A method for installing a ring feeder
Through a systematic step-by-step installation method, the problem of high requirements for installation complexity and accuracy of the annular feeder is solved, efficient and accurate equipment installation is achieved, and installation efficiency and quality are improved.
Patent Information
- Application Number
- CN202211598939.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-12-14
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2042-12-14
AI Technical Summary
The installation of the annular feeder is complex and has many parts, which makes it difficult to measure the equipment lifting sequence and reference standard, high installation accuracy requirements, and lacks an effective installation method.
Provide a method for installing an annular feeder, by installing inner and outer ring equipment in steps, including embedded plates, leveling studs, rail pressure plates, sealing devices, etc., to optimize the construction sequence and installation accuracy, and ensure the various components. High precision fit.
It shortens the installation time of the equipment, improves the installation efficiency and quality, and ensures the smooth operation and efficient operation of the equipment.
Smart Images

Figure CN115724147B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of installation engineering and equipment maintenance, and particularly relates to an installation method of a ring feeder. Background Art
[0002] The ring feeder is used as the discharge form at the bottom of the silo. It has the advantages of large equipment output, no material blockage, no material overflow, and high silo utilization rate, and is widely used.
[0003] The silo ring feeder adopts the ring gap type lower feeding, and the double ring gap type discharge port is composed of an inverted cone connected to the inner wall of the silo and a central mushroom cone, and its cross section is a double "W" shape. The ring gap is long, with a large discharge port area, good overall fluidity of the stored material, continuous and uniform discharge, and balanced lateral pressure of the material on the silo wall. The equipment is mainly composed of inner ring plowing car track, inner ring unloading car track, outer ring plowing car track, outer ring unloading car track, inner ring plowing car, inner ring unloading car, outer ring plowing car, outer ring unloading car, inner and outer ring equipment walking tracks, drive device, sealing device, unloading device, electrical system, etc.
[0004] The ring feeder has a complex structure and many equipment parts. When installed in a silo, the equipment lifting sequence and lifting channels are complicated, the installation benchmark measurement is difficult, there are many matching deviation requirements between components, and the installation accuracy requirements for tracks, car bodies, drives, etc. are high. At present, there is no public installation method for ring feeders at home and abroad. Summary of the invention
[0005] In view of this, the present invention provides an installation method of a ring feeder.
[0006] The specific plan is as follows:
[0007] A method for installing a ring feeder, wherein the ring feeder is installed at the bottom of a silo, and the ring feeder comprises an inner ring plowing vehicle track, an inner ring unloading vehicle track, an inner ring plowing vehicle, an inner ring unloading vehicle, an inner ring plowing vehicle driving device, an inner ring unloading vehicle driving device, an inner ring plowing vehicle sealing device, an inner ring unloading vehicle sealing device, an inner ring unloading device, an outer ring plowing vehicle track, an outer ring unloading vehicle track, an outer ring plowing vehicle, an outer ring unloading vehicle, an outer ring plowing vehicle driving device, an outer ring unloading vehicle driving device, an outer ring plowing vehicle sealing device, an outer ring unloading vehicle sealing device, an outer ring unloading device and an electrical system, wherein the installation method comprises the following steps:
[0008] Step 1: Install the inner ring unloading car track and the inner ring plowing car track;
[0009] Step 2: Install the inner ring plow truck and drive device;
[0010] Step 3: Install the inner ring unloading vehicle and the driving device;
[0011] Step 4: Install the inner ring unloading device;
[0012] Step 5: Install the inner ring plow car sealing device;
[0013] Step 6: Inner ring unloading car sealing device;
[0014] Step 7: Install the outer ring equipment;
[0015] Step 8: Install electrical system equipment and debug.
[0016] The inner ring unloading vehicle track and the inner ring plowing vehicle track include a primary embedded plate, a secondary civil engineering embedded plate, a leveling stud, a leveling nut, a track pressure plate, an elastic pad and a track;
[0017] The method for installing the inner ring unloading car track and the inner ring plowing car track in step 1 is:
[0018] A1): Take the pre-buried point in the center of the silo as the center of the circle, measure the radius of the inner ring unloading vehicle track through the pre-buried pipe in the inner tube of the silo, make a mark on the primary pre-buried plate of the track, and make 12 to 24 calibration points on the circumference;
[0019] A2): Connect the calibration points to make a track diameter circle on the primary embedded plate, and weld leveling studs on the plate with the circumference line of each primary embedded plate as the center line with a spacing of 260mm;
[0020] A3): Install the leveling nut and the secondary embedded plate on the leveling stud, level the secondary embedded plate, and ensure that the height difference error between the secondary embedded plate and the highest point of the driving base is +10mm;
[0021] A4): Install the track pads and lay the segmented tracks on the secondary embedded plates to ensure that the track diameter deviation is -5 to -3mm; the horizontal deviation is ≤1mm;
[0022] A5): When installing the inner ring plowing car track, take the inner ring unloading car track as the reference, use the hanging wire method to determine the diameter of the plowing car track, weld the leveling studs, install the leveling nuts and the secondary embedded plate, and lay the plowing car track after leveling the secondary embedded plate to ensure that the track diameter deviation is -5 to -3mm; the horizontal deviation is ≤1mm;
[0023] A6): Use elastic pads to adjust each section of track. The weld gap at the track joint is 1-2mm, and the height difference and lateral misalignment of the track surface are ≤1mm;
[0024] A7): Weld each section of track, preheat to 250℃ before welding, use J506 welding rod, heat to 400℃ after welding, keep warm and cool slowly, and finally grind the flat weld on the track to make it smooth;
[0025] A8): Carry out secondary grouting for the secondary embedded plates and adjusting bolts.
