Segmental assembly line type construction forming device and method for prefabricating inverted arch assembly
By using the base formwork mobile platform, side formwork components and clamping support frame devices in the construction of prefabricated invert components, the problem of high formwork costs in the existing technology is solved, and efficient and accurate molding of prefabricated invert components is achieved. installation, reducing construction costs.
Patent Information
- Application Number
- CN202410934824.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-12
- Publication Date
- 2024-10-01
AI Technical Summary
The existing segmental flow construction forming device for prefabricated invert components requires a set of fixed formwork, corresponding to one prefabricated invert component, resulting in high cost of formwork use and low construction efficiency.
A device is designed that includes a base formwork moving platform, a side formwork assembly and a clamping support frame. The base formwork moving stage realizes the combined processing of the bottom formwork and end formwork, and the side formwork assembly and clamping support frame realize the installation of the side formwork. and connections to reduce the number of template pieces used.
It realizes the step-by-step installation and molding of the prefabricated inverted arch component formwork with a reduced number of pieces, reduces the cost of using the formwork, and improves the construction efficiency and forming accuracy.
Smart Images

Figure CN118728429A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a segment water flow type construction forming device and method, in particular to a segment water flow type construction forming device and method for prefabricating an inverted arch component. Background Art
[0002] In order to improve the construction efficiency of high-speed tunnels, in accordance with geological conditions, an arch support assembly and a prefabricated inverted arch assembly are assembled to obtain a high-speed tunnel pavement support body. Therefore, a construction forming device for a prefabricated inverted arch assembly is an important construction component forming device. Among the existing segment flow-type construction forming devices for prefabricated inverted arch assemblies, there is no segment flow-type construction forming device for prefabricated inverted arch assemblies. The template assembly, concrete mortar pouring, demolding and steaming treatment of the prefabricated inverted arch assembly are performed separately at a fixed station. Since a set of templates of the prefabricated inverted arch assembly is required for one prefabricated inverted arch assembly, the use cost of the template of the prefabricated inverted arch assembly is increased. The present invention has the technical feature of reducing the number of pieces of the template body of the prefabricated inverted arch assembly and installing and forming them in steps, and has carried out effective exploration and research on the technical problem of performing template assembly, concrete mortar pouring, demolding and steaming treatment of the prefabricated inverted arch assembly at a fixed station. The statements here only provide background technology related to the present invention and do not necessarily constitute prior art. The technical solution of the present invention is made based on the technical briefing document provided by the applicant on April 26, 2024, which solves actual technical problems in the work process, and the existing technical problems, technical features and technical effects in the similar patent literature and background technology obtained through retrieval. Summary of the invention
[0003] The object of the present invention is a segment flow-type construction and forming device for prefabricating an inverted arch assembly. The object of the present invention is a segment flow-type construction and forming method for prefabricating an inverted arch component.
[0004] In order to overcome the above technical disadvantages, the purpose of the present invention is to provide a segment flow-type construction forming device and method for prefabricated inverted arch components, thereby reducing the use cost of the prefabricated inverted arch component template.
[0005] To achieve the above-mentioned purpose, the technical solution adopted by the present invention is: a segment flow-type construction forming device for prefabricated inverted arch components, comprising a base template moving platform with a bottom template and an end template of the prefabricated inverted arch component, a side template component arranged on the base template moving platform, and a clamping support frame arranged on the side template component.
[0006] Due to the design of the base template moving platform, the side template assembly and the clamping support frame, the bottom template and the end template of the prefabricated inverted arch assembly can be combined through the base template moving platform, the side template assembly and the clamping support frame can be installed on the base template moving platform to form the template body of the prefabricated inverted arch assembly, the other bottom templates and end templates can be connected one by one with the side template as the base to form the casting interval body of the prefabricated inverted arch assembly, the template body of the prefabricated inverted arch assembly can be installed and formed in steps with reduced number of pieces, and the technical problem of performing template assembly, concrete mortar pouring, demolding and steaming treatment of the prefabricated inverted arch assembly on a fixed station can be solved, thereby reducing the use cost of the template of the prefabricated inverted arch assembly.
[0007] The present invention is designed to connect the base template moving platform, the side template assembly and the clamping support frame to each other in a manner of reducing the number of pieces of the template body of the prefabricated inverted arch assembly and installing and forming them in steps.
[0008] The present invention is designed to connect the side formwork assembly and the clamping support frame with the base formwork moving platform in a manner that the side formwork is used as a base body to connect other bottom formworks and end formworks in pairs to form a casting interval body of the prefabricated inverted arch assembly.
[0009] The technical effects of the above three technical solutions are: realizing the early closing and installation of the bottom formwork and the end formwork of the prefabricated inverted arch assembly, and the later assembly and forming operation of the side formwork assembly, thereby reducing the usage of the side formwork assembly.
[0010] The present invention is designed to further include a first accessory device, and the first accessory device is arranged between the base template moving platform and the clamping support frame, and the first accessory device is arranged as a first track.
[0011] The present invention is designed to further include a second accessory device and the second accessory device is arranged on the first accessory device, and the second accessory device is arranged to include a second rail, a third rail, a fourth rail, a fifth rail and a sixth rail.
[0012] The present invention is designed to further include a third accessory device, and the third accessory device is arranged on the first accessory device, and the third accessory device is arranged as a steaming room.
[0013] The technical effects of the above three technical solutions are: realizing the integrated installation of other components, and expanding the technical effects of the present invention.
[0014] The present invention is designed that a second rail, a base template moving platform, a clamping support frame and a steaming room are respectively arranged on the first rail, a side template assembly is arranged between the base template moving platform and the clamping support frame, and a third rail, a fourth rail, a fifth rail and a sixth rail are respectively arranged on the first rail and the second rail.
[0015] The technical effect of the above technical scheme is that the first rail, the second rail, the third rail, the fourth rail, the fifth rail, the sixth rail, the base template moving platform, the side template assembly and the clamping support frame, and the steaming room constitute the basic technical scheme of the present invention and solve the technical problem of the present invention.
[0016] The present invention is designed that the base template moving platform is configured to include a moving chassis portion, a telescopic leg portion, a bottom template portion, an inner panel portion, a first end template portion, a second end template portion and an anti-collision block, and a receiving hole body is arranged on the front and rear side portions of the bottom template portion, the front and rear side portions of the moving chassis portion are configured to be connected to the shell of the telescopic leg portion, the upper end face portion of the moving chassis portion is configured to be connected to the lower end face portion of the bottom template portion and the front and rear edges of the upper end face portion of the bottom template portion are configured to be connected to the lower end face portion of the inner panel portion, the left end face portion of the bottom template portion is configured to be connected to the first end template portion through a pin shaft and the right end face portion of the bottom template portion is configured to be connected to the second end template portion through a pin shaft, the left and right end face portions of the moving chassis portion are configured to be connected to the anti-collision block and the wheel portion of the moving chassis portion is configured to be contact-connected to the first rail, the front and rear side portions of the bottom template portion The outer side surfaces of the side surface portion and the inner side panel portion are respectively arranged to be contact-connected with the side formwork assembly and the accommodating hole body is arranged to be connected with the side formwork assembly through connecting bolts, the mobile chassis portion is arranged to be a rail steel wheel transporter with a control panel on the left and right end surfaces, the telescopic leg portion is arranged to be a jack-type telescopic leg and the bottom formwork portion is arranged to be a seat-shaped body with an arc-shaped groove body on the upper end surface and ears on the left and right end surfaces, the inner panel portion is arranged to be an arc-shaped sheet body and the first end formwork portion and the second end formwork portion are arranged to be an N-shaped sheet body with ears on the lower end surface, the ears of the bottom formwork portion are respectively arranged to be connected with the ears of the first end formwork portion and the ears of the second end formwork portion through pins and the anti-collision block is arranged to be a rubber columnar body, the accommodating hole body is arranged to be a threaded hole body and the accommodating hole bodies are arranged to be arranged and distributed at intervals along the transverse center line of the bottom formwork portion.
