Quantitative algorithm for time-space conflict of construction machinery on arch dam deck
By constructing a micro element model and time-dividing step-by-step trajectory model of the arch dam wall surface construction machinery, the risk rate of time-space conflict in construction machinery is quantified, and the problem of lack of intuitive numerical values of the risk of time-space conflict during construction is solved, and construction efficiency and safety are improved , reducing the risks and losses caused by mechanical conflicts.
Patent Information
- Application Number
- CN202311303141.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-09
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2043-10-09
AI Technical Summary
During the construction of the arch dam wall surface, the safety risks and efficiency losses caused by time and space conflicts in construction machinery were not effectively quantitatively analyzed, resulting in the impact of construction quality and progress, and there is a lack of scientific and efficient organizational management references.
Using the micro element model and time-dividing step-by-step trajectory model of construction machinery, a quantification algorithm of space-time conflict risk rate is constructed, and the physical collision accident rate caused by space-time conflict between construction machinery is quantified through the calculation indicators of micro element permeability and maximum penetration depth. , safety risk rate and efficiency loss rate.
The fuzzy concept of space-time conflict in construction machinery is concretized, providing quantitative values of physical collision risks, safety risks and efficiency losses, improving the configuration rate and construction efficiency of construction machinery, and reducing safety risks and efficiency losses caused by mechanical conflicts.
Smart Images

Figure CN117408509B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of water conservancy project construction, and relates to a time-space conflict quantification algorithm for construction machinery, and in particular to a time-space conflict quantification algorithm for arch dam warehouse surface construction machinery. Background Art
[0002] The safety and efficiency of construction activities in the arch dam warehouse directly affect the quality and construction period of the dam construction, and are the core of the arch dam construction organization and management. Concrete pouring is one of the construction activities in the arch dam warehouse. In order to ensure the quality and construction period of concrete construction, the warehouse surface construction organization should be optimized as much as possible to improve the construction efficiency. Due to the limited space resources in the warehouse, the concrete pouring activities are numerous and cross-cutting, the construction process requirements are strict, the machinery and auxiliary equipment are complicated, and the narrow construction surface makes it difficult to arrange the machinery. It is very easy to produce time and space conflicts during the warehouse pouring operation, and there will be safety risks or efficiency loss problems, which to a certain extent affect the high-quality and rapid construction of the dam. However, the high-intensity and rapid construction of the dam can only be achieved under the premise of ensuring the construction quality and construction safety. This requires starting from the optimization of construction organization plan and resource allocation, the prediction and response of emergencies during the construction process, and the real-time adjustment and scheduling of the plan. Especially when the time and impact of the construction machinery time and space conflict during the pouring construction process are still unclear, the focus should be on the quantification of the construction machinery time and space conflict during the warehouse surface pouring operation, the analysis of the impact effect of time and space conflict, and the real-time dynamic adjustment of the pouring plan.
[0003] Domestic and foreign researchers have conducted research on the classification of conflict types between construction entities, spatial conflict detection, prevention and early warning of safety accidents, and other aspects. They have also conducted qualitative analysis on the spatiotemporal conflicts and safety issues caused by the construction of water conservancy projects and other construction projects, and have achieved certain research results. The dangerous or harmful factors in engineering construction activities are identified, and the problem of assessing and predicting safety risks caused by external environmental factors is solved. At the same time, since the impact of spatiotemporal conflicts between construction entities on construction safety and construction efficiency generally exists at the same time, scholars have also conducted relevant research on the efficiency loss problem in the construction process, mainly focusing on the efficiency loss caused by factors such as the quality of construction personnel, construction technology, construction machinery configuration, and construction environment in construction activities. These studies have achieved certain research results in the experience-guided or indicator evaluation, prediction, early warning and optimization of efficiency loss. However, as the construction of water conservancy projects gradually develops towards intelligence, higher requirements are put forward for the scientific and refined control of the bunker surface construction process, especially for the bunker surface pouring construction system of arch dams. While the time-space conflict of construction machinery causes safety risks, the efficiency loss problem in the pouring operation will also follow, affecting the concrete pouring construction process, and even causing local construction quality defects and progress delays. Therefore, it is important to clarify the time and impact of the efficiency loss caused by the time-space conflict of construction machinery during the bunker surface pouring operation, and to dynamically adjust the construction plan according to the quantitative result data of efficiency loss, so as to avoid or reduce efficiency loss, which is of great significance for improving construction quality and accelerating construction progress. At present, the qualitative analysis of time-space conflict and safety issues cannot provide intuitive and specific reference for the quantification of time-space conflict in bunker surface construction and the rationality evaluation of pouring schemes, and thus cannot provide scientific and efficient organizational management reference and guidance for construction management personnel; on the other hand, there is a lack of research results on the quantitative analysis of safety risks caused by time-space conflict between construction entities and the quantitative analysis of efficiency loss caused by time-space conflict of bunker surface construction machinery. Summary of the invention
[0004] In order to solve the above-mentioned technical problems existing in the background technology, the present invention provides a spatiotemporal conflict quantification algorithm for arch dam surface construction machinery, which can effectively improve the configuration rate and construction efficiency of surface construction machinery and reduce the safety risks and efficiency losses caused by mechanical conflicts and mutual interference at the construction site.
[0005] In order to achieve the above object, the present invention adopts the following technical solutions:
[0006] A quantification algorithm for time-space conflicts of arch dam bunker construction machinery, characterized in that the quantification algorithm for time-space conflicts of arch dam bunker construction machinery comprises the following steps:
[0007] 1) Construct a micro-element model of construction machinery and a time-sharing and step-by-step trajectory model of construction machinery;
[0008] 2) Based on step 1), a quantitative algorithm for the spatiotemporal conflict risk rate of construction machinery is constructed;
[0009] 3) Based on step 2), quantitative algorithms for the physical collision accident rate, safety risk rate and efficiency loss rate caused by spatiotemporal conflicts between construction machines at any time point, any time period or within the operation trajectory are constructed in sequence.
[0010] Preferably, the construction machinery micro-element model in step 1) adopted by the present invention is constructed in the following manner:
[0011] 1.1) Determine the three-dimensional dimensions and structure of the warehouse construction machinery;
[0012] 1.2) Based on the spatial three-dimensional dimensions of the warehouse construction machinery determined in step 1.1), a micro-element model of the construction machinery is constructed; the three-layered space for construction machinery is established, and the three-layered space for construction machinery includes physical space, safety space and efficiency space from the inside out, wherein the physical space is generated by the three-dimensional dimensions of the construction machinery, and the safety space and efficiency space are formed by the gradual expansion of the physical space. The three-layered space is divided into regular micro-elements, and unit volume micro-element units are divided, and the unit volume parameters are 0.1m×0.1m×0.1m, and the micro-element units have spatial coordinate attributes.
