Conversion construction process of double-side-wall pilot tunnel method and three-step excavation method
By combining the double-side wall guide pit method with the three-step excavation method in the excavation of deep hard surrounding rock tunnels, using anchor cables and concrete support, the low construction efficiency and safety of the single double-side wall guide pit method are solved Problems with major hidden dangers have been eliminated and more efficient and safer tunnel construction has been achieved.
Patent Information
- Application Number
- CN202410739315.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-07
- Publication Date
- 2024-10-01
AI Technical Summary
During the excavation of deep tunnels in hard surrounding rock, the single double-side wall guide pit method leads to large construction interference, low construction efficiency, difficulty in dismantling temporary supports, and potential safety hazards.
The double-side wall guide pit method and the three-step excavation method are used to convert the construction technology. First, the double-side wall guide pit method is excavated to a predetermined depth, and then converted to the three-step seven-step method, using anchor cables and concrete supports to reduce temporary Support and demolition to improve construction efficiency and safety.
It improves construction efficiency, reduces construction safety hazards, saves materials, reduces disturbance to stable earthwork, and improves the construction conditions of the tunnel inner wall support structure.
Smart Images

Figure CN118728392A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of tunnel construction, and in particular to a construction process for converting a double-side wall pilot tunnel method into a three-step excavation method. Background Art
[0002] During tunnel excavation construction, for the shallow buried biased section of V-level surrounding rock at the main entrance of the tunnel, the double-side wall pilot pit method combined with large pipe shed advance support construction should be adopted. The principle of the double-side wall pilot pit method is to use the unexcavated rock mass to divide the entire large section of the tunnel into three small sections: left, middle and right. The left and right pilot pits are constructed first, followed by the middle pilot pit. After the initial support arch is formed into a ring, the temporary supports of the guide pits on both sides are removed to form a full section.
[0003] With regard to the above-mentioned related technologies, when excavating a tunnel with deeply buried and unbiased hard surrounding rock, using a single double-side wall pilot pit method for tunnel excavation construction will result in larger cross-section blocks of the double-side wall pilot pit, and the construction will interfere with each other, causing greater disturbance; and the temporary support provided by the double-side wall pilot pit on one side of the core soil is difficult to remove later, and the removal will cause secondary disturbance to the already formed stable surrounding rock, posing certain safety hazards; in order to ensure the overall construction progress and construction safety of the tunnel, it is necessary to change the tunnel excavation method. Summary of the invention
[0004] In order to change the tunnel excavation method and reduce the potential safety hazards during construction, the present application provides a construction process for converting the double-side wall pilot tunnel method and the three-step excavation method.
[0005] The double-side wall pilot pit method and three-step excavation method conversion construction process provided in this application adopts the following technical solution: The double-side wall pilot pit method and the three-step excavation method conversion construction process include: S1: excavate the tunnel entrance at the predetermined location of the tunnel; S2: Double sidewall pilot pit excavation: First, excavate the first pilot pits on the left and right sides of the tunnel at the tunnel entrance. Each first pilot pit includes an upper pilot pit and a lower pilot pit. Then, excavate the second pilot pit in the center. The second pilot pit includes a middle pilot pit and a bottom pilot pit. S3: When the first pilot pit on one side is excavated to a predetermined depth, the excavation of the first pilot pit on that side is stopped, and the first pilot pit and the second pilot pit on the other side are continued to be excavated until the depth of the upper pilot pit at each location is the same as the depth of the middle pilot pit, and the depth of the lower pilot pit at each location is the same as the depth of the bottom pilot pit; S4: The third pilot pit is excavated at the top of the tunnel. The soil at the bottom of the third pilot pit forms the first step; the soil at the upper pilot pit forms the second step, and the soil at the lower pilot pit forms the third step. S5: Continue tunneling using the three-bench, seven-step method.