[0017] The technical effect of the above technical solution is: it realizes the installation of the moving carrier of the bottom template part, the first end template part and the second end template part, and realizes the positioning connection by the inner panel part.
[0018] The present invention is designed that the side formwork component is configured to include a main board portion, a frame rib portion, an annular rib portion, an angle plate portion, an outer panel portion, a connecting seat portion, a rod portion, a vibrating seat portion, a back rib portion and a core shaft portion, and the outer side surface portion of the main board portion is respectively configured to be connected to the inner side surface portion of the frame rib portion and the inner side surface portion of the annular rib portion, the transverse portion of the angle plate portion is configured to be connected to the main board portion and the longitudinal portion of the angle plate portion is configured to be connected to the peripheral side surface portion of the annular rib portion, the main board portion and the annular rib portion are respectively configured to be connected in a sleeve-type manner to the core shaft portion, and the lower side surface portion of the main board portion is respectively configured to be connected to the upper inner side surface portion of the outer panel portion, the transverse portion of the connecting seat portion, the upper inner side surface portion of the rod portion and the inner side surface portion of the vibrating seat portion, the side surface portion of the main board portion is configured to be connected to the back rib portion, and the lower inner side surface portion of the outer panel portion and the lower inner side surface portion of the rod portion are respectively configured to be movable with the base template The platform is connected in a contact manner, the outer panel portion is arranged to be connected to the base template moving platform through connecting bolts, and the longitudinal portion and the back rib portion of the connecting seat portion are respectively arranged to be connected to the clamping support frame through connecting bolts, the main board portion is arranged to be a convex sheet body with a frame strip on the peripheral side portion and the frame strip rib portion is arranged to be a cross-shaped frame body, the annular strip rib portion is arranged to be a circular strip body and the angle plate portion is arranged to be a right-angled sheet body, the angle plate portion is arranged to be arranged and distributed at intervals along the peripheral contour line of the annular strip rib portion and the outer panel portion is arranged to be an arcuate strip sheet body with a mounting hole body, the mounting hole body of the outer panel portion is arranged to be connected with the connecting bolts located on the base template moving platform and the connecting seat portion is arranged to be an L-shaped plate body, the bar portion is arranged to be a π-shaped frame body and the vibrating seat portion is arranged to be a block body, the back rib portion is arranged to be a string-shaped rod body and the core shaft portion is arranged to be an airbag core mold.
[0019] The technical effects of the above technical solution are: achieving reinforced support for the main board portion, achieving positioning connection between the outer panel portion and the bar portion, and achieving external connection between the connecting seat portion and the back rib portion.
[0020] The present invention is designed that the clamping support frame is configured to include a moving frame portion, a thrust telescopic cylinder portion, a support frame portion, an intermediate screw nut portion, a spring portion, an operating table portion and a tension rod portion, and the upper end face corner portion of the moving frame portion is configured to be connected to the lower end head of the screw of the intermediate screw nut portion, the screw of the intermediate screw nut portion is configured to be through-connected to the spring portion, and the upper end head of the screw of the intermediate screw nut portion is configured to be through-connected to the lower end face corner portion of the support frame portion, the nut of the intermediate screw nut portion is configured to be contact-connected to the lower end face corner portion of the support frame portion, and one of the ends of the spring portion is configured to be contact-connected to the upper end face corner portion of the moving frame portion, the other end head of the spring portion is configured to be contact-connected to the lower end face corner portion of the support frame portion, and the upper end face portion of the support frame portion is configured to be connected to the lower end face portion of the operating table portion, and the end head of the tension rod portion is configured to be through-connected to the side portion of the operating table portion and positioned The nut on the tie rod portion is arranged to be connected in contact with the side surface of the operating table portion, the lower end portion of the movable frame portion is arranged to be connected to one of the ends of the thrust telescopic cylinder portion through a pin shaft, and the other end of the thrust telescopic cylinder portion is arranged to be connected to the foundation of the first rail through a pin shaft, the lower end surface portion of the movable frame portion is arranged to be connected in contact with the foundation of the first rail, and the support frame portion is arranged to be connected to the side template assembly through a connecting bolt, the movable frame portion is arranged to be a concave-shaped frame body, and the thrust telescopic cylinder portion is arranged to be a two-section telescopic cylinder, the hydraulic port portion of the thrust telescopic cylinder portion is arranged to be connected in communication with a high-pressure liquid source, and the support frame portion is arranged to be a rectangular frame, the screw of the intermediate screw and nut portion is arranged to be a plain column bolt, and the nut of the intermediate screw and nut portion is arranged to be a hexagonal nut, the spring portion is arranged to be a columnar spring, and the operating table portion is arranged to be a table-shaped body with a fence, and the tie rod portion is arranged to be a rod-shaped body with a threaded body at the end.
[0021] The technical effect of the above technical solution is that it realizes the lateral movement of the side formwork assembly and realizes the assembly and connection of the formwork of the prefabricated invert arch assembly.
[0022] The present invention is designed that the first rail and the second rail are respectively arranged as double-row rails with I-shaped rail bodies and the first rail is arranged to be distributed in parallel with the second rail, the third rail and the fourth rail are respectively arranged at one end of the first rail and one end of the second rail, and the fifth rail and the sixth rail are respectively arranged at the other end of the first rail and the other end of the second rail, the first rail is arranged to be supported and connected to the base template moving platform, and a clamping support frame is arranged at the front and rear edges inside one end of the first rail, and a steaming room is arranged on the inner side of the other end of the first rail.
[0023] The present invention designs that the third rail, the fourth rail, the fifth rail and the sixth rail are respectively arranged as overhead double-row rails with I-shaped rail bodies, and the third rail, the fourth rail, the fifth rail and the sixth rail are respectively arranged at the end of the first rail and the end of the second rail.
[0024] The technical effects of the above two technical solutions are: achieving motion support for the track body and improving construction efficiency.
[0025] The present invention designs that the steaming room is arranged as a concrete component steaming shed and the steaming room is arranged to be connected with the first track in a leaping manner.
[0026] The technical effect of the above technical solution is that the maintenance treatment of the prefabricated invert arch assembly is realized.
[0027] The present invention is designed that the first rail, the second rail, the third rail, the fourth rail, the fifth rail and the sixth rail are arranged to be distributed in the manner of closing the casting formwork, and the first rail, the second rail, the third rail, the fourth rail, the fifth rail, the sixth rail, the base formwork moving platform, the side formwork assembly and the clamping support frame are arranged to be distributed in the manner of concrete component curing sections.
[0028] The present invention is designed that two side template assemblies and two clamping support frames are arranged on a base template moving platform, the support frame parts are respectively arranged to be connected to the connecting seat part and the back rib part through connecting bolts, the outer panel part is arranged to be connected to the inner panel part, the connecting bolts located on the mounting hole body of the outer panel part are arranged to be connected to the accommodating hole body, and the bar part is arranged to be connected to the bottom template part.
[0029] The present invention designs a segment flow-type construction and forming method for a prefabricated inverted arch assembly, and the steps are: a base template moving platform is used to realize the assembly processing of the bottom template and the end template of the prefabricated inverted arch assembly, a side template assembly and a clamping support frame are used to realize the installation of the side template assembly on the base template moving platform to form the template body of the prefabricated inverted arch assembly, the side template is used as a base to realize the connection of other bottom templates and end templates one by one to form the casting interval body of the prefabricated inverted arch assembly, and the template body of the prefabricated inverted arch assembly is installed and formed in steps with a reduced number of pieces.
[0030] The technical effect of the above technical scheme is: highlighting the technical feature of reducing the number of pieces of the template body of the prefabricated inverted arch assembly and installing it in steps, and introducing the application in the technical field of the segmented flow-type construction forming method for the prefabricated inverted arch assembly.