[0013] Preferably, the construction of the micro-element time-sharing and step-by-step trajectory model of the construction machinery in step 1) of the present invention requires the selection of an appropriate time step length T step With the spatial step size S step ;
[0014] The construction method of the construction machinery micro-element time-sharing and step-by-step trajectory model is:
[0015] a) A certain running track of the warehouse construction machinery is in a uniform speed state. This running track is divided into n segments of equal duration. There are n+1 nodes including the starting point and the end point. Assuming that the running time of this running track is T, then n=T / T step The time step is to divide the operation trajectory of the construction machinery on the warehouse surface based on time, obtain the changes in the operation status of the construction machinery in the evenly divided time period, take the start and end time points of each time period as known points, and obtain the relationship between the operation status and operation time of the construction machinery at each moment;
[0016] b) Number the n+1 nodes of equal duration in the running track and record the node coordinates as (X i ,Y i ,Z i), where i is the coordinate point number, and 0 < i ≤ n + 1; the node is a trajectory point, and the known points that reflect the characteristics of the construction operation trajectory on the silo surface are defined as key trajectory points, and the remaining trajectory points are non-key trajectory points. The relationship between the operating state and operating time of the construction machinery at the non-key trajectory points is obtained by using the interpolation algorithm. At the same time, it is defined that a certain non-key trajectory point j (0 < j ≤ i) is located within the key point interval [l, r] (0 < l ≤ j ≤ r), and the non-key trajectory point coordinates (X j , Y j , Z j ) The calculation formula is as follows:
[0017]
[0018]
[0019]
[0020] c) The process of dividing the construction machinery operation trajectory into continuous straight-line segment trajectory points based on the time step, and the spatial state change process is also divided accordingly. According to the spatial step S step , the operation trajectory between adjacent trajectory points is divided again to establish a regular micro-element time-sharing and step-by-step operation trajectory.
[0021] Preferably, the specific implementation method of establishing a regular micro-element time-sharing and step-by-step operation trajectory in step c) adopted by the present invention is:
[0022] c.1) According to the coordinates of adjacent (i - 1) and i trajectory points, calculate the adjacent step difference between adjacent trajectory points within the (i - 1)th time period That is, the magnitudes of the distances between adjacent trajectory points projected in the X, Y, and Z directions;
[0023] Among them, the calculation formula for the adjacent step difference between adjacent trajectory points is as follows:
[0024]
[0025]
[0026]
[0027] c.2) Calculate the micro-steps in the X, Y, and Z directions based on the adjacent step difference and the spatial step. Introduce the maximum adjacent step difference between adjacent trajectory points Take as the micro-steps. The micro-steps are the magnitudes of the distances between adjacent trajectory points projected in the X, Y, and Z directions with the spatial step as the unit;
[0028] The maximum adjacent step difference between adjacent trajectory points The calculation formula is:
[0029]
[0030] Microstep lengths between adjacent trajectory points in the X, Y, and Z directions The calculations are as follows:
[0031]
[0032]
[0033]
[0034] c.3) Sequentially divide the space between trajectory point i-1 and trajectory point i into equal steps The micro-step points are numbered and their coordinates are recorded as Where k is the coordinate point number, and At the same time, define any micro-step point k to be within the trajectory point interval [i-1,i], and get the coordinates of any micro-step point The calculation formula is as follows:
[0035]
[0036]
[0037]
[0038] c.4) Merge the trajectory points and micro-step points to form micro-element time-sharing and micro-step trajectory points. The micro-element time-sharing and micro-step trajectory model contains the relationship between the construction machinery operation trajectory and time.
[0039] Preferably, the time-space conflict risk rate in step 2) adopted by the present invention is the product of micro-element interpenetration and maximum penetration depth; the micro-element interpenetration is the severity of accident loss, the ratio of the maximum penetration depth to the safety distance or efficiency distance is the probability of time-space conflict; the time-space conflict risk rate includes the physical collision accident rate, the safety risk rate and the efficiency loss rate;
[0040] The physical collision accident rate is determined based on whether the physical spaces of the construction machinery layered spaces are in contact. When the physical spaces of the construction machinery layered spaces are not in contact, the physical collision accident rate is 0; when the physical spaces of the construction machinery layered spaces are in contact, the physical collision accident rate is 100%;
[0041] The safety risk rate and efficiency loss rate are calculated based on two indicators: the micro-element interpenetration degree of the safety space and the efficiency space and the maximum penetration depth.
[0042] Preferably, the calculation method of the microelement interpenetration in step 2) adopted by the present invention is:
[0043] a) Obtain the overlapping area of the intersecting projected rectangles. The specific implementation method is: based on the outermost layered space size of the flattener and the vibrator, it is inferred that when the outermost cuboid space of the flattener and the vibrator is projected onto the plane, at least one of the intersecting boundary vertices of the rectangles formed enters the interior of another projected rectangle; when calculating the intersection area of the layered space of the projection plane of the flattener and the vibrator, the intersection points are set as (x0, y0), (x1, y1), (x2, y2), ..., (x n-1 ,y n-1 );Get the overlapping area of the intersecting projection rectangles. The expression of the overlapping area of the intersecting projection rectangles is:
[0044]
[0045] in:
[0046] The expression for the area of the overlapping part of the intersecting projected rectangles is:
[0047] S csm =S csm-e +S csm-s +S csm-p
[0048] S cvm =S cvm-e +S cvm-s +S cvm-p
[0049] Where:
[0050] The S csm-e is the area of the overlapped part of the efficiency space of the liquidation machine;
[0051] The S csm-s The area of the overlapped part of the safety space of the liquidation machine;
[0052] The S csm-p is the area of the overlapping part of the physical space of the liquidation machine;
[0053] The S cvm-e is the area of the overlapped part of the efficiency space of the vibrator;
[0054] The S cvm-s The area of the overlapped part of the safety space of the vibrator;
[0055] The S cvm-p The area of the overlapped part of the physical space of the vibrator;
[0056] And when S csm-p With S cvm-pWhen both exist, it indicates that the leveler and vibrator have physically collided;
[0057] b) Obtaining the number of overlapping micro-elements in each layer of space according to the overlapping area of the intersecting projection rectangles, wherein the number of overlapping micro-elements in each layer of space is the quotient of the overlapping area of the intersecting projection rectangles and the projection plane area of the unit micro-element; the expression of the number of overlapping micro-elements in each layer of space is:
[0058]
[0059]
[0060]
[0061]
[0062]
[0063]
[0064] in:
[0065] The q csm-p The number of micro-elements of physical space overlap of the liquidation machine;
[0066] The q csm-s The number of micro-elements of the safety space overlap of the liquidation machine;
[0067] The q csm-e is the number of overlapping micro-elements in the liquidation machine efficiency space;
[0068] The q cvm-p is the number of overlapping micro-elements in the physical space of the vibrator;
[0069] The q cvm-s is the number of overlapping micro-elements of the safety space of the vibrator;
[0070] The q cvm-e is the number of overlapping micro-elements of the efficiency space of the vibrator;
[0071] S0 is the projected plane area of the unit microelement;
[0072] c) obtaining the micro-element interpenetration according to the number of overlapping micro-elements in each layer of space; the micro-element interpenetration includes the micro-element interpenetration of physical space, the micro-element interpenetration of efficiency space and the micro-element interpenetration of safety space;
[0073] The physical space micro-element interpenetration includes the physical space micro-element interpenetration of the vibrator to the warehouse closing machine and the physical space micro-element interpenetration of the warehouse closing machine to the vibrator; the expressions of the physical space micro-element interpenetration of the vibrator to the warehouse closing machine and the physical space micro-element interpenetration of the warehouse closing machine to the vibrator are respectively:
[0074]
[0075]
[0076] in:
[0077] q cs(v)m-p (t i ) is any time t i The physical space overlap micro-element of the flattener and the vibrator;
[0078] The physical space microelement interpenetration degree IntD cs(v)m-p (t i ) represents the physical collision accident rate, when IntD cs(v)m-p (t i )=0, no physical collision accident occurs, and the physical collision accident rate is 0; when IntD cs(v)m-p (t i )>0, a physical collision occurs, and the physical collision accident rate is 100%;
[0079] The efficiency space micro-element interpenetration is the ratio of the number of overlapping micro-elements in the efficiency space to the total number of micro-elements in the efficiency space on the contact side;
[0080] The safety space micro-element interpenetration is the ratio of the number of overlapping micro-elements in the safety space to the total number of micro-elements in the safety space on the contact side;
[0081] At any time t i The efficiency space micro-element interpenetration and safety space micro-element interpenetration of the flattener and vibrator are expressed as:
[0082]
[0083]
[0084]
[0085]
[0086] in:
[0087] The q csm-p (t i ) is t i When the layers of space touch each other, the number of micro-elements of the physical space of the liquidation machine overlaps;
[0088] The q csm-e (t i ) is t i When the layers of space touch each other, the number of micro-elements of the liquidation machine efficiency space overlap;
[0089] The q csm-s (t i ) is t i When the layers of space touch each other, the number of micro-elements of the safe space of the liquidation machine overlaps;
[0090] The q cvm-p (t i ) is t i When the layers of space are in contact, the number of micro-elements of the vibrator's physical space overlap;
[0091] The q cvm-e (t i ) is t i When the layers of space are in contact, the number of micro-elements of the vibrator efficiency space overlap;
[0092] The q cvm-s (t i ) is t i When the layers of space are in contact, the number of micro-elements of the vibrator safety space overlap;
[0093] The Q csm-p is the total amount of micro-element of the physical space of the liquidation machine;
[0094] The Q cvm-p is the total amount of micro-element of the physical space of the vibrator;
[0095] The Q csm-e It is the total amount of efficiency space microelement on one side of the stratified space contact of the liquidation machine;
[0096] The Q csm-s The total amount of micro-element of the safe space on one side of the liquidation machine's layered space contact;
[0097] The Q cvm-e The total amount of efficiency space micro-element on the contact side of the vibrator layered space;
[0098] The Q cvm-s It is the total amount of safe space micro-element on the contact side of the vibrator's layered space.
