Intelligent deviation rectifying open caisson construction method and system

By establishing multiple construction sub-areas during caisson construction and monitoring and adjusting the water knife sub-module parameters in real time, the problems of poor controllability and high cost of the sinking process in traditional caisson construction are solved, and caissons of higher quality and precision are achieved. construction.

CN118727801APending Publication Date: 2024-10-01POWER CHINA KUNMING ENG CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411065479.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-05
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

Traditional caisson construction methods are difficult to meet the environmental protection requirements in prosperous areas in urban centers. The sinking process of self-weight sinking caissons has poor controllability, is prone to sudden settlement or over-sinking problems, and has high construction costs.

Method used

By establishing multiple construction sub-areas, setting up water knife sub-modules and adjusting their working parameters by the central control unit, and cooperating with the mud suction pipe to achieve automatic subsidence, real-time monitoring and adjustment of the well wall subsidence and posture, and setting correction instructions to improve construction Precision and controllability.

Benefits of technology

It improves the quality and accuracy of caisson construction, reduces construction costs, ensures uniform sinking of the well wall, and enhances construction control.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118727801A_ABST
    Figure CN118727801A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of open caisson construction, in particular to an intelligent deviation rectifying open caisson construction method and system. Comprising the steps that multiple construction sub-areas are established according to parameters of a to-be-constructed open caisson, and a cutting plan is generated according to the parameters of the to-be-constructed open caisson Setting water jet cutting parameters of each construction sub-area and working parameters of a mud pumping pipe according to the cutting plan; and open caisson state parameters are obtained according to the preset feedback time node, and whether the water jet cutting parameters are corrected or not is judged according to the open caisson state parameters. A plurality of construction sub-areas are established according to equipment parameters of the open caisson, a water knife sub-module is arranged in each construction sub-area, working parameters between the water knife sub-modules are adjusted through a central control unit, soil bodies in the construction sub-areas are cut, automatic sinking of the open caisson is achieved in cooperation with a mud pumping pipe, and the construction quality of the open caisson is improved; and the construction cost of the open caisson is reduced. And according to the sinking posture of the open caisson, the deflection state of the open caisson is judged, a corresponding correction instruction is set, and the construction precision of the open caisson is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of caisson construction, and in particular to a caisson construction method and system with intelligent deviation correction. Background Art

[0002] With the rapid urbanization development in my country in recent decades, there is a strong demand for the construction of various underground structures in cities. Most underground structures require the design of vertical shaft structures as functional structures such as ventilation shafts and construction shafts. The traditional open-cut vertical shaft construction method has a great impact on the construction environment and can no longer meet the environmental protection requirements of the prosperous areas in the city center. The caisson technology, as a construction method suitable for soft water-bearing strata, has been widely used in cities in my country's coastal areas. The main principle of the caisson technology is to use manual and semi-automatic mechanical methods to excavate the soil, and place the prefabricated well body on the blade foot to gradually sink with the excavation of the soil relying on the self-weight of the structure. Finally, the bottom of the well is cast and sealed to complete the construction of the entire vertical shaft structure.

[0003] Since the self-weight-sinking caisson mainly relies on its own weight to sink, the controllability of the sinking process is poor, and sinking difficulties often occur in actual construction; the press-in sinking caisson avoids the problem of insufficient cutting force of the blade foot, but sudden sinking and over-sinking may also occur during the excavation process, and the sinking accuracy control ability is poor; VSM equipment solves the sudden sinking problem by hanging from below, but its construction cost is relatively high. Summary of the invention

[0004] The purpose of this application is: to solve the above-mentioned technical problems, this application provides an intelligent correction caisson construction method and system, aiming to improve the caisson construction quality and construction accuracy, and reduce the caisson construction cost.

[0005] In some embodiments of the present application, multiple construction sub-areas are established according to the equipment parameters of the caisson, and a water knife sub-module is set in each construction sub-area. The working parameters between the water knife sub-modules are adjusted by the central control unit to cut the soil in each construction sub-area, and the caisson is automatically sunk in cooperation with the mud suction pipe, thereby improving the construction quality of the caisson and reducing the construction cost of the caisson.

[0006] In some embodiments of the present application, by adding a correction unit and a monitoring unit, the state parameters of the caisson are monitored in real time to ensure that the well wall in each construction sub-area is at the same sinking amount, thereby improving the controllability of the sinking. At the same time, according to the sinking posture of the caisson, the deviation state of the caisson is judged, and corresponding correction instructions are set to ensure the construction accuracy of the caisson.

[0007] In some embodiments of the present application, a caisson construction method with intelligent deviation correction is provided, comprising:

[0008] Establish multiple construction sub-areas according to the parameters of the caisson to be constructed, and generate a cutting plan according to the parameters of the caisson to be constructed;

[0009] Set the water jet cutting parameters and mud extraction pipe working parameters for each construction sub-area according to the cutting plan;

[0010] The caisson status parameters are obtained according to the preset feedback time node, and it is determined whether to correct the water jet cutting parameters according to the caisson status parameters.

