A vertical spherical bearing and a processing method thereof
Through the fully automatic assembly process and heat dissipation design of vertical spherical bearings, the problems of complex installation and insufficient heat dissipation of traditional bearings are solved, rapid assembly and efficient heat dissipation are achieved, and the installation efficiency and performance of bearings are improved.
Patent Information
- Application Number
- CN202411230027.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-04
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2044-09-04
AI Technical Summary
Traditional bearings have inconvenience during installation and maintenance, which leads to complex and time-consuming installation, and is prone to heat generation during long-term use to affect system performance.
Vertical outer spherical bearings and their processing methods are adopted, and through a fully automatic assembly process, including the transmission of the vertical seat, the assembly of the ball and the installation of the sealing ring, the clamping frame, the synchronous transmission belt, the lifting cylinder and the adsorption vibrator are realized. Quickly assemble and install heat dissipation through holes on the cage to enhance heat dissipation performance.
The rapid and fully automatic assembly of the bearing is achieved, which reduces the time and energy investment of workers during the installation process, and improves the heat dissipation performance of the bearing through the heat dissipation through the heat dissipation holes and improves the efficiency and performance of the system.
Smart Images

Figure CN118728845B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of bearings, and in particular relates to a vertical outer spherical bearing and a processing method thereof. Background Art
[0002] Conventional bearings are widely used in the industrial and mechanical fields to support rotating parts and reduce friction losses. However, existing bearing designs may have some inconveniences in installation and maintenance, limiting their flexibility and efficiency in certain applications. Therefore, a new type of bearing structure with a bearing seat is needed to meet higher performance requirements. Conventional bearings are prone to heat generation during long-term use, affecting the performance of the overall system. Secondly, the bearing installation process may be complicated, causing workers to spend too much time and energy during the installation process. Summary of the invention
[0003] In view of the deficiencies in the prior art, the technical problem to be solved by the present invention is to provide a vertical spherical bearing and a processing method thereof, which can dissipate heat well and realize full-automatic assembly in conjunction with the structure.
[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is: a vertical spherical bearing processing method, comprising the following steps:
[0005] A. The stands are stacked and placed in a vertical conveyor channel, and then transported to the working conveyor platform in sequence;
[0006] B. The working conveyor table transmission stand is placed under the shaft placing and bead loading machine to place the rotating inner shaft and assemble the balls;
[0007] C. The working conveyor continues to transport the stand, so that the stand is placed under the cage installation machine and above the seal installation machine to install the cage and seal ring;
[0008] D. After assembly is completed, the work conveyor continues to transport the stand and places it in the collection box.
[0009] Preferably, the vertical transmission channel in step A is provided with a holding frame and a clamping frame, the clamping frame is installed on the holding frame, the clamping frame includes two fixed rods and two clamping rods, the two fixed rods are fixedly installed on the holding frame, the two clamping rods are swingably installed on the holding frame, and a driving rod for driving the clamping rod to swing is installed on the holding frame, and a limit slot supporting the two fixed rods is provided in the vertical transmission channel.
[0010] Preferably, the working conveyor platform in step A comprises a conveyor frame, a support plate and two synchronous conveyor belts, the two synchronous conveyor belts are symmetrically mounted on both sides of the conveyor frame, a rotating shaft for driving the two synchronous conveyor belts is rotatably mounted inside the conveyor frame, a driving motor for driving the rotating shaft to rotate is mounted outside the conveyor frame, and the support plate is mounted on the conveyor frame and is located between the two synchronous conveyor belts;
[0011] Lifting cylinders are installed equidistantly between the two synchronous transmission belts along their lengths, a transition groove for the lifting cylinders to pass through is opened on the support plate, a rotator is installed at the output end of the lifting cylinder, a supporting cross bar is installed at the rotating end of the rotator, both ends of the supporting cross bar are respectively placed on the two synchronous transmission belts, and limiting columns are respectively installed at both ends of the supporting cross bar.
[0012] Preferably, the shaft placing and bead loading machine in step B comprises an inner shaft conveying frame, a movable lifting member, a bead storage bucket and a bead conveying member, wherein the inner shaft conveying frame is located above the working conveying platform, the movable lifting member is installed in the inner shaft conveying frame, the bead storage bucket is installed on the inner shaft conveying frame, the bead conveying member is installed at the output end of the bead storage bucket, and the output port of the bead conveying member is arranged toward the working conveying platform;
[0013] The inner shaft conveying frame includes a lifting support frame and a transmission channel. A lifting cylinder for lifting and rotating the inner shaft is installed at the bottom of the lifting support frame. The lifting support frame is located on one side of the working conveying platform. The transmission channel is installed on the lifting support frame and is provided with an input port connected to the lifting support frame. The transmission channel is provided with an output port corresponding to the position of the working conveying platform.