[0026] The inner ring plow vehicle and driving device include a vehicle body, wheels, plow claws, a pin-tooth plate connecting plate, a driving device, a positioning device and a driving base;
[0027] The method for installing the inner ring plow vehicle and the drive device in step 2 is:
[0028] B1): After assembling the wheels and the vehicle body outside the silo, the sections of the inner ring plowing vehicle are hoisted into the unloading layer from the silo wall opening in sequence according to the production number. After entering the inner ring space, the equipment is hoisted onto the plowing vehicle track through the plowing gap using the silo pre-buried lifting ring;
[0029] B2): The four corners of the body flange are first positioned and connected with tapped hole bolts, and then the remaining flange holes are connected with high-strength bolts. The body flange is used to connect the various sections of the plow truck;
[0030] B3): After each section of the car body is connected, measure the flange gap and use grinding or adding adjustment pads to make the flange gap ≤1mm;
[0031] B4): Install the plow claws, adjust the height and levelness of the plow claws, the height should be more than 50mm from the civil engineering, and the levelness should be ≤0.5mm / m;
[0032] B5): Install the pin-tooth plate connecting plate, the concentricity of the upper and lower connecting plates should be ≤ Ф0.3mm, install the transmission pin at the connection, and then fix the pin shaft clamping plate;
[0033] B6): Manually push the plow truck to rotate it 3 to 5 times to make the truck body concentric with the track;
[0034] B7): The drive of the inner ring plowing vehicle is hoisted into the plowing layer from the hoisting hole on the outside of the middle tube of the unloading layer silo, and enters the outer driving foundation of the plowing vehicle through the middle tube channel;
[0035] B8): Adjust the eccentric mechanism of the positioning wheels on both sides of the driving device to be away from the vehicle body, and adjust the distance between the positioning wheel and the pin gear plate to 3-5mm;
[0036] B9): Use an inclined iron to adjust the height of the drive seat to ensure that the height error between the symmetry plane in the length direction of the pin wheel pin and the symmetry plane in the gear tooth width of the drive device is less than 1mm. Use J422 welding rod to weld the base and the foundation embedded parts firmly. The weld height is ≥15mm, the weld length is ≥50mm, and the number of welds is ≥12.
[0037] The inner ring unloading vehicle and driving device include a vehicle body, wheels, a receiving plate, a pin-tooth plate connecting plate, a driving device, a positioning device and a driving base;
[0038] The method for installing the inner ring unloading vehicle and the driving device in step 3 is:
[0039] C1): Assemble the unloading vehicle body and wheels outside the silo, and hoist each section of the inner ring unloading vehicle from the silo wall opening into the inner ring unloading layer in sequence according to the production number, and use the pre-buried lifting ring of the silo to hoist the equipment onto the unloading vehicle track;
[0040] C2): After the body flange connection is completed, the wear-resistant plate of the receiving plate at the welding connection is welded, using double-sided V-shaped welding and ground flat after welding;
[0041] C3): Install the pin-tooth plate connecting plate and the pin shaft at the connection, and manually push the unloading car so that the gap between the wheel rim and the track is maintained at 10-15mm regardless of the track position;
[0042] C4): Put the drive device in place, adjust the eccentric mechanism of the positioning wheels on both sides to be away from the vehicle body, and adjust the distance between the positioning wheel and the pin gear plate to 3-5mm;
[0043] C5): Install the sliding bin protection plate. The sliding bin protection plate is welded in the blanking gap of the inner ring plow truck. First, weld the rib plate on the embedded plate in the blanking gap, and then weld the sliding bin protection plate on the rib plate. The height of the protection plate should be flush with or slightly lower than the bottom of the plow platform to ensure that the static rest angle of the plow claw plow space is ≤35°.
[0044] The inner ring unloading vehicle unloading device includes a unloader, an electric push rod, a spring sweeper, a herringbone chute, a unloading hopper and a unloading pipe;
[0045] The method for installing the inner ring unloading car dropping device in step 4 is:
[0046] D1): Place the columns on both sides of the unloader on the embedded parts of civil engineering, connect the unloader shaft with the columns, and place a 10mm steel plate between the unloader and the wear-resistant plate of the vehicle body to ensure that the gap between the unloader and the wear-resistant plate is 10mm;
[0047] D2): Adjust the electric push rod to the extended state, connect the electric push rod base with the discharger column, connect the electric push rod head with the discharger rotating arm, and fix the rotating arm with the discharger shaft after the connection is completed;
[0048] D3): The spring cleaner is welded at the rear of the discharger. During welding, the spring is adjusted to be in a tensioned state. The cleaner is pressed against the wear-resistant plate of the discharger, and the outer side of the cleaner extends out of the outer edge of the wear-resistant plate of the vehicle body.
[0049] D4): The herringbone chute is welded and suspended above the discharger by angle steel and embedded civil engineering parts. The height position must ensure that the discharger does not interfere with the herringbone chute when it is lifted, and it cannot interfere with the seal under the plow truck. The horizontal position must ensure that the material will not hit the discharge board when it is dropped;
[0050] D5): The drop hopper is installed above the drop port, and the drop height and distance from the vehicle body are adjusted. The height difference between the drop hopper and the wear-resistant plate of the vehicle body is 25mm, and the inner side of the drop hopper extends into the wear-resistant plate by 30mm. After determining the position, weld it to the embedded parts of the drop port, and add sealing gaskets to the connecting seams.
[0051] The inner ring plow car sealing device includes a plow car labyrinth seal fixed part, a plow car labyrinth seal rotating part, a plow car lower seal and a plow car observation hole;
[0052] The method for installing the inner ring plow car seal in step 5 is as follows:
[0053] E1): The fixed part of the labyrinth seal is welded to the embedded parts of the civil engineering, and the horizontal direction is 100mm higher than the upper plane of the plow body. The welding level is ≤2mm / m, and the diameter deviation is ≤10mm. After welding, the gap between the labyrinth seal and the civil engineering is filled with sealant or grouting material;
[0054] E2): The rotating part of the plowing vehicle labyrinth seal is welded to the upper plane of the vehicle body, with a welding level of ≤2mm / m and a diameter deviation of ≤5mm;
[0055] E3): The lower seal of the plowing vehicle is welded to the lower plane of the vehicle body to ensure that the bottom of the lower seal extends into the plowing gap by more than 100mm and the gap with the civil engineering is more than 50mm;
[0056] E4): The rotating part of the plow truck labyrinth seal is provided with an observation hole, corresponding to the plow claw, a hole is opened at the plow claw and an observation window is installed.
