Combined full-length anchoring deformation-avoiding shear-resistant anchorage device and surrounding rock anchoring method
Through the shear casing and deformation support structure of the combined full-length anchor deformation shear anchor, the problem of insufficient shear resistance in mine tunnels is solved, and high-strength surrounding rock support and shear force absorption are achieved. Improved the stability and safety of the tunnel.
Patent Information
- Application Number
- CN202410775895.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-17
- Publication Date
- 2024-10-01
AI Technical Summary
Existing full-length anchoring technology has insufficient shear resistance in mine tunnel support, which leads to easy cracking and expansion of surrounding rocks and shear breakage of anchor rods/cables, which in turn causes tunnel instability disasters, and the jointed pipe anchors and grouting methods Insufficient strength and applicability.
A combined full-length anchor deformation-resistant shear anchor is used, including a shear sleeve, a deformation support body, an anchor rod body, a tray and a locking piece. Through the extrusion deformation of the shear sleeve and the pre-tightening force of the anchor rod body, Improve shear strength and absorb energy by deforming the support to reduce shear forces.
It achieves high-strength full-length anchoring, effectively inhibits the rupture and expansion of surrounding rock, improves shear resistance, enhances the stability and safety of tunnel support, and reduces construction costs.
Smart Images

Figure CN118728455A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of mine surrounding rock support, and in particular relates to a combined full-length anchoring deformable shear-resistant anchor and a surrounding rock anchoring method. Background Art
[0002] Anchor rods / cables are widely used in mine tunnel support in my country. Due to the performance of anchoring agents, end anchors or extended anchors are mostly used, and full-length anchoring is difficult to achieve. Due to the combined effects of high stress, rock distribution and strong mining in the tunnel, the tunnel surrounding rock is prone to large-scale deformation and damage, especially shear dislocation damage of the tunnel surrounding rock, which is easy to cause the group instability of the support body caused by the shear breakage of individual anchor rods / cables, and then induce the occurrence of tunnel instability disasters.
[0003] The common full-length anchor bolts / cables used in mine tunnels in my country are seam-tube anchor bolts, and some mines use surrounding rock grouting to achieve full-length anchoring. Due to its hollow structure, the seam-tube anchor bolt only relies on the friction of the wall to achieve full-length anchoring, which has low strength. When the surrounding rock of the tunnel is severely deformed and damaged, it has a low inhibitory effect on the expansion of surrounding rock ruptures and has poor applicability. When grouting is used to achieve full-length anchoring, cement slurry is generally used as the slurry, which has low bonding strength and weak inhibitory effect on the expansion of surrounding rock ruptures. In addition, the grouting process is relatively complicated, which has a great impact on the overall tunneling support process. In the anti-shear design of anchor bolts / cables, a new type of conical anti-shear lock is mainly developed for the shear dislocation between the anchor bolt / cable tray and the surrounding rock wall, while less consideration is given to the entire lock body of the anchor cable. Summary of the invention
[0004] The purpose of the present invention is to provide a combined full-length anchoring deformable shear-resistant anchor and surrounding rock anchoring method, so as to achieve high-strength full-length anchoring, effectively inhibit the expansion of surrounding rock rupture, and improve the full-size shear resistance.
[0005] In order to achieve the above object, the technical solutions adopted by the present invention are as follows:
[0006] A combined full-length anchoring deformable shearing anchor comprises a shearing sleeve, a deformable support body, an anchoring rod body, a tray and a locking piece;
[0007] The shear sleeve is a hollow structure, the side of the shear sleeve is provided with an opening along the axial direction, and the inner wall of the shear sleeve is provided with a plurality of deformable supports made of a flexible material at intervals along the circumferential direction;
[0008] The shear-resistant casing is used for a borehole extending into the surrounding rock;
[0009] The anchor rod body passes through the interior of the shear sleeve;
[0010] The portion of the inner end of the anchor rod body exposed from the shear sleeve is set as an anchor end, and the anchor end is used to connect the inner wall of the borehole of the surrounding rock through an anchoring agent;
[0011] The portion of the outer end of the anchor rod body exposed from the shear sleeve is sequentially equipped with a tray and a locking member, and the tray is used to abut against the outer wall of the surrounding rock;
[0012] Under the action of surrounding rock stress, the shear sleeve is squeezed, the opening of the shear sleeve shrinks, the deformed support body is squeezed and deformed by the shear sleeve and the anchor rod body, and the contact area between the deformed support body and the shear sleeve and the anchor rod body increases.