[0014] The mobile lifting component includes a rodless cylinder, a lifting drive cylinder and a push rod. The rodless cylinder is fixedly installed on the top of the transmission channel, the lifting drive cylinder is installed on the driving end of the rodless cylinder, and the push rod is installed on the output end of the lifting drive cylinder.
[0015] Preferably, the bead conveying member comprises a transmission tube, a rotating member, a telescopic tube, a telescopic driver and a plurality of storage tubes, the transmission tube is connected to the output port of the bead storage bucket, the top of the bead storage bucket is inclined from high to low toward the transmission tube, the rotating member is installed on the bead storage bucket and is located above the output of the transmission tube, a turntable is installed on the rotating end of the rotating member, a plurality of the storage tubes are arranged on the turntable, and the plurality of storage tubes are equidistantly arranged around the central axis of the turntable, the telescopic tube is installed on the transmission channel and is located downstream of the rotating member, the telescopic driver is installed on the transmission channel, and the output end of the telescopic driver is connected to the telescopic tube, one end of the storage tube below the turntable is connected to the transmission tube, and the shaft placing and bead loading machine is provided with a first blocking block at the other end of the storage tube, one end of the storage tube above the turntable is connected to the telescopic tube, and the shaft placing and bead loading machine is provided with a second blocking block at the other end of the storage tube;
[0016] The storage tube is provided with a plurality of oil filling ports, the side wall of the bead storage barrel is installed with an oil filling barrel, the oil filling barrel is installed with oil outlet pipes corresponding to the positions of the plurality of oil filling ports, and the pipe mouth of the oil outlet pipe is installed with a pneumatic oil outlet head connected to the oil filling port.
[0017] Preferably, the holding frame installation machine in step C includes a horizontal moving frame, an upper and lower driving cylinder, an oiling head, an adsorption vibrator, two holding storage frames and a plurality of oiling pipes, the two holding storage frames are symmetrically located on both sides of the working conveying platform, a screw lifter for lifting the holding frame is installed in the holding storage frame, the horizontal moving frame is installed above the two holding storage frames, the upper and lower driving cylinders are installed on the moving output end of the horizontal moving frame, the oiling head is installed on the output end of the upper and lower driving cylinders, and a mounting frame is also installed on the moving output end of the horizontal moving frame, the mounting frame has two lubricating oil barrels connected to the oiling head, a plurality of oiling pipes are equidistantly installed on the oiling head around the lifting shafts of the upper and lower driving cylinders, and are connected to the oiling head, the oiling head is located between the plurality of oiling pipes and a downward pressure cylinder is installed, and the adsorption vibrator is installed on the output end of the downward pressure cylinder;
[0018] The adsorption vibrator comprises a plurality of support rods, wherein the support rods are located between adjacent oil injection pipes, vacuum adsorption heads are installed at the ends of the support rods, and vibration generators are installed above the vacuum adsorption heads.
[0019] Preferably, the sealing installation machine in step C includes a lifting and pressing platform, a transmission platform and a calibration ring, the lifting and pressing platform and the transmission platform are both located below the working conveying platform, the transmission platform is located on one side of the lifting and pressing platform, the calibration ring is installed at the output of the transmission platform and is located directly above the lifting and pressing platform, an ultrasonic vibrator is installed below the calibration ring, and limit plates are installed on both symmetrical sides of the transmission platform.
[0020] Preferably, the lifting and pressing platform includes a lifting cylinder and an annular pressure rod, the annular pressure rod is installed on the output end of the lifting cylinder, the calibration ring includes an inner platform and an outer ring, the ultrasonic vibrator is installed under the inner platform, and a limiting groove for accommodating a sealing ring is provided between the inner platform and the outer ring, and the annular pressure rod is matched with the limiting groove.
[0021] A vertical external spherical bearing comprises a stand and a rotating inner shaft, the stand is provided with a rotating inner ring, the rotating inner shaft is rotatably placed in the rotating inner ring, a plurality of balls are arranged between the rotating inner shaft and the stand, a retaining frame is provided on the ball cover, a heat dissipation through hole is opened on the retaining frame at the position of the ball, and a sealing ring is provided at the position cover of the stand corresponding to the retaining frame.
