Intelligent compensation method and system for crane main beam camber deformation

Through intelligent compensation methods and systems, laser rangefinder and gyroscope are used to calculate the compensation value of the cable length, which solves the positioning error problem caused by the changes in the main beam of the bridge gantry crane, improves the accuracy and stability of the goods, and ensures that Crane safety.

CN118373330BActive Publication Date: 2024-11-08EUROCRANE (CHINA) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410818324.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-24
Publication Date
2024-11-08
Estimated Expiration
2044-06-24

AI Technical Summary

Technical Problem

The existing measurement methods for measuring the arcuate change of the main beam of the bridge gantry crane have large errors, resulting in low positioning accuracy of the load-bearing trolley, which may lead to position deviation and instability of the cargo during lifting, increasing safety hazards.

Method used

Using intelligent compensation methods and systems, by obtaining the mass and target position data of lifting goods, combining laser rangefinder and gyroscope, the horizontal distance compensation value of the bearing trolley and the length compensation value of the lifting trolley are calculated, and the length of the lifting cable is adjusted to maintain the Cargo balanced and precise movement.

Benefits of technology

It improves the positioning accuracy and operation stability of lifting goods, ensures the balance and safety of goods at the target position, and avoids safety hazards caused by imbalance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118373330B_ABST
    Figure CN118373330B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of crane operation compensation, and specifically discloses an intelligent compensation method and system for the deformation of the arch of a crane main beam, including: obtaining the mass value of the lifted cargo and marking it; comparing it with the load threshold of the crane main beam to obtain a light load signal; obtaining the lifting target position data of the lifted cargo; comparing the lifting target height value with the lifting height threshold, and at the same time comparing the lifting horizontal distance value with the lifting span threshold of the crane; obtaining a lifting signal; obtaining the driving positioning data of the load-bearing trolley on the crane main beam during the movement of the load-bearing trolley on the crane main beam; calculating and obtaining the horizontal distance compensation value of the load-bearing trolley for the deformation of the arch of the crane main beam, the near-hook lifting cable compensation value and the far-hook lifting cable compensation value, thereby ensuring the accuracy of the moving target of the lifted cargo, and further ensuring the stability of picking and placing the lifted cargo after it moves to the target position.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of crane operation compensation, and in particular to an intelligent compensation method and system for camber deformation of a crane main beam. Background Art

[0002] In order to ensure the safety of lifting goods by gantry cranes, the crane main beam is designed with a preset camber. When the main beam is loaded, the camber will decrease. This change in camber will interfere with the positioning of the crane and the lifting.

[0003] Existing methods for measuring the change in the camber of the main beam of a gantry crane include: connecting vessels, levels, and wire drawing measurement methods. However, the above measurement methods are affected by many factors such as instruments and environment, and there is a large measurement error between the measured value and the true value. At present, the positioning detection and calculation only use a linear encoder to reduce the measurement error of the main beam camber on the position of the trolley, and there is no compensation for the lifting height, nor for the measurement error of the linear encoder itself, which limits the positioning accuracy of the trolley and the lifting. When the positioning accuracy of the trolley is inaccurate, it is easy to cause position deviation of the lifted goods during the process of picking and placing, which may cause unstable placement.

[0004] In addition, some load-bearing trolleys use double-hook lifting cables to lift the cargo. During the lifting operation, due to the deformation of the arch of the crane main beam, the lifted cargo is prone to imbalance, resulting in unstable movement of the cargo and causing safety hazards.

[0005] Therefore, we propose an intelligent compensation method and system for the camber deformation of the crane main beam to improve the positioning accuracy and operation stability of the load-bearing trolley. Summary of the invention

[0006] The object of the present invention is to provide a method and system for intelligently compensating for camber deformation of a crane main beam, so as to solve the above-mentioned problems.

[0007] The purpose of the present invention can be achieved through the following technical solutions:

[0008] An intelligent compensation method for crane main beam camber deformation, comprising:

[0009] Obtain the mass value of the lifted cargo and mark it as Wm; compare it with the crane main beam load threshold LM to obtain a light load signal;

[0010] Based on the light load signal, the lifting target position data of the lifting cargo is obtained, including the lifting target height value MH and the lifting horizontal distance value MP;

[0011] Compare the lifting target height value MH with the lifting height threshold HG, and compare the lifting horizontal distance value MP with the lifting span threshold HK of the crane; obtain a lifting signal;

[0012] Determine the lifting horizontal distance value MP is between [0, ]or( , HK]; and then generate a lifting compensation signal; obtain the driving positioning data of the carrying trolley on the crane main beam during the movement of the carrying trolley on the crane main beam;

[0013] The horizontal distance compensation value of the load-bearing trolley, the compensation value of the near-hook lifting cable and the compensation value of the far-hook lifting cable for the camber deformation of the crane main beam are calculated.