[0011] In some embodiments of the present application, the establishing of multiple construction sub-areas includes:

[0012] Generate a construction evaluation value a of the caisson to be constructed according to a preset caisson evaluation model and parameters of the caisson to be constructed;

[0013]

[0014] Among them, pi is the reference value of the i-th construction evaluation index of the caisson to be constructed; αi is the influencing factor of the i-th construction evaluation index; θ is the number of construction evaluation indicators;

[0015] The number of construction sub-areas n is set according to the construction evaluation value a;

[0016] Preset a first construction evaluation value interval (A1, A2), a second construction evaluation value interval (A2, A3) and a third construction evaluation interval (A3, A4);

[0017] If the construction evaluation value a is within the preset first construction evaluation value interval, the number of construction sub-areas n is set to the preset first number n1;

[0018] If the construction evaluation value a is within the preset second construction evaluation value interval, the number of construction sub-areas n is set to the preset second number n2;

[0019] If the construction evaluation value a is within the preset third construction evaluation value interval, the number of construction sub-areas n is set to the preset third number n3; and n1<n2<n3;

[0020] A construction sub-area sequence B is established according to the parameters of the caisson to be constructed and the number of construction sub-areas, where B = (b1, b2...bn), wherein bi is the i-th construction sub-area.

[0021] In some embodiments of the present application, when a cutting plan is generated according to the parameters of the caisson to be constructed, it includes:

[0022] Obtain a water knife submodule sequence C, C = (c1, c2, ... cn), where ci is the water knife submodule corresponding to the i-th construction sub-area;

[0023] Obtain the expected construction speed range of the caisson to be constructed;

[0024] Generate multiple first-level cutting plans according to the expected construction progress, and establish a first-level cutting plan sequence J, J = (j1, j2...jm), where m is the number of first-level cutting plans; ji is the i-th first-level cutting plan;

[0025] Generate the operation evaluation value of each first-level cutting plan;

[0026] Establish an operation evaluation value sequence D, D = (d1, d2...dm), where di is the operation evaluation value of the i-th first-level cutting plan;

[0027] Set the first-level cutting plan corresponding to the maximum value dmax in the running evaluation value D as the second-level cutting plan;

[0028] According to the secondary cutting plan, the water jet cutting parameters and the working parameters of the mud extraction pipe in each construction sub-area are set.

[0029] In some embodiments of the present application, when generating the operation evaluation value of each primary cutting plan, it includes:

[0030] Select the target first-level cutting plan in sequence according to the first-level cutting plan sequence D;

[0031] Generate an operation evaluation value d of the target first-level cutting plan according to a preset construction evaluation model;

[0032]

[0033] Among them, e1 is the preset first weight coefficient, e2 is the preset second weight coefficient; Q1 is the preset first fixed coefficient; Q2 is the preset second fixed coefficient; fi is the reference evaluation value of the i-th water knife submodule in the target first-level cutting plan; μi is the influence factor of the i-th water knife submodule; pi is the reference value of the i-th operation evaluation index in the target first-level cutting plan; βi is the influence factor of the i-th operation evaluation index; r is the number of operation evaluation indicators;

[0034] Generate the operation evaluation value of each first-level cutting plan in turn.

[0035] In some embodiments of the present application, when determining whether to modify the water jet cutting parameters according to the caisson state parameters, it includes:

[0036] Generate the sinking amount of each construction sub-area at the current feedback time node according to the caisson state parameters;

[0037] Establish a subsidence amount sequence G at the current feedback time node, G = (g1, g2...gn), where gi is the subsidence amount of the i-th construction sub-area at the current feedback time node;

[0038] Generate the settlement deviation evaluation value d of the current feedback time node;

[0039]

[0040] Among them, e3 is the preset third weight coefficient, e4 is the preset fourth weight coefficient; Q3 is the preset third fixed coefficient; Q4 is the preset fourth fixed coefficient; g' is the standard sinking amount of the current feedback time node; △ g is the average value of all data in the sinking amount series G;

[0041] Preset settlement deviation evaluation value threshold D1;

[0042] If d>D1, a first-level correction instruction is generated, and the first-level correction parameters of each water knife sub-module are set according to the sinking amount series G.

[0043] In some embodiments of the present application, when judging whether to modify the water jet cutting parameters according to the caisson state parameters, it also includes:

[0044] Generate the shaft wall deviation of each construction sub-area according to the caisson state parameters;

[0045] Establish a wellbore deviation series H, H = (h1, h2...hn), where hi is the wellbore deviation of the i-th construction sub-area;

[0046] Preset the wellbore deviation threshold H1;

[0047] If hi>H1, generate the secondary correction instruction of the i-th construction sub-area, and set the secondary correction parameters of the i-th water knife sub-module.

[0048] In some embodiments of the present application, a smart deviation-correcting caisson construction system is provided, comprising:

[0049] The central control unit is used to establish multiple construction sub-areas according to the parameters of the caisson to be constructed;

[0050] A water jet unit, comprising a pressure pump truck and a plurality of water jet sub-modules, wherein the water jet sub-modules are arranged inside the well wall and are used to cut the soil in the construction sub-area;

[0051] Mud extraction unit, used to extract mud and water in the construction sub-area;

[0052] Monitoring unit, used to collect caisson status parameters;

[0053] The central control unit comprises:

[0054] A first processing module is used to establish multiple construction sub-areas;

[0055] The second processing module is used to generate a cutting plan according to the parameters of the caisson to be constructed, and set the water jet cutting parameters and the working parameters of the mud extraction pipe in each construction sub-area according to the cutting plan;

[0056] The first correction module is used to obtain the caisson state parameters according to the preset feedback time node, and determine whether to correct the water jet cutting parameters according to the caisson state parameters.