[0022] Preferably, the sealing ring includes an outer ring sealing rubber ring, a middle heat dissipation ring and an inner ring sealing rubber ring. The outer ring sealing rubber ring is fixedly mounted on the outer ring of the middle heat dissipation ring and fits with the stand. The inner ring sealing rubber ring is fixedly mounted on the inner ring of the middle heat dissipation ring and fits with the rotating inner shaft.
[0023] Compared with the prior art, the present invention has the following beneficial effects:
[0024] 1. The vertical outer spherical bearing processing method of the present invention performs full-automatic assembly, reducing the excessive time and energy spent by workers during the installation process.
[0025] 2. The vertical outer spherical bearing processing method of the present invention can be achieved by holding the holding frame, and then resisting the seat through two fixed rods, and then pulling the driving rod so that the two clamping rods cooperate with the two fixed rods to clamp the seat, so that the seat can be clamped and moved to the top of the next seat, and the seat is located above by loosening the driving rod, and then the two clamping rods move down to resist the bottom seat, and then the bottom seat is clamped by the two fixed rods. The above operations are performed in sequence, which may make multiple seats stacked between the two fixed rods and the two clamping rods, and then transported and placed in the vertical transmission channel to achieve rapid transportation.
[0026] 3. The processing method of the vertical outer spherical bearing of the present invention is to place the balls in the ball storage barrel into the storage tube through the transmission tube for storage, and then drive the storage tube to dock with the telescopic tube through the rotating part, so that the balls move along the storage tube and are placed in the telescopic tube, and then cooperate with the telescopic driver to drive the tube mouth of the telescopic tube to be placed between the stand and the rotating inner shaft to load the balls, and at the same time, the pneumatic oil outlet head cooperates with multiple oil filling ports to inject lubricating oil into the storage tube, so that the balls are coated with lubricating oil, which is more convenient for entering between the stand and the rotating inner shaft.
[0027] The oiling head is driven by the plurality of oiling pipes to be inserted into the upper and lower surfaces of the bearing and the bearing is fixed by the adsorption vibrator, and then the oiling head is driven by the plurality of oiling pipes to be inserted into the upper and lower surfaces of the bearing and the bearing is fixed by the adsorption vibrator.
[0028] 5. A vertical outer spherical bearing of the present invention has heat dissipation holes arranged in the retaining frame, so that heat energy can be dissipated through the heat dissipation holes during the rotation of the ball and transferred to the outside of the bearing through the sealing ring, thereby increasing the heat dissipation performance of the bearing. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 It is a schematic diagram of the exploded structure of the vertical outer spherical bearing of the present invention;
[0030] Figure 2 It is a structural schematic diagram of the bearing processing machine of the present invention;
[0031] Figure 3 It is a structural schematic diagram of the working conveying platform of the present invention;
[0032] Figure 4 It is a structural schematic diagram of the vertical transmission channel of the present invention;
[0033] Figure 5 It is an enlarged structural schematic diagram of the lifting cylinder of the present invention;
[0034] Figure 6 It is a structural schematic diagram of the shaft placing and bead loading machine of the present invention;
[0035] Figure 7 It is a structural schematic diagram of the bead conveying member of the present invention;
[0036] Figure 8 It is a schematic diagram of the planar structure of the turntable of the present invention;
[0037] Fig. 9 It is a structural schematic diagram of the protection frame installation machine of the present invention;
[0038] Fig.10 It is a schematic diagram of the cross-sectional structure of the storage rack of the present invention;
[0039] Fig.11 It is a structural schematic diagram of the adsorption vibrator of the present invention;
[0040] Fig.12 It is a structural schematic diagram of the sealing installation machine of the present invention;
[0041] Fig.13 It is a schematic diagram of the top view of the calibration ring of the present invention;
[0042] Fig.14 It is a schematic diagram of the top view of the annular pressure rod of the present invention.
