Scaffold lifting appliance and using method thereof
By designing the scaffolding spreader and using distribution beams, lifting lugs and booms to lift and move the erected scaffolding as a whole, the problems of long construction time and high labor costs caused by frequent disassembly and erection of long and narrow construction structures were solved, and the construction was realized Improvement of efficiency.
Patent Information
- Application Number
- CN202411109000.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-13
- Publication Date
- 2024-10-01
AI Technical Summary
When dealing with long and narrow construction structures, the existing technology requires frequent disassembly and erection of scaffolding, resulting in long construction times and high labor costs.
Design a scaffolding sling, including distribution beams, lifting lugs, slings and booms. The erected scaffolding is lifted as a whole and moved to the next construction position through the lifting equipment, avoiding multiple dismantling and reinstallation in traditional methods. Set up.
It greatly saves construction time and labor costs, enables rapid movement and reuse of scaffolding, and improves construction efficiency.
Smart Images

Figure CN118723760A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of scaffold construction, and in particular to a scaffold hanger and a use method thereof. Background Art
[0002] In the field of construction engineering, scaffolding is a crucial temporary support structure in the construction process. Its safety and efficiency are directly related to the overall quality and progress of the construction. Scaffolding not only provides a stable working platform for construction workers, ensuring the safety of high-altitude operations, but also serves as a medium for material transportation and stacking. When constructing some taller buildings, scaffolding is often required for construction work. In previous construction experience, it takes a long time to set up taller scaffolding.
[0003] In the prior art, especially when dealing with narrow and long construction structures, in order to save the scaffolding rental cost, the scaffolding is generally not erected all at once, but the construction method of segmentation is adopted. After each construction section is completed, the scaffolding is dismantled and moved to the next construction section, and the scaffolding is re-erected. Although this method is flexible and can achieve streamlined construction, it requires multiple dismantling and erecting of scaffolding, which has the problems of long construction time and high labor cost. Summary of the invention
[0004] The purpose of the present invention is to overcome the shortcomings of the prior art that when dealing with narrow and long construction structures, scaffolding needs to be frequently dismantled and erected, resulting in long construction time and high labor costs, and to provide a scaffolding hanger and a method for using the same.
[0005] In a first aspect, the present invention provides a scaffolding hanger, comprising:
[0006] A distribution beam, wherein the distribution beam is provided with a lifting lug, and the lifting lug is connected to the lifting equipment through a lifting rope;
[0007] A plurality of suspension rods, the upper ends of the suspension rods are connected to the distribution beams, the lower ends of the suspension rods are used to connect to the lifting points of the scaffolds, the plurality of suspension rods are arranged in two rows along the length direction of the distribution beams, and the spacing between the two rows of suspension rods matches the width of the scaffolds.
[0008] The present invention provides a scaffolding sling, wherein the upper end of the sling rope is connected to the hook of the lifting equipment, the lower end of the sling rope is connected to the distribution beam through the lifting ear, the distribution beam is connected with two rows of suspension rods, and the spacing between the two rows of suspension rods matches the width of the scaffolding, and the lower end of the suspension rod is used to connect the lifting point of the scaffolding. Therefore, through the sling rope, the distribution beam and the suspension rod, the vertical force provided by the hook of the lifting equipment can be dispersed into multiple vertical forces and act on the lifting point of the scaffolding, thereby lifting the entire erected scaffolding and moving it to the next construction position, thereby solving the problem that the traditional scaffolding needs to be frequently dismantled and erected when changing the construction section, resulting in long construction time and high labor cost.
[0009] Preferably, both ends of the distribution beam along the length direction are fixedly connected with a pull rope, and the distribution beam can be driven to rotate horizontally by pulling the pull rope clockwise or counterclockwise around the lifting point of the lifting device. The pull rope can be a hemp rope, a nylon rope, etc. This solution can conveniently control the orientation of the two ends of the distribution beam in the length direction by pulling the pull rope during the process of the distribution beam being lifted.