[0057] In some embodiments of the present application, the first processing module is further used to:

[0058] Generate a construction evaluation value a of the caisson to be constructed according to a preset caisson evaluation model and parameters of the caisson to be constructed;

[0059]

[0060] Among them, pi is the reference value of the i-th construction evaluation index of the caisson to be constructed; αi is the influencing factor of the i-th construction evaluation index; θ is the number of construction evaluation indicators;

[0061] The number of construction sub-areas n is set according to the construction evaluation value a;

[0062] Preset a first construction evaluation value interval (A1, A2), a second construction evaluation value interval (A2, A3) and a third construction evaluation interval (A3, A4);

[0063] If the construction evaluation value a is within the preset first construction evaluation value interval, the number of construction sub-areas n is set to the preset first number n1;

[0064] If the construction evaluation value a is within the preset second construction evaluation value interval, the number of construction sub-areas n is set to the preset second number n2;

[0065] If the construction evaluation value a is within the preset third construction evaluation value interval, the number of construction sub-areas n is set to the preset third number n3; and n1<n2<n3;

[0066] A construction sub-area sequence B is established according to the parameters of the caisson to be constructed and the number of construction sub-areas, where B = (b1, b2...bn), wherein bi is the i-th construction sub-area.

[0067] In some embodiments of the present application, the second processing module is further used to:

[0068] Obtain a water knife submodule sequence C, C = (c1, c2, ... cn), where ci is the water knife submodule corresponding to the i-th construction sub-area;

[0069] Obtain the expected construction speed range of the caisson to be constructed;

[0070] Generate multiple first-level cutting plans according to the expected construction progress, and establish a first-level cutting plan sequence J, J = (j1, j2...jm), where m is the number of first-level cutting plans; ji is the i-th first-level cutting plan;

[0071] Generate the operation evaluation value of each first-level cutting plan;

[0072] Establish an operation evaluation value sequence D, D = (d1, d2...dm), where di is the operation evaluation value of the i-th first-level cutting plan;

[0073] Set the first-level cutting plan corresponding to the maximum value dmax in the running evaluation value D as the second-level cutting plan;

[0074] Set the water jet cutting parameters and mud extraction pipe working parameters for each construction sub-area according to the secondary cutting plan;

[0075] The generating of the operation evaluation value of each primary cutting plan includes:

[0076] Select the target first-level cutting plan in sequence according to the first-level cutting plan sequence D;

[0077] Generate an operation evaluation value d of the target first-level cutting plan according to a preset construction evaluation model;

[0078]

[0079] Among them, e1 is the preset first weight coefficient, e2 is the preset second weight coefficient; Q1 is the preset first fixed coefficient; Q2 is the preset second fixed coefficient; fi is the reference evaluation value of the i-th water knife submodule in the target first-level cutting plan; μi is the influence factor of the i-th water knife submodule; pi is the reference value of the i-th operation evaluation index in the target first-level cutting plan; βi is the influence factor of the i-th operation evaluation index; r is the number of operation evaluation indicators;

[0080] Generate the operation evaluation value of each first-level cutting plan in turn.

[0081] In some embodiments of the present application, the first correction module is further used to:

[0082] Generate the sinking amount of each construction sub-area at the current feedback time node according to the caisson state parameters;

[0083] Establish a subsidence amount sequence G at the current feedback time node, G = (g1, g2...gn), where gi is the subsidence amount of the i-th construction sub-area at the current feedback time node;

[0084] Generate the settlement deviation evaluation value d of the current feedback time node;

[0085]

[0086] Among them, e3 is the preset third weight coefficient, e4 is the preset fourth weight coefficient; Q3 is the preset third fixed coefficient; Q4 is the preset fourth fixed coefficient; g' is the standard sinking amount of the current feedback time node; △ g is the average value of all data in the sinking amount series G;

[0087] Preset settlement deviation evaluation value threshold D1;

[0088] If d>D1, a first-level correction instruction is generated, and the first-level correction parameters of each water knife submodule are set according to the sinking amount series G;

[0089] Generate the shaft wall deviation of each construction sub-area according to the caisson state parameters;

[0090] Establish a wellbore deviation series H, H = (h1, h2...hn), where hi is the wellbore deviation of the i-th construction sub-area;

[0091] Preset the wellbore deviation threshold value H1;

[0092] If hi>H1, generate the secondary correction instruction of the i-th construction sub-area, and set the secondary correction parameters of the i-th water knife sub-module.

[0093] Compared with the prior art, the intelligent deviation-correcting caisson construction method and system of the present application embodiment has the following beneficial effects:

[0094] According to the equipment parameters of the caisson, multiple construction sub-areas are established, and a water knife sub-module is set in each construction sub-area. The working parameters between the water knife sub-modules are adjusted through the central control unit to cut the soil in each construction sub-area. The caisson is automatically sunk in cooperation with the mud suction pipe, thereby improving the construction quality of the caisson and reducing the construction cost of the caisson.