[0006] By adopting the above technical scheme, before excavating the tunnel, geological prediction is first carried out, and the location where superhard rock exists is set as the predetermined excavation depth using the double-side wall pilot method. Then, the double-side wall pilot method is used to excavate the tunnel to the predetermined depth, and then the conversion is started, and the earthwork of each pilot pit is formed into a three-layer step foundation of the three-step seven-step method, thereby reducing the construction process required for the conversion construction method; using this conversion process, first, it can improve the construction efficiency, from the original 30m / month construction efficiency of the double-side wall pilot method to 50m / month, greatly improving the construction efficiency; second, compared with the double-side wall pilot method, the converted construction method does not need to repeat temporary support and demolition, saving materials and public expenses. At the same time, after eliminating the construction of temporary support, the disturbance of the stabilized earthwork when removing the support is reduced, and the safety hazards during construction are reduced. Third, the conversion to the three-step seven-step excavation method can change the narrow double-side wall pilot site and the small construction operation radius, which is more conducive to the construction of tunnel inner wall support structures such as anchors.
[0007] Preferably, the specific method of step S2 includes: after excavating the first pilot pit, driving anchor cables into the earthwork of the inner wall of each location of the first pilot pit away from the geometric center of the tunnel, and then filling concrete into each location of the inner wall of the first pilot pit to seal it.
[0008] By adopting the above technical solution, the inner wall of the tunnel is supported by the connection between the anchor cable and the concrete, thereby improving the overall safety factor of the tunnel.
[0009] Preferably, the specific method of step S2 also includes: S21: after excavating the first pilot pit, using support components to temporarily support the inner walls of the first pilot pit, and then filling the inner walls of the first pilot pit with concrete to seal them.
[0010] By adopting the above technical solution, a support assembly is used to form a temporary support for the inner wall, thereby reducing the risk of collapse of the inner wall and improving the safety factor of workers during construction.
[0011] Preferably, corresponding support assemblies are provided on the left and right inner walls of each of the first guide pits, and an opening is formed between the two support assemblies in the same first guide pit for engineering machinery to enter the first guide pit; each of the support assemblies includes an engineering vehicle and a support frame, the engineering vehicle is movably arranged in the first guide pit along the length direction of the first guide pit, and the support frame is installed on the engineering vehicle and abuts against the corresponding inner wall.
[0012] By adopting the above technical solution, after a movable engineering vehicle is set up, when the workers complete the excavation of the first pilot pit in front, the engineering vehicle is moved, thereby driving the top plate to move to the inner wall filled with concrete to support the earthwork at that location, so as to facilitate the workers to fix the anchor cables and fill the concrete at the excavated earthwork. Compared with directly erecting the steel structure in the tunnel to support the inner wall, it is only necessary to move the support assembly to the side wall to quickly support the inner wall, thereby speeding up the construction speed of the workers, and multiple groups of engineering vehicles can be set up according to the on-site conditions to support various locations of the first pilot pit, thereby further improving the support strength; finally, because the tunnel design accuracy is relatively high, the support frame designed to be adapted to the inner wall of each location of the tunnel can accurately abut against the side wall, thereby improving the support strength of the support assembly for various locations of the first pilot pit.
[0013] Preferably, an airbag is provided on a side of the support frame away from the engineering vehicle.
[0014] By adopting the above technical solution, the ductile airbag can increase the contact area between the support frame and the inner wall, thereby improving the support capacity of the support frame to the inner wall.
[0015] Preferably, a side frame is circumferentially arranged on a side of the support frame away from the engineering vehicle, and each of the side frames and the support frame forms a template for fixing liquid concrete; a slurry inlet is arranged on the side frame, a plastic film is arranged on a side of the airbag away from the engineering vehicle, and a demoulding component for assisting concrete demoulding is installed on the support frame.
[0016] By adopting the above technical solution, the support frame is abutted against the inner wall, and then concrete is poured into the formwork through the slurry inlet until the concrete overflows from the slurry inlet. At this time, the formwork is full of concrete. At this time, it is only necessary to wait for the concrete to solidify and start the demoulding assembly to separate the support frame from the concrete, thereby completing the closure of the inner wall of each first guide pit. This method will first change the method of filling concrete to pouring concrete into the formwork until the high-pressure concrete slurry overflows, which means that the concrete is fully filled. Compared with the filling solution, the basic requirements for concrete construction are reduced. At the same time, the side frame intercepts the concrete in the formwork, thereby reducing the loss of concrete and reducing the project cost.