[0031] The present invention is designed, and the steps are: placing the movable chassis part on one end of the first rail, carrying the skeleton of the prefabricated inverted arch assembly on the transport vehicle on one end of the second rail to the base template moving platform through the swing vehicle located on the third rail and the fourth rail, placing the skeleton of the prefabricated inverted arch assembly on the bottom template part, installing the core shaft part in the skeleton of the prefabricated inverted arch assembly, thereby completing the installation of the skeleton of the prefabricated inverted arch assembly on the bottom template part, turning the first end template part and the second end template part on the bottom template part, making the first end template part and the second end template part in a vertical state, connecting the upper end of the first end template part and the upper end of the second end template part together through a steel wire, and making the movable chassis part move on the first rail, The base template moving platform is moved between the two side template assemblies, the telescopic leg part is in an extended state, the moving chassis part is separated from the first rail, the thrust telescopic cylinder part is in an extended state, and the lower end surface part of the moving frame part is driven to move inward on the foundation of the first rail, so that one end of the inner side surface of the main board part contacts the first end template part, and the other end of the inner side surface of the main board part contacts the second end template part. The end of the tie rod part is connected with the side surface of the operating table part in a through-type manner, so that the nut on the tie rod part rotates at the end of the tie rod part, and the nut on the tie rod part acts on the side surface of the operating table part, so that the tie rod part is installed between the two operating table parts, and a downward force is applied to the vibrating seat part, so that the spring part is in a compressed state. The bar portion moves downward on the front and rear side portions of the bottom template portion, so that the outer panel portion moves downward on the outer side portion of the inner panel portion, and the connecting bolts on the mounting hole body of the outer panel portion are rotated in the accommodating hole body, so that the main board portion is installed on the bottom template portion, and the core shaft portion is installed in the ring bar portion, so that the core shaft portion is in an expanded and filled state, and concrete mortar is injected into the skeleton of the prefabricated inverted arch assembly through the open portion between the first end template portion, the second end template portion and the main board portion. After the concrete mortar solidifies, the nut on the tie rod portion is rotated in the opposite direction at the end of the tie rod portion, the nut on the tie rod portion is separated from the end of the tie rod portion, and the end of the tie rod portion is taken out from the operating table portion, so that the core shaft portion is in a contracted and deflated state. The connecting bolts on the mounting hole body of the outer panel part are rotated in the opposite direction in the accommodating hole body, so that the connecting bolts on the mounting hole body of the outer panel part are separated from the accommodating hole body. Under the elastic energy storage action of the spring part, the bar part moves upward on the front and rear side parts of the bottom template part, so that the outer panel part moves upward on the outer side face part of the inner panel part, and the main board part is separated from the bottom template part, so that the thrust telescopic cylinder part is in a contracted state, and the lower end face part of the movable frame part is driven to move outward on the foundation of the first rail, so that one end part of the inner side face of the main board part is separated from the first end template part, and the other end part of the inner side face of the main board part is separated from the second end template part, and the steel wire is separated from the upper end head of the first end template part and the upper end head of the second end template part.The first end template part and the second end template part are flipped in opposite directions on the bottom template part, so that the first end template part and the second end template part are in a horizontal state, the core shaft part is taken out from the skeleton of the prefabricated inverted arch assembly, and the blank of the prefabricated inverted arch assembly is obtained on the bottom template part, the telescopic leg part is in a retracted state, the movable chassis part is placed on the first track, the movable chassis part is moved on the first track, the base template moving platform is moved to the steaming room, and the blank of the prefabricated inverted arch assembly is steamed and cured in the steaming room, and the prefabricated inverted arch assembly is obtained on the bottom template part, the movable chassis part is moved on the first track, the base template moving platform is moved to the bottom of the swinging vehicle located on the fifth track and the sixth track, and the prefabricated inverted arch assembly is transported to the transport vehicle located on the other end of the second track by the swinging vehicle located on the fifth track and the sixth track.
[0032] The technical effect of the above technical solution is to realize the skeleton installation, formwork assembly, concrete pouring, concrete curing and finished product transportation process operations of the prefabricated inverted arch assembly.
[0033] In the present technical scheme, the base template moving platform, the side template assembly and the clamping support frame are basic components and are also the necessary technical features of the present invention. The first rail, the second rail, the third rail, the fourth rail, the fifth rail, the sixth rail and the steaming room are functional components and are the features for realizing other technical effects of the present invention. The designs of the technical features of the movable chassis part, the telescopic support leg part, the bottom template part, the inner panel part, the first end template part, the second end template part, the anti-collision block, the accommodating hole body, the main board part, the frame rib part, the ring rib part, the angle plate part, the outer panel part, the connecting seat part, the bar part, the vibrating seat part, the back rib part, the core shaft part, the movable frame part, the thrust telescopic cylinder part, the support frame part, the intermediate screw nut part, the spring part, the operating table part and the tension rod part are technical features that comply with the Patent Law and its implementing rules.
[0034] In the technical solution, the formwork body of the prefabricated inverted arch assembly is subjected to the step-by-step installation and molding of the reduced number of pieces by the side formwork assembly and the clamping support frame.
[0035] In the present technical scheme, the base template moving platform, side template assembly and clamping support frame for reducing the number of pieces of the template body of the prefabricated inverted arch assembly and installing and forming them in steps are important technical features. In the technical field of segmented flow-type construction forming devices and methods for prefabricated inverted arch assemblies, it has novelty, creativity and practicality. The terms in the present technical scheme can be explained and understood using patent documents in this technical field. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0037] Figure 1 The present invention is a schematic diagram of a segment flow-type construction forming device for prefabricating an inverted arch assembly. Figure 2 is a schematic structural diagram of the base template moving platform 7, Figure 3 is a schematic diagram of the structure of the side formwork assembly 8, Figure 4 It is a schematic diagram of the connection relationship between the first rail 1, the base template moving platform 7, the side template assembly 8 and the clamping support frame 9. First rail-1, second rail-2, third rail-3, fourth rail-4, fifth rail-5, sixth rail-6, base template moving platform-7, side template assembly-8, clamping support frame-9, steaming room-90, mobile chassis part-71, telescopic support leg part-73, bottom template part-74, inner side panel part-75, first end template part-76, second end template part-77, anti-collision block-78, receiving hole body -72, main board part-81, frame rib part-82, ring rib part-83, angle plate part-84, outer panel part-85, connecting seat part-86, bar part-87, vibrating seat part-88, back rib part-89, core shaft part-80, movable frame part-99, thrust telescopic cylinder part-98, supporting frame part-97, intermediate screw nut part-96, spring part-95, operating table part-94, tension rod part-93. DETAILED DESCRIPTION
[0038] According to the Examination Guidelines, terms such as “having”, “including” and “comprising” used in the present invention should be understood as not dispensing with the existence or addition of one or more other elements or combinations thereof.
[0039] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0040] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or a segmented flow connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0041] In addition, the technical features involved in the different embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other. In addition, unless otherwise specified, the equipment and materials used in the following examples are commercially available. If the processing conditions are not clearly stated, please refer to the purchased product manual or proceed according to conventional methods in the art.
[0042] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0043] A segment flow-type construction forming device for prefabricating an inverted arch assembly, Figure 1 This is the first embodiment of the present invention, which is described in detail in conjunction with the accompanying drawings. It includes a first rail 1, a second rail 2, a third rail 3, a fourth rail 4, a fifth rail 5, a sixth rail 6, a base template moving platform 7, a side template assembly 8, a clamping support frame 9 and a steaming room 90, and the second rail 2, the base template moving platform 7, the clamping support frame 9 and the steaming room 90 are respectively arranged on the first rail 1, a side template assembly 8 is arranged between the base template moving platform 7 and the clamping support frame 9, and the third rail 3, the fourth rail 4, the fifth rail 5 and the sixth rail 6 are respectively arranged on the first rail 1 and the second rail 2.
[0044] In this embodiment, the first rail 1 and the second rail 2 are respectively arranged as double-row rails with I-shaped rail bodies and the first rail 1 is arranged to be distributed in parallel with the second rail 2, a third rail 3 and a fourth rail 4 are respectively arranged at one end of the first rail 1 and one end of the second rail 2, and a fifth rail 5 and a sixth rail 6 are respectively arranged at the other end of the first rail 1 and the other end of the second rail 2, the first rail 1 is arranged to be supported and connected to the base template moving platform 7, and a clamping support frame 9 is arranged on the front and rear edges of the inner side of one end of the first rail 1, and a steaming room 90 is arranged on the inner side of the other end of the first rail 1.
