overlap length of the horizontal reinforcement of the transverse side wall and the longitudinal side wall shall not be less than 35d. Figure 14-15 shown.

[0165] (2) Formwork Engineering:

[0166] The side wall is assembled with 15mm thick wooden formwork, 45×90mm wooden beams and Φ48×3.5mm double steel pipes. The side wall uses Φ48×3.5mm double steel pipes as the main ribs, arranged horizontally with a spacing of 1200mm. 45×90mm wooden beams are used as secondary ribs, arranged vertically with a spacing of 150mm. Φ48×3.5mm steel pipes are used as the support system, the wall formwork is equipped with diagonal braces, and transverse tension rods and scissor braces are set between the wall formworks. The external wall formwork uses φ14 water-stop tension screws, and the horizontal and vertical spacings are both 600mm. The steel bars used for the tension bolts must be inspected and qualified before they can be used. The spacing must not be increased at will to avoid the expansion of the mold.

[0167] S6, dark tunnel excavation and backfilling in the box:

[0168] S61, backfilling between the first line ground wall and the second line ground wall in layers with C15 plain concrete;

[0169] S62: After the initial setting of the concrete, backfill sand in the box to 1m above the tunnel vault. Backfill clay above 1m and compact it. The thickness of the clay backfill must ensure that the water and soil pressure in the pit is greater than the water and soil pressure outside the pit.

[0170] like Fig.16 shown.

[0171] S7, the shield machine passes under the second line and reaches the receiving station:

[0172] S71, before the TBM arrives:

[0173] Before the TBM arrives, the distance from the top of the shield cutterhead to the end continuous wall is calculated through actual measurement. When the TBM reaches this distance, it enters the excavation state, monitors the ground settlement twice a day, and takes measures such as grouting based on the monitoring data. When the TBM reaches the 50th ring, it stops advancing, arranges surveyors to conduct contact measurements, and rechecks the tunnel axis, and manually measures the TBM posture. After the measurement and re-measurement are correct, the tunnel axis and shield posture are rechecked. Shield excavation construction is carried out according to the measurement results.

[0174] S72, shield tunnel passes under the second line station:

[0175] The shield machine passed under the subway line 2 station within the range of 47.25m to 3.2m from the receiving tunnel gate, with a length of 44.05m, and entered the shield machine to reach the excavation section. The excavation parameters of the shield machine passing under the subway line 2 station are summarized in Table 2. The excavation parameter setting is continuously optimized according to the tunnel burial depth and monitoring data.

[0176] Serial number Excavation parameters Parameter Value 1 Total thrust 800t~1000t 2 Cutter speed 0.9r~1.2r 3 Torque 1500kN·m~2500kN·m 4 Advance speed 5mm / min~20mm / min 5 Soil tank pressure 1.5bar~2.3bar 6 Synchronous grouting pressure 2.0bar~2.5bar 7 Screw machine speed 3r / min~7r / min 8 Synchronous grouting volume <![CDATA[5.5m 3 ~6m 3 ]]> 9 Slag discharge per ring <![CDATA[Approximately 40m 3 >

[0177] Table 2

[0178] S73, when the shield machine passes under the second operating line and reaches the receiving tunneling process, it is necessary to pay close attention to the changes in the shield machine's tunneling parameters, especially the grouting volume, slag discharge volume, thrust, torque and other parameters. When abnormal parameters are found, the reasons should be analyzed first and judgments should be made. Blind tunneling should not be carried out. When the shield machine cutterhead is about 1 meter away from the tunnel entrance ground wall, the soil compartment pressure should be reduced and the tunneling speed should be reduced. It is advisable to control it within 5mm / min to 20mm / min to ensure timely and full grouting. When the shield machine hits the wall, it is necessary to closely monitor the changes in tunneling parameters. If there is any abnormality, stop the machine immediately.