[0043] Markings in the figure: 1, stand; 2, rotating inner shaft; 3, ball bearing; 4, retaining frame; 5, heat dissipation hole; 6, sealing ring; 7, vertical transmission channel; 71, holding frame; 72, clamping frame; 73, fixing rod; 74, clamping rod; 75, driving rod; 76, limit slot;
[0044] 8. Working conveyor platform; 81. Transmission frame; 82. Support plate; 83. Synchronous transmission belt; 84. Lifting cylinder; 85. Rotator; 86. Support crossbar; 87. Limiting column;
[0045] 9. Shaft-loading bead loading machine; 91. Inner shaft conveying frame; 92. Mobile lifting part; 93. Bead storage bucket; 94. Bead conveying part; 95. Lifting support frame; 96. Transmission channel; 97. Lifting cylinder; 98. Rodless cylinder; 99. Lifting drive cylinder; 910. Push rod; 911. Transmission pipe; 912. Rotating part; 913. Telescopic pipe; 914. Telescopic drive; 915. Storage pipe; 916. Turntable; 917. First block; 918. Second block; 919. Oil filling port; 920. Oil filling barrel; 921. Oil outlet pipe; 922. Pneumatic oil outlet head;
[0046] 10. Holder installation machine; 101. Horizontal moving frame; 102. Up and down driving cylinder; 103. Oiling head; 104. Adsorption vibrator; 105. Hold storage rack; 106. Oiling pipe; 107. Lubricating oil barrel; 108. Down-pressing cylinder; 109. Support rod; 1010. Vacuum adsorption head; 1011. Vibration generator; 1012. Screw lifter;
[0047] 11. Seal installation machine; 111. Transfer platform; 112. Calibration ring; 113. Ultrasonic vibrator; 114. Lifting cylinder; 115. Annular pressure rod; 116. Inner platform; 117. Outer ring;
[0048] 12. Collection box. DETAILED DESCRIPTION
[0049] In order to make the above features and advantages of the present invention more obvious and easy to understand, embodiments are given below with reference to the accompanying drawings for detailed description as follows.
[0050] like Figure 1-Figure 14 As shown, this embodiment provides a method for processing a vertical spherical bearing, comprising the following steps:
[0051] A. The stands 1 are stacked and placed in the vertical transport channel 7, and are then sequentially transported to the working transport platform 8;
[0052] B. The work conveyor table 8 transfers the stand 1 to be placed under the shaft placing and bead loading machine 9 to place the rotating inner shaft 2 and assemble the ball 3;
[0053] C. The working conveyor 8 continues to transport the stand 1, so that the stand 1 is placed below the cage installation machine 10 and above the seal installation machine 11 to install the cage 4 and the seal ring 6;
[0054] D. After the assembly is completed, the working conveying platform 8 continues to convey the stand 1 so that the stand 1 is placed in the collection box 12.
[0055] Fully automatic assembly is carried out to reduce the time and energy spent by workers during the installation process.
[0056] Furthermore, the vertical transmission track 7 in step A is provided with a holding frame 71 and a clamping frame 72, the clamping frame 72 is installed on the holding frame 71, the clamping frame 72 includes two fixed rods 73 and two clamping rods 74, the two fixed rods 73 are fixedly installed on the holding frame 71, the two clamping rods 74 are swingably installed on the holding frame 71, and a driving rod 75 for driving the clamping rod 74 to swing is installed on the holding frame 71, and a limiting slot 76 for supporting the two fixed rods 73 is provided in the vertical transmission track 7. The holding frame 71 can be held, and then the two fixing rods 73 can be used to resist the seat 1 first, and then the driving rod 75 can be pulled to make the two clamping rods 74 cooperate with the two fixing rods 73 to clamp the seat 1, so that the seat 1 can be clamped and moved to the top of the next seat 1, and the driving rod 75 can be released to make the seat 1 be located above it, and then the two clamping rods 74 can be moved down to resist the bottom seat 1, and then the bottom seat 1 can be clamped by the two fixing rods 73, and the above operations can be repeated, so that multiple seats 1 can be stacked between the two fixing rods 73 and the two clamping rods 74, and then transported and placed in the vertical transmission channel 7 to achieve fast transportation.
[0057] Furthermore, the working conveyor platform 8 in step A includes a transmission frame 81, a support plate 82 and two synchronous transmission belts 83, the two synchronous transmission belts 83 are symmetrically installed on both sides of the transmission frame 81, a rotating shaft for driving the two synchronous transmission belts 83 is rotatably installed inside the transmission frame 81, and a driving motor for driving the rotating shaft is installed outside the transmission frame 81, and the support plate 82 is installed on the transmission frame 81 and is located between the two synchronous transmission belts 83; between the two synchronous transmission belts 83, lifting cylinders 84 are equidistantly installed along their own lengths, and a transition groove for the lifting cylinders 84 to pass through is opened on the support plate 82, and a rotator 85 is installed at the output end of the lifting cylinder 84, and a supporting cross bar 86 is installed at the rotating end of the rotator 85, and the two ends of the supporting cross bar 86 are respectively placed on the two synchronous transmission belts 83, and the two ends of the supporting cross bar 86 are respectively installed with limiting columns 87. The stand 1 is transferred to two synchronous transmission belts 83 through the vertical transmission channel 7, and then the synchronous transmission belts 83 are driven so that the limiting column 87 is placed on the two screw holes of the stand 1 to limit and fix the stand 1, and then it is continuously transferred to be placed under the shaft placing and bead installing machine 9 to place the rotating inner shaft 2 and the ball 3, and then it is continuously transferred to be placed between the retainer installation machine 10 and the sealing installation machine 11 to assemble the retainer 4 and the sealing ring 6. After the retainer 4 is installed, the rotator 85 is driven to rise by the lifting cylinder 84, and then the rotator 85 drives the supporting cross bar 86 to reverse 180 degrees, and then the limiting column 87 drives the stand 1 to follow the rotation, and its lifting cylinder 84 is reset, so that the retainer 4 on the other side is installed while the sealing ring 6 is also installed, and then it is rotated again to install the sealing ring 6 on the other side.