[0045] Through the first rail 1 and the second rail 2, supporting connection points for the third rail 3, the fourth rail 4, the fifth rail 5, the sixth rail 6, the base template moving platform 7, the side template assembly 8 and the clamping support frame 9 are formed. The first rail 1 and the second rail 2 realize the connection with the third rail 3, the connection with the fourth rail 4, the connection with the fifth rail 5, and the connection with the sixth rail 6. The first rail 1 realizes the connection with the base template moving platform 7, the connection with the side template assembly 8, and the connection with the clamping support frame 9. The technical purpose is to be used as one of the supporting components for rail transportation.
[0046] In this embodiment, the third rail 3, the fourth rail 4, the fifth rail 5 and the sixth rail 6 are respectively arranged as overhead double-row rails with I-shaped rail bodies, and the third rail 3, the fourth rail 4, the fifth rail 5 and the sixth rail 6 are respectively arranged at the end of the first rail 1 and the end of the second rail 2.
[0047] The third rail 3, the fourth rail 4, the fifth rail 5 and the sixth rail 6 form supporting connection points for the first rail 1 and the second rail 2. The third rail 3, the fourth rail 4, the fifth rail 5 and the sixth rail 6 realize connection with the first rail 1 and connection with the second rail 2. The technical purpose is to serve as the second supporting component for rail transportation.
[0048] In the present embodiment, the base template moving platform 7 is configured to include a moving chassis portion 71, a telescopic leg portion 73, a bottom template portion 74, an inner panel portion 75, a first end template portion 76, a second end template portion 77 and an anti-collision block 78, and a accommodating hole body 72 is provided on the front and rear side portions of the bottom template portion 74, the front and rear side portions of the moving chassis portion 71 are configured to be connected to the shell of the telescopic leg portion 73, the upper end surface portion of the moving chassis portion 71 is configured to be connected to the lower end surface portion of the bottom template portion 74 and the front and rear edges of the upper end surface portion of the bottom template portion 74 are configured to be connected to the lower end surface portion of the inner panel portion 75, the left end surface portion of the bottom template portion 74 is configured to be connected to the first end template portion 76 through a pin shaft and the right end surface portion of the bottom template portion 74 is configured to be connected to the second end template portion 77 through a pin shaft, the left and right end surfaces of the moving chassis portion 71 are configured to be connected to the anti-collision block 78 and the wheel portion of the moving chassis portion 71 is configured to be contact-connected to the first track 1, and the bottom The front and rear side surfaces of the template portion 74 and the outer side surface of the inner panel portion 75 are respectively arranged to be contact-connected with the side template assembly 8 and the accommodating hole body 72 is arranged to be connected with the side template assembly 8 through connecting bolts, the mobile chassis portion 71 is arranged to be a rail steel wheel transporter with a control panel on the left and right end surfaces, the telescopic leg portion 73 is arranged to be a jack-type telescopic leg and the bottom template portion 74 is arranged to be a seat-shaped body with an arc-shaped groove body on the upper end surface and ears on the left and right end surfaces, the inner panel portion 75 is arranged to be an arc-shaped sheet body and the first end template portion 76 and the second end template portion 77 are arranged to be an N-shaped sheet body with ears on the lower end surface, the ears of the bottom template portion 74 are respectively arranged to be connected with the ears of the first end template portion 76 and the ears of the second end template portion 77 through pins and the anti-collision block 78 is arranged to be a rubber columnar body, the accommodating hole body 72 is arranged to be a threaded hole-shaped body and the accommodating hole bodies 72 are arranged to be arranged and distributed at intervals along the transverse center line of the bottom template portion 74.
[0049] Through the base template moving platform 7, a supporting connection point for the first rail 1 and the side template assembly 8 is formed, the connection with the first rail 1 is realized by the movable chassis part 71, the connection with the side template assembly 8 is realized by the inner panel part 75 and the accommodating hole body 72, the off-ground support connection of the movable chassis part 71 is realized by the telescopic support leg part 73, the bottom template part 74, the first end template part 76 and the second end template part 77 are used to realize the connection between the bottom template and the two end templates of the prefabricated inverted arch assembly, and the anti-collision block 78 is used to realize the safety protection of the movable chassis part 71. The technical purpose is to be used as a moving part of the bottom template and the two end templates of the prefabricated inverted arch assembly.
[0050] In this embodiment, the side template assembly 8 is configured to include a main board portion 81, a frame bar portion 82, a ring bar portion 83, a corner plate portion 84, an outer panel portion 85, a connecting seat portion 86, a bar portion 87, a vibrating seat portion 88, a back rib portion 89 and a core shaft portion 80, and the outer side surface portion of the main board portion 81 is respectively configured to be connected to the inner side surface portion of the frame bar portion 82 and the inner side surface portion of the ring bar portion 83, the transverse portion of the corner plate portion 84 is configured to be connected to the main board portion 81, and the longitudinal portion of the corner plate portion 84 is configured to be The main plate portion 81 and the ring rib portion 83 are respectively arranged to be connected to the core shaft portion 80 in a sleeve-type manner, and the lower part of the side of the main plate portion 81 is respectively arranged to be connected to the upper part of the inner side of the outer panel portion 85, the transverse part of the connecting seat portion 86, the upper part of the inner side of the bar portion 87 and the inner side of the vibrating seat portion 88, and the side of the main plate portion 81 is arranged to be connected to the back rib portion 89 and the lower part of the inner side of the outer panel portion 85 and the lower part of the inner side of the bar portion 87. They are respectively arranged to be contact-connected with the base template moving platform 7, the outer panel portion 85 is arranged to be connected with the base template moving platform 7 by connecting bolts, and the longitudinal portion of the connecting seat portion 86 and the back rib portion 89 are respectively arranged to be connected with the clamping support frame 9 by connecting bolts, the main board portion 81 is arranged to be a convex-shaped sheet body with a frame strip on the peripheral side portion and the frame strip rib portion 82 is arranged to be a cross-shaped frame body, the annular strip rib portion 83 is arranged to be a circular strip body and the angle plate portion 84 is arranged to be a right-angled sheet body, the angle plate portion 84 is arranged to be arranged to be spaced and distributed along the peripheral contour line of the annular strip rib portion 83 and the outer panel portion 85 is arranged to be an arc-shaped strip sheet body with a mounting hole body, the mounting hole body of the outer panel portion 85 is arranged to be connected with the connecting bolts located on the base template moving platform 7 and the connecting seat portion 86 is arranged to be an L-shaped plate body, the bar portion 87 is arranged to be a π-shaped frame body and the vibrating seat portion 88 is arranged to be a block body, the back rib portion 89 is arranged to be a string-shaped rod body and the core shaft portion 80 is arranged to be an airbag core mold.
[0051] Through the side formwork assembly 8, a supporting connection point for the base formwork moving platform 7 and the clamping support frame 9 is formed, the connection with the base formwork moving platform 7 is realized by the outer panel part 85 and the rod part 87, the connection with the clamping support frame 9 is realized by the connecting seat part 86 and the back rib part 89, the side formwork connection of the prefabricated inverted arch assembly is realized by the main board part 81, the correspondence with the reserved hole body of the prefabricated inverted arch assembly is realized by the annular rib part 83, the angle plate part 84 and the core shaft part 80, the main board part 81 is reinforced and supported by the frame rib part 82, and the external pressure treatment is realized by the vibrating seat part 88. Its technical purpose is to be used as a supporting component of the side formwork of the prefabricated inverted arch assembly.