[0179] When the shield machine is excavating within 10 meters before exiting the tunnel, the grouting volume per ring is required to be 5.5m 3 ~6m 3 The grouting pressure is controlled at 2.0bar~2.5bar, and each ring is required to undergo secondary grouting. The secondary grouting slurry is double-liquid slurry. The secondary grouting volume is mainly controlled by pressure, and the pressure control value is set at 0.2bar~0.3bar.

[0180] S74, shield cutting and grinding of underground continuous wall on the east side of the second line:

[0181] When the shield machine cuts the second layer of ground-connected wall, the soil pressure should be established to the theoretical calculated soil pressure to prevent the shield machine from over-excavating and causing the second line structure to sink. At the same time, during the excavation process, the excavation parameters should be adjusted dynamically in real time according to construction monitoring.

[0182] Hole-in settings:

[0183] Parameter settings: propulsion speed <5mm / min, total thrust <1000t; cutter head speed <1.2r;

[0184] Posture control when exiting the tunnel: In order to prevent the shield machine from falling headfirst when exiting the tunnel, the head of the shield machine is required to be 20mm to 30mm higher than the axis.

[0185] Excavation parameter settings in the box:

[0186] Parameter settings: Advance speed <5mm / min, thrust <500t; depending on the actual thrust size, the principle is not to exceed this value. The cutter disc speed is controlled at 0.5r~1.0r. Before the cutter disc rotates, it is necessary to contact the outside of the box to confirm the safety of personnel and equipment before the excavation mode can be carried out.

[0187] Attitude control when entering the box: The attitude of the shield machine must be controlled based on the actual measured center line of the tunnel door installation, and the center line deviation must be controlled within ±20mm. After the shield machine enters the box, pay attention to the attitude control and adjust it in time to ensure that the shield does not fall headfirst.

[0188] S75, grouting plugging:

[0189] To ensure the smooth reception of the shield, the shield tail of the shield machine is left 35cm inside the side wall of the main body of the first line, and the double liquid grouting sealing ring is started. The grouting volume of each ring is controlled according to the grouting pressure, which is about 0.35Mpa, and the grouting volume is not less than 180% to 250% of the gap between the pipe segment and the tunnel. During the grouting process, check whether there is leakage at the shield tail at all times. If there is leakage, reduce the grouting pressure immediately.

[0190] S76, box removal and shield machine dismantling:

[0191] After the grouting and sealing of the tunnel portal is completed and the grouting effect inspection meets the requirements, the shield continues to advance. After the shield machine reaches the side wall of the box, it breaks down the side wall of the box and the construction platform, cleans the backfill sand and soil, empties the debris in the soil bin, and carries out shield hoisting and dismantling construction.

[0192] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

[0193] It will be apparent to those skilled in the art that the present application is not limited to the details of the exemplary embodiments described above, and that the present application can be implemented in other specific forms without departing from the spirit or essential features of the present application. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the present application is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present application. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.

