Bent and twisted section hoisting method
By using crawler cranes and hydraulic balance spreaders in conjunction with hand chain hoists and three-way jacks, the precise posture adjustment and assembly of special-shaped steel bridge tower segments are achieved, solving the problems of extended construction period and increased costs in conventional hoisting methods, and ensuring construction accuracy and security.
Patent Information
- Application Number
- CN202411091241.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2024-10-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
During the hoisting process of special-shaped steel bridge towers, due to the complex structure and large height, conventional methods require the erection of floor-standing scaffolding and construction platforms, resulting in extended construction periods and increased costs, and it is difficult to ensure precise alignment and attitude adjustment of tower segments.
The crawler crane and hydraulic balancing spreader are used together with a hand chain hoist and a three-way jack. The four-point automatic balancing positioning of the hydraulic spreader and the horizontal brace plus longitudinal cable balancing system enables precise attitude adjustment and assembly of the segments, avoiding the need for the erection to fall to the ground. scaffold.
It effectively ensures the accuracy and structural stability of the steel tower construction, reduces the construction cost and construction period, achieves fine adjustment of the cantilever hoisting position of the steel tower, and improves construction safety.
Smart Images

Figure CN118723830A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of steel structure construction, and in particular relates to a method for hoisting a bending and torsion segment. Background Art
[0002] The cable tower of the special-shaped landscape cable-stayed bridge is the core structure that expresses the beauty of the entire bridge design. It often adopts various expressive spatial distortion shapes, and the structural appearance and force are complex. Generally, steel structures are used to meet its unique appearance and structural force requirements. Different from regular bridge towers, the axis of special-shaped steel bridge towers gradually develops from a plane curve to a spatial torsion curve. In addition, the bridge tower is high, the cross-sectional size and weight of the tower segment are large, and it is difficult to position and adjust the posture in the air.
[0003] For the spatial special-shaped twisted steel tower structure, the conventional hoisting method requires the construction of ground scaffolding and construction platform to connect the segments. The construction of ground scaffolding and construction platform will not only prolong the construction period, but also increase the material and labor costs. In addition, during the hoisting process, the main tower limbs will undergo three-dimensional deformation due to the complex effects of the self-weight of the assembled segments, welding deformation of the welds, construction loads, temperature and wind loads. The three axial coordinates need to be adjusted, which makes it impossible to guarantee the accuracy of the aerial alignment posture adjustment of the tower segments. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a method for hoisting a bending and torsion segment to at least solve part of the above-mentioned technical problems.
[0005] To achieve the above purpose, the technical solution adopted by the present invention is as follows:
[0006] A method for hoisting a bending and twisting segment comprises the following steps:
[0007] Step 1: Use a crawler crane to lift the assembled steel tower segment;
[0008] Step 2: Use the sling to lift the segment, adjust the posture, lift it above the A tower column, and complete the assembly between the segments;
[0009] Step 3: Use hand chain hoists and three-way jacks in conjunction with lifting equipment to accurately adjust the segments;
[0010] Step 4: Assemble the A and B tower limb steel tower segments respectively according to the standard process;
[0011] Step 5: Install a cable on each of the A and B tower limbs, and perform temporary tensioning according to monitoring instructions to adjust the tower column linearity. The specific installation position of the cable installation segment is determined through finite element simulation;
[0012] Step 6: Install the second cable on the A and B tower legs, and complete the temporary tensioning of the cable according to the monitoring instructions;
[0013] Step 7: Install the second cross brace, install the monitoring instructions to carry out the tower limb top operation, install the fourth cable of the A tower limb, and complete the temporary tensioning of the cable according to the monitoring instructions;
[0014] Step 8: Adjust the line shape of the closure, assemble the closure sections into a whole on the ground, and use a crawler crane to lift them to the designed position to complete the closure construction of the steel tower;
[0015] Step 9. Remove the cross brace, crawler crane and other temporary facilities, complete the installation and tensioning of permanent cables according to the construction process, and complete the main tower construction.
[0016] Furthermore, in step 2, the segment lifting adopts a four-point automatic balancing and positioning hydraulic lifting device, which includes an upper lifting belt, a hydraulic cylinder and a lower lifting belt. The four lower lifting belts are connected to the upper lifting ears of the tower segment, the hydraulic cylinder is connected between the upper lifting belt and the lower lifting belt, and the upper lifting belt is connected to the lifting equipment hook.