[0052] In this embodiment, the clamping support frame 9 is configured to include a moving frame portion 99, a thrust telescopic cylinder portion 98, a support frame portion 97, an intermediate screw nut portion 96, a spring portion 95, an operating table portion 94 and a tie rod portion 93, and the upper end face corner of the moving frame portion 99 is configured to be connected to the lower end head of the screw of the intermediate screw nut portion 96, the screw of the intermediate screw nut portion 96 is configured to be connected to the spring portion 95 through-type, and the upper end head of the screw of the intermediate screw nut portion 96 is configured to be connected to the lower end face corner of the support frame portion 97 through-type. Through-type connection, the nut of the intermediate screw nut part 96 is set to be in contact with the corner of the lower end face of the support frame part 97, and one end of the spring part 95 is set to be in contact with the corner of the upper end face of the moving frame part 99, and the other end of the spring part 95 is set to be in contact with the corner of the lower end face of the support frame part 97, and the upper end face of the support frame part 97 is set to be connected to the lower end face of the operating table part 94, and the end of the tie rod part 93 is set to penetrate the side part of the operating table part 94. The nut located on the tension rod portion 93 is set to be connected in a contacting manner with the side surface of the operating table portion 94, the lower end portion of the movable frame portion 99 is set to be connected to one of the ends of the thrust telescopic cylinder portion 98 through a pin shaft and the other end of the thrust telescopic cylinder portion 98 is set to be connected to the foundation of the first rail 1 through a pin shaft, the lower end surface portion of the movable frame portion 99 is set to be connected in a contacting manner with the foundation of the first rail 1 and the support frame portion 97 is set to be connected to the side template assembly 8 through a connecting bolt, the movable frame portion 99 is set to be a concave frame-like body and the thrust telescopic cylinder portion 98 is set to be a two-section telescopic cylinder, the hydraulic port portion of the thrust telescopic cylinder portion 98 is set to be connected in a communicating manner with a high-pressure liquid source and the support frame portion 97 is set to be a rectangular frame, the screw of the intermediate screw nut portion 96 is set to be a plain column bolt and the nut of the intermediate screw nut portion 96 is set to be a hexagonal nut, the spring portion 95 is set to be a columnar spring and the operating table portion 94 is set to be a table-like body with a fence, and the tension rod portion 93 is set to be a rod-like body with a threaded body at the end.
[0053] A supporting connection point for the first rail 1 and the side formwork assembly 8 is formed by the clamping support frame 9. The movable frame portion 99 and the thrust telescopic cylinder portion 98 realize the connection with the first rail 1. The support frame portion 97 realizes the connection with the side formwork assembly 8. The intermediate screw nut portion 96 and the spring portion 95 realize the buffer connection between the support frame portion 97 and the movable frame portion 99. The operating table portion 94 realizes the support for the operator. The tension rod portion 93 realizes the connection between the two clamping support frames 9. The technical purpose is to serve as a supporting carrier for the side formwork of the prefabricated inverted arch assembly.
[0054] In this embodiment, the steaming room 90 is configured as a concrete component steaming shed and the steaming room 90 is configured to be connected to the first track 1 in a leaping manner.
[0055] A supporting connection point for the first rail 1 is formed by the steaming room 90, and the connection with the first rail 1 is realized by the steaming room 90. The technical purpose is to be used as a component for curing the prefabricated invert assembly.
[0056] In this embodiment, the first rail 1, the second rail 2, the third rail 3, the fourth rail 4, the fifth rail 5 and the sixth rail 6 are arranged to be distributed in the manner of closing the casting formwork, and the first rail 1, the second rail 2, the third rail 3, the fourth rail 4, the fifth rail 5, the sixth rail 6, the base template moving platform 7, the side template assembly 8 and the clamping support frame 9 are arranged to be distributed in the manner of concrete component curing sections, two side template assemblies 8 and two clamping support frames 9 are arranged on the base template moving platform 7, the support frame portion 97 is respectively arranged to be connected to the connecting seat portion 86 and the back rib portion 89 through connecting bolts, the outer panel portion 85 is arranged to be connected to the inner panel portion 75, the connecting bolts located on the mounting hole body of the outer panel portion 85 are arranged to be connected to the accommodating hole body 72, and the bar portion 87 is arranged to be connected to the bottom template portion 74.
[0057] The present invention is further described below in conjunction with examples. The following examples are intended to illustrate the present invention rather than to further limit the present invention.
[0058] A segment flow-type construction molding method for prefabricated inverted arch components, the steps of which are: placing a mobile chassis part 71 on one end of a first track 1, transporting the skeleton of the prefabricated inverted arch component on a transport vehicle on one end of a second track 2 to a base template moving platform 7 through a swinging vehicle located on a third track 3 and a fourth track 4, placing the skeleton of the prefabricated inverted arch component on a bottom template part 74, installing a core shaft part 80 in the skeleton of the prefabricated inverted arch component, thereby completing the installation of the skeleton of the prefabricated inverted arch component on the bottom template part 74, turning over the first end template part 76 and the second end template part 77 on the bottom template part 74, making the first end template part 76 and the second end template part 77 in a vertical state, and fixing the first end template part 76 and the second end template part 77 on the bottom template part 74 by steel wire. The upper end of the end template portion 76 and the upper end of the second end template portion 77 are connected together, so that the movable chassis portion 71 moves on the first track 1, the base template moving platform 7 moves between the two side template assemblies 8, the telescopic leg portion 73 is in an extended state, the movable chassis portion 71 is separated from the first track 1, the thrust telescopic cylinder portion 98 is in an extended state, and the lower end surface portion of the movable frame portion 99 is driven to move inward on the foundation of the first track 1, so that one end of the inner side surface of the main board portion 81 contacts the first end template portion 76, and the other end of the inner side surface of the main board portion 81 contacts the second end template portion 77, and the end of the tie rod portion 93 is connected to the side surface of the operating table portion 94 in a through-type manner, so that the nut located on the tie rod portion 93 is The end of the tie rod portion 93 is rotated, and the nut on the tie rod portion 93 acts on the side of the operating table portion 94, so that the tie rod portion 93 is installed between the two operating table portions 94, and a downward force is applied to the vibrating seat portion 88, so that the spring portion 95 is in a compressed state, and the bar portion 87 moves downward on the front and rear side portions of the bottom template portion 74, so that the outer panel portion 85 moves downward on the outer side surface of the inner panel portion 75, and the connecting bolt on the mounting hole body of the outer panel portion 85 is rotated in the accommodating hole body 72, so that the main board portion 81 is installed on the bottom template portion 74, and the core shaft portion 80 is installed in the annular rib portion 83, so that the core shaft portion 80 is in an expanded and full state, through the first end template portion 76 and the second end template The open part between the part 77 and the main plate part 81 is used to inject concrete mortar into the skeleton of the prefabricated inverted arch assembly. After the concrete mortar solidifies, the nut on the tie rod part 93 is rotated in the opposite direction at the end of the tie rod part 93 to separate the nut on the tie rod part 93 from the end of the tie rod part 93, and the end of the tie rod part 93 is taken out from the operating table part 94, so that the core shaft part 80 is in a contracted and deflated state, and the connecting bolts on the mounting hole body of the outer panel part 85 are rotated in the opposite direction in the accommodating hole body 72 to separate the connecting bolts on the mounting hole body of the outer panel part 85 from the accommodating hole body 72. Under the elastic energy storage action of the spring part 95, the bar part 87 moves upward on the front and rear side parts of the bottom template part 74.The outer panel portion 85 is moved upward on the outer surface of the inner panel portion 75, the main plate portion 81 is separated from the bottom template portion 74, the thrust telescopic cylinder portion 98 is in a retracted state, and the lower end surface of the movable frame portion 99 is driven to move outward on the foundation of the first rail 1, so that one end of the inner side surface of the main plate portion 81 is separated from the first end template portion 76, and the other end of the inner side surface of the main plate portion 81 is separated from the second end template portion 77, the steel wire is separated from the upper end of the first end template portion 76 and the upper end of the second end template portion 77, the first end template portion 76 and the second end template portion 77 are turned over in the opposite direction on the bottom template portion 74, the first end template portion 76 and the second end template portion 77 are in a horizontal state, and the core shaft portion 80 is moved from the prefabricated upward The prefabricated inverted arch assembly is taken out from the skeleton of the arch assembly, and the blank of the prefabricated inverted arch assembly is obtained on the bottom template part 74, the telescopic leg part 73 is in a retracted state, the movable chassis part 71 is placed on the first track 1, the movable chassis part 71 moves on the first track 1, the base template moving platform 7 is moved to the steaming room 90, and the blank of the prefabricated inverted arch assembly is steamed and cured in the steaming room 90, and the prefabricated inverted arch assembly is obtained on the bottom template part 74, the movable chassis part 71 moves on the first track 1, and the base template moving platform 7 is moved to the bottom of the swing car located on the fifth track 5 and the sixth track 6, and the prefabricated inverted arch assembly is transported to the transport car located on the other end of the second track 2 through the swing car located on the fifth track 5 and the sixth track 6.