[0057] The inner ring unloading car sealing device comprises an unloading car sealing inner ring, an unloading car sealing outer ring, a spring clear deflector and an outer ring soft seal;
[0058] The method for installing the inner ring unloading car sealing device in step six is:
[0059] F1): When installing the inner seal ring of the unloading car, first weld the fixed angle steel to the embedded parts of the civil engineering. Take the vertical plate of the unloading car body as a reference, arrange it along the circumference with the required size of the drawing as the radius, and the deviation in the diameter direction is ≤5mm. Then weld the inner seal ring on the angle steel to ensure that the bottom of the inner seal ring is 50mm away from the wear-resistant surface of the car body. The top of the inner seal ring is welded to the embedded plate of the civil engineering, and fill the gap with the civil engineering with sealant to prevent powder leakage;
[0060] F2): The installation method of the outer ring of the unloading car is the same as that of the inner ring, ensuring that the distance between the bottom of the outer ring and the wear-resistant surface of the car body is 10mm;
[0061] F3): The spring deflector is installed on the inner side of the sealing outer ring. One is welded about 2m in front of each blanking port, and the rest are evenly distributed along the sealing cover. When welding, ensure that the spring of the spring deflector is pressed tightly, and ensure that the bottom of the deflector is pressed tightly against the wear-resistant surface of the vehicle body;
[0062] F4): Install a soft seal at the bottom of the outer ring of the seal to ensure that the sealing strip contacts the receiving plate smoothly. The inner sealing strip must not have bulges, protrusions or other poor contact phenomena. Use vulcanization and other connection measures at the joints of the sealing strip. If there is overlap, it must be ensured to be overlapped along the direction of the material flow to avoid leakage.
[0063] The outer ring equipment includes an outer ring plowing vehicle track, an outer ring plowing vehicle, an outer ring plowing vehicle driving device, an outer ring plowing vehicle sealing device, an outer ring unloading vehicle track, an outer ring unloading vehicle, an outer ring unloading vehicle driving device, an outer ring unloading device and an outer ring unloading vehicle sealing device;
[0064] The method for installing the outer ring device in step 7 is:
[0065] G1): When installing the outer ring unloading car track, the inner ring track is used as the reference for setting out, or the pre-buried point in the center of the silo is used as the center of the circle. The measuring ruler measures the track diameter through the pre-buried wire threading pipes in the inner and middle tubes of the silo. The track diameter deviation is a negative difference of -10 to -5mm; the track leveling method is the same as step A6) in the inner ring track installation method;
[0066] G2): When installing the outer ring plowing car track, the outer ring unloading car track diameter is used as the reference, and the outer ring plowing car track diameter is determined by the hanging wire method, with a diameter deviation of -10 to -5m;
[0067] G3): The outer ring plowing car and the unloading car are hoisted into the silo through the plowing layer wall and the unloading layer wall respectively, and are connected on the track in sequence according to the production number after the secondary pre-embedded track solidifies;
[0068] G4): After the outer ring plow truck and unloading truck drive device are installed in place, apply No. 3 lithium ester to the dovetail groove of the drive seat to ensure flexible sliding of the floating seat, adjust the nut at the tail of the drive seat to ensure that the spring compression deformation is 8mm, and the spring preload force is 4×500Kg;
[0069] G5): After the plow truck and the unloading truck are assembled and installed, the gap between the positioning wheel and the pin wheel rim is ≤5mm, and when the positioning wheel is in action, the wheel rim is not allowed to contact the top side of the track. At least 70-80% of the inner and outer rings should be in contact with the track, and the gap between the non-contact wheel tread and the track is ≤0.5mm;
[0070] G6): When installing the unloading device of the outer ring plow truck, measure the distance between the tripod and the inner side plate of the outer ring plow truck. If the distance is 20mm, weld the tripod on the embedded civil engineering parts. After welding, you can weld the fixed sealing cover. If the distance is greater than 20mm, adjust the tripod welding height to ensure that the distance between the fixed sealing cover and the rotating part is 20mm.
[0071] The electrical system includes a PLC cabinet, a frequency conversion cabinet, a local operation box and cables;
[0072] The method for installing the electrical system and debugging the equipment in step eight is:
[0073] H1): PLC cabinet and frequency converter cabinet are usually installed in the electrical control room next to the silo, and should not be placed 100m away from the silo to facilitate equipment debugging and ensure that the control is not interfered by other signals;
[0074] H2): The power supply adopts three-phase four-wire AC ∽380V / 50HZ power supply, and the control power supply is 220V / 50hz AC and 24V DC power supply. The system power circuits are all connected by busbar power supply, and each sub-circuit adopts air switch for short circuit and overcurrent protection, and each motor is protected by motor comprehensive protector for fault overload;
[0075] H3): Use programmable controller as the field logic control center to collect equipment switches and operation signals and control relay output;
[0076] H4): Both the power drive system of the unloading vehicle and the power drive system of the plowing vehicle adopt a drive control method that combines relay output with contactor and inverter;
[0077] H5): Install the field control boxes on the plowing layer and the discharge layer of the inner and outer rings of the ring feeder for on-site debugging;
[0078] H6): Turn the "local / remote" knob on the PLC control cabinet to the "local" position; turn the "debug / auto" knob to the "debug" position; close the circuit breaker of the corresponding circuit, then the interlocking between the electrical equipment is released, the "automatic start" button and "automatic stop" button set on the PLC control box lose their function, and the "allow debugging" signal light on the local control box is turned on. The debugging of the electrical equipment on the plowing layer and the unloading layer is carried out on the on-site control boxes at their respective levels, and the corresponding operations are performed on the local control boxes.
[0079] The invention discloses an installation method for a ring feeder. When installing the ring feeder equipment, the construction sequence is optimized, the installation time of the equipment is shortened, the purpose of saving construction period is achieved, the installation efficiency and quality of the equipment are improved, and the stable operation of the equipment is ensured. BRIEF DESCRIPTION OF THE DRAWINGS
[0080] Figure 1 Shown is a schematic diagram of the ring feeder structure.
[0081] Figure 2 The figure shows the schematic diagram of the track installation structure.
[0082] Figure 3 Shown is a schematic diagram of the installation structure of the plow truck.
[0083] Figure 4Shown is a schematic diagram of the installation structure of the unloading vehicle.
[0084] Figure 5 The figure shows the installation diagram of the slide box protection plate.
[0085] Figure 6 Shown is a schematic diagram of the installation structure of the unloading device.
[0086] Figure 7 Shown is a schematic diagram of the installation of the inner ring plow truck sealing device.
[0087] Figure 8 The figure shows the installation diagram of the sealing device of the unloading vehicle.
[0088] Fig. 9 The figure shows the installation diagram of the outer ring drive device.