Claims

1. A shield receiving construction method based on an urban subway tunnel, characterized in that: Comprising a first circuit and a second circuit, comprising the following steps: S1, the ground connection wall of the first line is broken; S2, underground excavation and support of 3.2m interlayer soil between the ground connection wall of the first line and the second line; S3, WSS grouting reinforcement behind the ground connection wall of the second line; S4, remove the surface steel bars and cross steel plate joints of the second line ground connection wall in layers; S5, receiving box side wall construction; S6, dark excavation of tunnel and backfilling in the box; S7, the shield machine passes under the second line and reaches the receiving area; In the step S1, during the construction of the ground-connected wall removal at the receiving end of the first line, a pneumatic pick is used to manually remove the concrete of the ground-connected wall surrounding the tunnel, oxygen is used to cut the steel bars of the surrounding ground-connected wall, and a manual auxiliary crane is used to lift the concrete slag to the ground, and the concrete slag is unloaded and transported to the slag dump; In the step S2, the outer contour of the dark tunnel excavation range is a 7300 mm tunnel, the initial support thickness is 300 mm, the CRD method is used for excavation, four pilot holes are excavated, and an I-beam bulkhead and an I-beam invert are erected. The temporary invert also serves as a working platform to facilitate arch frame installation and shotcrete spraying operations; Excavate the first part of the soil, spray 5cm of concrete to seal the face, erect the arch steel frame and the middle partition I-beam frame, connect them with bolts, hang steel mesh and spray concrete, remove the bottom soil, erect a temporary invert steel frame, drive the foot anchor pipe, and seal it with spray concrete; Grouting of the anchor pipe was carried out, the second part of the soil was excavated, 5 cm of concrete was sprayed to seal the face, steel frames and I-beam frames of the middle partition were erected, and they were connected with bolts, and mesh sprayed with concrete to seal; Excavate the third part of the soil, spray 5cm of concrete, seal the face, erect the upper steel frame, hang the net and spray concrete, remove the bottom soil, erect a temporary invert steel frame, install the locking anchor pipe, and seal with spray concrete; Grouting of the anchor pipe, excavation of the fourth part of the soil, initial spraying of 5cm of concrete, sealing of the face, erection of the I-beam frame, and spraying of concrete for sealing; The middle partition wall and temporary invert were demolished, and the steel bars and cross steel plate joints of the ground-connected wall on the east side of the second line were removed. After the removal, C15 plain concrete was backfilled to seal the dark-excavated tunnel.

2. The shield receiving construction method based on the urban subway tunnel according to claim 1 is characterized in that: In the S3 step, WSS grouting is performed by drilling a hole to a predetermined depth using a double-tube drilling rig, and then grouting is performed. The slurry uses cement slurry and water glass double-liquid slurry. The two slurries are fully mixed through a slurry mixer at the end of the double tube. During the grouting, electronic monitoring means are used to implement directional, quantitative, and constant pressure grouting, so that the voids or pores in the soil layer are filled with slurry and solidified, thereby changing the properties of the soil layer. Two rows of WSS grouting holes are set on both sides of the cross steel plate of the second line ground connection wall for drilling and grouting, with 50 grouting holes for a single tunnel and 100 grouting holes for a double tunnel. The reinforcement range is 3m behind the second line ground connection wall, the drilling depth is 4.2m, and grouting is performed from bottom to top in sequence.

3. The shield receiving construction method based on urban subway tunnel according to claim 1 is characterized in that: In the step S4, the surface concrete of the second line ground connection wall is firstly removed by chiseling, and the surface concrete is removed in sections of 0.5m from top to bottom, and the first layer of steel bars can be cut off at the same time; After the surface concrete and the first layer of steel bars are chiseled off, the cross steel plate is chiseled off. The cross steel plate is chiseled off in layers of 0.5m from bottom to top, and the cross steel plate is cut off simultaneously. If the face condition is relatively stable, the concrete can be chiseled off in layers of 1m, and the cross steel plate is still cut off in sections of 0.5m. To ensure the stability of the second line ground connection wall, after each section of the cross steel plate is cut off, the formwork is immediately supported and poured with early-strength C15 plain concrete to proceed to the next chiseling process.