[0017] Preferably, the demoulding assembly comprises an air pump and an air nozzle, the air nozzle is mounted on the air bag, and the air pump is connected to the air bag via an air pipe.
[0018] By adopting the above technical solution, when the concrete pouring is completed and demoulding is required, it is only necessary to deflate the airbag so that the airbag shrinks and no longer presses against the concrete, and the concrete is demoulded. Then the engineering vehicle is moved to make the support frame completely separate from the concrete. At this time, the airbag is inflated again, and the support assembly can be used to support the inner wall of the first guide pit.
[0019] Preferably, the steps after S21 further include: after two demoulding operations of concrete are completed in sequence using the support assembly, filling the gap between the two groups of formed concrete.
[0020] By adopting the above technical solution, due to the thickness of the side frame, after completing one round of concrete pouring, there is a gap between the two groups of formed concrete. At this time, after the gap is filled manually, the supporting stability of the entire inner wall of the tunnel is improved.
[0021] Preferably, the specific method of S5 includes: after excavating the tunnel using the three-step seven-step method, removing the support components in each of the first pilot pits and located close to the geometric center of the tunnel, and retaining the support components in each of the first pilot pits and away from the geometric center of the tunnel to support the inner wall of the tunnel.
[0022] By adopting the above technical solution, since the inner wall shapes of the tunnel at various locations along the length direction are consistent, the support components far away from the geometric center of the tunnel can continue to support the inner wall of the tunnel excavated using the three-step seven-step method and pour concrete to form a stable support structure, thereby realizing the reverse use of the support components.
[0023] In summary, the present application includes at least one of the following beneficial technical effects: 1. First, it can improve construction efficiency, from the original 30m / month construction efficiency of the double-side wall pilot method to 50m / month, greatly improving construction efficiency; second, compared with the double-side wall pilot method, the converted construction method does not need to repeat temporary support and removal, saving materials and public expenses. At the same time, after eliminating the construction of temporary support, the disturbance of the stabilized earthwork during the removal of support is reduced, reducing safety hazards during construction. Third, the conversion to the three-step seven-step excavation method can change the narrow double-side wall pilot site and small construction radius, which is more conducive to the construction of tunnel inner wall support structures such as anchors; 2. Move the support assembly to the side wall to quickly support the inner wall, speed up the construction of workers, and set up multiple groups of engineering vehicles according to the site conditions to support various locations of the first pilot pit, further improving the support strength; 3. The method of filling concrete will be changed to pouring concrete into the formwork until the high-pressure concrete slurry overflows, which means the concrete is fully filled. Compared with the filling solution, the basic requirements for concrete construction are reduced. At the same time, the side frame intercepts the concrete in the formwork, reducing the loss of concrete and reducing the project cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a schematic diagram of the tunnel structure when the double-side wall pilot pit method is used for excavation in an embodiment of the present application.
[0025] Figure 2 It is a front view of the tunnel structure when the double-side wall pilot pit method is used for excavation in an embodiment of the present application.
[0026] Figure 3 This is a diagram showing the relationship between the tunnel and anchor cable positions when the double-side wall pilot tunnel method is used for excavation in an embodiment of the present application.
[0027] Figure 4 It is a cross-sectional view of the support assembly of an embodiment of the present application.
[0028] Figure 5 It is a schematic diagram of the tunnel structure when the three-step seven-step method is used for excavation in an embodiment of the present application.
[0029] Figure 6 This is a front view of the tunnel when the three-step seven-step method is used for excavation in the embodiment of the present application.
[0030] Figure 7 This is a top view of the tunnel when the three-step seven-step method is used for excavation in the embodiment of the present application.
[0031] Description of reference numerals: 1. Tunnel; 11. Anchor cable; 2. First pilot pit; 21. Upper pilot pit; 22. Lower pilot pit; 3. Second pilot pit; 31. Middle pilot pit; 32. Bottom pilot pit; 4. Third pilot pit; 51. First step; 52. Second step; 53. Third step; 6. Support assembly; 61. Engineering vehicle; 62. Support frame; 63. Side frame; 64. Airbag; 65. Air pump. DETAILED DESCRIPTION
[0032] The following is combined with Figure 1-7 This application is described in further detail.