[0010] Preferably, the distribution beam is a horizontally placed steel truss. The steel truss can distribute the vertical force provided by the hook of the lifting device from one point to multiple lifting points on the same horizontal plane, so that the applied force can be evenly and stably distributed to each lifting point, ensuring the stability of the scaffolding during the lifting process and avoiding excessive force on local lifting points. The steel truss can be made of I-beams, channel steels or angle steels.
[0011] Preferably, the steel truss is welded from I18, I20A, I20B, I22A or I22B I-beams.
[0012] Preferably, the suspension rod is a telescopic component. The telescopic connection of the telescopic component can be a threaded connection between two components, the thread has a certain length, and the two components are moved closer or farther away from each other by rotating the thread. The telescopic connection of the telescopic component can also be that both components are provided with a number of screw holes with the same spacing along their length direction, and the two components are moved so that one or more groups of the screw holes are aligned, and then bolts are passed through the screw holes and matched with nuts for tightening.
[0013] Preferably, the telescopic component includes a first connecting rod and a second connecting rod, and the first connecting rod and the second connecting rod are connected by a thread. For example, the first connecting rod is provided with an internal thread sleeve, and the second connecting rod is provided with a matching external thread. The external thread of the second connecting rod is screwed into the internal thread sleeve of the first connecting rod to complete the connection, and the rotating thread can gradually separate or approach the first connecting rod and the second connecting rod. This solution can play a role in quickly adjusting the length of the suspension rod when it is necessary to fine-tune the length of the suspension rod, so as to quickly connect the suspension rod to the lifting point of the scaffold.
[0014] Preferably, the suspension rope is a steel wire rope, and the diameter of the steel wire rope is 16mm-22mm.
[0015] Preferably, the overall length of the distribution beam is 12m-20m.
[0016] In a second aspect, the present invention provides a method for using a scaffolding hanger, comprising the following steps:
[0017] S1: Connect the upper end of the lifting rope with the lifting equipment to lift the distribution beam and move it to the top of the scaffolding;
[0018] S2: Connect the lower end of the boom to the lifting point of the scaffolding;
[0019] S3: dismantling the support of the scaffolding;
[0020] S4: continue to hoist the distribution beam upwards so that the bottom of the scaffold is off the ground, and move the scaffold as a whole to above the next construction placement position;
[0021] S5: lowering the distribution beam so that the bottom of the scaffolding contacts the ground;
[0022] S6: Install the support of the scaffolding, remove the connection between the suspension rod and the scaffolding, and complete the lifting and moving of the scaffolding.
[0023] The present invention provides a method for using a scaffolding hanger. By using the distribution beam in combination with the hanging rope and the hanging rod, a scaffolding that has been erected can be moved from one construction section to the next construction section in an integral hoisting manner. In this process, the time for dismantling and re-erecting a traditional scaffolding is eliminated, which greatly saves the labor cost and time cost of dismantling and erecting.
[0024] Preferably, the steps S1 and S4 further include, when the two ends of the distribution beam along the length direction are not facing the predetermined direction, pulling the pull rope in the area outside the scaffold to adjust the direction of the two ends of the distribution beam along the length direction. This solution can control the posture of the distribution beam during the hoisting process and avoid unnecessary rotation of the distribution beam or collision with other structures during the hoisting process.
[0025] Compared with the prior art, the present invention has the following beneficial effects:
[0026] 1. The present invention provides a scaffolding hoist, which is connected to the lifting lugs on the distribution beam by a provided lifting rope, and the lifting rod on the distribution beam is connected to the lifting point of the scaffold, so that the entire erected scaffold can be lifted and moved to the next construction position by using a lifting device through the device, thereby solving the problem that the traditional scaffolding needs to be frequently dismantled and erected when changing the construction section, resulting in long construction time and high labor costs.
[0027] 2. The present invention provides a method for using a scaffolding hanger. By means of the distribution beam in combination with the lifting rope and the hanging rod, the scaffolding that has been erected can be moved from one construction section to the next construction section in an integral lifting manner, thereby avoiding the need to dismantle and erect the scaffolding again, greatly saving the labor cost and time cost of dismantling and erecting the scaffolding. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 The utility model discloses a hoisting scaffold and a front view of the scaffold of a scaffold hoist.