4. The shield receiving construction method based on urban subway tunnel according to claim 1 is characterized in that: In the step S5, the shield is received by a concrete box structure, which is arranged at the bottom of the receiving end well. The external dimensions of the concrete box structure are 8.05m long, 6m wide and 7.82m high. The surrounding area is connected to the main structure by steel bars, and the depth of the steel bars embedded in the structure is not less than 20d. The box body is backfilled with sand and clay, and the box body is poured with C25 concrete; The thickness of the box side wall is 400mm. The longitudinal and transverse reinforcements are HRBФ20 steel bars with a spacing of 150mm and arranged in double rows. The reinforcements are HRBФ12 steel bars, arranged @500×500mm. The main reinforcement is connected to the bottom plate structure by embedded reinforcement, and the depth of the embedded bottom plate is not less than 400mm. The horizontal reinforcement is connected to the main side wall structure by embedded reinforcement, and the depth of the embedded bottom plate is not less than 360mm. The contact surface is roughened. When welding overlap is preferred for the longitudinal main reinforcement connection, the welding length of the reinforcement is 10d for single-sided welding and 5d for double-sided welding. The overlap length of the horizontal reinforcement of the transverse side wall and the longitudinal side wall is not less than 35d. The side walls are assembled with 15mm thick wooden formwork, 45×90mm wooden beams and Φ48×3.5mm double steel pipes; the side walls use Φ48×3.5mm double steel pipes as main ribs, arranged horizontally with a spacing of 1200mm; 45×90mm wooden beams are used as secondary ribs, arranged vertically with a spacing of 150mm; Φ48×3.5mm steel pipes are used as the support system, the wall formwork is equipped with diagonal braces, and transverse tension rods and scissors braces are installed between the wall formworks; the exterior wall formwork uses φ14 water-stop tension screws, and the horizontal and vertical arrangements are both 600mm.

5. The shield receiving construction method based on urban subway tunnel according to claim 1 is characterized in that: The step S6 further includes: S61, backfilling between the first line ground wall and the second line ground wall in layers with C15 plain concrete; S62: After the initial setting of the concrete, backfill sand in the box to 1m above the tunnel vault. Backfill clay above 1m and compact it. The thickness of the clay backfill must ensure that the water and soil pressure in the pit is greater than the water and soil pressure outside the pit.

6. The shield receiving construction method based on urban subway tunnel according to claim 1 is characterized in that: The step S7 further includes: S71, before the TBM arrives, calculate the distance from the top of the shield cutterhead to the end continuous wall through actual measurement; when the TBM arrives at this distance, it enters the excavation state, monitors the ground settlement twice a day, and takes measures such as grouting based on the monitoring data; when the TBM reaches the 50th ring, it stops advancing, arranges surveyors to conduct continuous measurement, and rechecks the tunnel axis, and manually measures the TBM posture. After the measurement and re-measurement are correct, recheck the tunnel axis and shield posture, and carry out shield excavation construction based on the measurement results; S72, the shield machine passes under the second line station. The shield machine passes under the second line station in operation at a distance of 47.25m to 3.2m from the receiving tunnel gate. The length is 44.05m, and the shield machine enters the excavation section. S73, shield cutting and grinding the underground continuous wall on the east side of the second line. When the shield cutting and grinding the second layer of the underground continuous wall, the soil pressure should be established to the theoretical calculated soil pressure to prevent the shield from over-excavation and causing the settlement of the second line structure. At the same time, during the excavation process, the excavation parameters should be adjusted dynamically in real time according to the construction monitoring; S74, the parameters for tunneling are set as the advancement speed <5mm / min, the total thrust <10000kN; the cutter head speed <1.2rpm; in order to prevent the shield machine from falling when exiting the tunnel, the shield machine head is required to be 20mm~30mm higher than the axis; the excavation parameters in the box are set as the advancement speed <5mm / min, the total thrust <5000kN; depending on the actual thrust size, the cutter head speed is controlled at 0.5~1.0rpm in principle, not exceeding this value; S75, grouting and sealing. To ensure smooth reception of the shield machine, the shield tail of the shield machine is left 35cm inside the side wall of the main body of the first line, and double-liquid grouting and sealing rings are started. The grouting volume of each ring is controlled according to the grouting pressure, which is about 0.35Mpa. The grouting volume is not less than 180% to 250% of the gap between the pipe segment and the tunnel door; S76, the box body is removed and the shield machine is disassembled. The grouting and sealing of the tunnel gate is completed. After the grouting effect is checked and meets the requirements, the shield continues to advance. After the shield machine arrives at the box, it breaks down the side walls of the box body and the construction platform, cleans and backfills sand and soil, empties the debris in the soil bin, and carries out shield hoisting and dismantling construction.