[0089] Fig.10 Shown is a schematic diagram of the outer ring plow truck sealing device. DETAILED DESCRIPTION
[0090] The following will be combined with the accompanying drawings in the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the implementation of the present invention, not all of the implementations. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0091] like Figure 1 As shown, a method for installing a ring feeder is shown, wherein the ring feeder is installed at the bottom of a circular silo 1. The silo ring feeder adopts a double annular seam type discharge port, which is composed of an inverted cone connected to the inner wall of the silo and a central mushroom cone. Its cross section is a double "W " shape, the equipment includes two parts, the inner and outer rings, and the inner and outer rings are composed of two layers of equipment respectively. The inner ring includes: inner ring plow car track 4, inner ring unloading car track 14, inner ring plow car 5, inner ring unloading car 17, inner ring plow car driving device 7, inner ring unloading car driving device 13, inner ring plow car sealing device 6, inner ring unloading car sealing device 16, inner ring unloading device 18; the outer ring includes: outer ring plow car track 2, outer ring unloading car track 11, outer ring plow car 3, outer ring unloading car 19, outer ring plow car driving device 9, outer ring unloading car driving device 10, outer ring plow car sealing device 8, outer ring unloading car sealing device 12, outer ring unloading device 20, electrical system. Regardless of the outer ring or the inner ring, the working principle is the same. The plowing car rotates counterclockwise under the drive of the driving device, driving the plowing claws that penetrate into the annular gap of the storage silo to continuously discharge the materials in the silo to the unloading car below. The unloading car rotates clockwise at the same time. According to the operation of the belt, the corresponding unloader falls, and the materials on the unloading car will continuously fall through the unloading hopper onto the running ground belt. The installation method of the ring feeder includes the following steps:
[0092] Step 1: Install the inner ring unloading car track and the inner ring plowing car track. Figure 2 The inner ring unloading vehicle track and the inner ring plow vehicle track include secondary civil engineering embedded plates 24 , leveling studs 26 , leveling nuts 25 , track pressure plates 22 , elastic pads 23 , and tracks 14 .
[0093] With the embedded point in the center of the silo as the center of the circle, the measuring tool measures the radius of the inner ring unloading vehicle track through the embedded pipe in the inner tube of the silo, makes a mark on the primary embedded plate of the track, and makes 12 to 24 calibration points on the circumference.
[0094] Connect the calibration points to make a track diameter circle on the primary embedded plate 21, and weld leveling studs 26 on the plate with the circumference line of each primary embedded plate as the center line with a spacing of 260mm;
[0095] Install the leveling nut 25 and the secondary embedded plate 24 on the leveling stud 26, level the secondary embedded plate 24, and ensure that the height difference error between the secondary embedded plate elevation and the highest point of the driving base is +5 to +10mm;
[0096] Install the track elastic pad 23, lay the segmented track on the secondary embedded plate, and ensure that the track diameter deviation is -5 to -3 mm; the horizontal deviation is ≤1 mm;
[0097] Use the hanging wire method, take the unloading car track 14 as the reference, determine the diameter of the plowing car track 4, weld the leveling studs 26, install the leveling nuts 25 and the secondary embedded plate 24, and lay the plowing car track after leveling the secondary embedded plate to ensure that the track diameter deviation is -5 to -3mm; the horizontal deviation is ≤1mm;
[0098] Adjust each section of track, the weld gap at the joint is 1-2mm, and the height difference and lateral misalignment of the track surface are ≤1mm;
[0099] Weld each section of track, preheat to 250℃ before welding, use J506 welding rod, heat to 400℃ after welding, keep warm and cool slowly, and finally grind the flat weld on the track to make it smooth;
[0100] Secondary grouting of track installation foundation 27;
[0101] When installing the inner ring plow car track 4, the inner ring unloading car track 14 is used as a reference, and the track diameter is determined by the hanging wire method. The track diameter error is -5 to -3 mm, and the rest of the installation method is consistent with the inner ring unloading car track installation method.
[0102] Step 2: Install the inner ring plow vehicle and the driving device. The inner ring plow vehicle and the driving device include a vehicle body 5, wheels 31, plow claws 28, pin tooth plate connecting plate 35, a driving device 32, a positioning device 34, and a driving base 33.
[0103] After the wheels 31 and the vehicle body 5 are assembled outside the silo, Figure 3 , hoist each section of the inner ring plowing vehicle into the unloading layer from the silo wall opening in sequence according to the production number, and after entering the inner ring space, hoist the equipment onto the plowing vehicle track through the plowing material gap using the pre-buried lifting ring in the silo;
[0104] The four corners of the body flange 37 are first positioned and connected with tapped hole bolts, and then the remaining flange holes are connected with high-strength bolts; each two sections of the body are connected with flanges. During installation, they are butt-jointed according to the markings on both ends of the body when assembled in the factory. The four corners of the flange are first positioned and connected with GB27-88 tapped hole bolts, and then connected with high-strength bolts. When connecting, the stress that is not allowed in the connection should be minimized as much as possible, and forced assembly connection is strictly prohibited. The initial tightening torque of the M16 high-strength bolt is 126 Newton meters, and the final tightening torque is 252 Newton meters; the initial tightening torque of the M20 high-strength bolt is 240 Newton meters, and the final tightening torque is 480 Newton meters;
[0105] Install the pin tooth plate connecting plate 35, the concentricity of the upper and lower connecting plates is ≤ Ф0.3mm, and install the transmission pin 36 at the connection;
[0106] Install the plow claw, adjust the angle of the plow claw by the pull rod 29, ensure that the claw body is 60mm away from the civil engineering, and adjust the height and levelness of the plow claw by the plow claw shaft 30, the height is more than 50mm away from the civil engineering, and the levelness is ≤0.5mm / m;
[0107] Manually push the plow truck to rotate it 3 to 5 times to make the truck body concentric with the track;
[0108] The inner ring plowing vehicle is driven from the lifting hole on the outside of the middle cylinder of the unloading layer silo to the plowing layer, and enters the outer driving foundation of the plowing vehicle through the middle cylinder channel;
[0109] Adjust the eccentric mechanism of the positioning wheels on both sides of the driving device to be away from the vehicle body side, and the clearance between the positioning wheel and the pin tooth plate is ≤2mm. When the positioning wheel is in action, the wheel rim is not allowed to contact the top side of the track;
[0110] Use an inclined iron to adjust the height of the drive seat to ensure that the height error between the symmetric plane of the pin wheel pin length direction and the symmetric plane of the drive device gear tooth width is less than 1mm. Use J422 welding rod to weld the base and the foundation embedded parts firmly, with the weld height ≥15mm, weld length ≥50mm, and weld number ≥12;
[0111] Step 3 Install the inner ring unloading car and drive device. Figure 4 The inner ring unloading vehicle and the driving device include a vehicle body 38 , wheels 39 , a material receiving plate wear-resistant plate 40 , a pin-tooth plate connecting plate 44 , a driving device 41 , a positioning device 43 , and a driving base 42 .