[0013] Preferably, the front end of the shear-resistant sleeve is configured to be a frustum.
[0014] Preferably, a plurality of barbs are provided on the outer wall of the shear-resistant sleeve, and the ends of the barbs extend toward one side of the outer end of the shear-resistant sleeve.
[0015] Preferably, the locking member comprises a nut, and the nut is threadedly connected to the outer end of the anchor rod body.
[0016] Preferably, the locking member further comprises a gasket, wherein the gasket is sleeved on the outer end of the anchor rod body, and the gasket is located between the tray and the nut.
[0017] Preferably, the gasket is made of nylon material.
[0018] Preferably, the angle of the opening
[0019] In the formula,
[0020] E is the elastic modulus of the shear casing; S is the cross-sectional area of the shear casing subjected to surrounding rock stress; T is the surrounding rock stress.
[0021] Preferably, the flexible material is polyvinyl chloride material.
[0022] Preferably, the shear-resistant sleeve is made of metal material.
[0023] A surrounding rock anchoring method, using the above-mentioned combined full-length anchoring deformation shear anchor, the method comprises the following steps:
[0024] Step 1: Drill a hole in the surrounding rock of the tunnel, the inner diameter of the hole being larger than the outer diameter of the anchor rod body and smaller than the outer diameter of the shear casing;
[0025] Step 2, extending the anchor rod into the borehole, and connecting the anchor end of the anchor rod to the inner wall of the borehole of the surrounding rock through an anchoring agent;
[0026] Step 3, sleeve the shear sleeve on the anchor rod body, and extend the shear sleeve into the drilled hole of the surrounding rock, so that the front end of the shear sleeve extends to the anchoring end of the anchor rod body, and assemble the tray and the locking piece on the outer end of the anchor rod body in sequence, apply pre-tightening force to the anchor rod body through the locking piece, and the tray abuts the outer wall of the surrounding rock.
[0027] The beneficial technical effects of the present invention are:
[0028] 1. The combined full-length anchoring deformable shear anchor of the present invention is a combined structure, and the components it constitutes are relatively simple in structure, easy to process and manufacture, and also convenient for on-site assembly and construction, with low product and construction cost investment.
[0029] 2. The combined full-length anchoring deformable shear anchor and surrounding rock anchoring method of the present invention, after anchoring, the shear sleeve part can immediately passively support the surrounding rock, and achieve the full-length anchoring effect together with the anchor rod body and the active support part of the anchoring agent; when the outer wall of the shear sleeve contacts and squeezes the surrounding rock, radial compressive stress and axial friction force along the full length of the shear sleeve will be generated and act together with the preload force of the anchor rod body to improve the initial shear strength and enhance the overall shear resistance, so that the combined full-length anchoring deformable shear anchor can provide high-strength support for the surrounding rock; when the shear force generated by the surrounding rock undergoes a slight deformation exceeds the initial shear strength of the shear sleeve When the strength is high, the shear sleeve will be squeezed and contracted, thereby increasing the radial compressive stress and axial friction force. At this time, the axial tension of the anchor rod body will also increase, and the overall shear strength will be further enhanced; when the surrounding rock undergoes a large shrinkage deformation, the shear sleeve will be squeezed, the opening of the shear sleeve will shrink, the deformed support body will be squeezed and deformed by the shear sleeve and the anchor rod body, the contact area between the deformed support body and the shear sleeve and the anchor rod body will increase, and the deformed support body will tightly wrap the anchor rod body; through the deformation of the deformed support body, a certain amount of energy can be fully absorbed and shared, which plays a role in buffering and reducing the pressure of the surrounding rock, reducing the shear force and pressure borne by the anchor rod body, and preventing the anchor rod body from being damaged. After the deformed support body is squeezed and deformed, the contact area between the deformed support body and the shear sleeve and the anchor rod body increases, and its shear strength also increases. The shear slip deformation of the surrounding rock is greatly limited, thereby maintaining the stability of the surrounding rock and the anchor rod body, enabling the anchor to better cope with the working conditions of severe surrounding rock deformation, and ensuring the safety and reliability of the support system. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 It is a schematic diagram of the arrangement of a combined full-length anchoring deformation shear anchor according to an embodiment of the present invention;
[0031] Figure 2 for Figure 1 Middle AA section view;
[0032] Figure 3 for Figure 1Middle BB section view;
[0033] Figure 4 This is a schematic structural diagram of a shear sleeve according to an embodiment of the present invention;
[0034] Figure 5 It is a schematic diagram of the deformation process of the combined full-length anchoring deformable shear-resistant anchor under shear force according to an embodiment of the present invention;
[0035] Figure 6 This is a schematic diagram of the structure of a gasket according to an embodiment of the present invention;
[0036] Figure 7 It is a test curve diagram of preload force and preload torque of the combined full-length anchoring deformable shear anchor and the common anchor rod according to the embodiment of the present invention;
[0037] Figure 8 This is a shear force variation curve diagram of the combined full-length anchoring deformable shear anchor and the ordinary anchor rod according to the embodiment of the present invention. DETAILED DESCRIPTION
[0038] In order to make the purpose, technical scheme and beneficial effects of the present invention more clearly understood, the present invention is further described in detail below in combination with specific embodiments and with reference to the accompanying drawings. Certain embodiments of the present invention will be described more comprehensively with reference to the accompanying drawings, in which some but not all embodiments will be shown. In fact, the various embodiments of the present invention can be implemented in many different forms and should not be construed as being limited to the embodiments described herein; rather, these embodiments are provided so that the present invention meets applicable legal requirements.