[0017] Furthermore, the hydraulic cylinder is connected to the oil pump through an oil pipe, and the installation posture of the tower segment can be accurately adjusted by different sling lengths and the hydraulic cylinder. The sling can adapt to the posture adjustment of the segment within 20°.
[0018] Furthermore, in step three, when the hoisting segment is 1m away from the installed segment, the segment to be installed is slowly lowered by loosening the hook through the hand winch and the hoisting equipment, and temporarily placed on the three-way jack; the segment is accurately adjusted by the three-way jack, and the hoisting equipment does not loosen the hook at this time to complete the precise adjustment of the segment.
[0019] Furthermore, in the step six, the first cross brace is installed between the steel tower columns. The first cross brace is hoisted by a crawler crane to the bull legs at both ends and temporarily placed. After the installation of the first cross brace is completed, the jack is arranged at the top, and two jacks are set at the pushing end for positioning, and the center of the jack piston is aligned with the center of the cross brace.
[0020] Furthermore, during jacking, graded pressure control is performed according to the calculated pre-jacking force required to be applied.
[0021] Furthermore, the graded pressure is graded in 10 MPa steps.
[0022] Furthermore, when reaching the last four levels of the designed pre-jacking force, graded pressure control is performed with a step difference of 5 MPa.
[0023] Furthermore, after the horizontal support and jacking operation is completed, the cushion block structure is hoisted to the designed position by a crawler crane and welded and fixed, and then connected to one side tower column into a whole.
[0024] Compared with the prior art, the present invention has the following beneficial effects:
[0025] The design of the present invention is scientific and reasonable. By establishing a horizontal brace plus longitudinal cable balance system and using a hydraulic balance hanger to adjust the segment docking posture, the construction accuracy, structural stability and construction safety of the steel tower can be effectively ensured. During the steel tower installation process, there is no need to set up a ground scaffolding, and the cantilever hoisting alignment and fine adjustment of the steel tower can be achieved. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a schematic diagram of the process flow of the bending and torsion segment lifting method of the present invention.
[0027] Figure 2 This is a schematic diagram of the present invention using a crawler crane to lift the assembled steel tower segments.
[0028] Figure 3 The figure is a schematic elevation view of the sling of the present invention (dimensions in mm).
[0029] Figure 4 The figure is a schematic cross-sectional view of the sling of the present invention (dimension unit: mm).
[0030] Figure 5 It is a plan view of the sling of the present invention (dimension unit: mm).
[0031] Figure 6 It is a schematic diagram of the sling of the present invention.
[0032] Figure 7 The figure is a structural diagram of the telescopic oil cylinder of the present invention (dimension unit: mm).
[0033] Figure 8 It is a schematic diagram of the plan layout of the cable tower segment lifting ears of the present invention.
[0034] Fig. 9 It is a schematic diagram of the arrangement of the lifting lugs of the present invention.
[0035] Fig.10 Schematic diagram of segment docking of the present invention Figure 1 .
[0036] Fig.11 Schematic diagram of segment docking of the present invention Figure 2 .
[0037] Fig.12 The present invention is a schematic diagram of assembling the A and B tower limb steel tower segments according to the standard process.
[0038] Fig.13 This is a schematic diagram of step five of the present invention.
[0039] Fig.14 This is a schematic diagram of step six of the present invention.
[0040] Fig.15 This is a schematic elevation diagram of the installation of the crossbeam of the present invention.
[0041] Fig.16 It is a schematic diagram of the cross brace placement and the corbel of the present invention.
[0042] Fig.17 This is a schematic diagram of step seven of the present invention.
[0043] Fig.18 This is a schematic diagram of step eight of the present invention. DETAILED DESCRIPTION
[0044] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0045] like Figure 1-8 As shown, the present invention provides a method for hoisting a bending and twisting segment, comprising the following steps:
[0046] Step 1: Use a crawler crane to lift the assembled steel tower segment.
[0047] Step 2: Use the lifting sling to lift the segment, adjust the posture, lift it above the A tower column, and complete the assembly between the segments.