[0112] Assemble the unloading vehicle body 38 and wheels 39 outside the silo, and hoist each section of the inner ring unloading vehicle from the silo wall opening into the inner ring unloading layer in sequence according to the production number, and use the pre-buried lifting ring of the silo to hoist the equipment onto the unloading vehicle track;
[0113] The four corners of the body flange 46 are first positioned and connected with tapped hole bolts, and then the remaining flange holes are connected with high-strength bolts;
[0114] After each section of the car body is connected, measure the flange gap and use grinding or adding adjustment pads to make the flange gap ≤1mm;
[0115] The wear-resistant plate 40 of the receiving plate at the welding connection adopts double-sided V-shaped welding and is ground flat after welding;
[0116] Install the pin-tooth plate connecting plate 44 and the pin shaft 45 at the connection, and manually push the unloading vehicle so that the clearance between the wheel rim and the track is maintained at 10 to 15 mm regardless of the track position;
[0117] Put the driving device 41 in place, adjust the eccentric mechanism of the positioning wheels on both sides to be away from the vehicle body side, adjust the distance between the positioning wheel and the pin gear plate to 3-5 mm, and after the adjustment is completed, weld the driving base and the foundation embedded parts firmly;
[0118] Install the slide guard. Figure 5 The sliding bin protection plate 47 is welded in the blanking gap P of the inner ring plowing vehicle. First, the rib plate 47 is welded on the pre-embedded plate of the blanking gap, and the sliding bin protection plate is welded on the rib plate. The height of the protection plate is flush with or slightly lower than the bottom of the plowing platform to ensure that the static rest angle θ of the plowing claw plowing space is ≤35°;
[0119] Step 4 Install the inner ring unloading car unloading device, such as Figure 6 The inner ring unloading vehicle unloading device includes a discharger 52, an electric push rod 49, a spring cleaner 51, a herringbone chute 50, and a unloading hopper 53;
[0120] Place the columns on both sides of the discharger 52 on the embedded parts of the civil engineering, connect the discharger shaft with the columns, and place a 10mm steel plate between the discharger and the wear-resistant plate of the vehicle body to ensure that the gap between the discharger 52 and the wear-resistant plate 40 is 10mm;
[0121] The electric push rod 49 is adjusted to the extended state, the base of the electric push rod is connected to the discharger column, the head of the electric push rod is connected to the discharger rotating arm, and after the connection is completed, the rotating arm is fixed to the discharger shaft;
[0122] The spring cleaner 51 is welded behind the discharger 52. During welding, the spring is adjusted to be in a tensioned state, the cleaner is pressed against the wear plate 40 of the discharger, and the outer side of the cleaner extends out of the outer edge of the wear plate of the vehicle body;
[0123] The herringbone chute 50 is welded and suspended above the discharger by angle steel and embedded civil engineering parts. The height position must ensure that the discharger does not interfere with the herringbone chute when it is lifted, and it cannot interfere with the seal under the plow truck. The horizontal position must ensure that the material does not hit the discharge board when it falls.
[0124] The drop hopper 53 is installed above the drop port, and the drop height and the distance from the vehicle body are adjusted. The height difference between the drop hopper and the vehicle body wear plate is 25mm, and the inner side of the drop hopper extends into the wear plate by 30mm. After determining the position, it is welded to the embedded parts of the drop port, and a sealing gasket is added to the connecting seam.
[0125] Step 5 Install the inner ring plow car seal. Figure 7 The inner ring plow truck sealing device includes a plow truck lower seal 54, a plow truck labyrinth seal fixed part 55, a plow truck labyrinth seal rotating part 56, and a plow truck observation window 57.
[0126] The labyrinth seal fixing part 55 is welded to the embedded part of the civil engineering, and the horizontal direction is 100mm higher than the upper plane of the plow body, the welding level is ≤2mm / m, and the diameter deviation is ≤10mm. After welding, the gap between the labyrinth seal and the civil engineering is filled with sealant or grouting material;
[0127] The rotating part 56 of the plowing vehicle labyrinth seal is welded to the upper plane of the vehicle body, with a welding level of ≤2mm / m and a diameter deviation of ≤5mm;
[0128] The lower seal of the plowing vehicle is welded to the lower plane of the vehicle body 54, ensuring that the bottom of the lower seal extends into the plowing gap by more than 100 mm and the gap S with the civil engineering is more than 50 mm;
[0129] The rotating part of the labyrinth seal of the plowing vehicle is provided with an observation hole, corresponding to the plowing claw, and a hole is opened at the plowing claw and an observation window 57 is installed;
[0130] Step 6 Install the inner ring unloading car seal. Figure 8 The inner ring unloading car sealing device includes an unloading car sealing inner ring 58, an unloading car sealing outer ring 60, a spring clear deflector 59, and an outer ring soft seal 61.
[0131] When installing the inner seal ring 58 of the unloading car, first weld the fixed angle steel to the embedded parts of the civil engineering, take the vertical plate of the unloading car body as a reference, arrange it along the circumference with the required size of the drawing as the radius, and the deviation in the diameter direction is ≤5mm, and then weld the inner seal ring on the angle steel to ensure that the bottom of the inner seal ring 58 is 50mm away from the wear-resistant surface of the car body, and the top of the inner seal ring 58 is welded to the embedded plate of the civil engineering, and fill the gap with the civil engineering with sealant to prevent powder leakage;
[0132] The installation method of the unloading car seal outer ring 60 is the same as the inner ring installation method, ensuring that the distance between the bottom of the seal outer ring and the wear-resistant surface of the car body is 10mm;
[0133] The spring deflector 59 is installed on the inner side of the sealing outer ring. One is welded about 2m in front of each blanking port, and the rest are evenly distributed along the sealing cover. During welding, the spring of the spring deflector is pressed tightly, and the bottom of the deflector is pressed tightly against the wear-resistant surface of the vehicle body.
[0134] Install soft seal 61 at the bottom of the outer ring of the seal to ensure that the sealing strip contacts the receiving plate smoothly. The inner sealing strip must not have bulges, protrusions or other poor contact phenomena. Vulcanization and other connection measures are used for the joints of the sealing strip. If there is overlap, it must be ensured to be overlapped along the direction of material flow to avoid leakage.