[0099] Preferably, the maximum penetration depth in step 2) of the present invention is calculated as follows:
[0100] When defining the layered space contact, the maximum penetration depths into the efficiency space and safety space of the liquidator are and The maximum penetration depths into the vibrator's efficiency space and safety space are and Definition H csm-e , H csm-s are the depths of the efficiency space and safety space on the contact side of the liquidation machine layered space, Hcvm-e , H cvm-s They are the depths of the efficiency space and safety space on the contact side of the vibrator layered space, and both meet the following requirements:
[0101]
[0102]
[0103]
[0104]
[0105] The d CSM-e is the horizontal efficiency distance of the liquidator;
[0106] The d CSM-s It is the horizontal safety distance of the liquidation machine;
[0107] The d CVM-e is the lateral efficiency distance of the vibrator;
[0108] The d CVM-s It is the lateral safety distance of the vibrator;
[0109] The l CSM-e is the longitudinal efficiency distance of the liquidator;
[0110] The l CSM-s It is the longitudinal safety distance of the liquidation machine;
[0111] The l CVM-e is the longitudinal efficiency distance of the vibrator;
[0112] The l CVM-s It is the longitudinal safety distance of the vibrator;
[0113] Define the straight line edge occupying a certain mechanical unilateral boundary in the overlapping microelement formation area as the reference line; define the maximum distance from any point of the overlapping microelement to the reference line as the maximum penetration depth of the unilateral contact machine; the X-axis and Y-axis extreme value coordinates of the overlapping microelement on the boundary after the safety space is projected on the two-dimensional plane are x max-e , x min-e ,y max-e ,y min-e ;x max-s , x min-s ,y max-s ,y min-s ; Define the extreme value coordinates of entering a certain mechanical efficiency and safety space as (X min-e , Y e )、(X min-s , Y s), when the extreme value coordinate point is located in the efficiency space, it is necessary to derive the reference straight line equation and calculate the maximum depth value entering the efficiency space; when the extreme value coordinate point is located in the safety space, the maximum depth value entering the efficiency space at this time is the maximum efficiency distance of the contact side, and the maximum depth value entering the safety space needs to be calculated by deriving the straight line equation;
[0114] The single-sided boundary of the contact side is assumed to be located on the vibrator, and the reference straight line plane equations for calculating efficiency and the maximum distance of the safe space are derived as follows:
[0115]
[0116]
[0117] Then the distance from any point in each layer space of the overlapped area to the respective reference straight line is:
[0118]
[0119]
[0120] Where h i-e 、h i-s are the depth values of any point in the overlapping micro-element region from the efficiency space and the safety space, respectively. Based on this, the maximum depth values from the efficiency space and the safety space of the vibrator are obtained as follows:
[0121]
[0122]
[0123] Calculate the efficiency of the liquidation machine and the maximum depth of the safety space based on the extreme value coordinate points;
[0124]
[0125]
[0126] Preferably, in step 3) of the present invention, at any time point between the construction machines, the physical collision accident rate, safety risk rate, and efficiency loss rate of the vibrator against the flattening machine and the flattening machine against the vibrator are R csm (t i ) and P cvm (t i ), S csm (t i ) and S cvm (t i ), E csm (t i ) and E cvm (t i), their respective calculation expressions are expressed as:
[0127]
[0128]
[0129]
[0130]
[0131]
[0132]
[0133] Preferably, in step 3) of the present invention, when the construction machines are at any time point, taking into account the movement speed, movement direction and movement process, combined with the distribution weight coefficient, the expression of the physical collision accident rate, safety risk rate and efficiency loss rate caused by the space-time conflict between the leveler and the vibrator at any time is:
[0134] P(t i )=w csm ·P csm (t i )+w cvm ·P cvm (t i )
[0135] S(t i )=w csm ·S csm (t i )+w cvm ·S cvm (t i )
[0136] E(t i )=w csm ·E csm (t i )+w cvm ·E cvm (t i )
[0137] Where:
[0138] i∈N;
[0139] P(t i ) is t i The accident rate of physical collision between the time leveler and the vibrator;
[0140] S(t i ) is t iThe safety risk ratio between the time-closer and the vibrator;
[0141] E(t i ) is t i The efficiency loss rate between the time leveler and the vibrator;
[0142] w csm is the weight coefficient of the liquidation machine in the time-space conflict generated during the construction process;
[0143] w cvm is the weight coefficient of the vibrator in the time-space conflict generated during the construction process;
[0144] P csm (t i ) is the accident rate of physical collision of vibrator with the leveler;
[0145] P cvm (t i ) is the accident rate of physical collision of the leveler with the vibrator;
[0146] S csm (t i ) is the safety risk ratio of the vibrator to the flattener;
[0147] S cvm (t i ) is the safety risk ratio of the liquidator to the vibrator;
[0148] E csm (t i ) is the efficiency loss rate of the vibrator to the flattener;
[0149] E cvm (t i ) is the efficiency loss rate of the leveler to the vibrator.
[0150] Preferably, in step 3) of the present invention, the expression of the quantitative algorithm for the physical collision accident rate, safety risk rate and efficiency loss rate caused by the spatiotemporal conflict between construction machines in any time period or operation trajectory route is:
[0151]
[0152]
[0153]
[0154] in:
[0155] Said is t0 to t n The accident rate of physical collision between the trimmer and the vibrator during any running trajectory of the trimmer and the vibrator during this period;
[0156] Said is t0 to t n The safety risk rate between the flattening machine and the vibrating machine during any running trajectory of the flattening machine and the vibrating machine during this period;
[0157] Said is t0 to t n The efficiency loss rate between the flattener and the vibrator during any running trajectory of the flattener and the vibrator during this period;
[0158] The P(t i ) is t i The accident rate of physical collision between the time leveler and the vibrator;
[0159] The S(t i ) is t i The safety risk ratio between the time-closer and the vibrator;
[0160] The E(t i ) is t i The efficiency loss rate between the time leveler and the vibrator;
[0161] Said n∈N.