[0033] The present application embodiment discloses a construction process for converting a double-sidewall pilot pit method into a three-step excavation method. Figure 1 The conversion construction process of double side wall pilot pit method and three-step excavation method includes: S1: Conduct advance geological prediction and measurement of the planned excavation location of Tunnel 1, and carry out advance support at the planned excavation location of Tunnel 1. Then workers use excavators to excavate the entrance of Tunnel 1; S2: Double sidewall pilot method excavation: refer to Figure 1 and Figure 2, the first pilot pits 2 on the left and right sides are excavated in sequence at the tunnel entrance 1, wherein the excavation depth of the first pilot pit 2 on one side is greater than the excavation depth of the first pilot pit 2 on the other side; each first pilot pit 2 includes an upper pilot pit 21 and a lower pilot pit 22. During excavation, the upper pilot pit 21 is excavated first, and when the upper pilot pit 21 is deep enough, the lower pilot pit 22 is excavated; when the first pilot pits 2 on both sides are excavated to a predetermined depth, the excavation of the middle second pilot pit 3 is started, and the second pilot pit 3 includes a middle pilot pit 31 and a bottom pilot pit 32. During excavation, the middle pilot pit 31 is excavated to a predetermined depth first, and then the bottom pilot pit 32 is excavated, so that the earthwork at the middle pilot pit 31 has sufficient bearing capacity for the internal construction equipment and personnel.
[0034] Reference Figure 3 The specific method in S2 includes: S21: after excavating the first pilot pit 2, anchor cables 11 are driven into the earthwork of the inner wall of each location of the first pilot pit 2 away from the geometric center of the tunnel 1, and the inner wall of each location of the first pilot pit 2 is temporarily supported by the support assembly 6, and then the inner wall of each location of the first pilot pit 2 is filled with concrete to seal it. Through the combination of concrete and anchor cables 11, the stability of the inner wall of the tunnel 1 is improved, thereby enhancing the overall structural stability of the tunnel 1.
[0035] Reference Figure 1 and Figure 2 , the inner walls on both sides of each first guide pit 2 are provided with corresponding support components 6, and a hole for engineering machinery to enter the first guide pit 2 is formed between the two support components 6 in the same first guide pit 2; Figure 4 Each support assembly 6 includes an engineering vehicle 61 and a support frame 62. The engineering vehicle 61 is movably arranged in the first guide pit 2 along the length direction of the first guide pit 2. The support frame 62 is installed on the engineering vehicle 61 and abuts against the corresponding inner wall. A pair of driving cylinders are rotatably installed on the engineering vehicle 61, and the output ends of the two driving cylinders are rotatably installed on the support frame 62. The position of the support frame 62 on the engineering vehicle 61 can be adjusted by starting and stopping the driving cylinder, thereby adjusting the position of the support frame 62 at the inner wall of the tunnel 1, so that the support frame 62 can adapt to the inner wall; the side walls of each support frame 62 are adapted to the corresponding inner wall of the first guide pit 2; an air bag 64 is arranged on the side of the support frame 62 away from the engineering vehicle 61, and the abutment of the air bag 64 can increase the abutment area of the clamping frame against the inner wall and make the support frame 62 further adapt to the inner walls of various places of the first guide pit 2, so that the support assembly 6 plays a stable supporting role.
[0036] In S21, when the support assembly 6 is used for construction, after the first pilot pit 2 of a certain depth is excavated, concrete is first laid on the bottom of the first pilot pit 2 to form a bottom plate, the earthwork at the location is fixed, and then each support assembly 6 is hoisted as a whole into each first pilot pit 2; After each group of engineering vehicles 61 and support frames 62 are hoisted into each first guide pit 2, the driving cylinder is started to adjust the position of the support frame 62 until the airbag 64 accurately abuts against the inner wall at each location. At this time, the support of the interior of each location in the first guide pit 2 is completed, and the workers can carry out excavation construction in the first guide pit 2, thereby improving the construction safety factor of the workers in the first guide pit 2; and when the pouring of concrete at that location is completed, the air nozzle is opened, and after the airbag 64 leaks and shrinks, the support frame 62 is no longer tightly attached to the inner wall, and the engineering vehicle 61 has room for movement. At this time, the workers can move the engineering vehicle 61 along the length direction of the tunnel 1 to start supporting the next section of the tunnel 1.