[0029] Figure 2 The utility model discloses a side view of a hoisting scaffold and a scaffold of a scaffold hoist.
[0030] Figure 3 A diagram showing scaffolding erected next to a long and narrow structure.
[0031] Figure 4 A schematic diagram of a distribution beam of a scaffolding hanger.
[0032] Figure 5 A schematic diagram of a lifting lug of a scaffolding hanger.
[0033] Figure 6 The computer model diagram of the scaffolding hanger and scaffolding under a working condition.
[0034] Figure 7 for Figure 6 Normal stress contours of the distributed beams in the model.
[0035] Figure 8 for Figure 6 Normal stress contour of the wire rope in the model.
[0036] Fig. 9 for Figure 6 Normal stress contour of the hanger in the model.
[0037] Fig.10 for Figure 6 Normal stress contours of the scaffolding crossbars and diagonal bars in the model.
[0038] Fig.11 for Figure 6 Normal stress contour of the scaffolding uprights in the model.
[0039] Markings in the figure:
[0040] 1- Distribution beam,
[0041] 2- hanging ears,
[0042] 3-Lifting rope,
[0043] 4- boom,
[0044] 5- Scaffolding,
[0045] 6- Pull rope,
[0046] 7-Anti-fall net,
[0047] 8- Support,
[0048] 9- Ground,
[0049] 10-Long and narrow structure. DETAILED DESCRIPTION
[0050] The present invention is further described in detail below in conjunction with specific embodiments. However, this should not be understood as the scope of the above subject matter of the present invention being limited to the following embodiments, and all technologies realized based on the content of the present invention belong to the scope of the present invention.
[0051] Unless otherwise specified, in the description of the specific embodiments of the present invention, the terms indicating the orientation or position relationship such as "up", "down", "left", "right", "center", "inside", "outside", etc. are all based on the expression of the orientation or position relationship shown in the drawings, or are the orientation or position relationship when the invented product / equipment / device is usually used. These terms of orientation or position relationship are only for the convenience of describing the scheme of the present invention or simplifying the description in the specific embodiments, so as to facilitate the technicians to quickly understand the scheme, and do not indicate or imply that a specific device / component / element must have a specific orientation, or be constructed and operated in a specific position relationship, and therefore cannot be understood as a limitation on the present invention.
[0052] In addition, if the terms "horizontal", "vertical", "overhanging", "parallel" and the like appear, it does not mean that the corresponding devices / components / elements are required to be absolutely horizontal or vertical or overhanging or parallel, but may be slightly tilted or have deviations. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but may be slightly tilted. Alternatively, it can be simplified to mean that the corresponding devices / components / elements are set in directions such as "horizontal", "vertical", "overhanging", "parallel", etc., and can have an error / deviation of ±10% relative to the corresponding direction setting, more preferably an error / deviation within ±8%, more preferably an error / deviation within ±6%, more preferably an error / deviation within ±5%, and more preferably an error / deviation within ±4%. As long as the corresponding device / component / element is within the error / deviation range, it can still achieve its role in the scheme of the present invention.
[0053] In addition, the expressions “first”, “second”, “third”, etc., which appear in the terms, are merely used to distinguish the description of the same or similar components and should not be understood as emphasizing or implying the relative importance of specific components.
[0054] In addition, in the description of the embodiments of the present invention, "several", "plurality" and "a number" represent at least 2. It can be any number such as 2, 3, 4, 5, 6, 7, 8, 9, and even more than 9.
[0055] In addition, in the description of the technical solution of the present invention, unless otherwise clearly specified / defined / restricted, the terms "set", "install", "connect", "connected", "provided with", "laid", and "arranged" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection, and can be welding, riveting, bolting, threading, and other commonly used connection means in the field. This connection can be a mechanical connection, an electrical connection, or a communication connection; it can be a direct connection, or an indirect connection through an intermediate medium, and it can be the internal connection of two elements.