[0058] Furthermore, the shaft placing and bead loading machine 9 in step B includes an inner shaft conveying frame 91, a movable lifting member 92, a bead storage barrel 93 and a bead transport member 94, the inner shaft conveying frame 91 is located above the working conveying platform 8, the movable lifting member 92 is installed in the inner shaft conveying frame 91, the bead storage barrel 93 is installed on the inner shaft conveying frame 91, and the bead transport member 94 is installed at the output end of the bead storage barrel 93, and the output port of the bead transport member 94 is arranged toward the working conveying platform 8; the rotating inner shaft 2 is transmitted through the inner shaft conveying frame 91, and then the topmost rotating inner shaft 2 is moved and placed in the stand 1 of the working conveying platform 8 through the movable lifting member 92, and then the ball 3 is transmitted between the stand 1 and the rotating inner shaft 2 through the cooperation of the bead storage barrel 93 and the bead transport member 94, so as to realize the automatic assembly of the ball 3. Specifically, the inner shaft conveying frame 91 includes a lifting support frame 95 and a transmission channel 96. A lifting cylinder 97 for lifting and rotating the inner shaft 2 is installed at the bottom of the lifting support frame 95. The lifting support frame 95 is located on one side of the working conveying platform 8. The transmission channel 96 is installed on the lifting support frame 95 and is provided with an input port connected to the lifting support frame 95. The transmission channel 96 is provided with an output port corresponding to the position of the working conveying platform 8; the mobile lifting component 92 includes a rodless cylinder 98, a lifting drive cylinder 99 and a push rod 910. The rodless cylinder 98 is fixedly installed on the top of the transmission channel 96, the lifting drive cylinder 99 is installed on the driving end of the rodless cylinder 98, and the push rod 910 is installed on the output end of the lifting drive cylinder 99. The lifting cylinder 97 is lifted so that the rotating inner shaft 2 in the lifting support frame 95 is continuously transmitted upward, and then the rodless cylinder 98 drives the lifting drive cylinder 99 to drive the push rod 910 to move and place it on the rotating inner shaft 2. The lifting drive cylinder 99 drives the push rod 910 to descend and be placed in the inner ring of the rotating inner shaft 2. The lifting drive cylinder 99 is then driven by the rodless cylinder 98 to move, thereby driving the transmission of the rotating inner shaft 2. When filling the balls 3, the rodless cylinder 98 and the lifting drive cylinder 99 can be used to drive the push rod 910 to move the rotating inner shaft 2, so that the rotating inner shaft 2 is tilted to the lower side for convenient filling of the balls 3. After the balls 3 are filled, the rodless cylinder 98 and the lifting drive cylinder 99 are used to drive the push rod 910 to move the rotating inner shaft 2 to reset.