[0037] Reference Figure 4 A side frame 63 is circumferentially arranged on the side of the support frame 62 away from the engineering vehicle 61, and each side frame 63 and the support frame 62 form a template for fixing liquid concrete; a slurry inlet is arranged on the side frame 63, and a plastic film is arranged on the side of the air bag 64 away from the engineering vehicle 61, and the plastic film can separate the air bag 64 from the concrete slurry, making it difficult for the concrete slurry to condense on the air bag 64, so that the concrete can be completely adhered to the inner wall of the tunnel 1.
[0038] Reference Figure 4 A demoulding assembly for assisting concrete demoulding is installed on the support frame 62; the demoulding assembly includes an air pump 65 and an air nozzle, the air nozzle is installed on the air bag 64, the air pump 65 is connected to the air bag 64 through an air pipe, when the air nozzle is opened to extract the gas in the air bag 64, the air bag 64 shrinks and no longer abuts against the concrete, and there is room for movement on the support frame 62, and then the driving cylinder is started to drive the support frame 62 to move towards the engineering vehicle 61, at this time, the support frame 62 is completely separated from the concrete, thereby realizing the demoulding of the concrete; after demoulding, the air pump 65 is started to fill the air bag 64, and at the same time, the workers move the engineering vehicle 61 to support the support assembly 6 to support the next excavated segment and to seal the concrete grouting of the inner wall.
[0039] The steps after S21 also include: after completing two concrete demouldings in sequence using the support assembly 6, filling the gap between the two groups of formed concrete; after completing the large area of inner wall concrete filling, the workers only need to fill the smaller gaps with concrete to complete the concrete filling of the entire inner wall of the tunnel 1 at that location, reducing the workers' manual workload.
[0040] S3: When the first pilot pit 2 on one side is excavated to a predetermined depth, the excavation of the first pilot pit 2 on the side is stopped, and the first pilot pit 2 and the second pilot pit 3 on the other side are continued to be excavated until the depth of the upper pilot pit 21 at each location is the same as the depth of the middle pilot pit 31, and the depth of the lower pilot pit 22 at each location is the same as the depth of the bottom pilot pit 32. At this time, the depths of the pilot pits at the same height are the same, which is a good foundation for forming steps at the same height; S4: Reference Figure 5 , Figure 6 and Figure 7 , a third pilot pit 4 is excavated at the top of the tunnel 1, and the earthwork at the bottom of the third pilot pit 4 forms a first step 51; the earthwork at the upper pilot pit 21 forms a second step 52, and the earthwork at the lower pilot pit 22 forms a third step 53, thereby forming the construction foundation of the three-step seven-step method; S5: Complete the construction method conversion and continue to excavate Tunnel 1 using the three-bench seven-step method.
[0041] The specific method of S5 includes: S51: After excavating the tunnel 1 using the three-step seven-step method, remove the support components 6 in each first pilot pit 2 and located near the geometric center of the tunnel 1, and retain the support components 6 in each first pilot pit 2 and away from the geometric center of the tunnel 1 to support the inner wall of the tunnel 1. There is a slope formed by earthwork between the steps on the same side to facilitate the movement of the support components 6 on each step.
[0042] S52: After a certain length of tunnel 1 is excavated using the three-step seven-step method, the driving cylinder is started to adjust the position of the support frame 62 so that the support frame 62 is close to the inner wall of the tunnel 1 at that location, and then concrete slurry is injected into the template formed by the support frame 62 and the side frame 63 through the grouting port. After the concrete slurry solidifies, the air nozzle is opened to shrink the air bag 64 and no longer abut against the concrete. At the same time, the driving cylinder is started to move the support frame 62 toward the engineering vehicle 61, thereby completing the demoulding of the concrete.