[0056] Example 1
[0057] like Figure 1 , Figure 2 As shown, a scaffolding hanger includes a distribution beam 1, a lifting lug 2, a lifting rope 3, and a hanging rod 4.
[0058] The distribution beam 1 is provided with a lifting lug 2, which is connected to the lifting equipment via a lifting rope 3. Figure 4 As shown, four lifting ears 2 can be provided, and two lifting ears 2 are provided as a group on two parallel I-beams, and the position line of the four lifting ears 2 just forms a rectangle. The specific style of the lifting ears 2 can be as follows Figure 5 The lifting rope 3 can be a flat lifting belt or a steel wire rope.
[0059] A plurality of suspension rods 4, the upper ends of which are connected to the distribution beam 1, and the lower ends of which are used to connect to the hoisting points of the scaffolding 5, are arranged in two rows along the length direction of the distribution beam 1, and the spacing between the two rows of suspension rods 4 matches the width of the scaffolding 5. Each row of suspension rods 4 can be perpendicular to the length direction of the distribution beam 1 and evenly spaced along the length direction of the distribution beam 1, and more than two suspension rods 4 can be arranged in each row. Figure 1 As shown, specifically, five hangers 4 can be provided in each row, and the spacing between two rows of hangers 4 matches the width of the scaffolding 5. For example, when the width of the scaffolding 5 is 90 cm, the spacing between two rows of hangers 4 is also 90 cm. The hanging point is arranged at the middle and upper part of the scaffolding 5, and this position is the intersection of the crossbar and the vertical bar of the scaffolding 5. The connection mode between the upper end of the hanger 4 and the distribution beam 1 can be welding connection, bolt connection, pin connection or hinged connection. The connection mode between the lower end of the hanger 4 and the hanging point of the scaffolding 5 can be bolt connection or hook connection, that is, the lower end of the hanger 4 is provided with a hook, and the hook can be hooked on the crossbar of the hanging point of the scaffolding 5. The scaffolding 5 can be a steel pipe fastener type scaffolding or a disc buckle type scaffolding, and the scaffolding 5 is provided with an anti-falling net 7.
[0060] In an optional embodiment, both ends of the distribution beam 1 along the length direction are fixedly connected with a drawstring 6, and the drawstring 6 can be pulled clockwise or counterclockwise around the lifting point of the lifting device to drive the distribution beam 1 to rotate horizontally. The drawstring 6 can be made of hemp rope, nylon rope, etc. The fixed connection method of the drawstring 6 and the distribution beam 1 can be a knot connection or a mechanical connection, wherein the knot connection refers to tying one end of the drawstring 6 to the distribution beam 1 by tying a knot, and the mechanical connection refers to connecting the rope to the component using a special mechanical connector (such as a buckle, a clip, etc.).
[0061] In an optional embodiment, the distribution beam 1 may be a horizontally placed steel truss.
[0062] In an optional embodiment, the steel truss can be welded from I18, I20A, I20B, I22A or I22B I-beams. Figure 4 As shown, two long I-beams are arranged in parallel, and five short I-beams are perpendicular to the long I-beams and evenly arranged along the length direction of the long I-beams to form four rectangular frames. On a set of diagonal lines of each rectangular frame, additional oblique I-beams are arranged to enhance the stability of the steel truss. When selecting I-beams of corresponding specifications and models, the appropriate specifications and models can be determined according to the total weight of the scaffolding 5 to be hoisted.
[0063] In an optional embodiment, the suspension rod 4 may be a telescopic component.
[0064] In an optional embodiment, the telescopic component includes a first connecting rod and a second connecting rod, and the first connecting rod and the second connecting rod are connected by a thread. The first connecting rod is provided with an internal thread sleeve, and the second connecting rod is provided with a matching external thread, and the external thread of the second connecting rod is screwed into the internal thread sleeve of the first connecting rod to complete the connection, and rotating the thread can gradually separate or approach the first connecting rod and the second connecting rod.