[0095] By adding correction units and monitoring units, the status parameters of the caisson are monitored in real time to ensure that the well wall in each construction sub-area is at the same sinking amount, thereby improving the controllability of the sinking. At the same time, the inclination state of the caisson is judged according to the sinking posture of the caisson, and corresponding correction instructions are set to ensure the construction accuracy of the caisson. BRIEF DESCRIPTION OF THE DRAWINGS

[0096] Figure 1 It is a flow chart of a caisson construction method with intelligent deviation correction in the preferred embodiment of the present application. DETAILED DESCRIPTION

[0097] The specific implementation methods of the present application are further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present application but are not intended to limit the scope of the present application.

[0098] In the description of the present application, it should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.

[0099] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, unless otherwise specified, "plurality" means two or more.

[0100] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0101] like Figure 1 As shown, a preferred embodiment of the present application embodiment is a caisson construction method with intelligent deviation correction, comprising:

[0102] S101: establishing multiple construction sub-areas according to the parameters of the caisson to be constructed, and generating a cutting plan according to the parameters of the caisson to be constructed;

[0103] S102: setting water jet cutting parameters and mud extraction pipe working parameters for each construction sub-area according to the cutting plan;

[0104] S103: Acquire caisson state parameters according to a preset feedback time node, and determine whether to correct the water jet cutting parameters according to the caisson state parameters.

[0105] Specifically, when establishing multiple construction sub-areas, including:

[0106] Generate a construction evaluation value a of the caisson to be constructed according to a preset caisson evaluation model and parameters of the caisson to be constructed;

[0107]

[0108] Among them, pi is the reference value of the i-th construction evaluation index of the caisson to be constructed; αi is the influencing factor of the i-th construction evaluation index; θ is the number of construction evaluation indicators;

[0109] The number of construction sub-areas n is set according to the construction evaluation value a;

[0110] Preset a first construction evaluation value interval (A1, A2), a second construction evaluation value interval (A2, A3) and a third construction evaluation interval (A3, A4);

[0111] If the construction evaluation value a is within the preset first construction evaluation value interval, the number of construction sub-areas n is set to the preset first number n1;

[0112] If the construction evaluation value a is within the preset second construction evaluation value interval, the number of construction sub-areas n is set to the preset second number n2;

[0113] If the construction evaluation value a is within the preset third construction evaluation value interval, the number of construction sub-areas n is set to the preset third number n3; and n1<n2<n3;

[0114] A construction sub-area sequence B is established according to the parameters of the caisson to be constructed and the number of construction sub-areas, where B = (b1, b2...bn), wherein bi is the i-th construction sub-area.

[0115] Specifically, the construction evaluation indicators include but are not limited to the cross-sectional area of ​​the caisson, the circumference of the caisson wall, soil parameters, etc. The larger the construction evaluation value, the greater the difficulty of the current caisson construction. By dynamically adjusting the number of construction sub-areas and increasing the corresponding water knife sub-modules, the control over the construction process is increased, thereby improving the construction speed and accuracy of the caisson.

[0116] In a preferred embodiment of the present application, when a cutting plan is generated according to the parameters of the caisson to be constructed, it includes:

[0117] Obtain a water knife submodule sequence C, C = (c1, c2, ... cn), where ci is the water knife submodule corresponding to the i-th construction sub-area;

[0118] Obtain the expected construction speed range of the caisson to be constructed;

[0119] Generate multiple first-level cutting plans according to the expected construction progress, and establish a first-level cutting plan sequence J, J = (j1, j2...jm), where m is the number of first-level cutting plans; ji is the i-th first-level cutting plan;

[0120] Generate the operation evaluation value of each first-level cutting plan;

[0121] Establish an operation evaluation value sequence D, D = (d1, d2...dm), where di is the operation evaluation value of the i-th first-level cutting plan;

[0122] Set the first-level cutting plan corresponding to the maximum value dmax in the running evaluation value D as the second-level cutting plan;

[0123] According to the secondary cutting plan, the water jet cutting parameters and the working parameters of the mud extraction pipe in each construction sub-area are set.

[0124] Specifically, a single primary cutting plan includes the water jet speed, water output, continuous cutting time and start / stop parameters of each water jet submodule, the working efficiency and operating cost parameters of the mud pump, and the estimated construction time parameters.

[0125] Specifically, when cutting the soil, each water knife sub-module can cut at the same time, or different water knife sub-modules can cut alternately, thereby reducing the cost of caisson construction.

[0126] Specifically, when generating the operation evaluation value of each primary cutting plan, it includes:

[0127] Select the target first-level cutting plan in sequence according to the first-level cutting plan sequence D;

[0128] Generate an operation evaluation value d of the target first-level cutting plan according to a preset construction evaluation model;

[0129]

[0130] Among them, e1 is the preset first weight coefficient, e2 is the preset second weight coefficient; Q1 is the preset first fixed coefficient; Q2 is the preset second fixed coefficient; fi is the reference evaluation value of the i-th water knife submodule in the target first-level cutting plan; μi is the influence factor of the i-th water knife submodule; pi is the reference value of the i-th operation evaluation index in the target first-level cutting plan; βi is the influence factor of the i-th operation evaluation index; r is the number of operation evaluation indicators;

[0131] Generate the operation evaluation value of each first-level cutting plan in turn.