[0014] As a further solution of the present invention: if the mass value Wm of the lifted cargo is less than or equal to the load threshold value LM of the crane main beam; a light load signal is obtained;

[0015] If the mass value Wm of the lifted cargo is greater than the load threshold LM of the crane main beam, an overload signal is obtained and an overload warning prompt is issued.

[0016] As a further solution of the present invention: if the lifting target height value MH is less than or equal to the lifting height threshold HG and the lifting horizontal distance value MP is less than or equal to the lifting span threshold HK of the crane; a lifting signal is generated;

[0017] Otherwise, an out-of-range signal is generated.

[0018] As a further solution of the present invention: if the lifting horizontal distance value MP is in [0, ], a left hoisting compensation signal is generated;

[0019] If the lifting horizontal distance value MP is at ( , HK], a right lifting compensation signal is generated.

[0020] As a further solution of the present invention: the lifting compensation signal includes a left lifting compensation signal and a right lifting compensation signal.

[0021] As a further solution of the present invention: if the lifting compensation signal is a left lifting compensation signal, the lifting horizontal distance value MP is calculated based on the laser distance measurement value cn and the inclination angle θn of the load-bearing trolley in the driving positioning data;

[0022] And then through The horizontal distance compensation value SBCn of the load-bearing trolley caused by the camber deformation of the crane main beam can be calculated.

[0023] As a further solution of the present invention: based on the lifting compensation signal, Calculate the compensation value JBCn of the near hook lifting cable, through Calculate and obtain the far hook lifting cable compensation value YBCn.

[0024] As a further solution of the present invention: if the lifting compensation signal is a right lifting compensation signal, the lifting horizontal distance value MP is calculated based on the laser distance measurement value cm and the inclination angle θm of the carrying trolley in the driving positioning data;

[0025] pass The horizontal distance compensation value SBCm of the load-bearing trolley caused by the camber deformation of the crane main beam can be calculated.

[0026] As a further solution of the present invention: if the lifting compensation signal is a right lifting compensation signal, the rope distance value SJ between the lifting cables on the load-bearing trolley is obtained;

[0027] pass Calculate the compensation value JBCm of the near hook lifting cable, through Calculate and obtain the far hook lifting cable compensation value YBCm.

[0028] An intelligent compensation system for crane main beam camber deformation, comprising:

[0029] Data acquisition module: The data acquisition module is used to obtain the mass value of the lifted cargo and mark it as Wm; and compare it with the load threshold LM of the crane main beam to obtain a light load signal;

[0030] Based on the light load signal, the lifting target position data of the lifting cargo is obtained, including the lifting target height value MH and the lifting horizontal distance value MP;

[0031] Data processing module: The data processing module is used to compare the lifting target height value MH with the lifting height threshold HG, and compare the lifting horizontal distance value MP with the lifting span threshold HK of the crane; and obtain a lifting signal;

[0032] Determination module: The determination module is used to determine whether the lifting horizontal distance value MP is between [0, ]or( , HK]; and then generate a lifting compensation signal; obtain the driving positioning data of the carrying trolley on the crane main beam during the movement of the carrying trolley on the crane main beam;

[0033] Compensation calculation module: The compensation calculation module is used to calculate the horizontal distance compensation value of the load-bearing trolley, the near-hook lifting cable compensation value and the far-hook lifting cable compensation value of the crane main beam camber deformation.

[0034] Beneficial effects of the present invention:

[0035] In the present invention, by acquiring the lifting target position data of the lifted cargo, and then measuring the position information of the load-bearing trolley on the crane main beam through a laser rangefinder and a gyroscope, the compensation value of the horizontal moving distance position of the load-bearing trolley lifting the cargo and the length compensation value of the lifting cable in the lifting height are further calculated, so that the lifted cargo can maintain a balanced and stable state and move to the target position more accurately, thereby ensuring the accuracy of the lifting cargo moving target and further ensuring the stability of picking and placing the lifted cargo after it moves to the target position;

[0036] In the present invention, during the operation of the load-bearing trolley, the load-bearing trolley lifts the lifted cargo together through the near-hook lifting cable and the far-hook lifting cable. When the load-bearing trolley moves, the near-hook lifting cable and the far-hook lifting cable change with the laser ranging value and the inclination angle of the load-bearing trolley, and the length of the lifting cable is also adjusted automatically, so that during the operation of the load-bearing trolley, the lifted cargo is in a balanced state, ensuring the balance of the lifted cargo, further ensuring the safety of lifting, and effectively ensuring the smooth operation of the lifted cargo, further ensuring the stability of the entire crane main beam, the load-bearing trolley and other structures, and avoiding the safety hazards caused by the imbalance of the lifted cargo. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] The present invention will be further described below in conjunction with the accompanying drawings.