[0059] When verifying the present invention, the inventor abandoned the existing technical features of separately performing formwork assembly, concrete mortar pouring, formwork removal and steaming treatment of the prefabricated inverted arch assembly at a fixed workstation, and first proposed a technical feature of reducing the number of pieces of the formwork body of the prefabricated inverted arch assembly and installing and forming it in steps, thereby obtaining a first unexpected technical effect: realizing the segmental formwork assembly in the construction process, reducing the amount of formwork used, and obtaining a second unexpected technical effect: realizing the use of the side formwork assembly 8 as the installation reference, thereby improving the forming accuracy of the prefabricated inverted arch assembly and improving the consistency of the prefabricated inverted arch assembly, and obtaining a third unexpected technical effect: realizing the motion and displacement support of the bottom formwork portion 74, the first end formwork portion 76 and the second end formwork portion 77, satisfying the segmental implementation of the process of assembly, pouring, maintenance and testing, and improving the prefabricated inverted arch assembly. The efficiency of the construction and forming of the components has achieved a fourth unexpected technical effect: cross-transportation by the first track 1, the second track 2, the third track 3, the fourth track 4, the fifth track 5 and the sixth track 6 has been realized, and the orderly performance of transportation, the efficiency and safety of construction and forming have been improved. The fifth unexpected technical effect has been achieved: the lateral docking and vertical connection of the opposite side formwork components 8 have been achieved, the installation accuracy of the opposite side formwork components 8 has been improved, and the dimensional accuracy of the prefabricated inverted arch components has been improved. The sixth unexpected technical effect has been achieved: the clamping and jacking fixation of the formwork of the prefabricated inverted arch component has been achieved, the working state stability performance of the formwork of the prefabricated inverted arch component has been improved, and the solidification state strength of the concrete mortar has been improved. The seventh unexpected technical effect has been achieved: rapid steaming and curing of the prefabricated inverted arch component has been achieved, and the performance parameters of the prefabricated inverted arch component have been improved.
[0060] In the second embodiment of the present invention, the base template moving platform 7, the side template assembly 8 and the clamping support frame 9 are connected to each other in a manner of reducing the number of pieces of the template body of the prefabricated inverted arch assembly and installing and molding in steps.
[0061] In this embodiment, the side formwork assembly 8 and the clamping support frame 9 are connected to the base formwork moving platform 7 in such a way that the side formwork is used as a base to connect other bottom formworks and end formworks in pairs to form a casting interval body of the prefabricated inverted arch assembly.
[0062] In this embodiment, a first accessory device is also included and is arranged between the base template moving platform 7 and the clamping support frame 9 , and the first accessory device is arranged as a first rail 1 .
[0063] In this embodiment, a second accessory device is further included and is arranged on the first accessory device. The second accessory device is arranged to include a second rail 2 , a third rail 3 , a fourth rail 4 , a fifth rail 5 and a sixth rail 6 .
[0064] In this embodiment, a third accessory device is further included and is arranged on the first accessory device. The third accessory device is arranged as a steaming room 90 .
[0065] The second embodiment of the present invention is based on the first embodiment. The second embodiment of the present invention comprises the following steps: the base template moving platform 7 is used to realize the assembly processing of the bottom template and the end template of the prefabricated inverted arch assembly; the side template assembly 8 and the clamping support frame 9 are used to realize the installation of the side template assembly 8 on the base template moving platform 7 to form the template body of the prefabricated inverted arch assembly; the other bottom templates and end templates are connected one by one with the side template as the matrix to form the casting interval body of the prefabricated inverted arch assembly; and the template body of the prefabricated inverted arch assembly is installed and formed in steps with the number of pieces reduced.
[0066] The second embodiment of the present invention is based on the first embodiment.
[0067] The present invention has the following characteristics: 1. Due to the design of the base template moving platform 7, the side template assembly 8 and the clamping support frame 9, the bottom template and the end template of the prefabricated inverted arch assembly are combined through the base template moving platform 7, the side template assembly 8 is installed on the base template moving platform 7 to form the template body of the prefabricated inverted arch assembly through the side template assembly 8 and the clamping support frame 9, the other bottom templates and end templates are connected one by one with the side template as the base to form the casting interval body of the prefabricated inverted arch assembly, and the template body of the prefabricated inverted arch assembly is installed and formed in steps with reduced number of pieces, which solves the technical problem of performing template assembly, concrete mortar pouring, demolding and steaming treatment of the prefabricated inverted arch assembly on a fixed station, thereby reducing the use cost of the template of the prefabricated inverted arch assembly.
[0068] 2. Due to the design of the first track 1, the guide rail body movement support for the base template moving platform 7 is achieved.
[0069] 3. Due to the design of the second rail 2, the third rail 3, the fourth rail 4, the fifth rail 5 and the sixth rail 6, supporting service transportation for the construction and forming of the prefabricated invert arch components is realized.
[0070] 4. Due to the design of the steam curing room 90, it is possible to perform curing treatment on the prefabricated inverted arch components during the construction and forming process.
[0071] 5. Since the design limits the numerical range of the structural shape, the numerical range is the technical feature in the technical solution of the present invention, rather than a technical feature calculated by a formula or obtained through a limited number of tests. Tests have shown that the technical feature of this numerical range has achieved good technical effects.
[0072] 6. Due to the design of the technical features of the present invention, the effects of the individual and combined technical features have been shown through experiments to have various performance indicators of the present invention that are at least 1.7 times the existing performance indicators, and have been evaluated to have good market value.
[0073] There are other technical features that are connected to the base template moving platform 7, the side template assembly 8 and the clamping support frame 9 for reducing the number of pieces of the template body of the prefabricated arch assembly and installing them in steps. They are all one of the embodiments of the present invention, and the various technical features of the above-mentioned embodiments can be combined arbitrarily. In order to meet the requirements of the Patent Law, Patent Implementation Rules and Examination Guidelines, all possible combinations of the various technical features in the above-mentioned embodiments will no longer be described.
[0074] The above embodiment is only one implementation form of the segment flow-type construction forming device and method for prefabricated inverted arch components provided by the present invention. Other variations of the scheme provided by the present invention, adding or reducing components or steps therein, or applying the present invention to other technical fields close to the present invention, all fall within the protection scope of the present invention.
Claims
1. A segment flow-type construction and forming device for prefabricating an inverted arch assembly, characterized in that: The invention comprises a base template moving platform (7) having a bottom template and an end template of a prefabricated inverted arch assembly, a side template assembly (8) arranged on the base template moving platform (7), and a clamping support frame (9) arranged on the side template assembly (8).
2. The segment flow-type construction and forming device for prefabricating an inverted arch assembly according to claim 1 is characterized in that: The base template moving platform (7), the side template assembly (8) and the clamping support frame (9) are connected to each other in a manner of reducing the number of pieces of the template body of the prefabricated inverted arch assembly and installing and forming them in steps.
3. The segment flow-type construction and forming device for prefabricating an inverted arch assembly according to claim 2 is characterized in that: The side formwork assembly (8) and the clamping support frame (9) are connected to the base formwork moving platform (7) in a manner that the side formwork is used as a base body to connect other bottom formworks and end formworks in pairs to form a casting interval body of the prefabricated inverted arch assembly.