[0135] Step 7: Install the outer ring equipment. Figure 1 The outer ring equipment includes an outer ring plow vehicle track 2, an outer ring plow vehicle 3, an outer ring plow vehicle driving device 9, an outer ring plow vehicle sealing device 8, an outer ring unloading vehicle track 11, an outer ring unloading vehicle 19, an outer ring unloading vehicle drive 10, an outer ring unloading device 20, and an outer ring unloading vehicle sealing device 12.
[0136] When installing the outer ring unloading car track 11, the inner ring track 14 is used as the reference for setting out, or the pre-buried point in the center of the silo is used as the center of the circle. The measuring ruler measures the track diameter through the pre-buried wire threading pipes in the inner and middle tubes of the silo. The track diameter deviation is a negative difference of -10 to -5mm. The remaining track adjustment methods are the same as the inner ring track installation method.
[0137] When installing the outer ring plowing car track 2, the diameter of the outer ring unloading car track 11 is used as a reference, and the diameter of the outer ring plowing car track is determined by the hanging wire method, with a diameter deviation of -10 to -5m;
[0138] The outer ring plowing vehicle 3 and the unloading vehicle 19 are respectively hoisted into the silo through the plowing layer silo wall and the unloading layer silo wall, and are connected in sequence on the track according to the production number after the secondary pre-embedded track solidifies;
[0139] After the outer ring plow truck and unloading truck drive device are installed in place, Fig. 9 Apply No. 3 lithium ester to the dovetail groove 62 of the driving seat to ensure the flexible sliding of the floating seat, and adjust the nut at the tail of the driving seat to ensure that the spring 63 is compressed and deformed by 8mm, and the spring preload is 4×500Kg;
[0140] After the plow truck and the unloading truck are assembled and installed, Fig. 9 The gap between the positioning wheel 65 and the pin wheel rim 64 is ≤5mm, and when the positioning wheel is in action, the wheel rim is not allowed to contact the top side of the track. The inner and outer rings should at least ensure that 70-80% of the wheels are in contact with the track, and the gap between the non-contact wheel tread and the track is ≤0.5mm.
[0141] When the outer ring plow truck unloading device 8 is installed, Fig.10Measure the distance between the tripod 70 and the inner side plate of the outer ring plowing vehicle. If the distance is about 20 mm, directly weld the tripod on the embedded civil engineering parts. After welding, the fixed sealing cover 69 can be welded. If the distance is greater than 20 mm, the tripod welding height can be appropriately adjusted to ensure that the distance between the fixed sealing cover and the rotating part 67 is about 20 mm.
[0142] Step 8: Install the electrical system and debug the equipment. The electrical system includes PLC cabinet, frequency conversion cabinet, local operation box, cables, etc.
[0143] PLC cabinets and frequency converter cabinets are usually installed in the electrical control room next to the silo. They should not be placed 100m away from the silo to facilitate equipment debugging and ensure that the control is not interfered by other signals.
[0144] The power supply adopts three-phase four-wire AC∽380V / 50HZ power supply, and the control power supply is 220V / 50hz AC and 24V DC power supply. The system power circuits are all connected to the busbar power supply, and each sub-circuit adopts air switches for short circuit and overcurrent protection. Each motor is protected by a motor comprehensive protector for fault overload protection;
[0145] This system uses a programmable controller as the on-site logic control center to collect equipment switches and operating signals and control relay outputs, thereby realizing automatic program operation, increasing control functions, improving equipment reliability, and reducing system failure rates;
[0146] The power drive system of the unloading and plowing vehicle adopts the drive control mode of relay output + contactor + inverter (or soft start). The whole drive system is reliably controlled, the unloading vehicle and plowing vehicle start and run smoothly, and the plowing vehicle running speed system output is continuously adjustable;
[0147] Install field control boxes on the plowing layer and discharge layer of the inner and outer rings of the ring feeder for on-site debugging;
[0148] Turn the "local / remote" knob on the PLC control cabinet to the "local" position; turn the "debugging / automatic" knob to the "debugging" position; and close the circuit breaker of the corresponding circuit. At this time, the interlocking between the electrical equipment is released, and the "automatic start" button and "automatic stop" button set on the PLC control box lose their function. The "allow debugging" signal light on the local control box is turned on, and the debugging of the electrical equipment of the plowing layer and the unloading layer is carried out on the field control boxes of their respective levels, and the corresponding operations are carried out on the local control box.
[0149] By applying this method to install equipment, the installation time of the equipment is shortened, the purpose of saving construction period is achieved, and the installation efficiency and quality of the equipment are improved.
[0150] The technical means disclosed in the scheme of the present invention are not limited to the technical means disclosed in the above-mentioned implementation mode, but also include technical schemes composed of any combination of the above-mentioned technical features. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention, and these improvements and modifications are also regarded as the protection scope of the present invention.