[0162] The advantages of the present invention are:
[0163] The present invention provides a quantitative algorithm for the spatiotemporal conflict of construction machinery for arch dam bunker surface pouring. By establishing a micro-element model of construction machinery and a time-sharing and step-by-step trajectory model, it is proposed to use two calculation indicators, micro-element interpenetration and maximum penetration depth, to construct a quantitative algorithm for the spatiotemporal conflict risk rate of construction machinery: the micro-element interpenetration is described as the severity of accident loss; the ratio of the maximum penetration depth to the safety or efficiency distance is described as the probability of occurrence, and the product of the two indicators is described as the spatiotemporal conflict risk rate, and a quantitative algorithm for the physical collision accident rate, safety risk rate and efficiency loss rate caused by the spatiotemporal conflict between construction machinery at any time point, any time period or within the running trajectory is sequentially constructed. The problem of the lack of intuitive numerical quantification of the spatiotemporal conflict risk of construction machinery in the bunker surface pouring construction process is solved, and the vague concept of conflict is concretized, so that the physical collision risk, safety risk and efficiency loss of the construction process are quantified into specific values, which has important guiding significance for improving the configuration rate and construction efficiency of bunker surface construction machinery and reducing the safety risk and efficiency loss caused by mechanical conflict and mutual interference at the construction site. BRIEF DESCRIPTION OF THE DRAWINGS
[0164] Figure 1 It is a schematic diagram of the construction process of the time-sharing and step-by-step trajectory model of construction machinery;
[0165] Figure 2This is a schematic diagram of the layered spatial contact of the micro-element model of construction machinery;
[0166] Figure 3 It is a schematic diagram of the intersecting area of the layered space of construction machinery;
[0167] Figure 4 Schematic diagram of the maximum penetration depth of construction machinery in layered space. DETAILED DESCRIPTION
[0168] The following is a detailed example of the quantification algorithm of spatiotemporal conflict of construction machinery on the surface of the arch dam in the present invention, in conjunction with the accompanying drawings. The main purpose of this embodiment is to establish a micro-element model of construction machinery and a time-sharing and step-by-step trajectory model, and propose to use two calculation indicators, micro-element interpenetration and maximum penetration depth, to construct a quantification algorithm for the risk rate of spatiotemporal conflict of construction machinery: the micro-element interpenetration is described as the severity of the accident loss; the ratio of the maximum penetration depth to the safety or efficiency distance is described as the probability of occurrence, and the product of the two indicators is described as the spatiotemporal conflict risk rate, and a quantification algorithm for the physical collision accident rate, safety risk rate and efficiency loss rate caused by spatiotemporal conflict between construction machinery at any time point, any time period or within the running trajectory is sequentially constructed. The specific steps are as follows:
[0169] Step 1: Construct a micro-element model of construction machinery and its time-sharing and step-by-step trajectory model;
[0170] Step 2: Two calculation indicators, namely, microelement interpenetration and maximum penetration depth, are proposed to quantitatively calculate the risk rate of space-time conflict;
[0171] Step 3: Construct a quantitative algorithm for the spatiotemporal conflict risk rate of construction machinery;
[0172] Step 4: Construct quantitative algorithms for the physical collision accident rate, safety risk rate, and efficiency loss rate caused by spatiotemporal conflicts between construction machines at any time point, in any time period, or within the operation trajectory.
[0173] In the preferred scheme, the construction of the construction machinery micro-element model is mainly divided into two steps: (1) In combination with the actual operation process and motion characteristics of the construction machinery, the three-dimensional shape dimensions are appropriately regularized to ensure the regularity and integrity of the shape, and the three-dimensional dimensions and structure of the warehouse surface construction machinery are finally determined based on this; (2) The construction machinery micro-element model is constructed, and a three-layered space for construction machinery is established, which includes physical, safety and efficiency spaces from the inside to the outside. The physical space is produced by the three-dimensional dimensions, and the safety and efficiency spaces are formed by the gradual expansion of the physical space. The three-layered space is divided into regular micro-elements and divided into unit volume micro-element units. The unit volume parameters are 0.1m×0.1m×0.1m, and the micro-element units have spatial coordinate attributes, thereby realizing the construction of the construction machinery micro-element model.
[0174] In the preferred embodiment, Figure 1 As shown, the construction of the micro-element time-sharing and step-by-step trajectory model of construction machinery requires the selection of an appropriate time step T step and spatial step S step . The selection of the time step and spatial step needs to consider the operating trajectory characteristics of the construction machinery on the silo surface and the construction site conditions, the specifications of the divided micro-elements, and the state changing with time and space, the calculation workload, calculation accuracy, etc. The steps for constructing the micro-element time-sharing and step-by-step trajectory model are as follows:
[0175] Step 1: When a certain operating trajectory of the construction machinery on the silo surface is in a uniform motion state, this section of the operating trajectory is divided into n segments with equal time lengths, then there are (n + 1) nodes including the starting and ending points. Assuming that the operating time length of this section of the operating trajectory is T, then n = T / T step . The time step is used to divide the operating trajectory of the construction machinery on the silo surface based on time, and the change in the operating state of the construction machinery within the evenly divided time periods is obtained. Taking the start and end time points of each time period as known points, the relationship between the operating state of the construction machinery and the operating time at each moment can be obtained by using the interpolation algorithm;
[0176] Step 2: Number the (n + 1) nodes obtained by dividing the operating trajectory with equal time lengths in sequence and record their coordinates as (X i , Y i , Z i ), where i is the coordinate point number, and 0 < i ≤ n + 1. In the present invention, the nodes are defined as trajectory points, and the known points that reflect the operating trajectory characteristics of the construction on the silo surface are defined as key trajectory points, and the remaining trajectory points are non-key trajectory points. The relationship between the operating state of the construction machinery at the non-key trajectory points and the operating time can be obtained by using the interpolation algorithm. At the same time, it is defined that a certain non-key trajectory point j (0 < j ≤ i) is located within the key point interval [l, r] (0 < l ≤ j ≤ r). Based on this, the calculation formula for the coordinates (X j , Y j , Z j ) of the non-key trajectory point is as follows: (All trajectory points are points divided by the time step, that is, the number of non-key points between adjacent key points is determined)
[0177]
[0178]
[0179]
[0180] The reasons for selecting key trajectory points include speed change, direction change, etc., and they are points that can reflect the operating trajectory characteristics of construction machinery. By using the interpolation algorithm to calculate non-key trajectory points, the originally curved operating trajectory can be transformed into continuously connected straight line segments;
[0181] Step 3: Based on the time step, the construction machinery operation trajectory is divided into continuous straight line segment trajectory points, and its spatial state change process is also divided accordingly. step , the running track between adjacent track points is divided again to establish a regular micro-element time-sharing and step-by-step running track. First, according to the coordinates of the adjacent (i-1) and i track points, the adjacent step difference between the adjacent track points in the (i-1) time period can be calculated. That is, the distance between adjacent trajectory points is projected in the X, Y and Z directions; then the number of microsteps in the X, Y and Z directions is calculated based on the adjacent step difference and the spatial step length. Here, the maximum adjacent step difference of adjacent trajectory points is introduced. Pick (rounded down) is the number of microsteps, which is the size of the distance between adjacent trajectory points projected in the X, Y and Z directions in units of spatial step length.