[0048] The segment lifting adopts a four-point automatic balancing and positioning hydraulic lifting device, which includes an upper lifting belt, a hydraulic cylinder and a lower lifting belt. The four lower lifting belts are connected to the upper lifting ears of the tower segment, the hydraulic cylinder is connected between the upper lifting belt and the lower lifting belt, and the upper lifting belt is connected to the hook of the lifting equipment.
[0049] The hydraulic cylinder and oil pump are connected through oil pipes. The installation posture of the tower segment can be accurately adjusted by different sling lengths and hydraulic cylinders. The sling can adapt to the posture adjustment of the segment within 20°.
[0050] Step 3: Use hand hoists and three-way jacks in conjunction with lifting equipment to accurately adjust the segments.
[0051] When the hoisting segment is 1m away from the installed segment, the segment to be installed is slowly lowered by the hand winch and the hoisting equipment, and temporarily placed on the three-way jack; the segment is accurately adjusted by the three-way jack, and the hoisting equipment does not release the hook at this time to complete the precise adjustment of the segment.
[0052] Step 4: Assemble the A and B tower limb steel tower segments separately according to the standard process.
[0053] Step 5: Install a cable on each of the A and B tower legs, and perform temporary tensioning according to monitoring instructions to adjust the tower column line. The specific installation position of the cable installation segment is determined through finite element simulation.
[0054] Step 6: Install the second cable on the A and B tower legs, and complete the temporary tensioning of the cable according to the monitoring instructions.
[0055] Install the first cross brace between the steel tower columns. The first cross brace is hoisted by a crawler crane to the bull legs at both ends and temporarily placed there. After the installation of the first cross brace is completed, the jack is arranged at the top, and two jacks are set at the pushing end to position them. The center of the jack piston is aligned with the center of the cross brace.
[0056] During jacking, graded pressure control is performed according to the calculated pre-jacking force required.
[0057] The graded pressure is graded in 10MPa steps.
[0058] When reaching the last four levels of designed pre-jacking force, graded pressure control is performed with a step difference of 5 MPa.
[0059] After the horizontal support and jacking operation is completed, the cushion block structure is hoisted to the designed position by a crawler crane and welded and fixed, and then connected to one side of the tower column into a whole.
[0060] Step 7. Install the second cross brace and perform the tower limb top-to-top operation according to the monitoring instructions. Install the fourth cable of tower limb A and complete the temporary tensioning of the cable according to the monitoring instructions.
[0061] Step 8. Adjust the line shape of the joint mouth, assemble the joint sections into a whole on the ground, use a crawler crane to lift them to the designed position, and complete the steel tower joint construction.
[0062] Step 9. Remove the cross brace, crawler crane and other temporary facilities, complete the installation and tensioning of permanent cables according to the construction process, and complete the main tower construction.
[0063] The design of the present invention is scientific and reasonable. By establishing a horizontal brace plus longitudinal cable balance system and using a hydraulic balance hanger to adjust the segment docking posture, the construction accuracy, structural stability and construction safety of the steel tower can be effectively ensured. During the steel tower installation process, there is no need to set up a ground scaffolding, and the cantilever hoisting alignment and fine adjustment of the steel tower can be achieved.
[0064] In order to ensure stability and linear control when hoisting tower segments during the construction process of the present invention, two measures, namely, lateral internal support and longitudinal prestressed temporary cable tensioning steel strands, are adopted in the hoisting process to ensure the lateral and longitudinal stability of the main tower.
[0065] According to calculation and analysis, transverse internal supports and longitudinal temporary cables are set when the main tower segments are hoisted to a certain height, which together form the internal support and tensioning system of the steel main tower.
[0066] The main tower of the present invention is a space-distorted structure, and the aerial posture of the tower segment needs to be continuously adjusted during the hoisting process. During the hoisting process, a total of 4 lifting points are set on the tower segment, and the posture adjustment is achieved through a four-point automatic balancing and positioning hydraulic spreader.
[0067] During the steel tower installation process of the present invention, there is no need to set up a ground-based scaffolding, and fine adjustment of the cantilever hoisting position of the steel tower can be achieved.
[0068] The present invention provides a method for hoisting a bending and torsion segment, which is specifically:
[0069] like Figure 2 As shown, the assembled steel tower segments are lifted using a crawler crane.
[0070] like Figure 3-Figure 9 As shown, the segment is lifted by slings (slings + cylinders + shackles), and after adjusting the posture, it is lifted above tower column A to complete the assembly between segments.