Claims
1. A method for installing a ring feeder, wherein the ring feeder is installed at the bottom of a silo, and the ring feeder comprises an inner ring plowing vehicle track, an inner ring unloading vehicle track, an inner ring plowing vehicle, an inner ring unloading vehicle, an inner ring plowing vehicle driving device, an inner ring unloading vehicle driving device, an inner ring plowing vehicle sealing device, an inner ring unloading vehicle sealing device, an inner ring unloading device, an outer ring plowing vehicle track, an outer ring unloading vehicle track, an outer ring plowing vehicle, an outer ring unloading vehicle, an outer ring plowing vehicle driving device, an outer ring unloading vehicle driving device, an outer ring plowing vehicle sealing device, an outer ring unloading vehicle sealing device, an outer ring unloading device and an electrical system, Features: The installation method comprises the following steps: Step 1: Install the inner ring unloading car track and the inner ring plowing car track; Step 2: Install the inner ring plow truck and drive device; Step 3: Install the inner ring unloading vehicle and the driving device; Step 4: Install the inner ring unloading car unloading device; Step 5: Install the inner ring plow car sealing device; Step 6: Inner ring unloading car sealing device; Step 7: Install the outer ring equipment; Step 8: Install electrical system and debug equipment; The inner ring unloading vehicle track and the inner ring plowing vehicle track include a primary embedded plate, a secondary civil engineering embedded plate, a leveling stud, a leveling nut, a track pressure plate, an elastic pad and a track; The method for installing the inner ring unloading car track and the inner ring plowing car track in step 1 is: A1): Take the pre-buried point in the center of the silo as the center of the circle, measure the radius of the inner ring unloading vehicle track through the pre-buried pipe in the inner tube of the silo, make a mark on the primary pre-buried plate of the track, and make 12 to 24 calibration points on the circumference; A2): Connect the calibration points to make a track diameter circle on the primary embedded plate, and weld leveling studs on the plate with the circumference line of each primary embedded plate as the center line with a spacing of 260mm; A3): Install the leveling nut and the secondary embedded plate on the leveling stud, level the secondary embedded plate, and ensure that the height difference error between the secondary embedded plate and the highest point of the driving base is +10mm; A4): Install the track pads and lay the segmented tracks on the secondary embedded plates to ensure that the track diameter deviation is -5 to -3mm; the horizontal deviation is ≤1mm; A5): When installing the inner ring plowing car track, take the inner ring unloading car track as the reference, use the hanging wire method to determine the diameter of the plowing car track, weld the leveling studs, install the leveling nuts and the secondary embedded plate, and lay the plowing car track after leveling the secondary embedded plate to ensure that the track diameter deviation is -5 to -3mm; the horizontal deviation is ≤1mm; A6): Use elastic pads to adjust each section of track. The weld gap at the track joint is 1-2mm, and the height difference and lateral misalignment of the track surface are ≤1mm; A7): Weld each section of track, preheat to 250℃ before welding, use J506 welding rod, heat to 400℃ after welding, keep warm and cool slowly, and finally grind the flat weld on the track to make it smooth; A8): Carry out secondary grouting for the secondary embedded plate and adjusting bolts; The inner ring plow vehicle and driving device include a vehicle body, wheels, plow claws, a pin-tooth plate connecting plate, a driving device, a positioning device and a driving base; The method for installing the inner ring plow vehicle and the drive device in step 2 is: B1): After assembling the wheels and the vehicle body outside the silo, the sections of the inner ring plowing vehicle are hoisted into the unloading layer from the silo wall opening in sequence according to the production number. After entering the inner ring space, the equipment is hoisted onto the plowing vehicle track through the plowing gap using the silo pre-buried lifting ring; B2): The four corners of the body flange are first positioned and connected with tapped hole bolts, and then the remaining flange holes are connected with high-strength bolts. The body flange is used to connect the various sections of the plow truck; B3): After each section of the car body is connected, measure the flange gap and use grinding or adding adjustment pads to make the flange gap ≤1mm; B4): Install the plow claws, adjust the height and levelness of the plow claws, the height should be more than 50mm from the civil engineering, and the levelness should be ≤0.5mm / m; B5): Install the pin-tooth plate connecting plate, the concentricity of the upper and lower connecting plates should be ≤ Ф0.3mm, install the transmission pin at the connection, and then fix the pin shaft clamping plate; B6): Manually push the plow truck to rotate it 3 to 5 times to make the truck body concentric with the track; B7): The drive of the inner ring plowing vehicle is hoisted into the plowing layer from the hoisting hole on the outside of the middle tube of the unloading layer silo, and enters the outer driving foundation of the plowing vehicle through the middle tube channel; B8): Adjust the eccentric mechanism of the positioning wheels on both sides of the driving device to be away from the vehicle body, and adjust the distance between the positioning wheel and the pin gear plate to 3-5mm; B9): Use an inclined iron to adjust the height of the drive seat to ensure that the height error between the symmetric plane of the pin wheel pin length direction and the symmetric plane of the drive gear tooth width is less than 1mm, and use J422 welding rod to weld the base and the foundation embedded parts firmly, with the weld height ≥15mm, weld length ≥50mm, and weld number ≥12; The inner ring unloading vehicle and driving device include a vehicle body, wheels, a receiving plate, a pin-tooth plate connecting plate, a driving device, a positioning device and a driving base; The method for installing the inner ring unloading vehicle and the driving device in step 3 is: C1): Assemble the unloading vehicle body and wheels outside the silo, and hoist each section of the inner ring unloading vehicle from the silo wall opening into the inner ring unloading layer in sequence according to the production number, and use the pre-buried lifting ring of the silo to hoist the equipment onto the unloading vehicle track; C2): After the body flange connection is completed, the wear-resistant plate of the receiving plate at the welding connection is welded, using double-sided V-shaped welding and ground flat after welding; C3): Install the pin-tooth plate connecting plate and the pin shaft at the connection, and manually push the unloading car so that the gap between the wheel rim and the track is maintained at 10-15mm regardless of the track position; C4): Put the drive device in place, adjust the eccentric mechanism of the positioning wheels on both sides to be away from the vehicle body, and adjust the distance between the positioning wheel and the pin gear plate to 3-5mm; C5): Install the sliding compartment protection plate. The sliding compartment protection plate is welded in the blanking gap of the inner ring plowing vehicle. First, weld the rib plate on the pre-buried plate of the civil engineering in the blanking gap, and weld the sliding compartment protection plate on the rib plate. The height of the protection plate should be flush with or slightly lower than the bottom of the plowing platform to ensure that the static rest angle of the plowing claw plowing space is ≤35°; The inner ring unloading vehicle unloading device includes a unloader, an electric push rod, a spring sweeper, a herringbone chute, a unloading hopper and a unloading pipe; The method for installing the inner ring unloading car dropping device in step 4 is: D1): Place the columns on both sides of the unloader on the embedded parts of civil engineering, connect the unloader shaft with the columns, and place a 10mm steel plate between the unloader and the wear-resistant plate of the vehicle body to ensure that the gap between the unloader and the wear-resistant plate is 10mm; D2): Adjust the electric push rod to the extended state, connect the electric push rod base with the discharger column, connect the electric push rod head with the discharger rotating arm, and fix the rotating arm with the discharger shaft after the connection is completed; D3): The spring cleaner is welded at the rear of the discharger. During welding, the spring is adjusted to be in a tensioned state. The cleaner is pressed against the wear-resistant plate of the discharger, and the outer side of the cleaner extends out of the outer edge of the wear-resistant plate of the vehicle body. D4): The herringbone chute is welded and suspended above the discharger by angle steel and embedded civil engineering parts. The height position must ensure that the discharger does not interfere with the herringbone chute when it is lifted, and it cannot interfere with the seal under the plow truck. The horizontal position must ensure that the material will not hit the discharge board when it is dropped; D5): The hopper is installed above the blanking port, and the blanking height and distance from the vehicle body are adjusted. The height difference between the hopper and the wear-resistant plate of the vehicle body is 25mm, and the inner side of the hopper extends into the wear-resistant plate by 30mm. After determining the position, it is welded to the embedded parts of the blanking port, and a sealing gasket is added to the connection seam; The inner ring plow car sealing device includes a plow car labyrinth seal fixed part, a plow car labyrinth seal rotating part, a plow car lower seal and a plow car observation hole; The method for installing the inner ring plow car seal in step 5 is as follows: E1): The fixed part of the labyrinth seal is welded to the embedded parts of the civil engineering, and the horizontal direction is 100mm higher than the upper plane of the plow body. The welding level is ≤2mm / m, and the diameter deviation is ≤10mm. After welding, the gap between the labyrinth seal and the civil engineering is filled with sealant or grouting material; E2): The rotating part of the plowing vehicle labyrinth seal is welded to the upper plane of the vehicle body, with a welding level of ≤2mm / m and a diameter deviation of ≤5mm; E3): The lower seal of the plowing vehicle is welded to the lower plane of the vehicle body to ensure that the bottom of the lower seal extends into the plowing gap by more than 100mm and the gap with the civil engineering is more than 50mm; E4): The rotating part of the plow truck labyrinth seal is provided with an observation hole, corresponding to the plow claw, a hole is opened at the plow claw and an observation window is installed.