[0039] In the description of the present invention, it should be noted that the terms "inside", "outside", "upper", "lower", "front", "back" and the like indicate directions or positional relationships based on directions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0040] In an embodiment of the present invention, a combined full-length anchoring deformation shear anchor and surrounding rock anchoring method are provided. Please refer to Figures 1 to 8 shown.
[0041] A combined full-length anchoring deformable shear-resistant anchor comprises a shear sleeve 1, a deformable support body 2, an anchor rod body 3, a tray 4 and a locking piece.
[0042] The shear sleeve 1 is made of metal material and is used for extending into a borehole in a surrounding rock 5 . The shear sleeve 1 is a hollow structure, and an opening 11 is arranged on a side of the shear sleeve 1 along the axial direction.
[0043] Among them, the angle of the opening 11
[0044] In the formula,
[0045] E is the elastic modulus of the shear casing 1; S is the cross-sectional area of the shear casing 1 subjected to the stress of the surrounding rock 5; T is the stress of the surrounding rock 5.
[0046] When the stress of the surrounding rock 5 acts on the shear casing 1, the shear casing 1 is squeezed and deformed, and the opening 11 of the shear casing 1 shrinks, thereby enhancing the elasticity of the shear casing 1, so that the shear casing 1 can adapt to the dynamic deformation of the surrounding rock 5 and ensure the long-term stability of the surrounding rock structure.
[0047] Three deformable supports 2 made of flexible material (polyvinyl chloride material) are arranged at intervals along the circumferential direction on the inner wall of the shear sleeve 1. When the shear sleeve 1 is just sleeved on the anchor rod 3, the thickness of the deformable support 2 is less than the difference between the inner radius of the shear sleeve 1 and the radius of the anchor rod 3, so that the anchor rod 3 can be assembled inside the shear sleeve 1.
[0048] The anchor rod body 3 passes through the interior of the shear sleeve 1 ; the portion of the inner end of the anchor rod body 3 exposed from the shear sleeve 1 is set as an anchor end, and the anchor end is used to connect to the inner wall of the borehole of the surrounding rock 5 through the anchoring agent 6 .
[0049] The portion of the outer end of the anchor rod body 3 exposed from the shear sleeve 1 is sequentially assembled with a tray 4 and a locking piece, and the tray 4 is used to abut against the outer wall of the surrounding rock 5 .
[0050] In this embodiment, the tray 4 is configured as a disc-shaped tray, which can not only support the outer end of the shear sleeve 1 to achieve a fixing effect after anchoring, but also protect the outer end of the anchor rod body 3 from shear damage at the outer edge section of the drill hole.
[0051] The locking member includes a nut 71 and a washer 72, wherein the nut 71 is threadedly connected to the outer end of the anchor rod body 3, and the washer 72 is sleeved on the outer end of the anchor rod body 3, and the washer 72 is located between the tray 4 and the nut 71. The washer 72 is made of nylon material, and the washer 72 can reduce the friction between the tray 4 and the nut 71, thereby increasing the pre-tightening force of the anchor rod body 3.