[0038] Figure 1 It is a schematic diagram of the working method of the present invention;

[0039] Figure 2 is a system block diagram of the present invention;

[0040] Figure 3 It is a schematic diagram of the crane main beam structure in the present invention. DETAILED DESCRIPTION

[0041] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Embodiment 1

[0042] See also Figure 1 and Figure 3 As shown, the present invention is an intelligent compensation method for crane main beam camber deformation, comprising:

[0043] Step 001: Get the mass value of the lifted cargo and mark it as Wm;

[0044] Compare the mass value Wm of the lifted cargo with the load threshold LM of the crane main beam;

[0045] If the mass value Wm of the lifted cargo is less than or equal to the load threshold LM of the crane main beam, a light load signal is obtained;

[0046] If the mass value Wm of the lifted cargo is greater than the load threshold LM of the crane main beam, an overload signal is obtained;

[0047] Step 002: Based on the overload signal, an overload warning is issued to remind the staff that the mass of the overloaded lifting cargo exceeds the maximum load-bearing capacity of the crane main beam;

[0048] Based on the light load signal, the lifting target position data of the lifting cargo is obtained, including the lifting target height value MH and the lifting horizontal distance value MP;

[0049] The lifting target height value MH refers to the height value of the lifting target position of the lifting cargo from the horizontal plane, and the lifting horizontal distance value MP refers to the horizontal distance value of the lifting target position of the lifting cargo from the ranging reflector;

[0050] Step 003: Acquire mechanical data of the crane main beam; the mechanical data includes a lifting height threshold and a lifting span threshold of the crane, which are marked as HG and HK respectively; wherein the lifting height threshold HG is the highest lifting value of the crane, and the lifting span threshold HK is the maximum value of the horizontal distance of the crane from the ranging reflector;

[0051] The lifting target height value MH is compared with the lifting height threshold value HG, and the lifting horizontal distance value MP is compared with the lifting span threshold value HK of the crane;

[0052] If the lifting target height value MH is less than or equal to the lifting height threshold HG and the lifting horizontal distance value MP is less than or equal to the lifting span threshold HK of the crane; a lifting signal is generated;

[0053] Otherwise, an over-distance signal is generated; a target over-distance information is generated, indicating that the target position data of the lifted cargo exceeds the lifting range of the crane, that is, the target position data is wrong, and a prompt is given to the staff to reposition the target position data of the lifted cargo;

[0054] Step 004: Based on the lifting signal, determine whether the lifting horizontal distance value MP is between [0, ]or( , HK]; and then generating a lifting compensation signal; wherein the lifting compensation signal includes a left lifting compensation signal and a right lifting compensation signal;

[0055] If the lifting horizontal distance value MP is at [0, ], a left hoisting compensation signal is generated;

[0056] If the lifting horizontal distance value MP is at ( , HK], a right hoisting compensation signal is generated;

[0057] Step 005: Lift the load by lifting the double hooks under the load-carrying trolley; after lifting the load, the load-carrying trolley moves on the main beam of the crane;

[0058] When the trolley moves on the crane main beam, the driving positioning data of the trolley on the crane main beam is obtained, wherein the driving positioning data includes the distance between the laser and the ranging reflector measured by the laser rangefinder on the trolley, that is, the laser ranging value, and is marked as c; and also includes the tilt angle of the trolley measured by the gyroscope in the trolley, that is, the tilt angle θ of the trolley;

[0059] Obtain the double-hook lifting data of the transport mechanism in the load-bearing trolley; wherein, the double-hook lifting data includes the length value of the near-hook lifting cable and the length value of the far-hook lifting cable, which are marked as JSC and YSC respectively. Specifically, the length value of the near-hook lifting cable is the release length value of the lifting cable near the ranging reflector on the load-bearing trolley; the length value of the far-hook lifting cable is the release length value of the lifting cable far from the ranging reflector on the load-bearing trolley;