[0182] The calculation formula of the adjacent step difference of adjacent trajectory points is as follows:
[0183]
[0184]
[0185]
[0186] Maximum step difference between adjacent trajectory points The calculation formula is:
[0187]
[0188] Microstep lengths between adjacent trajectory points in the X, Y, and Z directions The calculations are as follows:
[0189]
[0190]
[0191]
[0192] Sequentially divide the space between trajectory point i-1 and trajectory point i into equal steps The micro-step points are numbered and their coordinates are recorded as Where k is the coordinate point number, and At the same time, it is defined that any micro-step point k is located in the trajectory point interval [i-1,i] interval, based on which the coordinates of any micro-step point can be known The calculation formula is as follows:
[0193]
[0194]
[0195]
[0196] The trajectory points and micro-step points are merged to form micro-element time-sharing and micro-step trajectory points. The micro-element time-sharing and micro-step trajectory model contains the relationship between the construction machinery operation trajectory and time.
[0197] In the preferred embodiment, Figures 2-3 As shown, the present invention proposes two calculation indicators, namely, microelement interpenetration and maximum penetration depth, and comprehensively considers the relationship between the number of interpenetrating microelements in the respective layered spaces of construction machinery and information such as spatial hierarchy and spatial distance, and constructs a quantification algorithm for spatiotemporal conflicts of construction machinery, ultimately achieving the quantification of the physical collision accident rate, safety risk rate and efficiency loss rate caused by spatiotemporal conflicts of construction machinery.
[0198] In the preferred scheme, the present invention focuses on analyzing the time and space conflicts during the construction operations of arch dam warehouse surface construction machinery (leveling machines and vibrators), wherein the physical collision accident rate has only two cases, 0 and 100%, and whether the physical space of the layered space of the construction machinery is in contact is used as the basis for judgment. If there is no contact, the value is 0; if there is contact, the value is 100%; the safety risk rate and the efficiency loss rate are calculated based on the two indicators of the microelement interpenetration of the safety space and the efficiency space and the maximum penetration depth.
[0199] In the preferred scheme, the time-space conflict risk rates are calculated separately according to the mutual influence between the construction machinery, and the time-space conflict risk rate of a certain machine to another machine is calculated separately. When there is layered spatial contact between the leveler and the vibrator during the construction process, the safety risk and efficiency loss risk of the leveler are respectively considered as the influence of the vibrator on the leveler. In contrast, the safety risk and efficiency loss risk of the vibrator are the influence of the leveler on the vibrator. At the same time, combined with the safety risk and efficiency loss risk of the mutual influence between the two, considering factors such as movement speed, direction, movement process, etc., a comprehensive weight coefficient is allocated, and the safety risk rate and efficiency loss rate of the leveler and the vibrator at this moment and in this state are recorded as the comprehensive risk rate between the two, and the time-space conflict risk rate is calculated accordingly.
[0200] In the preferred solution, define any time t i The physical space overlap between the flattener and the vibrator is q cs(v)m-p (t i ), with the interpenetration degree of the physical space microelement IntD cs(v)m-p (t i ) represents the physical collision accident rate, when IntD cs(v)m-p (t i )=0, it means that no physical collision accident occurs and the physical collision accident rate is 0; when IntD cs(v)m-p(t i )>0, it means that a physical collision occurs, and the physical collision accident rate is 100%. The physical collision accident rates of the vibrator against the flattener and the flattener against the vibrator can be expressed as:
[0201]
[0202]
[0203] Furthermore, the interpenetration degree IntD of the efficiency space and the safety space can be defined as the ratio of the number of overlapping elements in the efficiency space to the total number of elements in the efficiency space on the contact side, and the ratio of the number of overlapping elements in the safety space to the total number of elements in the safety space on the contact side in the case of layered space contact. In particular, when the layered space contact involves at most two sides, the ratio of the number of overlapping elements to the total number of elements on both sides is used for calculation. Based on this, it can be clearly seen that the liquidator and the vibrator are in a state of contact at any time t i , the respective efficiencies and spatial element interpenetration can be expressed as:
[0204]
[0205]
[0206]
[0207]
[0208] In the formula, q cs(v)m-p (t i ),q csm-e (t i ),q csm-s (t i ),q cvm-e (t i ) and q cvm-s (t i ) are t i When the layers of space are in contact, the number of overlapping micro-elements of the physical space of the closeout machine and the vibrator, the number of overlapping micro-elements of the efficiency space of the closeout machine, the number of overlapping micro-elements of the safety space of the closeout machine, the number of overlapping micro-elements of the efficiency space of the vibrator, and the number of overlapping micro-elements of the safety space of the vibrator. Q csm-p With Q cvm-p , Q csm-e With Q csm-s , Q cvm-e With Q cvm-s They are respectively the total amount of physical space micro-elements of the liquidator and the vibrator, the total amount of efficiency space and safety space micro-elements on the contact side of the stratified space of the liquidator, and the total amount of efficiency space and safety space micro-elements on the contact side of the stratified space of the vibrator.
[0209] In the preferred scheme, the intersecting micro-element area is introduced as a quantitative indicator to calculate the amount of intersecting micro-element. The intersection points are obtained by using the coordinates of the four points of the rectangle projected to the plane and the equation of the straight line formed by the four points, and the total intersecting area is obtained based on this. Further, according to the situation of the intersecting micro-elements entering the layered space, the total intersecting area is decomposed into the area of the intersection of each layered space, and the area of the known unit micro-element is used to solve the amount of intersecting micro-element in each layered space. At the same time, the maximum vertical depth of each layered space can be further obtained by using the coordinates of the intersection points and the intersecting areas of each layered space. According to the size of the outermost layered space of the leveler and the vibrator, it can be inferred that when the outermost rectangular space of the two is projected to the plane, at least one of the vertices of the rectangular intersection boundary formed enters the inside of the other projected rectangle. When calculating the intersection area of the layered space of the projection plane of the leveler and the vibrator, it is necessary to follow the following steps:
[0210] Step 1: Determine whether at least one of the four vertices of the construction machinery layered space projection rectangle enters the inner area of another projection rectangle. If so, it indicates that the projection rectangles intersect;
[0211] Step 2: Determine the vertices that enter each other's projection plane area (generally speaking, if the projection rectangles intersect, at least one vertex enters the projection plane area);
[0212] Step 3: According to the coordinates of the vertex entered, determine the intersection of the two line segments connecting the vertex of the projected rectangle with the line segment on the near side of the other projected rectangle, and solve the coordinates of the intersection point (the intersection point is considered a valid intersection point only if and only if both intersection points are located inside the two intersecting line segments);
[0213] Step 4: According to the polygon area calculation principle, list the vertices and line segment intersections that enter the projection area in sequence, connect one point in the polygon with other points using the subdivision idea, divide the polygon into multiple triangles, calculate the area of each triangle separately, and add them up to get the polygon area.
[0214] Step 5: Repeat the above steps to calculate the overlapping area of the projected rectangles of each layered space.
[0215] The temporal and spatial conflict quantification algorithm for construction machinery on the arch dam surface is characterized in that the intersection points are set in sequence as (x0, y0), (x1, y1), (x2, y2), ..., (x n-1 ,y n-1 ). Based on this, the overlapping area of the intersecting projected rectangles can be obtained, and its expression is:
[0216]
[0217] Among them, the area of the overlapping part of the intersecting projection rectangles may be composed of parts of the three-layered space of physics, safety and efficiency. At this time, the area of the overlapping part of the intersecting projection rectangles can be further expressed as:
[0218] S csm =S csm-e +S csm-s +S csm-p
[0219] S cvm =S cvm-e +S cvm-s +S cvm-p
[0220] In the formula, S csm-e , S csm-s , S csm-p With S cvm-e , S cvm-s , S cvm-p are the efficiency, safety and overlapping area of the physical stratification space of the flattener and vibrator respectively. And when S csm-p With S cvm-p When both exist, it indicates that a physical collision has occurred between the two. At this time, we will not discuss the efficiency and the overlap area and overlap microelement of the projection rectangle of the safety space. We will only calculate and quantify the physical collision accident rate. Usually, S csm-p With S cvm-p If one of the two exists or even none of them exists, we need to discuss and calculate the overlapping area of the projection rectangles of each layered space one by one.