[0043] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. The double-side wall pilot pit method and the three-step excavation method conversion construction process is characterized by: The construction process includes: S1: excavating a tunnel (1) entrance at a predetermined position of the tunnel (1); S2: excavation using the double sidewall pilot pit method: firstly excavating the first pilot pits (2) on the left and right sides of the tunnel (1) at the tunnel (1) entrance, each first pilot pit (2) comprising an upper pilot pit (21) and a lower pilot pit (22); then excavating the second pilot pit (3) in the center, the second pilot pit (3) comprising a middle pilot pit (31) and a bottom pilot pit (32); S3: When the first pilot pit (2) on one side is excavated to a predetermined depth, the excavation of the first pilot pit (2) on that side is stopped, and the first pilot pit (2) and the second pilot pit (3) on the other side are continued to be excavated until the depth of the upper pilot pit (21) at each location is the same as the depth of the middle pilot pit (31), and the depth of the lower pilot pit (22) at each location is the same as the depth of the bottom pilot pit (32); S4: excavating a third pilot pit (4) at the top of the tunnel (1); the earthwork at the bottom of the third pilot pit (4) forms a first step (51); the earthwork at the upper pilot pit (21) forms a second step (52); and the earthwork at the lower pilot pit (22) forms a third step (53); S5: Continue tunnel excavation using the three-bench seven-step method (1).
2. The double-side wall pilot pit method and three-step excavation method conversion construction process according to claim 1 is characterized in that: The specific method of S2 includes: S21: after excavating the first pilot pit (2), driving anchor cables (11) into the earthwork of the inner wall of each location of the first pilot pit (2) away from the geometric center of the tunnel (1), and then filling concrete into each location of the inner wall of the first pilot pit (2) to seal it.
3. The double-side wall pilot pit method and three-step excavation method conversion construction process according to claim 2 is characterized in that: The specific method before filling the various inner walls of the first pilot pit (2) with concrete for sealing also includes: using a support assembly (6) to temporarily support the various inner walls of the first pilot pit (2).
4. The double-side wall pilot pit method and three-step excavation method conversion construction process according to claim 3 is characterized in that: The left and right inner walls of each first guide pit (2) are provided with corresponding support assemblies (6), and an opening for engineering machinery to enter the first guide pit (2) is formed between the two support assemblies (6) in the same first guide pit (2); each support assembly (6) comprises an engineering vehicle (61) and a support frame (62), the engineering vehicle (61) being movably arranged in the first guide pit (2) along the length direction of the first guide pit (2), and the support frame (62) being installed on the engineering vehicle (61) and abutting against the corresponding inner wall.
5. The double-side wall pilot pit method and three-step excavation method conversion construction process according to claim 4 is characterized in that: An air bag (64) is provided on a side of the support frame (62) away from the engineering vehicle (61).
6. The double-side wall pilot pit method and three-step excavation method conversion construction process according to claim 5 is characterized in that: A side frame (63) is circumferentially arranged on a side of the support frame (62) away from the engineering vehicle (61), and each of the side frames (63) and the support frame (62) encloses a template for fixing liquid concrete; a slurry inlet is arranged on the side frame (63), a plastic film is arranged on a side of the air bag (64) away from the engineering vehicle (61), and a demoulding component for assisting concrete demoulding is installed on the support frame (62).
7. The double-side wall pilot pit method and three-step excavation method conversion construction process according to claim 6 is characterized in that: The demoulding assembly comprises an air pump (65) and an air nozzle, wherein the air nozzle is mounted on the air bag (64), and the air pump (65) is connected to the air bag (64) via an air pipe.
8. The double-side wall pilot pit method and three-step excavation method conversion construction process according to claim 6 is characterized in that: The steps after S21 also include: after the support assembly (6) is used to sequentially complete two demoulding operations of the concrete, the gap between the two groups of formed concrete is filled.
9. The double-side wall pilot pit method and three-step excavation method conversion construction process according to claim 3 is characterized in that: The specific method of S5 comprises: after excavating the tunnel (1) using the three-step seven-step method, removing the support components (6) in each of the first pilot pits (2) and located close to the geometric center of the tunnel (1), and retaining the support components (6) in each of the first pilot pits (2) and located away from the geometric center of the tunnel (1) to support the inner wall of the tunnel (1).