[0060] Obtain the rope distance value SJ between the near hook lifting cable and the far hook lifting cable on the carrying trolley;

[0061] Step 006: If the lifting compensation signal is a left lifting compensation signal, the laser distance measurement value is cn, the inclination angle of the trolley is θn, the near hook lifting cable compensation value is JBCn, and the far hook lifting cable compensation value is YBCn;

[0062] Based on the laser distance measurement value cn in the driving positioning data and the inclination angle θn of the load-bearing trolley, the lifting horizontal distance value MP is calculated; it should be noted that ;

[0063] And then through Then the horizontal distance compensation value SBCn of the trolley for the crane main beam camber deformation can be calculated;

[0064] pass Calculate the compensation value JBCn of the near hook lifting cable, through Calculate and obtain the far hook lifting cable compensation value YBCn;

[0065] Step 007: If the lifting compensation signal is a right lifting compensation signal, the laser distance measurement value is cm, the inclination angle of the trolley is θm, the near hook lifting cable compensation value is JBCm, and the far hook lifting cable compensation value is YBCm;

[0066] Based on the laser distance measurement value cm and the inclination angle θm of the load-bearing trolley in the driving positioning data, the lifting horizontal distance value MP is obtained; it should be noted that, ;

[0067] And then through Then the horizontal distance compensation value SBCm of the trolley for the crane main beam camber deformation can be calculated;

[0068] pass Calculate the compensation value JBCm of the near hook lifting cable, through Calculate and obtain the far hook lifting cable compensation value YBCm;

[0069] The position information of the trolley on the crane main beam is measured by the laser rangefinder and the gyroscope, and the compensation value of the horizontal movement distance of the goods lifted by the trolley and the length compensation value of the lifting cable in the lifting height are further calculated, so that the lifted goods can maintain a balanced and stable state and move to the target position more accurately, ensuring the accuracy of the moving target of the lifted goods;

[0070] It should be noted that the above-mentioned horizontal distance compensation value of the load-bearing trolley, the compensation value of the near hook lifting cable and the compensation value of the far hook lifting cable are all greater than zero;

[0071] During the operation of the trolley, the trolley lifts the cargo through the near hook lifting cable and the far hook lifting cable. When the trolley moves, the near hook lifting cable and the far hook lifting cable change with the laser ranging value and the inclination angle of the trolley, and the length of the lifting cable is automatically adjusted, so that the cargo is in a balanced state during the operation of the trolley, ensuring the balance of the cargo, further ensuring the safety of the lifting, and effectively ensuring the smooth operation of the cargo, further ensuring the stability of the entire crane main beam and the trolley structure, and avoiding the potential safety hazards caused by the imbalance of the cargo.

[0072] By acquiring the lifting target position data of the lifted cargo, and then measuring the position information of the load-bearing trolley on the main beam of the crane through a laser rangefinder and a gyroscope, the compensation value of the horizontal moving distance position of the load-bearing trolley lifting the cargo and the length compensation value of the lifting cable at the lifting height are further calculated, so that the lifted cargo can maintain a balanced and stable state and move to the target position more accurately, ensuring the accuracy of the lifting cargo's moving target, and further ensuring the stability of picking and placing the lifted cargo after it moves to the target position. Embodiment 2

[0073] Based on the above embodiment, when the load-bearing trolley moves on the main beam of the crane, the body of the load-bearing trolley is in a non-horizontal state; therefore, when the load-bearing trolley is moving, the length value JSC of the near-hook lifting cable and the length value YSC of the far-hook lifting cable above it need to be adjusted according to the movement of the load-bearing trolley to ensure that the lifted cargo is always in a balanced state during the movement of the load-bearing trolley, and to ensure the stability of the lifted cargo during movement; to avoid the situation in which the lifted cargo is unbalanced and causes unstable operation during the movement of the load-bearing trolley, and to avoid the risk of the lifted cargo shaking and sliding;

[0074] Specifically: This embodiment is about lifting cargo during the lifting process;

[0075] If the lifting compensation signal is the left lifting compensation signal;

[0076] Obtain the laser ranging value ct and the tilt angle θt of the carrying vehicle in the driving positioning data at the driving time t during the driving process;

[0077] At this time, the calculation method of the compensation value JBCt of the near hook lifting cable is: ;

[0078] The calculation method of the far hook lifting cable compensation value YBCt is: ;

[0079] Based on the near hook lifting cable compensation value JBCt and the far hook lifting cable compensation value YBCt; we can get:

[0080] The length of the cable near the hook is JSCt and the length of the cable far from the hook is YSCt; ; ;