4. The segment flow-type construction and forming device for prefabricating an inverted arch assembly according to claim 1 is characterized in that: It also includes a first accessory device, and the first accessory device is arranged between the base template moving platform (7) and the clamping support frame (9), and the first accessory device is arranged as a first track (1). Or, further comprising a second accessory device and the second accessory device is arranged on the first accessory device, the second accessory device being arranged to comprise a second rail (2), a third rail (3), a fourth rail (4), a fifth rail (5) and a sixth rail (6), Or, it further comprises a third accessory device and the third accessory device is arranged on the first accessory device, and the third accessory device is arranged as a steaming room (90).
5. The segment flow-type construction and forming device for prefabricating an inverted arch assembly according to claim 4 is characterized in that: A second rail (2), a base template moving platform (7), a clamping support frame (9) and a steaming room (90) are respectively arranged on the first rail (1), a side template assembly (8) is arranged between the base template moving platform (7) and the clamping support frame (9), and a third rail (3), a fourth rail (4), a fifth rail (5) and a sixth rail (6) are respectively arranged on the first rail (1) and the second rail (2).
6. The segment flow-type construction and forming device for prefabricating an inverted arch assembly according to claim 5 is characterized in that: The base template moving platform (7) is configured to include a moving chassis portion (71), a telescopic leg portion (73), a bottom template portion (74), an inner panel portion (75), a first end template portion (76), a second end template portion (77) and an anti-collision block (78), and a receiving hole body (72) is provided on the front and rear side portions of the bottom template portion (74), the front and rear side portions of the moving chassis portion (71) are configured to be connected to the shell of the telescopic leg portion (73), and the upper end surface portion of the moving chassis portion (71) is configured to be connected to the bottom template portion (74). The lower end surface portion is connected and the front and rear edges of the upper end surface of the bottom template portion (74) are arranged to be connected to the lower end surface portion of the inner panel portion (75), the left end surface portion of the bottom template portion (74) is arranged to be connected to the first end template portion (76) through a pin shaft and the right end surface portion of the bottom template portion (74) is arranged to be connected to the second end template portion (77) through a pin shaft, the left and right end surfaces of the movable chassis portion (71) are arranged to be connected to the anti-collision block (78) and the wheel portion of the movable chassis portion (71) is arranged to be contact-connected with the first track (1) The front and rear side surfaces of the bottom template part (74) and the outer side surface of the inner panel part (75) are respectively arranged to be contact-connected with the side template assembly (8), and the receiving hole body (72) is arranged to be connected with the side template assembly (8) through connecting bolts, the mobile chassis part (71) is arranged to be a rail steel wheel transporter with a control panel on the left and right end surfaces, the telescopic leg part (73) is arranged to be a jack-type telescopic leg, and the bottom template part (74) is arranged to be a seat-shaped body with an arc-shaped groove body on the upper end surface and ear seats on the left and right end surfaces, and the inner panel The part (75) is configured as an arc-shaped sheet body, and the first end template part (76) and the second end template part (77) are configured as N-shaped sheet bodies with ear seats on the lower end surface parts, the ear seats of the bottom template part (74) are respectively configured to be connected with the ear seats of the first end template part (76) and the ear seats of the second end template part (77) through pin shafts, and the anti-collision block (78) is configured as a rubber columnar body, the receiving hole body (72) is configured as a threaded hole body, and the receiving hole bodies (72) are configured to be arranged and distributed at intervals along the transverse center line of the bottom template part (74), Alternatively, the side formwork assembly (8) is configured to include a main plate portion (81), a frame bar portion (82), a ring bar portion (83), a corner plate portion (84), an outer panel portion (85), a connecting seat portion (86), a bar portion (87), a vibrating seat portion (88), a back rib portion (89) and a core shaft portion (80), and the outer side surface portion of the main plate portion (81) is configured to be connected to the inner side surface portion of the frame bar portion (82) and the inner side surface portion of the ring bar portion (83), and the transverse portion of the corner plate portion (84) is configured to be connected to the main plate portion (81), and the corner plate portion (84) The longitudinal portion of the main plate portion (81) is arranged to be connected to the peripheral side surface portion of the ring rib portion (83), the main plate portion (81) and the ring rib portion (83) are arranged to be connected to the core shaft portion (80) in a sleeve-type manner, and the lower side portion of the main plate portion (81) is arranged to be connected to the upper inner side surface portion of the outer panel portion (85), the transverse portion of the connecting seat portion (86), the upper inner side surface portion of the bar portion (87) and the inner side surface portion of the vibrating seat portion (88), the side surface portion of the main plate portion (81) is arranged to be connected to the back rib portion (89), and the lower inner side surface portion of the outer panel portion (85) and the bar portion (88) are connected to the inner side surface portion of the vibrating seat portion (88). The lower part of the inner side surface of the base template moving platform (7) is respectively configured to be contact-connected with the base template moving platform (7), the outer panel part (85) is configured to be connected to the base template moving platform (7) through connecting bolts, and the longitudinal part and the back rib part (89) of the connecting seat part (86) are respectively configured to be connected to the clamping support frame (9) through connecting bolts, the main board part (81) is configured to be a convex-shaped sheet body with a frame strip on the peripheral side part, and the frame bar rib part (82) is configured to be a cross-shaped frame body, the ring bar rib part (83) is configured to be a circular bar body, and the corner plate part (84) is configured to be a right-angled sheet body , the angle plate portion (84) is arranged to be spaced and distributed along the peripheral contour line of the annular rib portion (83) and the outer panel portion (85) is arranged to be an arc-shaped strip sheet with a mounting hole, the mounting hole of the outer panel portion (85) is arranged to be connected with the connecting bolts located on the base template moving platform (7) and the connecting seat portion (86) is arranged to be an L-shaped plate-shaped body, the bar portion (87) is arranged to be a π-shaped frame-shaped body and the vibrating seat portion (88) is arranged to be a block-shaped body, the back rib portion (89) is arranged to be a string-shaped rod-shaped body and the core shaft portion (80) is arranged to be an airbag core mold, Alternatively, the clamping support frame (9) is configured to include a movable frame portion (99), a thrust telescopic cylinder portion (98), a support frame portion (97), an intermediate screw nut portion (96), a spring portion (95), an operating table portion (94) and a tie rod portion (93), and the upper end face corner portion of the movable frame portion (99) is configured to be connected to the lower end head of the screw of the intermediate screw nut portion (96), the screw of the intermediate screw nut portion (96) is configured to be through-connected to the spring portion (95), and the upper end head of the screw of the intermediate screw nut portion (96) is configured to be connected to the lower end face of the support frame portion (97). The nut of the intermediate screw nut part (96) is arranged to be connected in contact with the corner of the lower end face of the support frame part (97), and one end of the spring part (95) is arranged to be connected in contact with the corner of the upper end face of the movable frame part (99), and the other end of the spring part (95) is arranged to be connected in contact with the corner of the lower end face of the support frame part (97), and the upper end face of the support frame part (97) is arranged to be connected with the lower end face of the operating table part (94), and the end of the pull rod part (93) is arranged to be connected to the side of the operating table part (94). The nut on the tie rod portion (93) is configured to be connected in a contacting manner with the side surface of the operating table portion (94); the lower end portion of the movable frame portion (99) is configured to be connected to one end of the thrust telescopic cylinder portion (98) through a pin shaft, and the other end of the thrust telescopic cylinder portion (98) is configured to be connected to the foundation of the first rail (1) through a pin shaft; the lower end surface portion of the movable frame portion (99) is configured to be connected in a contacting manner with the foundation of the first rail (1), and the support frame portion (97) is configured to be connected to the side template assembly (8) through a connecting bolt; The movable frame portion (99) is configured as a concave-shaped frame body and the thrust telescopic cylinder portion (98) is configured as a two-section telescopic cylinder, the hydraulic port portion of the thrust telescopic cylinder portion (98) is configured to be connected to a high-pressure liquid source and the support frame portion (97) is configured as a rectangular frame, the screw of the intermediate screw nut portion (96) is configured as a plain column bolt and the nut of the intermediate screw nut portion (96) is configured as a hexagonal nut, the spring portion (95) is configured as a columnar spring and the operating table portion (94) is configured as a table-shaped body with a fence, and the pull rod portion (93) is configured as a rod-shaped body with a threaded body at the end.