[0052] Under the stress of the surrounding rock 5, the shear sleeve 1 is squeezed, the opening 11 of the shear sleeve 1 shrinks, the deformable support body 2 is squeezed and deformed by the shear sleeve 1 and the anchor rod body 3, the thickness of the deformable support body 2 becomes thinner, and the contact area between the deformable support body 2 and the shear sleeve 1 and the anchor rod body 3 increases.
[0053] The front end of the shear sleeve 1 is configured to be in a frustum shape, so that the shear sleeve 1 can be more easily inserted into the borehole of the surrounding rock 5, thereby reducing the difficulty of assembling the components of the anchor and effectively improving the construction efficiency.
[0054] The outer wall of the shear sleeve 1 is provided with a plurality of barbs 12 along the axial direction and the radial direction, and the ends of the barbs 12 extend toward one side of the outer end of the shear sleeve 1. The barbs 12 are provided, and the resistance of the shear sleeve 1 extending into the borehole of the surrounding rock 5 is basically not increased. However, when the shear sleeve 1 is squeezed by the stress of the surrounding rock and tends to move out of the borehole, the barbs 12 can increase the resistance between the shear sleeve 1 and the inner wall of the borehole, and prevent the shear sleeve 1 from slipping out of the borehole.
[0055] A surrounding rock anchoring method, using the combined full-length anchoring deformable shear anchor described in this embodiment, the method comprising the following steps:
[0056] Step 1: construct a drill hole in the tunnel surrounding rock 5 , wherein the inner diameter of the drill hole is larger than the outer diameter of the anchor rod body 3 , and the inner diameter of the drill hole is smaller than the outer diameter of the shear sleeve 1 .
[0057] The inner diameter of the borehole is smaller than the outer diameter of the shear casing 1 , so that after the shear casing 1 is inserted into the borehole, the outer wall of the shear casing 1 abuts against the inner wall of the borehole, so that the shear casing 1 immediately supports the surrounding rock 5 .
[0058] Step 2: Extend the anchor rod 3 into the borehole, and the anchoring end of the anchor rod 3 is connected to the inner wall of the borehole of the surrounding rock 5 via the anchoring agent 6.
[0059] Step 3, sleeve the shear sleeve 1 on the anchor rod body 3, and extend the shear sleeve 1 into the drilled hole of the surrounding rock 5, so that the front end of the shear sleeve 1 extends to the anchoring end of the anchor rod body 3, and assemble the tray 4 and the locking piece on the outer end of the anchor rod body 3 in sequence, apply a pre-tightening force to the anchor rod body 3 through the locking piece, and the tray 4 abuts against the outer wall of the surrounding rock.
[0060] The combined full-length anchoring of this embodiment allows the deformable shear anchor to be anchored on the surrounding rock 5, which significantly improves the shear resistance of the rod body in terms of stable support of the surrounding rock 5, which is specifically reflected in the following three aspects:
[0061] First, after the combined full-length anchor is installed to anchor the deformable shear anchor, the shear casing 1 part can immediately passively support the surrounding rock 5, and achieve the full-length anchoring effect together with the anchor rod 3 and the active support part of the anchor 6. On the basis of the original anchoring force, when the surrounding rock 5 of the borehole wall shrinks and squeezes the shear casing 1, stress is applied to the shear casing 1, and the shear casing 1 begins to prevent the surrounding rock 5 from shrinking after being stressed. At this time, according to the Moore-Coulomb theory, when the surrounding rock 5 of the borehole wall shrinks and squeezes the shear casing 1, the resistance F provided by the shear casing 1 is:
[0062]
[0063] In the formula,
[0064] I ais the moment of inertia of the section; H is the diameter of the shear sleeve 1; w is the shrinkage amount of the opening 11 of the shear sleeve 1;
[0065] According to the shrinkage of the opening 11 of the shear sleeve 1 and the change in the angle θ of the opening 11, w can be deduced:
[0066]
[0067] In the formula,
[0068] H 1 H is the diameter of the shear sleeve 1 before the opening 11 of the shear sleeve 1 is shrunk; 2 θ is the diameter of the shear sleeve 1 after the opening 11 of the shear sleeve 1 is contracted; 1 θ is the angle of the shear sleeve 1 opening 11 before contraction; 2 It is the angle after the opening 11 of the shear sleeve 1 is contracted.