[0132] Specifically, the reference evaluation value of the water knife sub-module is set according to parameters such as the water knife speed, continuous working time, start and stop frequency and failure probability of the water knife sub-module. The higher the operation evaluation value, the higher the operation efficiency of the corresponding water knife sub-module.

[0133] Specifically, the operation evaluation indicators include, but are not limited to, overall construction cost, workload of mud pumping pipes, accumulation of mud and water in construction sub-areas, uniformity of well wall subsidence in each construction sub-area and other parameters, and the value range of each operation evaluation indicator is the same.

[0134] Specifically, the model is normalized by using the first fixed coefficient and the second fixed coefficient so that each indicator is in the same value range.

[0135] Specifically, the higher the operation evaluation value, the higher the feasibility of the current first-level cutting plan, and the higher the overall benefit of its construction.

[0136] It can be understood that in the above embodiment, multiple construction sub-areas are established according to the equipment parameters of the caisson, and a water knife sub-module is set in each construction sub-area. The working parameters between the water knife sub-modules are adjusted by the central control unit to cut the soil in each construction sub-area, and the caisson is automatically sunk in cooperation with the mud suction pipe, thereby improving the construction quality of the caisson and reducing the construction cost of the caisson.

[0137] In a preferred embodiment of the present application, when judging whether to correct the water jet cutting parameters according to the caisson state parameters, it includes:

[0138] Generate the sinking amount of each construction sub-area at the current feedback time node according to the caisson state parameters;

[0139] Establish a subsidence amount sequence G at the current feedback time node, G = (g1, g2...gn), where gi is the subsidence amount of the i-th construction sub-area at the current feedback time node;

[0140] Generate the settlement deviation evaluation value d of the current feedback time node;

[0141]

[0142] Among them, e3 is the preset third weight coefficient, e4 is the preset fourth weight coefficient; Q3 is the preset third fixed coefficient; Q4 is the preset fourth fixed coefficient; g' is the standard sinking amount of the current feedback time node; △ g is the average value of all data in the sinking amount series G;

[0143] Preset settlement deviation evaluation value threshold D1;

[0144] If d>D1, a first-level correction instruction is generated, and the first-level correction parameters of each water knife sub-module are set according to the sinking amount series G.

[0145] Specifically, the first-level correction parameter is to appropriately increase the water jet cutting speed in the construction sub-area where the settlement amount is lower than the average level, and to appropriately reduce the water jet cutting speed in the construction sub-area where the settlement amount is higher than the average level, so as to ensure the overall settlement uniformity of the caisson and improve the construction control over the caisson.

[0146] Specifically, when judging whether to modify the water jet cutting parameters according to the caisson state parameters, it also includes:

[0147] Generate the shaft wall deviation of each construction sub-area according to the caisson state parameters;

[0148] Establish a wellbore deviation series H, H = (h1, h2...hn), where hi is the wellbore deviation of the i-th construction sub-area;

[0149] Preset the wellbore deviation threshold H1;

[0150] If hi>H1, generate the secondary correction instruction of the i-th construction sub-area, and set the secondary correction parameters of the i-th water knife sub-module.

[0151] Specifically, when deviation occurs, the deviation is corrected by controlling the degree to which the water jet submodule in the corresponding construction sub-area cuts the soil.

[0152] It can be understood that in the above embodiment, by real-time monitoring of the status parameters of the caisson, it is ensured that the well wall in each construction sub-area is at the same sinking amount, thereby improving the controllability of the sinking. At the same time, according to the sinking posture of the caisson, the inclination state of the caisson is judged, and corresponding correction instructions are set to ensure the construction accuracy of the caisson.

[0153] Based on another preferred embodiment of an intelligent deviation-correcting caisson construction system in any of the above preferred embodiments, this preferred embodiment provides an intelligent deviation-correcting caisson construction method, including:

[0154] The central control unit is used to establish multiple construction sub-areas according to the parameters of the caisson to be constructed;

[0155] The water jet unit includes a pressure pump truck and a plurality of water jet sub-modules. The water jet sub-modules are arranged on the inner side of the well wall and are used to cut the soil in the construction sub-area.

[0156] Mud extraction unit, used to extract mud and water in the construction sub-area;

[0157] Monitoring unit, used to collect caisson status parameters;

[0158] The central control unit includes:

[0159] A first processing module is used to establish multiple construction sub-areas;

[0160] The second processing module is used to generate a cutting plan according to the parameters of the caisson to be constructed, and set the water jet cutting parameters and the working parameters of the mud extraction pipe in each construction sub-area according to the cutting plan;

[0161] The first correction module is used to obtain the caisson state parameters according to the preset feedback time node, and determine whether to correct the water jet cutting parameters according to the caisson state parameters.

[0162] Specifically, the central control unit establishes a connection with the water jet unit and the mud pumping unit through wireless signals, thereby adjusting the working parameters of the water jet unit and the mud pumping unit in real time.

[0163] Specifically, the water jet unit is arranged on the wall of the caisson, and the mud pumping unit is preferably a mud pumping pipe, which can be arranged outside the wall or pre-buried in the middle. The soil is cut by the high-pressure water jet, and the caisson is automatically sunk in cooperation with the mud pumping pipe.