7. The segment flow-type construction and forming device for prefabricating an inverted arch assembly according to claim 5 is characterized in that: The first rail (1) and the second rail (2) are respectively arranged as double-row rails with an I-shaped rail body, and the first rail (1) is arranged to be distributed in parallel with the second rail (2), a third rail (3) and a fourth rail (4) are respectively arranged at one end of the first rail (1) and one end of the second rail (2), and a fifth rail (5) and a sixth rail (6) are respectively arranged at the other end of the first rail (1) and the other end of the second rail (2), the first rail (1) is arranged to be supported and connected to the base template moving platform (7), and a clamping support frame (9) is arranged at the front and rear edges inside one end of the first rail (1), and a steaming room (90) is arranged at the inner side of the other end of the first rail (1), Or, the third rail (3), the fourth rail (4), the fifth rail (5) and the sixth rail (6) are respectively arranged as overhead double-row rails with I-shaped rail bodies, and the third rail (3), the fourth rail (4), the fifth rail (5) and the sixth rail (6) are respectively arranged at the end of the first rail (1) and the end of the second rail (2), Alternatively, the steaming room (90) is configured as a concrete component steaming shed and the steaming room (90) is configured to be connected to the first track (1) in a straddling manner.
8. The segment flow-type construction forming device and method for prefabricating an inverted arch assembly according to any one of claims 1 to 7, characterized in that: The first rail (1), the second rail (2), the third rail (3), the fourth rail (4), the fifth rail (5) and the sixth rail (6) are arranged to be distributed in the manner of closing the casting formwork, and the first rail (1), the second rail (2), the third rail (3), the fourth rail (4), the fifth rail (5), the sixth rail (6), the base formwork moving platform (7), the side formwork assembly (8) and the clamping support frame (9) are arranged to be distributed in the manner of concrete component curing sections, Alternatively, two side template assemblies (8) and two clamping support frames (9) are arranged on a base template moving platform (7), the support frame portion (97) is respectively arranged to be connected to the connecting seat portion (86) and the back rib portion (89) through connecting bolts, the outer panel portion (85) is arranged to be connected to the inner panel portion (75), the connecting bolts located on the mounting hole body of the outer panel portion (85) are arranged to be connected to the accommodating hole body (72), and the bar portion (87) is arranged to be connected to the bottom template portion (74).
9. A segment flow-type construction method for prefabricating an inverted arch assembly, characterized in that the steps are: The base template moving platform (7) realizes the combined processing of the bottom template and the end template of the prefabricated inverted arch assembly, the side template assembly (8) and the clamping support frame (9) realize the installation of the side template assembly (8) on the base template moving platform (7) to form the template body of the prefabricated inverted arch assembly, the other bottom templates and end templates are connected one by one with the side template as the base to form the casting interval body of the prefabricated inverted arch assembly, and the template body of the prefabricated inverted arch assembly is installed and formed in steps with reduced number of pieces.
10. The segment flow-type construction and forming method for prefabricating an inverted arch assembly according to claim 5, characterized in that the steps are: The movable chassis part (71) is placed on one end of the first rail (1), and the frame of the prefabricated inverted arch assembly on the transport vehicle at one end of the second rail (2) is moved to the base template moving platform (7) through the swing vehicle located on the third rail (3) and the fourth rail (4), and the frame of the prefabricated inverted arch assembly is placed on the bottom template part (74), and the core shaft part (80) is installed in the frame of the prefabricated inverted arch assembly, thereby completing the installation of the frame of the prefabricated inverted arch assembly on the bottom template part (74), and the first end template part (76) and the second end template part (77) are turned over on the bottom template part (74), so that the first end template part (76) and the second end template part (77) are in a vertical state, and the steel wire is used to connect the first end template part (76) and the second end template part (77) to the bottom template part (74). The upper end of the first end template part (76) and the upper end of the second end template part (77) are connected together, so that the movable chassis part (71) moves on the first track (1), the base template moving platform (7) moves between the two side template assemblies (8), the telescopic leg part (73) is in an extended state, the movable chassis part (71) is separated from the first track (1), the thrust telescopic cylinder part (98) is in an extended state, and the lower end surface part of the movable frame part (99) is driven to move inward on the foundation of the first track (1), so that one end of the inner side surface of the main board part (81) contacts the first end template part (76), and the other end of the inner side surface of the main board part (81) contacts the second end template part (77), The end of the tie rod portion (93) is connected to the side of the operating table portion (94) in a through-type manner, so that the nut on the tie rod portion (93) rotates at the end of the tie rod portion (93), and the nut on the tie rod portion (93) acts on the side of the operating table portion (94), thereby installing the tie rod portion (93) between the two operating table portions (94), applying a downward force to the vibrating seat portion (88), so that the spring portion (95) is in a compressed state, and the bar portion (87) moves downward on the front and rear side portions of the bottom template portion (74), so that the outer panel portion (85) moves downward on the outer side surface of the inner panel portion (75), and the connecting bolt on the mounting hole body of the outer panel portion (85) is inserted into the receiving hole body (72). ), so that the main plate portion (81) is installed on the bottom plate portion (74), and the core shaft portion (80) is installed in the ring rib portion (83), so that the core shaft portion (80) is in an expanded and filled state, and concrete mortar is injected into the skeleton of the prefabricated inverted arch assembly through the open portion between the first end plate portion (76), the second end plate portion (77) and the main plate portion (81). After the concrete mortar solidifies, the nut on the tie rod portion (93) is rotated in the opposite direction at the end of the tie rod portion (93), the nut on the tie rod portion (93) is separated from the end of the tie rod portion (93), and the end of the tie rod portion (93) is taken out from the operating table portion (94), so that the core shaft portion (80) is in a contracted and deflated state.The connecting bolts on the mounting hole body of the outer panel part (85) are rotated in the opposite direction in the receiving hole body (72) so that the connecting bolts on the mounting hole body of the outer panel part (85) are separated from the receiving hole body (72). Under the elastic energy storage action of the spring part (95), the bar part (87) moves upward on the front and rear side parts of the bottom template part (74) so that the outer panel part (85) moves upward on the outer side surface part of the inner panel part (75) so that the main board part (81) is separated from the bottom template part (74). The thrust telescopic cylinder (98) is placed in a contracted state, driving the lower end surface of the movable frame (99) to move outward on the foundation of the first rail (1), so that one end of the inner side surface of the main plate (81) is separated from the first end template (76), and the other end of the inner side surface of the main plate (81) is separated from the second end template (77), and the steel wire is separated from the upper end of the first end template (76) and the upper end of the second end template (77), so that the first end template (76) and the second end template (77) are separated. 7) the bottom template part (74) is turned over in the opposite direction, so that the first end template part (76) and the second end template part (77) are in a horizontal state, the core shaft part (80) is taken out from the skeleton of the prefabricated inverted arch assembly, and a blank of the prefabricated inverted arch assembly is obtained on the bottom template part (74), the telescopic leg part (73) is in a retracted state, the movable chassis part (71) is placed on the first track (1), the movable chassis part (71) moves on the first track (1), and the base template moving platform (7) is moved to the steaming room ( 90), the blank of the prefabricated inverted arch assembly is subjected to steam curing treatment in the steam curing room (90), and the prefabricated inverted arch assembly is obtained on the bottom template part (74), and the movable chassis part (71) is moved on the first track (1), so that the base template moving platform (7) is moved under the swinging vehicle located on the fifth track (5) and the sixth track (6), and the prefabricated inverted arch assembly is transported to the transport vehicle located on the other end of the second track (2) by the swinging vehicle located on the fifth track (5) and the sixth track (6).