[0221] Since the projected plane area of the unit microelement is a fixed value, it depends on the division size of the unit microelement. When the total area of the overlapping microelement is known, the number of overlapping microelement in each layer of space can be further calculated by dividing the unit microelement area by the overlapping area of the projected rectangle of each layered space. It can be seen that the expression of the number of overlapping microelement in each layer of space is:
[0222]
[0223]
[0224]
[0225]
[0226]
[0227]
[0228] Where q cs(v)m-p ,q csm-s ,q csm-e With qcs(v)m-p ,q cvm-s ,q cvm-e are the numbers of overlapping micro-elements of physics, safety and efficiency of the leveler and vibrator respectively; S0 is the projected plane area of the unit micro-element.
[0229] In the preferred solution, when defining the contact of the layered space, the maximum penetration depths into the efficiency space and the safety space of the liquidation machine are and The maximum penetration depths into the vibrator's efficiency space and safety space are and Definition H csm-e , H csm-s are the depths of the efficiency space and safety space on the contact side of the liquidation machine layered space, H cvm-e , H cvm-s They are the depths of the efficiency space and safety space on the contact side of the vibrator layered space, and both meet the following requirements:
[0230]
[0231]
[0232]
[0233]
[0234] d CSM-e d CSM-s They are the horizontal efficiency and safety distance of the liquidator respectively; d CVM-e d CVM-s are the lateral efficiency and safety distance of the vibrator respectively; l CSM-e , l CSM-s are the longitudinal efficiency and safety distance of the liquidator respectively; l CVM-e , l CVM-s They are longitudinal efficiency and safety distance of vibrator respectively.
[0235] In order to calculate the maximum depth of entry into each other's layered space, it is first necessary to determine the range of the two mechanical layered spaces occupied by the overlapping micro-element, determine the extreme coordinates of the overlapping micro-element in the X and Y axis directions, and the contact points of the plane contact area formed by the overlapping micro-element can be roughly divided into two types. The overlapping area is displayed as a polygon in the plane projection, thus forming the extreme coordinates of multiple points respectively. After determining the overlapping micro-element units of the construction machinery layered space, according to the safety and efficiency space boundary data, the range of entry into the layered space, as well as the maximum and minimum coordinate values of the X-axis coordinates on the contact boundary, and the maximum and minimum coordinate values of the Y-axis coordinates can be determined.
[0236] like Figure 4The figure shows the maximum penetration depth of the safety and efficiency space. (a) shows the contact between efficiency and efficiency space; (b) shows the contact between efficiency and efficiency and safety space; (c) shows the contact between efficiency, safety and efficiency and safety space. Define the straight line edge that occupies a certain mechanical unilateral boundary in the area formed by the overlapping microelement as the reference line; define the maximum distance from any point of the overlapping microelement to the reference line as the maximum penetration depth of the unilateral contact machine; the extreme value coordinates of the X-axis and Y-axis in the overlapping microelement on the boundary after the safety space is projected on the two-dimensional plane are x max-e , x min-e ,y max-e ,y min-e ;x max-s , x min-s ,y max-s ,y min-s The extreme coordinates of entering a mechanical efficiency and safety space are defined as (X min-e ,Y e )、(X min-s ,Y s ), when the extreme value coordinate point is located in the efficiency space, it is necessary to derive the reference straight line equation and calculate the maximum depth value entering the efficiency space; when the extreme value coordinate point is located in the safety space, the maximum depth value entering the efficiency space at this time is the maximum efficiency distance of the contact side, and the maximum depth value entering the safety space needs to be calculated by deriving the straight line equation.
[0237] The single-sided boundary of the contact side is assumed to be located on the vibrator, and the reference straight line plane equations for calculating efficiency and the maximum distance of the safe space are derived as follows:
[0238]
[0239]
[0240] Then the distance from any point in each layer space of the overlapped area to the respective reference straight line is:
[0241]
[0242]
[0243] Where h i-e 、h i-s are the depth values of any point in the overlapping micro-element region from the efficiency space and the safety space, respectively. Based on this, the maximum depth values of the distance from the efficiency space and the safety space of the vibrator can be obtained:
[0244]
[0245]
[0246] Further calculation of the efficiency of the liquidation machine and the maximum depth of the safety space are based on the extreme value coordinate points.
[0247]
[0248]
[0249] In the preferred solution, the safety risk and efficiency loss caused by the space-time conflict of construction machinery at any time is a unique space-time state jointly affected and formed by the conflicting objects. The physical collision accident rate, safety risk rate, and efficiency loss rate of the vibrator against the flattener and the flattener against the vibrator are R csm (t i ) and P cvm (t i ), S csm (t i ) and S cvm (t i )、E csm (t i ) and E cvm (t i ), their respective calculation expressions can be expressed as:
[0250]
[0251]
[0252]
[0253]
[0254]
[0255]
[0256] Considering factors such as movement speed, direction, movement process, etc., the weight coefficient is comprehensively allocated. By analyzing the conflict weight coefficient caused by construction machinery, combined with the calculation of the micro-element interpenetration degree and the maximum interpenetration depth of each layered space, the physical collision accident rate, safety risk rate and efficiency loss rate at any time can be quantified. Based on this, the physical collision accident rate, safety risk rate and efficiency loss rate caused by the space-time conflict between the flattener and the vibrator at any time can be clearly expressed as:
[0257] P(t i )=w csm ·P csm (t i )+w cvm ·P cvm (t i )
[0258] S(t i )=w csm ·S csm (t i )+w cvm ·S cvm (t i )
[0259] E(t i )=w csm ·E csm (t i )+w cvm ·E cvm (t i )
[0260] In the formula, i∈N, P(t i )、S(t i )、E(t i ) are t i The physical collision accident rate, safety risk rate and efficiency loss rate between the time leveler and the vibrator; csm 、w cvm They are the weight coefficients of the leveler and vibrator in the time and space conflicts generated during the construction process. The weight coefficients will be analyzed comprehensively based on multiple factors in actual engineering.
[0261] In the preferred solution, the spatiotemporal conflict states of construction machinery at countless arbitrary moments constitute the spatiotemporal operation characteristics of a specific operation trajectory or time period, and the physical collision accident rate, safety risk and efficiency loss rate caused by the spatiotemporal conflict in this operation trajectory or time period are quantified by the average method based on the physical collision accident rate, safety risk and efficiency loss rate at discrete time points. n During this period, the safety risk and efficiency loss rate of the liquidator and vibrator during any operation trajectory Expressed as:
[0262]
[0263]
[0264]
[0265] Where n∈N, From t0 to t n The physical collision accident rate, safety risk rate and efficiency loss rate between the leveler and vibrator during the time period.