[0164] Specifically, the monitoring unit is preferably a rangefinder arranged on the outer wall of the caisson, which senses the sinking posture of the caisson through the rangefinder. If deviation occurs, the deviation is corrected by controlling the degree of water jet cutting of the soil in the corresponding area.

[0165] Specifically, the first processing module is also used for:

[0166] Generate a construction evaluation value a of the caisson to be constructed according to a preset caisson evaluation model and parameters of the caisson to be constructed;

[0167]

[0168] Among them, pi is the reference value of the i-th construction evaluation index of the caisson to be constructed; αi is the influencing factor of the i-th construction evaluation index; θ is the number of construction evaluation indicators;

[0169] The number of construction sub-areas n is set according to the construction evaluation value a;

[0170] Preset a first construction evaluation value interval (A1, A2), a second construction evaluation value interval (A2, A3) and a third construction evaluation interval (A3, A4);

[0171] If the construction evaluation value a is within the preset first construction evaluation value interval, the number of construction sub-areas n is set to the preset first number n1;

[0172] If the construction evaluation value a is within the preset second construction evaluation value interval, the number of construction sub-areas n is set to the preset second number n2;

[0173] If the construction evaluation value a is within the preset third construction evaluation value interval, the number of construction sub-areas n is set to the preset third number n3; and n1<n2<n3;

[0174] A construction sub-area sequence B is established according to the parameters of the caisson to be constructed and the number of construction sub-areas, where B = (b1, b2...bn), wherein bi is the i-th construction sub-area.

[0175] In a preferred embodiment of the present application, the second processing module is also used for:

[0176] Obtain a water knife submodule sequence C, C = (c1, c2, ... cn), where ci is the water knife submodule corresponding to the i-th construction sub-area;

[0177] Obtain the expected construction speed range of the caisson to be constructed;

[0178] Generate multiple first-level cutting plans according to the expected construction progress, and establish a first-level cutting plan sequence J, J = (j1, j2...jm), where m is the number of first-level cutting plans; ji is the i-th first-level cutting plan;

[0179] Generate the operation evaluation value of each first-level cutting plan;

[0180] Establish an operation evaluation value sequence D, D = (d1, d2...dm), where di is the operation evaluation value of the i-th first-level cutting plan;

[0181] Set the first-level cutting plan corresponding to the maximum value dmax in the running evaluation value D as the second-level cutting plan;

[0182] Set the water jet cutting parameters and mud extraction pipe working parameters for each construction sub-area according to the secondary cutting plan;

[0183] When generating the operational evaluation values ​​for each primary cutting plan, it includes:

[0184] Select the target first-level cutting plan in sequence according to the first-level cutting plan sequence D;

[0185] Generate an operation evaluation value d of the target first-level cutting plan according to a preset construction evaluation model;

[0186]

[0187] Among them, e1 is the preset first weight coefficient, e2 is the preset second weight coefficient; Q1 is the preset first fixed coefficient; Q2 is the preset second fixed coefficient; fi is the reference evaluation value of the i-th water knife submodule in the target first-level cutting plan; μi is the influence factor of the i-th water knife submodule; pi is the reference value of the i-th operation evaluation index in the target first-level cutting plan; βi is the influence factor of the i-th operation evaluation index; r is the number of operation evaluation indicators;

[0188] Generate the operation evaluation value of each first-level cutting plan in turn.

[0189] In a preferred embodiment of the present application, the first correction module is also used for:

[0190] Generate the sinking amount of each construction sub-area at the current feedback time node according to the caisson state parameters;

[0191] Establish a subsidence amount sequence G at the current feedback time node, G = (g1, g2...gn), where gi is the subsidence amount of the i-th construction sub-area at the current feedback time node;

[0192] Generate the settlement deviation evaluation value d of the current feedback time node;

[0193]

[0194] Among them, e3 is the preset third weight coefficient, e4 is the preset fourth weight coefficient; Q3 is the preset third fixed coefficient; Q4 is the preset fourth fixed coefficient; g' is the standard sinking amount of the current feedback time node; △ g is the average value of all data in the sinking amount series G;

[0195] Preset settlement deviation evaluation value threshold D1;

[0196] If d>D1, a first-level correction instruction is generated, and the first-level correction parameters of each water knife submodule are set according to the sinking amount series G;

[0197] Generate the shaft wall deviation of each construction sub-area according to the caisson state parameters;

[0198] Establish a wellbore deviation series H, H = (h1, h2...hn), where hi is the wellbore deviation of the i-th construction sub-area;

[0199] Preset the wellbore deviation threshold value H1;

[0200] If hi>H1, generate the secondary correction instruction of the i-th construction sub-area, and set the secondary correction parameters of the i-th water knife sub-module.

[0201] According to the first concept of the present application, multiple construction sub-areas are established according to the equipment parameters of the caisson, and a water knife sub-module is set in each construction sub-area. The working parameters between the water knife sub-modules are adjusted by the central control unit to cut the soil in each construction sub-area. The caisson is automatically sunk by cooperating with the mud suction pipe, thereby improving the construction quality of the caisson and reducing the construction cost of the caisson.