[0059] Furthermore, the bead transport member 94 includes a transmission tube 911, a rotating member 912, a telescopic tube 913, a telescopic driver 914 and a plurality of storage tubes 915. The transmission tube 911 is connected to the output port of the bead storage barrel 93, and the top of the bead storage barrel 93 is tilted from high to low toward the transmission tube 911. The rotating member 912 is installed on the bead storage barrel 93 and is located above the output of the transmission tube 911. A turntable 916 is installed on the rotating end of the rotating member 912. A plurality of storage tubes 915 are arranged on the turntable 916, and the plurality of storage tubes 915 are equidistantly arranged around the central axis of the turntable 916, and the storage tubes 915 are tilted from high to low from the transmission tube 911 toward the telescopic tube 913. The telescopic tube 913 is installed on the transmission channel 96 and is located downstream of the rotating member 912. Actuator 914 is installed on the transmission channel 96, and the output end of the telescopic driver 914 is connected to the telescopic tube 913, one end of the storage tube 915 located below the turntable 916 is connected to the transmission tube 911, and the shaft-releasing bead-loading machine 9 is provided with a first blocking block 917 at the other end of the storage tube 915, one end of the storage tube 915 located above the turntable 916 is connected to the telescopic tube 913, and the shaft-releasing bead-loading machine 9 is provided with a second blocking block 918 at the other end of the storage tube 915; specifically, the storage tube 915 is provided with a plurality of oil filling ports 919, and an oil filling barrel 920 is installed on the side wall of the bead storage barrel 93, and the oil filling barrel 920 is provided with oil outlet pipes 921 corresponding to the positions of the plurality of oil filling ports 919, and the pipe mouth of the oil outlet pipe 921 is provided with a pneumatic oil outlet head 922 connected to the oil filling port 919. The balls 3 in the bead storage barrel 93 are placed in the storage tube 915 through the transmission tube 911 for storage, and then the storage tube 915 is driven by the rotating member 912 to dock with the telescopic tube 913, so that the balls 3 move along the storage tube 915 and are placed in the telescopic tube 913, and then the telescopic driver 914 drives the tube mouth of the telescopic tube 913 to be placed between the stand 1 and the rotating inner shaft 2 for loading the balls, and at the same time, the pneumatic oil outlet head 922 cooperates with the multiple oil filling ports 919 to inject lubricating oil into the storage tube 915, so that the balls 3 are coated with lubricating oil, which makes it easier for them to enter between the stand 1 and the rotating inner shaft 2.
[0060] Furthermore, the rack installation machine 10 in step C includes a horizontal moving frame 101, an upper and lower driving cylinder 102, an oiling head 103, an adsorption vibrator 104, two holding storage frames 105 and a plurality of oiling pipes 106, the two holding storage frames 105 are symmetrically located on both sides of the working conveying platform 8, and a screw lifter 1012 for lifting the holding frame 4 is installed in the holding storage frame 105. The horizontal moving frame 101 is installed above the two holding storage frames 105, the upper and lower driving cylinders 102 are installed on the moving output end of the horizontal moving frame 101, the oiling head 103 is installed on the output end of the upper and lower driving cylinders 102, and the moving output end of the horizontal moving frame 101 is also installed with a screw lifter 1012. The mounting frame has two lubricating oil barrels 107 connected to the oiling head 103, and multiple oiling pipes 106 are equidistantly installed on the oiling head 103 around the lifting shaft of the upper and lower driving cylinders 102, and are connected to the oiling head 103. The oiling head 103 is located between the multiple oiling pipes 106 and is equipped with a downward pressure cylinder 108, and the adsorption vibrator 104 is installed on the output end of the downward pressure cylinder 108; specifically, the adsorption vibrator 104 includes multiple support rods 109, the support rods 109 are located between adjacent oiling pipes 106, and the ends of the support rods 109 are equipped with vacuum adsorption heads 1010, and the support rods 109 are equipped with vibration generators 1011 above the vacuum adsorption heads 1010. The horizontal moving frame 101 drives the up and down driving cylinders 102 to drive the oiling head 103 to be placed on one of the holding storage frames 105, and then the screw lifter 1012 of the holding storage frame 105 pushes the holding frame 4 to rise, so that multiple oiling pipes 106 pass through the heat dissipation holes of the holding frame 4, and then are adsorbed and fixed by the adsorption vibrator 104, and then the horizontal moving frame 101 drives the up and down driving cylinders 102 to drive the oiling head 103 to be placed above the stand 1, and then the up and down driving cylinders 102 drive the oiling head 103 to descend so that the holding frame 4 contacts the ball 3, and then the adsorption vibrator 10 4, the vibration generator 1011 generates vibration, and while vibrating, the upper and lower driving cylinders 102 continue to descend, so that the ball 3 moves to be placed under the heat dissipation hole, and the vibration is stopped, and the downward pressing cylinder 108 drives the adsorption vibrator 104 to press down so that the retainer cover is on the ball 3, and is interference fit between the stand 1 and the rotating inner shaft 2, and in the process of the downward pressing cylinder 108 driving the downward pressing, the oiling head 103 cooperates with multiple oiling pipes 106 to inject lubricating oil, and the upper and lower driving cylinders 102 are slowly driven to rise, so that the lubricating oil can be injected simultaneously during the process of assembling the retainer 4, thereby increasing the assembly efficiency.