[0069] Secondly, when the outer wall of the shear sleeve 1 contacts and squeezes the surrounding rock 5, radial compressive stress and axial friction force will be generated along the entire length of the shear sleeve 1, and will work together with the preload force of the anchor rod 3 to improve the initial shear strength and enhance the overall shear resistance, so that the combined full-length anchoring allows the deformable shear anchor to provide high-strength support for the surrounding rock 5. When the shear force generated by the slight deformation of the surrounding rock 5 exceeds the initial shear strength of the shear sleeve 1, the shear sleeve 1 will be squeezed and contracted, thereby increasing the radial compressive stress and axial friction force. At this time, the axial tension of the anchor rod 3 will also increase, and the overall shear strength will be further enhanced.
[0070] In addition, when the surrounding rock 5 undergoes a large shrinkage deformation, the shear sleeve 1 is squeezed, the opening 11 of the shear sleeve 1 shrinks, the deformed support body 2 is squeezed and deformed by the shear sleeve 1 and the anchor rod 3, the contact area between the deformed support body 2 and the shear sleeve 1 and the anchor rod 3 increases, and the deformed support body 2 tightly wraps the anchor rod 3. The deformed support body 2 fully absorbs and shares a certain amount of energy through deformation, plays a role in buffering and reducing the pressure of the surrounding rock 5, reduces the shear force and pressure borne by the anchor rod 3, and prevents the anchor rod 3 from being damaged. At this time, the shear force magnitude τ of the deformed support body 2 is:
[0071]
[0072] In the formula,
[0073] μ is the shear force action range coefficient, which is generally 20%-50%.
[0074] After the deformable support body 2 is squeezed and deformed, the contact area between the deformable support body 2 and the shear sleeve 1 and the anchor rod body 3 increases, and its shear strength also increases. The shear slip deformation of the surrounding rock 5 is greatly limited, thereby maintaining the stability of the surrounding rock 5 and the anchor rod body 3, enabling the anchor to better cope with the working conditions of severe deformation of the surrounding rock 5, thereby ensuring the safety and reliability of the support system.
[0075] Specifically, the deformation process of the anchor under shear force is as follows: Figure 5 As shown:
[0076] like Figure 5 As shown in (a), when the anchor is just extended into the borehole of the surrounding rock 5, the shear sleeve 1 is not squeezed, deformed or shrunk, and there is a certain gap between the deformed support body 2 and the anchor rod body 3.
[0077] like Figure 5 As shown in (b), after the anchor is extended into the borehole of the surrounding rock 5, the shear sleeve 1 is squeezed and shrunk by the pressure of the surrounding rock 5 and part of the shear force, and the opening 11 also shrinks accordingly, and the deformed support body 2 tightly wraps the middle position of the anchor rod body 3.
[0078] like Figure 5 As shown in (c), after a period of time, due to the influence of mining and geological structure, the surrounding rock 5 becomes loose and dislocated, and the shear force acting on the anchor rod 3 increases. At this time, the shear sleeve 1 continues to be squeezed and contracted after being stressed, and the deformable support body 2 absorbs the energy generated by the shear force by deforming and covering the surroundings after being stressed. Since the shear strength of the shear sleeve 1 and the deformable support body 2 increases, the middle part of the anchor rod 3 only bears a small part of the shear force and will not deform.
[0079] like Figure 5 As shown in (d), when the pressure and shear force generated by the surrounding rock 5 gradually increase, the deformable support body 2 will eventually deform to cover the entire cross-section of the middle part of the anchor rod body 3 after being subjected to the force. At this time, its shear strength reaches its maximum value, which can fully reduce the shear force of the surrounding rock 5 on the middle part of the anchor rod body 3, and effectively ensure the stability of the support of the anchor rod body 3.
[0080] The preload test and shear test are carried out on the combined full-length anchoring deformation shear anchor (combined full-length anchoring deformation shear anchor (cable)) and the ordinary anchor:
[0081] The combined full-length anchoring makes the anchor rod body 3 of the deformable shear anchor use a threaded steel anchor rod with a diameter of 22mm, the shear sleeve 1 uses a Q355 steel pipe with a thickness of 2mm, the deformable support body 2 uses a 5mm thick PVC plastic, the gasket 72 uses a nylon gasket, and the ordinary anchor rod uses a threaded steel anchor rod with a diameter of 22mm.
[0082] like Figure 7As shown in Figure 2, from the preload force and preload torque test results, it can be seen that the combined full-length anchoring increases the preload force of the deformable shear anchor by 43% to 62% compared to the preload force of the ordinary anchor rod, thereby achieving the provision of high preload force.