[0071] The segment lifting adopts a four-point automatic balancing and positioning hydraulic lifting device, which consists of an upper lifting belt, a cylinder, a lower lifting belt and a shackle. The four lower lifting belts are connected to the lifting ears on the tower segment, the cylinder is set between the upper and lower lifting belts, and the upper lifting belt is connected to the equipment hook.
[0072] The telescopic cylinder is connected to the oil pump through an oil pipe, and the oil pump is connected to the power supply. The installation posture of the tower segment can be accurately adjusted by different sling lengths and the oil cylinder. The sling can adapt to the posture adjustment of the segment within 20°.
[0073] like Fig.10 and Fig.11 As shown in the figure, when the hoisting segment is 1m away from the installed segment, the segment to be installed is lowered by slowly loosening the hook with the hand chain hoist and the equipment, and temporarily placed on the three-way jack. The segment is accurately adjusted by the three-way jack, and the equipment does not loosen the hook at this time to complete the accurate adjustment of the segment.
[0074] like Fig.12 As shown, according to the standard process, the A and B tower limb steel tower segments are assembled separately.
[0075] like Fig.13 As shown, a cable is installed on each of the AB tower limbs, and temporary tensioning is performed according to monitoring instructions to adjust the tower column line. The specific installation position of the cable installation segment is determined by finite element simulation.
[0076] like Figure 14-16 As shown, the second cable is installed on the A and B tower legs, and the temporary tensioning of the cable is completed according to the monitoring instructions; the first cross brace is installed between the steel tower columns, and the cross brace is temporarily placed on the brackets at both ends by using a crawler crane. After the installation of the cross brace is completed, the jack is arranged at the top, and two jacks are set at the pushing end to position them, and the center of the jack piston is aligned with the center of the cross brace.
[0077] During jacking, graded pressure control is carried out according to the calculated pre-jacking force required, and the graded pressure is carried out in 10MPa steps, and the last few steps close to the designed pre-jacking force are carried out in 5MPa steps.
[0078] After the cross brace pushing operation is completed, the cushion block structure is hoisted to the designed position using a crawler crane, and fixed by welding, connecting it to one side tower column into a whole.
[0079] Fig.16 This is a schematic diagram of the cross brace placement and the bracket of the present invention, and is also Fig.15 Schematic diagram of the left end of .
[0080] like Fig.17 As shown, install the second cross brace and install the monitoring instructions to carry out the tower leg top operation. Install the fourth cable of the A tower leg and complete the temporary tensioning of the cable according to the monitoring instructions.
[0081] like Fig.18 As shown, adjust the line shape of the joint mouth, assemble the joint sections into a whole on the ground, use a crawler crane to lift them to the designed position, and complete the steel tower closure construction.
[0082] The cross braces, crawler cranes and other temporary facilities were removed, and permanent cable installation and tensioning were completed according to the construction process to complete the main tower construction.
[0083] The design of the present invention is scientific and reasonable. By establishing a horizontal brace plus longitudinal cable balance system and using a hydraulic balance hanger to adjust the segment docking posture, the construction accuracy, structural stability and construction safety of the steel tower can be effectively ensured. During the steel tower installation process, there is no need to set up a ground scaffolding, and the cantilever hoisting alignment and fine adjustment of the steel tower can be achieved.
[0084] In order to ensure stability and linear control when hoisting tower segments during the construction process of the present invention, two measures, namely, lateral internal support and longitudinal prestressed temporary cable tensioning steel strands, are adopted in the hoisting process to ensure the lateral and longitudinal stability of the main tower.
[0085] According to calculation and analysis, transverse internal supports and longitudinal temporary cables are set when the main tower segments are hoisted to a certain height, which together form the internal support and tensioning system of the steel main tower.
[0086] The main tower of the present invention is a space-distorted structure, and the aerial posture of the tower segment needs to be continuously adjusted during the hoisting process. During the hoisting process, a total of 4 lifting points are set on the tower segment, and the posture adjustment is achieved through a four-point automatic balancing and positioning hydraulic spreader.
[0087] During the steel tower installation process of the present invention, there is no need to set up a ground-based scaffolding, and fine adjustment of the cantilever hoisting position of the steel tower can be achieved.