[0061] Furthermore, the sealing installation machine 11 in step C includes a lifting and pressing platform, a transmission platform 111 and a calibration ring 112. The lifting and pressing platform and the transmission platform 111 are both located below the working conveying platform 8. The transmission platform 111 is located on one side of the lifting and pressing platform. The calibration ring 112 is installed at the output of the transmission platform 111 and is located directly above the lifting and pressing platform. An ultrasonic vibrator 113 is installed below the calibration ring 112, and limit plates are installed on both symmetrical sides of the transmission platform 111. Specifically, the lifting and pressing platform includes a lifting cylinder 114 and an annular pressure rod 115. The annular pressure rod 115 is installed on the output end of the lifting cylinder 114. The calibration ring 112 includes an inner platform 116 and an outer ring 117. The ultrasonic vibrator 113 is installed below the inner platform 116. There is a limit groove for accommodating the sealing ring 6 between the inner platform 116 and the outer ring 117. The annular pressure rod 115 is matched with the limit groove. When assembling the sealing ring 6, the sealing ring 6 is transferred through the transfer platform 111 and placed on the calibration ring 112, and then the sealing ring 6 is vibrated by the ultrasonic vibrator 113 to be placed in the limit groove for positioning, and then the annular pressure rod 115 is pushed by the lifting cylinder 114 output to drive the sealing ring 6 to be pressed between the stand 1 and the rotating inner shaft 2.
[0062] A vertical external spherical bearing includes a seat 1 and a rotating inner shaft 2. The seat 1 is provided with a rotating inner ring. The rotating inner shaft 2 is rotatably placed in the rotating inner ring. A plurality of balls 3 are provided between the rotating inner shaft 2 and the seat 1. A retaining frame 4 is provided on the ball 3. The retaining frame 4 is provided with heat dissipation holes 5 at the positions of the balls 3. A sealing ring 6 is provided at the position of the seat 1 corresponding to the retaining frame 4. By providing the heat dissipation holes 5 on the retaining frame 4, heat energy can be dissipated through the heat dissipation holes 5 during the rotation of the balls 3, and is transferred to the outside of the bearing through the sealing ring 6 by heat conduction, thereby increasing the heat dissipation performance of the bearing. Specifically, the sealing ring 6 includes an outer ring sealing rubber ring, a middle heat dissipation ring and an inner ring sealing rubber ring. The outer ring sealing rubber ring is fixedly mounted on the outer ring of the middle heat dissipation ring and fits with the seat 1. The inner ring sealing rubber ring is fixedly mounted on the inner ring of the middle heat dissipation ring and fits with the rotating inner shaft 2. The gap is sealed by the cooperation of the outer ring sealing rubber ring and the inner ring sealing rubber ring, and the middle heat dissipation ring guides out the heat energy discharged from its heat dissipation through hole 5, and a plurality of heat dissipation fins are arranged on the middle heat dissipation ring.
[0063] The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for illustrating the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which shall fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.
Claims
1. A method for processing a vertical spherical bearing, characterized in that: The steps include: A. The stands are stacked and placed in a vertical conveyor channel, and then transported to the working conveyor platform in sequence; B. The working conveyor table transmission stand is placed under the shaft placing and bead loading machine to place the rotating inner shaft and assemble the balls; C. The working conveyor continues to transport the stand, so that the stand is placed under the cage installation machine and above the seal installation machine to install the cage and seal ring; D. After the assembly is completed, the work conveyor continues to transport the stand so that the stand is placed in the collection box; The shaft placing and bead loading machine in step B comprises an inner shaft conveying frame, a movable lifting member, a bead storage bucket and a bead conveying member, wherein the inner shaft conveying frame is located above the working conveying platform, the movable lifting member is installed in the inner shaft conveying frame, the bead storage bucket is installed on the inner shaft conveying frame, the bead conveying member is installed at the output end of the bead storage bucket, and the output port of the bead conveying member is arranged toward the working conveying platform; The inner shaft conveying frame includes a lifting support frame and a transmission channel. A lifting cylinder for lifting and rotating the inner shaft is installed at the bottom of the lifting support frame. The lifting support frame is located on one side of the working conveying platform. The transmission channel is installed on the lifting support frame and is provided with an input port connected to the lifting support frame. The transmission channel is provided with an output port corresponding to the position of the working conveying platform. The mobile lifting member includes a rodless cylinder, a lifting drive cylinder and a push rod, wherein the rodless cylinder is fixedly mounted on the top of the transmission channel, the lifting drive cylinder is mounted on the driving end of the rodless cylinder, and the push rod is mounted on the output end of the lifting drive cylinder; The bead conveying member includes a transmission tube, a rotating member, a telescopic tube, a telescopic driver and a plurality of storage tubes. The transmission tube is connected to the output port of the bead storage bucket, and the top of the bead storage bucket is inclined from high to low toward the transmission tube. The rotating member is installed on the bead storage bucket and is located above the output of the transmission tube. A turntable is installed on the rotating end of the rotating member. A plurality of storage tubes are arranged on the turntable, and the plurality of storage tubes are arranged equidistantly around the central axis of the turntable. The telescopic tube is installed on the transmission channel and is located downstream of the rotating member. The telescopic driver is installed on the transmission channel, and the output end of the telescopic driver is connected to the telescopic tube. One end of the storage tube below the turntable is connected to the transmission tube, and the shaft placing and bead loading machine is provided with a first blocking block at the other end of the storage tube. One end of the storage tube above the turntable is connected to the telescopic tube, and the shaft placing and bead loading machine is provided with a second blocking block at the other end of the storage tube. The storage tube is provided with a plurality of oil filling ports, the side wall of the bead storage barrel is installed with an oil filling barrel, the oil filling barrel is installed with oil outlet pipes corresponding to the positions of the plurality of oil filling ports, and the pipe mouth of the oil outlet pipe is installed with a pneumatic oil outlet head connected to the oil filling port.