Claims
1. A method for quantifying the time-space conflict of arch dam silo construction machinery, characterized by: The method for quantifying the time-space conflict of arch dam deck construction machinery comprises the following steps: 1) Construct a micro-element model of construction machinery and a time-sharing and step-by-step trajectory model of construction machinery, where: The construction machinery micro-element model is constructed in the following way: 1.1) Determine the three-dimensional dimensions and structure of the warehouse construction machinery; 1.2) Based on the spatial three-dimensional dimensions of the warehouse construction machinery determined in step 1.1), a micro-element model of the construction machinery is constructed; a three-layer hierarchical space of the construction machinery is established, wherein the three-layer hierarchical space of the construction machinery includes a physical space, a safety space, and an efficiency space from the inside out, wherein the physical space is generated by the three-dimensional dimensions of the construction machinery, and the safety space and the efficiency space are formed by the layer-by-layer expansion of the physical space, and the three-layer hierarchical space is divided into regular micro-element units, and the unit volume parameters are 0.1m×0.1m×0.1m, and the micro-element units have spatial coordinate attributes; The construction of the micro-element time-sharing and step-by-step trajectory model of construction machinery requires the selection of an appropriate time step length T step With the spatial step size S step ; The construction method of the construction machinery micro-element time-sharing and step-by-step trajectory model is: a) A certain running track of the warehouse construction machinery is in a uniform speed state. This running track is divided into n segments of equal duration. There are n+1 nodes including the starting point and the end point. Assuming that the running time of this running track is T, then n=T / T step The time step is to divide the operation trajectory of the construction machinery on the warehouse surface based on time, obtain the changes in the operation status of the construction machinery in the evenly divided time period, take the start and end time points of each time period as known points, and obtain the relationship between the operation status and operation time of the construction machinery at each moment; b) Number the n + 1 nodes obtained by equally dividing the operation trajectory by time in sequence, and denote the node coordinates as (X i , Y i , Z i ), where i is the coordinate point number, and 0 < i ≤ n + 1; the nodes are trajectory points, and the known points that reflect the characteristics of the operation trajectory on the silo surface are defined as key trajectory points, and the remaining trajectory points are non - key trajectory points. The relationship between the operating state and the operating time of the construction machinery at the non - key trajectory points is obtained by using the interpolation algorithm; at the same time, it is defined that a non - key trajectory point j is located in the key point interval [l, r], where 0 < l ≤ j ≤ r. The calculation formula for the coordinates (X j , Y j , Z j ) of the non - key trajectory point is as follows: c) Based on the time step, the construction machinery operation trajectory is divided into continuous straight line segment trajectory points, and its spatial state change process is also divided accordingly. step , the running track between adjacent track points is divided again to establish a regular micro-element time-sharing and step-by-step running track. The specific implementation method of establishing a regular micro-element time-sharing and step-by-step running track in step c) is: c.1) According to the coordinates of the adjacent (i-1) and i trajectory points, calculate the adjacent step difference between the adjacent trajectory points in the (i-1) time period That is, the distance between adjacent trajectory points is projected in the X, Y and Z directions; The calculation formula of the adjacent step difference of adjacent trajectory points is as follows: c.2) Calculate the number of microsteps in the X, Y, and Z directions based on the adjacent step difference and spatial step length, and introduce the maximum adjacent step difference of adjacent trajectory points Pick is the number of microsteps, which is the projection of the distance between adjacent trajectory points in the X, Y and Z directions in units of spatial step length; The maximum step difference between adjacent trajectory points The calculation formula is: Microstep lengths between adjacent trajectory points in the X, Y, and Z directions The calculations are as follows: c.3) Sequentially divide the space between trajectory point i-1 and trajectory point i into equal steps The micro-step points are numbered and their coordinates are recorded as Where k is the coordinate point number, and At the same time, define any micro-step point k to be within the trajectory point interval [i-1, i], and get the coordinates of any micro-step point The calculation formula is as follows: c.4) The trajectory points and micro-step points are combined to form micro-element time-sharing and micro-stepping trajectory points. The micro-element time-sharing and micro-stepping trajectory model contains the relationship between the construction machinery operation trajectory and time; 2) Based on step 1), a method for quantifying the time-space conflict risk rate of construction machinery is constructed, wherein the time-space conflict risk rate is the product of the micro-element interpenetration and the maximum penetration depth; the micro-element interpenetration is the severity of the accident loss, and the ratio of the maximum penetration depth to the safety distance or the efficiency distance is the probability of time-space conflict; the time-space conflict risk rate includes the physical collision accident rate, the safety risk rate and the efficiency loss rate; The physical collision accident rate is determined based on whether the physical spaces in the construction machinery layered space are in contact. When the physical spaces in the construction machinery layered space are not in contact, the physical collision accident rate is 0; when the physical spaces in the construction machinery layered space are in contact, the physical collision accident rate is 100%; The safety risk rate and efficiency loss rate are calculated based on two indicators: the micro-element interpenetration degree of the safety space and the efficiency space and the maximum penetration depth; 3) Based on step 2), a quantitative method for the physical collision accident rate, safety risk rate and efficiency loss rate caused by spatiotemporal conflicts between construction machines at any time point, any time period or within the operation trajectory is constructed in sequence.
2. The method for quantifying the time-space conflict of arch dam deck construction machinery according to claim 1 is characterized by: The calculation method of the microelement interpenetration in step 2) is: a) Obtain the overlapping area of the intersecting projected rectangles. The specific implementation method is: based on the outermost layered space size of the flattener and the vibrator, it is inferred that when the outermost cuboid space of the flattener and the vibrator is projected onto the plane, at least one of the intersecting boundary vertices of the rectangles formed enters the interior of another projected rectangle; when calculating the intersection area of the layered space of the projection plane of the flattener and the vibrator, the intersection points are set as (x0, y0), (x1, y1), (x2, y2), ..., (x n-1 ,y n-1 );Get the overlapping area of the intersecting projection rectangles. The expression of the overlapping area of the intersecting projection rectangles is: in: The expression for the area of the overlapping part of the intersecting projected rectangles is: S csm =S csm-e +S csm-s +S csm-p S cvm =S cvm-e +S cvm-s +S cvm-p Where: The S csm is the area of the overlapping part of the intersecting projections of the liquidation machine; The S cvm is the area of the overlapping parts of the intersecting projections of the vibrators; The S csm-e is the area of the overlapped part of the efficiency space of the liquidation machine; The S csm-s The area of the overlapped part of the safety space of the liquidation machine; The S csm-p is the area of the overlapping part of the physical space of the liquidation machine; The S cvm-e is the area of the overlapped part of the efficiency space of the vibrator; The S cvm-s The area of the overlapped part of the safety space of the vibrator; The S cvm-p The area of the overlapped part of the physical space of the vibrator; And when S csm-p With S cvm-p When both exist, it indicates that the leveler and vibrator have physically collided; b) Obtaining the number of overlapping micro-elements in each layer of space according to the overlapping area of the intersecting projection rectangles, wherein the number of overlapping micro-elements in each layer of space is the quotient of the overlapping area of the intersecting projection rectangles and the projection plane area of the unit micro-element; the expression of the number of overlapping micro-elements in each layer of space is: in: The q csm-p The number of micro-elements of physical space overlap of the liquidation machine; The q csm-s The number of micro-elements of the safety space overlap of the liquidation machine; The q csm-e is the number of overlapping micro-elements in the liquidation machine efficiency space; The q cvm-p is the number of overlapping micro-elements in the physical space of the vibrator; The q cvm-s is the number of overlapping micro-elements of the safety space of the vibrator; The q cvm-e is the number of overlapping micro-elements of the efficiency space of the vibrator; S0 is the projected plane area of the unit microelement; The h cvm is the depth of the contact side of the vibrator layer space; c) obtaining the micro-element interpenetration according to the number of overlapping micro-elements in each layer of space; the micro-element interpenetration includes the micro-element interpenetration of physical space, the micro-element interpenetration of efficiency space and the micro-element interpenetration of safety space; The physical space micro-element interpenetration includes the physical space micro-element interpenetration of the vibrator to the warehouse closing machine and the physical space micro-element interpenetration of the warehouse closing machine to the vibrator; the expressions of the physical space micro-element interpenetration of the vibrator to the warehouse closing machine and the physical space micro-element interpenetration of the warehouse closing machine to the vibrator are respectively: in: q cs(v)m-p (t i ) is t i When the layers of space are in contact, the physical space of the flattener and the vibrator overlaps by a microelement; The Q csm-p is the total amount of micro-element of the physical space of the liquidation machine; The Q cvm-p is the total amount of micro-element of the physical space of the vibrator; The physical space microelement interpenetration degree IntD cs(v)m-p (t i ) represents the physical collision accident rate, when IntD cs(v)m-p (t i )=0, no physical collision accident occurs, and the physical collision accident rate is 0; when IntD cs(v)m-p (t i )>0, a physical collision occurs, and the physical collision accident rate is 100%; The efficiency space micro-element interpenetration is the ratio of the number of overlapping micro-elements in the efficiency space to the total number of micro-elements in the efficiency space on the contact side; The safety space micro-element interpenetration is the ratio of the number of overlapping micro-elements in the safety space to the total number of micro-elements in the safety space on the contact side; At any time t i The efficiency space micro-element interpenetration and safety space micro-element interpenetration of the flattener and vibrator are expressed as: in: The q csm-e (t i ) is t i When the layers of space touch each other, the number of micro-elements of the liquidation machine efficiency space overlap; The q csm-s (t i ) is t i When the layers of space touch each other, the number of micro-elements of the safe space of the liquidation machine overlaps; The q cvm-e (t i ) is t i When the layers of space are in contact, the number of micro-elements of the vibrator efficiency space overlap; The q cvm-s (t i ) is t i When the layers of space are in contact, the number of micro-elements of the vibrator safety space overlap; The Q csm-e It is the total amount of efficiency space microelement on one side of the stratified space contact of the liquidation machine; The Q csm-s The total amount of micro-element of the safe space on one side of the liquidation machine's layered space contact; The Q cvm-e The total amount of efficiency space micro-element on the contact side of the vibrator layered space; The Q cvm-s It is the total amount of safe space micro-element on the contact side of the vibrator's layered space.