[0088] Finally, it should be noted that the above embodiments are only preferred embodiments of the present invention to illustrate the technical solution of the present invention, but not to limit it, and certainly not to limit the patent scope of the present invention. Any changes or modifications that are made to the main design concept and spirit of the present invention without any substantial meaning, and the technical problems they solve are still consistent with the present invention, should be included in the protection scope of the present invention; in addition, the direct or indirect application of the technical solution of the present invention in other related technical fields is also included in the patent protection scope of the present invention.
Claims
1. A method for hoisting a bending and twisting segment, characterized in that: The following steps are involved: Step 1: Use a crawler crane to lift the assembled steel tower segment; Step 2: Use the sling to lift the segment, adjust the posture, lift it above the A tower column, and complete the assembly between the segments; Step 3: Use hand chain hoists and three-way jacks in conjunction with lifting equipment to accurately adjust the segments; Step 4: Assemble the A and B tower limb steel tower segments respectively according to the standard process; Step 5: Install a cable on each of the A and B tower limbs, and perform temporary tensioning according to monitoring instructions to adjust the tower column linearity. The specific installation position of the cable installation segment is determined through finite element simulation; Step 6: Install the second cable on the A and B tower legs, and complete the temporary tensioning of the cable according to the monitoring instructions; Step 7: Install the second cross brace, install the monitoring instructions to carry out the tower limb top operation, install the fourth cable of the A tower limb, and complete the temporary tensioning of the cable according to the monitoring instructions; Step 8: Adjust the line shape of the closure, assemble the closure sections into a whole on the ground, and use a crawler crane to lift them to the designed position to complete the closure construction of the steel tower; Step 9. Remove the cross brace, crawler crane and other temporary facilities, complete the installation and tensioning of permanent cables according to the construction process, and complete the main tower construction.
2. A method for hoisting a bending and torsion segment according to claim 1, characterized in that: In step 2, the segment lifting adopts a four-point automatic balancing and positioning hydraulic lifting device, which includes an upper lifting belt, a hydraulic cylinder and a lower lifting belt. The four lower lifting belts are connected to the upper lifting ears of the tower segment, the hydraulic cylinder is connected between the upper lifting belt and the lower lifting belt, and the upper lifting belt is connected to the lifting equipment hook.
3. A method for hoisting a bending and torsion segment according to claim 2, characterized in that: The hydraulic cylinder and oil pump are connected through oil pipes. The installation posture of the tower segment can be accurately adjusted through different sling lengths and hydraulic cylinders. The sling can adapt to the posture adjustment of the segment within 20°.
4. A method for hoisting a bending and torsion segment according to claim 1, characterized in that: In the step three, when the hoisting segment is 1m away from the installed segment, the segment to be installed is slowly lowered by the hand winch and the hoisting equipment, and temporarily placed on the three-way jack; the segment is accurately adjusted by the three-way jack, and the hoisting equipment does not release the hook at this time to complete the precise adjustment of the segment.
5. A method for hoisting a bending and torsion segment according to claim 1, characterized in that: In step six, the first cross brace is installed between the steel tower columns. The first cross brace is hoisted by a crawler crane to the brackets at both ends and temporarily placed. After the installation of the first cross brace is completed, the jack is arranged at the top, and two jacks are set at the pushing end for positioning, and the center of the jack piston is aligned with the center of the cross brace.
6. A method for hoisting a bending and torsion segment according to claim 5, characterized in that: During jacking, graded pressure control is performed according to the calculated pre-jacking force required.
7. A method for hoisting a bending and torsion segment according to claim 6, characterized in that: The graded pressure is graded in 10MPa steps.
8. A method for hoisting a bending and torsion segment according to claim 7, characterized in that: When reaching the last four levels of designed pre-jacking force, graded pressure control is performed with a step difference of 5 MPa.
9. A method for hoisting a bending and torsion segment according to claim 5, characterized in that: After the horizontal support and jacking operation is completed, the cushion block structure is hoisted to the designed position by a crawler crane and welded and fixed, and then connected to one side of the tower column into a whole.
Citation Information
Cited By
Secondary pre-splicing jig frame of steel leaning tower and space attitude adjusting method
CN119593313A
Secondary pre-assembling jig frame of steel inclined tower and spatial posture adjusting method
CN119593313B
Construction method of spatial curved surface special-shaped steel leaning tower without temporary support