[0081] That is, during the operation of the load-bearing trolley, the load-bearing trolley lifts the lifted cargo together through the near-hook lifting cable and the far-hook lifting cable. When the load-bearing trolley moves, the near-hook lifting cable and the far-hook lifting cable change with the laser ranging value ct and the inclination angle θt of the load-bearing trolley, and the length of the lifting cable is also adjusted automatically, so that during the operation of the load-bearing trolley, the lifted cargo is in a balanced state, thereby ensuring the balance of the lifted cargo and further ensuring the safety of lifting. Embodiment 3

[0082] Based on the above embodiment 2, further, if the lifting compensation signal is a right lifting compensation signal;

[0083] The first half of the operation of the load-carrying trolley is the operation state in the second embodiment, that is, the travel from the distance measuring reflector on the crane main beam to the center of the main beam. In the first half of the operation state, the length value of the far hook lifting cable YSCt is greater than the length value of the near hook lifting cable JSCt; when the load-carrying trolley runs to the middle of the main beam, the length value of the far hook lifting cable YSCt is equal to the length value of the near hook lifting cable JSCt;

[0084] In the second half of the operation, the length of the far hook lifting cable YSCt is less than the length of the near hook lifting cable JSCt; at this time, the calculation method of the near hook lifting cable compensation value JBCt is: ; The calculation method of the far hook lifting cable compensation value YBCt is: ;

[0085] At this time, the length of the near hook lifting cable JSCt and the length of the far hook lifting cable YSCt can be obtained; among them, ; ;

[0086] That is, during the operation of the load-carrying trolley, when the load-carrying trolley moves on the left side of the crane main beam, the changes of the length value JSCt of the near hook lifting cable and the length value YSCt of the far hook lifting cable are as in the second embodiment, and when the load-carrying trolley moves to the right side of the crane main beam, the changes of the length value JSCt of the near hook lifting cable and the length value YSCt of the far hook lifting cable are as in the length change calculation formula in this embodiment;

[0087] It should be noted that, regardless of embodiment 2 or embodiment 1, the compensation value of the near-hook lifting cable and the compensation value of the far-hook lifting cable are both values ​​greater than zero; so that during the operation of the carrying trolley, the length value of the far-hook lifting cable and the length value of the near-hook lifting cable can both be translated to meet the state that the lifted goods are at the target height value, and effectively ensure the smooth operation of the lifted goods, further ensure the stability of the entire crane main beam, the carrying trolley and other structures, and avoid safety hazards caused by unbalanced lifting of goods. Embodiment 4

[0088] Reference Figure 2 As shown, the present invention is an intelligent compensation system for the deformation of the crane main beam camber, comprising: a data acquisition module: the data acquisition module is used to obtain the mass value of the lifted cargo and mark it as Wm; and compare it with the load threshold LM of the crane main beam to obtain a light load signal;

[0089] Based on the light load signal, the lifting target position data of the lifting cargo is obtained, including the lifting target height value MH and the lifting horizontal distance value MP;

[0090] Data processing module: The data processing module is used to compare the lifting target height value MH with the lifting height threshold HG, and compare the lifting horizontal distance value MP with the lifting span threshold HK of the crane; and obtain a lifting signal;

[0091] Determination module: The determination module is used to determine whether the lifting horizontal distance value MP is between [0, ]or( , HK]; and then generate a lifting compensation signal; obtain the driving positioning data of the carrying trolley on the crane main beam during the movement of the carrying trolley on the crane main beam;

[0092] Compensation calculation module: The compensation calculation module is used to calculate the horizontal distance compensation value of the load-bearing trolley for the deformation of the crane main beam camber;

[0093] By acquiring the lifting target position data of the lifted cargo, and then measuring the position information of the load-bearing trolley on the crane main beam through the laser rangefinder and the gyroscope, the compensation value of the horizontal moving distance position of the load-bearing trolley lifting cargo and the length compensation value of the lifting cable in the lifting height are further calculated, so that the lifted cargo can maintain a balanced and stable state and move to the target position more accurately, ensuring the accuracy of the lifting cargo moving target, and further ensuring the stability of picking and placing the lifted cargo after it moves to the target position;

[0094] In the present invention, during the operation of the load-bearing trolley, the load-bearing trolley lifts the lifted cargo together through the near-hook lifting cable and the far-hook lifting cable. When the load-bearing trolley moves, the near-hook lifting cable and the far-hook lifting cable change with the laser ranging value and the inclination angle of the load-bearing trolley, and the length of the lifting cable is also adjusted automatically, so that during the operation of the load-bearing trolley, the lifted cargo is in a balanced state, ensuring the balance of the lifted cargo, further ensuring the safety of lifting, and effectively ensuring the smooth operation of the lifted cargo, further ensuring the stability of the entire crane main beam, the load-bearing trolley and other structures, and avoiding the safety hazards caused by the imbalance of the lifted cargo.