2. The installation method of the ring feeder according to claim 1, Features: The inner ring unloading car sealing device comprises an unloading car sealing inner ring, an unloading car sealing outer ring, a spring clear deflector and an outer ring soft seal; The method for installing the inner ring unloading car sealing device in step six is: F1): When installing the inner seal ring of the unloading car, first weld the fixed angle steel to the embedded parts of the civil engineering. Take the vertical plate of the unloading car body as a reference, arrange it along the circumference with the required size of the drawing as the radius, and the deviation in the diameter direction is ≤5mm. Then weld the inner seal ring on the angle steel to ensure that the bottom of the inner seal ring is 50mm away from the wear-resistant surface of the car body. The top of the inner seal ring is welded to the embedded plate of the civil engineering, and fill the gap with the civil engineering with sealant to prevent powder leakage; F2): The installation method of the outer ring of the unloading car is the same as that of the inner ring, ensuring that the distance between the bottom of the outer ring and the wear-resistant surface of the car body is 10mm; F3): The spring deflector is installed on the inner side of the sealing outer ring. One is welded about 2m in front of each blanking port, and the rest are evenly distributed along the sealing cover. When welding, ensure that the spring of the spring deflector is pressed tightly, and ensure that the bottom of the deflector is pressed tightly against the wear-resistant surface of the vehicle body; F4): Install a soft seal at the bottom of the outer ring of the seal to ensure that the sealing strip contacts the receiving plate smoothly. The inner sealing strip must not have bulges or protrusions that cause poor contact. Use vulcanization connection measures at the joints of the sealing strip. If there is overlap, it must be ensured to be overlapped along the direction of the material flow to avoid leakage.
3. The installation method of the ring feeder according to claim 1, Features: The outer ring equipment includes an outer ring plowing vehicle track, an outer ring plowing vehicle, an outer ring plowing vehicle driving device, an outer ring plowing vehicle sealing device, an outer ring unloading vehicle track, an outer ring unloading vehicle, an outer ring unloading vehicle driving device, an outer ring unloading device and an outer ring unloading vehicle sealing device; The method for installing the outer ring device in step 7 is: G1): When installing the outer ring unloading car track, the inner ring track is used as the reference for setting out, or the pre-buried point in the center of the silo is used as the center of the circle. The measuring ruler measures the track diameter through the pre-buried wire pipe in the inner and middle tubes of the silo. The track diameter deviation is a negative difference of -10 to -5mm; track leveling The method is the same as step A6) in the inner ring track installation method; G2): When installing the outer ring plowing car track, the outer ring unloading car track diameter is used as the reference, and the outer ring plowing car track diameter is determined by the hanging wire method, with a diameter deviation of -10 to -5m; G3): The outer ring plowing car and the unloading car are hoisted into the silo through the plowing layer wall and the unloading layer wall respectively, and are connected on the track in sequence according to the production number after the secondary pre-embedded track solidifies; G4): After the outer ring plow truck and unloading truck drive device are installed in place, apply No. 3 lithium ester to the dovetail groove of the drive seat to ensure flexible sliding of the floating seat, adjust the nut at the tail of the drive seat to ensure that the spring compression deformation is 8mm, and the spring preload force is 4×500Kg; G5): After the plow truck and the unloading truck are assembled and installed, the gap between the positioning wheel and the pin wheel rim is ≤5mm, and when the positioning wheel is in action, the wheel rim is not allowed to contact the top side of the track. At least 70-80% of the inner and outer rings should be in contact with the track, and the gap between the non-contact wheel tread and the track is ≤0.5mm; G6): When installing the unloading device of the outer ring plow truck, measure the distance between the tripod and the inner side plate of the outer ring plow truck. If the distance is 20mm, weld the tripod on the embedded civil engineering parts. After welding, you can weld the fixed sealing cover. If the distance is greater than 20mm, adjust the tripod welding height to ensure that the distance between the fixed sealing cover and the rotating part is 20mm.
4. The method for installing the ring feeder according to claim 1, Features: The electrical system includes a PLC cabinet, a frequency conversion cabinet, a local operation box and cables; The method for installing the electrical system and debugging the equipment in step eight is: H1): PLC cabinet and frequency converter cabinet are usually installed in the electrical control room next to the silo, and should not be placed 100m away from the silo to facilitate equipment debugging and ensure that the control is not interfered by other signals; H2): The power supply adopts three-phase four-wire AC ∽380V / 50HZ power supply, and the control power supply is 220V / 50hz AC and 24V DC power supply; The system power circuits are all connected to the busbar power supply, and each sub-circuit uses an air switch for short circuit and overcurrent protection. Each motor is protected by a motor integrated protector for fault overload protection; H3): Use programmable controller as the field logic control center to collect equipment switches and operation signals and control relay output; H4): Both the power drive system of the unloading vehicle and the power drive system of the plowing vehicle adopt a drive control method that combines relay output with contactor and inverter; H5): Install the field control boxes on the plowing layer and the discharge layer of the inner and outer rings of the ring feeder for on-site debugging; H6): Turn the "local / remote" knob on the PLC control cabinet to the "local" position; turn the "debug / auto" knob to the "debug" position; close the circuit breaker of the corresponding circuit, then the interlocking between the electrical equipment is released, the "auto start" button and "auto stop" button set on the PLC control box lose their function, and the "allow debugging" signal light on the local control box is turned on. The debugging of the electrical equipment on the plowing layer and the unloading layer is carried out on the field control boxes at their respective levels, and the corresponding operations are carried out on the local control box.