[0083] like Figure 8 As shown in the figure, the shear test results show that the shear force change curves are not much different in the early stage of the experiment. When the shear displacement reaches 5mm at point A, the combined full-length anchoring makes the shear deformation of the deformable shear anchor significantly require a larger shear force than the ordinary anchor rod. The reason is that the internal deformable support body 2 absorbs and disperses most of the energy generated by the shear force through its own deformation, and before reaching point B, the shear force increases with the increase of shear displacement, indicating that the shear resistance of the deformable support body 2 is getting stronger during the action process. It can be seen that the combined full-length anchoring improves the shear resistance of the deformable shear anchor by about 60% compared with the ordinary anchor rod, and has a stronger ability to resist shear deformation.
[0084] So far, the present embodiment has been described in detail in conjunction with the accompanying drawings. Based on the above description, those skilled in the art should have a clear understanding of the combined full-length anchoring deformable shear anchor and surrounding rock anchoring method of the present invention. Of course, the specific embodiments described above further describe the purpose, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above is only a specific embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A combined full-length anchoring deformation shear anchor, It is characterized in that It includes a shear sleeve, a deformable support body, an anchor rod body, a tray and a locking piece; The shear sleeve is a hollow structure, the side of the shear sleeve is provided with an opening along the axial direction, and the inner wall of the shear sleeve is provided with a plurality of deformable supports made of a flexible material at intervals along the circumferential direction; The shear-resistant casing is used for a borehole extending into the surrounding rock; The anchor rod body passes through the interior of the shear sleeve; The portion of the inner end of the anchor rod body exposed from the shear sleeve is set as an anchor end, and the anchor end is used to connect the inner wall of the borehole of the surrounding rock through an anchoring agent; The portion of the outer end of the anchor rod body exposed from the shear sleeve is sequentially equipped with a tray and a locking member, and the tray is used to abut against the outer wall of the surrounding rock; Under the action of surrounding rock stress, the shear sleeve is squeezed, the opening of the shear sleeve shrinks, the deformed support body is squeezed and deformed by the shear sleeve and the anchor rod body, and the contact area between the deformed support body and the shear sleeve and the anchor rod body increases.
2. A combined full-length anchoring deformable shear anchor according to claim 1, It is characterized in that The front end of the shear sleeve is arranged in a frustum shape.
3. A combined full-length anchoring deformable shear anchor according to claim 1, It is characterized in that The outer wall of the shear-resistant sleeve is provided with a plurality of barbs, and the ends of the barbs extend toward one side of the outer end of the shear-resistant sleeve.
4. A combined full-length anchoring deformable shear anchor according to claim 1, It is characterized in that The locking member comprises a nut which is threadedly connected to the outer end of the anchor rod body.
5. A combined full-length anchoring deformable shear anchor according to claim 4, It is characterized in that The locking member further comprises a gasket, which is sleeved on the outer end of the anchor rod body and is located between the tray and the nut.
6. A combined full-length anchoring deformable shear anchor according to claim 5, It is characterized in that The gasket is made of nylon material.
7. A combined full-length anchoring deformable shear anchor according to claim 1, It is characterized in that The angle of the opening In the formula, E is the elastic modulus of the shear casing; S is the cross-sectional area of the shear casing subjected to surrounding rock stress; T is the surrounding rock stress.
8. A combined full-length anchoring deformable shear anchor according to claim 1, It is characterized in that The flexible material is configured as polyvinyl chloride material.
9. A combined full-length anchoring deformable shear anchor according to claim 1, It is characterized in that The shear sleeve is made of metal material.
10. A surrounding rock anchoring method, It is characterized in that Using the combined full-length anchoring deformable shear anchor according to any one of claims 1 to 9, the method comprises the following steps: Step 1: Drill a hole in the surrounding rock of the tunnel, the inner diameter of the hole being larger than the outer diameter of the anchor rod body and smaller than the outer diameter of the shear casing; Step 2, extending the anchor rod into the borehole, and connecting the anchor end of the anchor rod to the inner wall of the borehole of the surrounding rock through an anchoring agent; Step 3, sleeve the shear sleeve on the anchor rod body, and extend the shear sleeve into the drilled hole of the surrounding rock, so that the front end of the shear sleeve extends to the anchoring end of the anchor rod body, and assemble the tray and the locking piece on the outer end of the anchor rod body in sequence, apply pre-tightening force to the anchor rod body through the locking piece, and the tray abuts the outer wall of the surrounding rock.