[0065] In an optional embodiment, the suspension rope 3 may be a steel wire rope having a diameter of 16 mm to 22 mm, and the specific diameter may be 16 mm, 18 mm, 20 mm, or 22 mm.
[0066] In an optional embodiment, the overall length of the distribution beam 1 can be 12m-20m, and the specific length can be 12m, 13m, 14m, 15m, 16m, 17m, 18m, 19m, or 20m.
[0067] Example 2
[0068] A method for using a scaffolding hanger comprises the following steps:
[0069] S1: After the scaffolding 5 is set up in the first construction section of the narrow and long structure 10 and is used, Figure 3 As shown, the distribution beam 1 is lifted and moved above the scaffold 5 by connecting the upper end of the lifting rope 3 with the lifting equipment. The lifting equipment can be a crane, a gantry crane, etc.
[0070] In an optional embodiment, step S1 may further include, when both ends of the distribution beam 1 along the length direction are not facing the predetermined direction, pulling the pull rope 6 in the area outside the scaffolding 5 to adjust the direction of both ends of the distribution beam 1 along the length direction.
[0071] S2: Connect the lower end of the suspension rod 4 to the lifting point of the scaffold 5.
[0072] In an optional implementation, step S2 may also include adjusting the length of the suspension rod 4 during the process of connecting the hanging points of the scaffold 5 , so as to quickly connect the suspension rod 4 to the hanging points of the scaffold 5 .
[0073] S3: Remove the support 8 of the scaffold 5. The support 8 can be a wall connecting member, which is a component that connects the scaffold 5 to the main building. The support 8 can also be a diagonal brace, such as Figure 3 As shown, one end of the support 8 is connected to the upper middle portion of the scaffold 5 , and the other end of the support 8 is connected to the ground 9 .
[0074] S4: Continue to lift the distribution beam 1 upwards so that the bottom of the scaffolding 5 is separated from the ground 9, and move the scaffolding 5 as a whole to above the next construction placement position.
[0075] In an optional embodiment, step S4 may also include that when the two ends of the distribution beam 1 along the length direction are not facing the predetermined direction, the pull rope 6 may be pulled in the area outside the scaffolding 5 to adjust the direction of the two ends of the distribution beam 1 along the length direction. Since the length direction of the distribution beam 1 is always consistent with the length direction of the scaffolding 5 during the process of hoisting the scaffolding 5, when the pull rope 6 is pulled to control the two ends of the distribution beam 1 in the length direction to face the predetermined direction, the two ends of the scaffolding 5 in the length direction can also be synchronously driven to face the predetermined direction. The predetermined direction may be a direction parallel to the long and narrow structure 10. This step can avoid unnecessary collisions between the distribution beam 1 and the scaffolding 5 and the long and narrow structure 10 or other structures, equipment, etc. during the hoisting process.
[0076] S5: lower the distribution beam 1 so that the bottom of the scaffold 5 contacts the ground 9 .
[0077] In an optional implementation, step S5 may further include adjusting the base of the scaffolding 5 to ensure that the base under each upright pole of the scaffolding 5 is firmly and evenly in contact with and in contact with the ground 9 to enhance the overall stability and safety of the scaffolding 5 .
[0078] S6: Install the support 8 of the scaffolding 5, remove the connection between the suspension rod 4 and the scaffolding 5, and complete the lifting and moving of the scaffolding 5.
[0079] The following selects a working condition of a sling and a scaffold 5 for computer modeling calculation.
[0080] like Figure 6 As shown, the distribution beam 1 uses I20A type I-beam, the I-beam material is Q235, the overall length of the distribution beam 1 is 16m, and the width is 1.2m. The diameter of the wire rope is 16mm. The suspension rods 4 are arranged in two rows, four in each row, and the cross-sectional area of the suspension rods 4 is 50mm 2 , the material is Q235. Scaffold 5 has a horizontal distance of 90cm, a vertical distance of 90cm, a step distance of 150cm, a height of 6m, a horizontal length of 18m, and a vertical length of 0.6m. It is a single-row work frame, and the entire scaffold 5 structure weighs about 3 tons.