3. The method for quantifying the time-space conflict of arch dam deck construction machinery according to claim 2 is characterized by: The maximum penetration depth in step 2) is calculated as follows: When defining the layered space contact, the maximum penetration depths into the efficiency space and safety space of the liquidator are and The maximum penetration depths into the vibrator's efficiency space and safety space are and Definition H csm-e , H csm-s are the depths of the efficiency space and safety space on the contact side of the liquidation machine layered space, H cvm-e , H cvm-s They are the depths of the efficiency space and safety space on the contact side of the vibrator layered space, and both meet the following requirements: The d CSM-e is the horizontal efficiency distance of the liquidator; The d CSM-s It is the horizontal safety distance of the liquidation machine; The d CVM-e is the lateral efficiency distance of the vibrator; The d CVM-s It is the lateral safety distance of the vibrator; The l CSM-e is the longitudinal efficiency distance of the liquidator; The l CSM-s It is the longitudinal safety distance of the liquidation machine; The l CVM-e is the longitudinal efficiency distance of the vibrator; The l CVM-s It is the longitudinal safety distance of the vibrator; Define the straight line edge occupying a certain mechanical unilateral boundary in the overlapping microelement formation area as the reference line; define the maximum distance from any point of the overlapping microelement to the reference line as the maximum penetration depth of the unilateral contact machine; the X-axis and Y-axis extreme value coordinates of the overlapping microelement on the boundary after the safety space is projected on the two-dimensional plane are x max-e , x min-e ,y max-e ,y min-e ;x max-s , x min-s ,y max-s ,y min-s ; Define the extreme value coordinates of entering a certain mechanical efficiency and safety space as (X min-e , Y e )、(X min-s , Y s ), when the extreme value coordinate point is located in the efficiency space, it is necessary to derive the reference straight line equation and calculate the maximum depth value entering the efficiency space; when the extreme value coordinate point is located in the safety space, the maximum depth value entering the efficiency space at this time is the maximum efficiency distance of the contact side, and the maximum depth value entering the safety space needs to be calculated by deriving the straight line equation; The single-sided boundary of the contact side is assumed to be located on the vibrator, and the reference straight line plane equations for calculating efficiency and the maximum distance of the safe space are derived as follows: Then the distance from any point in each layer space of the overlapped area to the respective reference straight line is: Where x i-e ,y i-e 、x i-s ,y i-s They are the coordinates of any point in the overlapping micro-element region from the efficiency space and the safety space; h i-e 、h i-s are the depth values of any point in the overlapping micro-element area from the efficiency space and the safety space, respectively. Based on this, the maximum penetration depths into the efficiency space and safety space of the vibrator are obtained as follows: Calculate the maximum penetration depth into the efficiency space and safety space of the liquidation machine based on the extreme value coordinate points; 4. The method for quantifying the time-space conflict of arch dam deck construction machinery according to claim 3 is characterized by: In the step 3), at any time point between the construction machines, the physical collision accident rate, safety risk rate, and efficiency loss rate of the vibrator against the flattener and the flattener against the vibrator are P respectively. csm (t i ) and P cvm (t i ), S csm (t i ) and S cvm (t i )、E csm (t i ) and E cvm (t i ), their respective calculation expressions are expressed as:
5. The method for quantifying the time-space conflict of arch dam deck construction machinery according to claim 4 is characterized by: In the step 3), at any time point between the construction machines, taking into account the movement speed, movement direction and movement process, combined with the distribution weight coefficient, the expression of the physical collision accident rate, safety risk rate and efficiency loss rate caused by the space-time conflict between the leveler and the vibrator at any time is: P(t i )=w csm ·P csm (t i )+w cvm ·P cvm (t i ) S(t i )=w csm ·S csm (t i )+w cvm ·S cvm (t i ) E(t i )=w csm ·E csm (t i )+w cvm ·E cvm (t i ) Where: i∈N; P(t i ) is t i The accident rate of physical collision between the time leveler and the vibrator; S(t i ) is t i The safety risk ratio between the time-settler and the vibrator; E(t i ) is t i The efficiency loss rate between the time leveler and the vibrator; w csm is the weight coefficient of the liquidation machine in the time-space conflict generated during the construction process; w cvm is the weight coefficient of the vibrator in the time-space conflict generated during the construction process; P csm (t i ) is the accident rate of physical collision of vibrator with the leveler; P cvm (t i ) is the accident rate of physical collision of the leveler with the vibrator; S csm (t i ) is the safety risk ratio of the vibrator to the flattener; S cvm (t i ) is the safety risk ratio of the liquidator to the vibrator; E csm (t i ) is the efficiency loss rate of the vibrator to the flattener; E cvm (t i ) is the efficiency loss rate of the leveler to the vibrator.
6. The method for quantifying the time-space conflict of arch dam deck construction machinery according to claim 5 is characterized by: In step 3), the expression of the quantification method of the physical collision accident rate, safety risk rate and efficiency loss rate caused by the time-space conflict between construction machines in any time period or operation trajectory route is: in: Said is t1 to t n+1 The accident rate of physical collision between the trimmer and the vibrator during any running trajectory of the trimmer and the vibrator during this period; Said is t1 to t n+1 The safety risk rate between the flattening machine and the vibrating machine during any running trajectory of the flattening machine and the vibrating machine during this period; Said is t1 to t n+1 The efficiency loss rate between the flattener and the vibrator during any running trajectory of the flattener and the vibrator during this period; The P(t i ) is t i The accident rate of physical collision between the time leveler and the vibrator; The S(t i ) is t i The safety risk ratio between the time-settler and the vibrator; The E(t i ) is t i The efficiency loss rate between the time leveler and the vibrator; Said n∈N.
Citation Information
Patent Citations
Warehouse surface construction space-time conflict quantitative calculation method based on time product elements
CN111079339A
Safety distance calculation method considering safe and efficient space for warehouse surface construction machine
CN111915588A