[0095] The above is a detailed description of an embodiment of the present invention, but the content is only a preferred embodiment of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.

Claims

1. An intelligent compensation method for crane main beam camber deformation, characterized in that: include: Get the mass value of the lifted cargo and mark it as Wm; And compare it with the crane main beam load threshold LM; If the mass value Wm of the lifted cargo is less than or equal to the load threshold LM of the crane main beam, a light load signal is obtained; If the mass value Wm of the hoisted cargo is greater than the load threshold LM of the crane main beam, an overload signal is obtained and an overload warning is issued; Based on the light load signal, the lifting target position data of the lifting cargo is obtained, including the lifting target height value MH and the lifting horizontal distance value MP; The lifting target height value MH is compared with the lifting height threshold value HG, and the lifting horizontal distance value MP is compared with the lifting span threshold value HK of the crane; If the lifting target height value MH is less than or equal to the lifting height threshold HG and the lifting horizontal distance value MP is less than or equal to the lifting span threshold HK of the crane; a lifting signal is generated; Otherwise, an over-range signal is generated; Determine the lifting horizontal distance value MP is between [0, ]or( , HK]; If the lifting horizontal distance value MP is at [0, ], a left hoisting compensation signal is generated; If the lifting horizontal distance value MP is at ( , HK], a right hoisting compensation signal is generated; Acquire the driving positioning data of the trolley on the crane main beam during the movement of the trolley on the crane main beam; Calculate and obtain the horizontal distance compensation value of the trolley, the near hook lifting cable compensation value and the far hook lifting cable compensation value of the crane main beam camber deformation; If the lifting compensation signal is a left lifting compensation signal, the lifting horizontal distance value MP is calculated based on the laser distance measurement value cn in the driving positioning data and the inclination angle θn of the load-bearing trolley; And then through Then the horizontal distance compensation value SBCn of the trolley for the crane main beam camber deformation can be calculated; Based on the left side lifting compensation signal, Calculate the compensation value JBCn of the near hook lifting cable, through Calculate and obtain the far hook lifting cable compensation value YBCn.

2. The intelligent compensation method for crane main beam camber deformation according to claim 1 is characterized in that: If the lifting compensation signal is a right lifting compensation signal, the lifting horizontal distance value MP is calculated based on the laser distance measurement value cm and the inclination angle θm of the carrying trolley in the driving positioning data; pass The horizontal distance compensation value SBCm of the load-bearing trolley caused by the camber deformation of the crane main beam can be calculated.

3. The intelligent compensation method for crane main beam camber deformation according to claim 2 is characterized in that: If the lifting compensation signal is a right lifting compensation signal, obtain the rope distance value SJ between the lifting cables on the load-bearing trolley; pass Calculate the compensation value JBCm of the near hook lifting cable, through Calculate and obtain the far hook lifting cable compensation value YBCm.

4. An intelligent compensation system for crane main beam camber deformation, characterized in that: The system is used to implement the intelligent compensation method for crane main beam camber deformation as described in any one of claims 1 to 3 above, comprising: Data acquisition module: The data acquisition module is used to obtain the mass value of the lifted cargo and mark it as Wm; and compare it with the load threshold LM of the crane main beam to obtain a light load signal or an overload signal; Based on the light load signal, the lifting target position data of the lifting cargo is obtained, including the lifting target height value MH and the lifting horizontal distance value MP; Data processing module: The data processing module is used to compare the lifting target height value MH with the lifting height threshold HG, and compare the lifting horizontal distance value MP with the lifting span threshold HK of the crane; obtain a lifting signal or an over-distance signal; Determination module: The determination module is used to determine whether the lifting horizontal distance value MP is between [0, ]or( , HK]; and then generating a left lifting compensation signal or a right lifting compensation signal; obtaining the driving positioning data of the carrying trolley on the crane main beam during the movement of the carrying trolley on the crane main beam; Compensation calculation module: The compensation calculation module is used to calculate the horizontal distance compensation value of the load-bearing trolley, the near-hook lifting cable compensation value and the far-hook lifting cable compensation value of the crane main beam camber deformation.