[0081] like Figure 7 As shown, the maximum normal stress of the distribution beam 1 is 61.2 MPa, which is less than the allowable normal stress of 145 MPa.
[0082] like Figure 8 As shown, the maximum positive stress of the wire rope is 982Mpa, which is less than the maximum tensile strength of the wire rope 1960Mpa.
[0083] like Fig. 9 As shown, the maximum normal stress of the hanger 4 is 41.1 MPa, which is less than the allowable normal stress of 145 MPa.
[0084] like Fig.10 As shown, the maximum normal stress of the crossbars and diagonal bars of the scaffold 5 is 83.9 MPa, which is less than the allowable normal stress of 145 MPa.
[0085] like Fig.11 As shown, the maximum normal stress of the uprights of the scaffold 5 is 112.5 MPa, which is less than the allowable normal stress of 210 MPa.
[0086] The stresses of the various components and the scaffold 5 under the above working conditions are all within the allowable range and meet the requirements of normal use.
[0087] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A scaffolding hanger, It is characterized in that include: A distribution beam (1), wherein the distribution beam (1) is provided with a lifting lug (2), and the lifting lug (2) is connected to a lifting device via a lifting rope (3); A plurality of suspension rods (4), the upper ends of the suspension rods (4) being connected to the distribution beam (1), the lower ends of the suspension rods (4) being used to connect to the lifting points of the scaffolding (5), the plurality of suspension rods (4) being arranged in two rows along the length direction of the distribution beam (1), the spacing between the two rows of suspension rods (4) matching the width of the scaffolding (5).
2. A scaffolding hanger according to claim 1, It is characterized in that Both ends of the distribution beam (1) along the length direction are fixedly connected with pull ropes (6), and pulling the pull ropes (6) clockwise or counterclockwise around the lifting point of the lifting device can drive the distribution beam (1) to rotate horizontally.
3. A scaffolding hanger according to claim 2, It is characterized in that The distribution beam (1) is a horizontally placed steel truss.
4. A scaffolding hanger according to claim 3, It is characterized in that The steel truss is welded from I18, I20A, I20B, I22A or I22B I-beams.
5. A scaffolding hanger according to any one of claims 1 to 4, It is characterized in that The suspension rod (4) is a telescopic component.
6. A scaffolding hanger according to claim 5, It is characterized in that The telescopic component includes a first connecting rod and a second connecting rod, and the first connecting rod and the second connecting rod are connected by threads.
7. A scaffolding hanger according to claim 5, It is characterized in that The suspension rope (3) is a steel wire rope, and the diameter of the steel wire rope is 16 mm-22 mm.
8. A scaffolding hanger according to claim 5, It is characterized in that The overall length of the distribution beam (1) is 12m-20m.
9. A method for using a scaffolding sling. It is characterized in that A scaffolding hanger as claimed in any one of claims 2 to 8, comprising the following steps: S1: Connect the upper end of the lifting rope (3) with the lifting equipment to lift the distribution beam (1) and move it to the top of the scaffolding (5); S2: Connect the lower end of the suspension rod (4) to the lifting point of the scaffold (5); S3: dismantling the support (8) of the scaffold (5); S4: Continue to hoist the distribution beam (1) upwards so that the bottom of the scaffold (5) is separated from the ground (9), and the scaffold (5) is moved as a whole to above the next construction placement position; S5: lowering the distribution beam (1) so that the bottom of the scaffold (5) contacts the ground (9); S6: Install the support (8) of the scaffold (5), and remove the connection between the suspension rod (4) and the scaffold (5). The hoisting and moving of the scaffolding (5) is completed.
10. A method for using a scaffolding hanger according to claim 9, It is characterized in that The step S1 and the step S4 also include, when the two ends of the distribution beam (1) along the length direction are not facing the predetermined direction, pulling the pull rope (6) in the area outside the scaffolding (5) to adjust the direction of the two ends of the distribution beam (1) along the length direction.