2. The method for processing a vertical spherical bearing according to claim 1, characterized in that: The vertical transmission track in step A is provided with a holding frame and a clamping frame, the clamping frame is installed on the holding frame, the clamping frame includes two fixed rods and two clamping rods, the two fixed rods are fixedly installed on the holding frame, the two clamping rods are swingably installed on the holding frame, and a driving rod for driving the clamping rod to swing is installed on the holding frame, and a limit slot for supporting the two fixed rods is provided in the vertical transmission track.
3. The method for processing a vertical spherical bearing according to claim 1, characterized in that: The working conveyor platform in step A comprises a conveyor frame, a support plate and two synchronous conveyor belts, the two synchronous conveyor belts are symmetrically mounted on both sides of the conveyor frame, a rotating shaft for driving the two synchronous conveyor belts is rotatably mounted inside the conveyor frame, a driving motor for driving the rotating shaft to rotate is mounted outside the conveyor frame, and the support plate is mounted on the conveyor frame and is located between the two synchronous conveyor belts; Lifting cylinders are installed equidistantly between the two synchronous transmission belts along their lengths, a transition groove for the lifting cylinders to pass through is opened on the support plate, a rotator is installed at the output end of the lifting cylinder, a supporting cross bar is installed at the rotating end of the rotator, both ends of the supporting cross bar are respectively placed on the two synchronous transmission belts, and limiting columns are respectively installed at both ends of the supporting cross bar.
4. The method for processing a vertical spherical bearing according to claim 1, characterized in that: The holding frame installation machine in step C includes a horizontal moving frame, an upper and lower driving cylinder, an oiling head, an adsorption vibrator, two holding storage frames and a plurality of oiling pipes, the two holding storage frames are symmetrically located on both sides of the working conveying platform, the holding storage frames are installed with a screw lifter for lifting the holding frame, the horizontal moving frame is installed above the two holding storage frames, the upper and lower driving cylinders are installed on the moving output end of the horizontal moving frame, the oiling head is installed on the output end of the upper and lower driving cylinders, and a mounting frame is also installed on the moving output end of the horizontal moving frame, the mounting frame has two lubricating oil barrels connected to the oiling head, a plurality of oiling pipes are equidistantly installed on the oiling head around the lifting shafts of the upper and lower driving cylinders, and are connected to the oiling head, the oiling head is located between the plurality of oiling pipes and is installed with a downward pressure cylinder, and the adsorption vibrator is installed on the output end of the downward pressure cylinder; The adsorption vibrator comprises a plurality of support rods, wherein the support rods are located between adjacent oil injection pipes, vacuum adsorption heads are installed at the ends of the support rods, and vibration generators are installed above the vacuum adsorption heads.
5. The method for processing a vertical spherical bearing according to claim 1, characterized in that: The sealing installation machine in step C includes a lifting and pressing platform, a transmission platform and a calibration ring. The lifting and pressing platform and the transmission platform are both located below the working conveying platform. The transmission platform is located on one side of the lifting and pressing platform. The calibration ring is installed at the output of the transmission platform and is located directly above the lifting and pressing platform. An ultrasonic vibrator is installed below the calibration ring, and limit plates are installed on both symmetrical sides of the transmission platform.
6. The method for processing a vertical spherical bearing according to claim 5, characterized in that: The lifting and pressing platform includes a lifting cylinder and an annular pressure rod, the annular pressure rod is installed on the output end of the lifting cylinder, the calibration ring includes an inner platform and an outer ring, the ultrasonic vibrator is installed under the inner platform, and a limiting groove for accommodating a sealing ring is provided between the inner platform and the outer ring, and the annular pressure rod is matched with the limiting groove.