[0202] According to the second concept of the present application, by adding a correction unit and a monitoring unit, the state parameters of the caisson are monitored in real time to ensure that the well wall in each construction sub-area is at the same sinking amount, thereby improving the controllability of the sinking. At the same time, the inclination state of the caisson is judged according to the sinking posture of the caisson, and corresponding correction instructions are set to ensure the construction accuracy of the caisson.

[0203] The above is only a preferred implementation of the present application. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present application. These improvements and substitutions should also be regarded as the scope of protection of the present application.

Claims

1. A caisson construction method with intelligent deviation correction, characterized in that: include: Establish multiple construction sub-areas according to the parameters of the caisson to be constructed, and generate a cutting plan according to the parameters of the caisson to be constructed; Set the water jet cutting parameters and mud extraction pipe working parameters for each construction sub-area according to the cutting plan; The caisson status parameters are obtained according to the preset feedback time node, and it is determined whether to correct the water jet cutting parameters according to the caisson status parameters.

2. The intelligent deviation-correcting caisson construction method according to claim 1, characterized in that: The establishment of multiple construction sub-areas includes: Generate a construction evaluation value a of the caisson to be constructed according to a preset caisson evaluation model and parameters of the caisson to be constructed; Among them, pi is the reference value of the i-th construction evaluation index of the caisson to be constructed; αi is the influencing factor of the i-th construction evaluation index; θ is the number of construction evaluation indicators; The number of construction sub-areas n is set according to the construction evaluation value a; Preset a first construction evaluation value interval (A1, A2), a second construction evaluation value interval (A2, A3) and a third construction evaluation interval (A3, A4); If the construction evaluation value a is within the preset first construction evaluation value interval, the number of construction sub-areas n is set to the preset first number n1; If the construction evaluation value a is within the preset second construction evaluation value interval, the number of construction sub-areas n is set to the preset second number n2; If the construction evaluation value a is within the preset third construction evaluation value interval, the number of construction sub-areas n is set to the preset third number n3; and n1<n2<n3; A construction sub-area sequence B is established according to the parameters of the caisson to be constructed and the number of construction sub-areas, where B = (b1, b2...bn), wherein bi is the i-th construction sub-area.

3. The intelligent deviation-correcting caisson construction method according to claim 2, characterized in that: When generating a cutting plan based on the parameters of the caisson to be constructed, it includes: Obtain a water knife submodule sequence C, C = (c1, c2, ... cn), where ci is the water knife submodule corresponding to the i-th construction sub-area; Obtain the expected construction speed range of the caisson to be constructed; Generate multiple first-level cutting plans according to the expected construction progress, and establish a first-level cutting plan sequence J, J = (j1, j2...jm), where m is the number of first-level cutting plans; ji is the i-th first-level cutting plan; Generate the operation evaluation value of each first-level cutting plan; Establish an operation evaluation value sequence D, D = (d1, d2...dm), where di is the operation evaluation value of the i-th first-level cutting plan; Set the first-level cutting plan corresponding to the maximum value dmax in the running evaluation value D as the second-level cutting plan; According to the secondary cutting plan, the water jet cutting parameters and the working parameters of the mud extraction pipe in each construction sub-area are set.

4. The intelligent deviation-correcting caisson construction method according to claim 3 is characterized in that: When generating the operational evaluation values ​​for each primary cutting plan, it includes: Select the target first-level cutting plan in sequence according to the first-level cutting plan sequence D; Generate an operation evaluation value d of the target first-level cutting plan according to a preset construction evaluation model; Among them, e1 is the preset first weight coefficient, e2 is the preset second weight coefficient; Q1 is the preset first fixed coefficient; Q2 is the preset second fixed coefficient; fi is the reference evaluation value of the i-th water knife submodule in the target first-level cutting plan; μi is the influence factor of the i-th water knife submodule; pi is the reference value of the i-th operation evaluation index in the target first-level cutting plan; βi is the influence factor of the i-th operation evaluation index; r is the number of operation evaluation indicators; Generate the operation evaluation value of each first-level cutting plan in turn.

5. The intelligent deviation-correcting caisson construction method according to claim 4, characterized in that: When judging whether to modify the water jet cutting parameters according to the caisson status parameters, it includes: Generate the sinking amount of each construction sub-area at the current feedback time node according to the caisson state parameters; Establish a subsidence amount sequence G at the current feedback time node, G = (g1, g2...gn), where gi is the subsidence amount of the i-th construction sub-area at the current feedback time node; Generate the settlement deviation evaluation value d of the current feedback time node; Among them, e3 is the preset third weight coefficient, e4 is the preset fourth weight coefficient; Q3 is the preset third fixed coefficient; Q4 is the preset fourth fixed coefficient; g' is the standard sinking amount of the current feedback time node; △ g is the average value of all data in the sinking amount series G; Preset settlement deviation evaluation value threshold D1; If d>D1, a first-level correction instruction is generated, and the first-level correction parameters of each water knife sub-module are set according to the sinking amount series G.

6. The intelligent deviation-correcting caisson construction method according to claim 5, characterized in that: When judging whether to modify the water jet cutting parameters according to the caisson status parameters, it also includes: Generate the shaft wall deviation of each construction sub-area according to the caisson state parameters; Establish a wellbore deviation series H, H = (h1, h2...hn), where hi is the wellbore deviation of the i-th construction sub-area; Preset the wellbore deviation threshold H1; If hi>H1, generate the secondary correction instruction of the i-th construction sub-area, and set the secondary correction parameters of the i-th water knife sub-module.

7. An intelligent deviation-correcting caisson construction system, using the intelligent deviation-correcting caisson construction method described in any one of claims 1 to 6, characterized in that: include: The central control unit is used to establish multiple construction sub-areas according to the parameters of the caisson to be constructed; A water jet unit, comprising a pressure pump truck and a plurality of water jet sub-modules, wherein the water jet sub-modules are arranged inside the well wall and are used to cut the soil in the construction sub-area; Mud extraction unit, used to extract mud and water in the construction sub-area; Monitoring unit, used to collect caisson status parameters; The central control unit comprises: A first processing module is used to establish multiple construction sub-areas; The second processing module is used to generate a cutting plan according to the parameters of the caisson to be constructed, and set the water jet cutting parameters and the working parameters of the mud extraction pipe in each construction sub-area according to the cutting plan; The first correction module is used to obtain the caisson state parameters according to the preset feedback time node, and determine whether to correct the water jet cutting parameters according to the caisson state parameters.

8. The intelligent deviation-correcting caisson construction system according to claim 7, characterized in that: The first processing module is also used for: Generate a construction evaluation value a of the caisson to be constructed according to a preset caisson evaluation model and parameters of the caisson to be constructed; Among them, pi is the reference value of the i-th construction evaluation index of the caisson to be constructed; αi is the influencing factor of the i-th construction evaluation index; θ is the number of construction evaluation indicators; The number of construction sub-areas n is set according to the construction evaluation value a; Preset a first construction evaluation value interval (A1, A2), a second construction evaluation value interval (A2, A3) and a third construction evaluation interval (A3, A4); If the construction evaluation value a is within the preset first construction evaluation value interval, the number of construction sub-areas n is set to the preset first number n1; If the construction evaluation value a is within the preset second construction evaluation value interval, the number of construction sub-areas n is set to the preset second number n2; If the construction evaluation value a is within the preset third construction evaluation value interval, the number of construction sub-areas n is set to the preset third number n3; and n1<n2<n3; A construction sub-area sequence B is established according to the parameters of the caisson to be constructed and the number of construction sub-areas, where B = (b1, b2...bn), wherein bi is the i-th construction sub-area.

9. The intelligent deviation-correcting caisson construction system according to claim 8, characterized in that: The second processing module is also used for: Obtain a water knife submodule sequence C, C = (c1, c2, ... cn), where ci is the water knife submodule corresponding to the i-th construction sub-area; Obtain the expected construction speed range of the caisson to be constructed; Generate multiple first-level cutting plans according to the expected construction progress, and establish a first-level cutting plan sequence J, J = (j1, j2...jm), where m is the number of first-level cutting plans; ji is the i-th first-level cutting plan; Generate the operation evaluation value of each first-level cutting plan; Establish an operation evaluation value sequence D, D = (d1, d2...dm), where di is the operation evaluation value of the i-th first-level cutting plan; Set the first-level cutting plan corresponding to the maximum value dmax in the running evaluation value D as the second-level cutting plan; Set the water jet cutting parameters and mud extraction pipe working parameters for each construction sub-area according to the secondary cutting plan; The generating of the operation evaluation value of each primary cutting plan includes: Select the target first-level cutting plan in sequence according to the first-level cutting plan sequence D; Generate an operation evaluation value d of the target first-level cutting plan according to a preset construction evaluation model; Among them, e1 is the preset first weight coefficient, e2 is the preset second weight coefficient; Q1 is the preset first fixed coefficient; Q2 is the preset second fixed coefficient; fi is the reference evaluation value of the i-th water knife submodule in the target first-level cutting plan; μi is the influence factor of the i-th water knife submodule; pi is the reference value of the i-th operation evaluation index in the target first-level cutting plan; βi is the influence factor of the i-th operation evaluation index; r is the number of operation evaluation indicators; Generate the operation evaluation value of each first-level cutting plan in turn.

10. The intelligent deviation-correcting caisson construction system according to claim 9, characterized in that: The first correction module is also used for: Generate the sinking amount of each construction sub-area at the current feedback time node according to the caisson state parameters; Establish a subsidence amount sequence G at the current feedback time node, G = (g1, g2...gn), where gi is the subsidence amount of the i-th construction sub-area at the current feedback time node; Generate the settlement deviation evaluation value d of the current feedback time node; Among them, e3 is the preset third weight coefficient, e4 is the preset fourth weight coefficient; Q3 is the preset third fixed coefficient; Q4 is the preset fourth fixed coefficient; g' is the standard sinking amount of the current feedback time node; △ g is the average value of all data in the sinking amount series G; Preset settlement deviation evaluation value threshold D1; If d>D1, a first-level correction instruction is generated, and the first-level correction parameters of each water knife submodule are set according to the sinking amount series G; Generate the shaft wall deviation of each construction sub-area according to the caisson state parameters; Establish a wellbore deviation series H, H = (h1, h2...hn), where hi is the wellbore deviation of the i-th construction sub-area; Preset the wellbore deviation threshold H1; If hi>H1, generate the secondary correction instruction of the i-th construction sub-area, and set the secondary correction parameters of the i-th water knife sub-module.