Underground mine mining point column boundary joint-cutting pipe interval charging presplitting blasting method
By adopting an uncoupled charging structure with slotted tube intervals in underground mining, the cracking problem at the connection between the pre-split hole and the buffer hole is solved, the smoothness and semi-porosity of the tunnel after blasting are improved, and the impact on the rock mass is reduced. damage and costs.
Patent Information
- Application Number
- CN202411032134.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-10-01
AI Technical Summary
The existing point-pillar boundary pre-split blasting technology for underground mining has the following problems: the connection between the pre-split hole of the previous shot and the pre-split hole of the next shot is prone to cracking, the drilling angle does not meet the design requirements, and the bottom of the pre-split hole and buffer hole is insufficiently charged. Excessive hole spacing leads to problems such as over-under-excavation and unevenness, and a reduction in half-hole ratio after blasting.
Adopting a slotted tube interval uncoupled charging structure, by strictly controlling the distance between the pre-split hole and the buffer hole, filling the emulsion explosive and installing a detonator in the pre-split hole, using the slotted tube to charge the pre-split hole with air intervals to form an arc Structure to reduce blasting disturbance and ensure the continuity and smoothness of pre-cracks.
It effectively avoids the problems of uneven rock walls and excessive over-excavation, reduces blasting damage to surrounding rock masses, improves the smoothness and semi-porosity of the tunnel profile after blasting, and reduces blasting material and labor costs.
Smart Images

Figure CN118729893A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method for pre-splitting blasting of a point column boundary slotted pipe with interval charging in underground mining, belonging to the technical field of pre-splitting blasting in underground mining. Background Art
[0002] At present, when underground mining reaches the final stage, the blasting work involves the problem of protecting the stability of the surrounding pillars. Pre-splitting blasting is to drill a row of parallel holes with small hole spacing along the designed excavation contour to reduce the amount of charge. It uses an uncoupled charge structure and is detonated before the main blasting hole in the excavation area. A flat pre-crack is formed in the direction of the line between the row of pre-crack holes. After the pre-crack is formed, the main blasting hole and buffer hole are detonated.
[0003] However, the current blasting method has the following problems: 1. The connection between the previous pre-crack hole and the next pre-crack hole is prone to cracking, resulting in uneven rock wall; 2. The drillers have different proficiency and technical levels, resulting in the drilling angle not meeting the design requirements, and some blast holes are tilted forward after blasting; 3. The bottom of the pre-crack hole and the buffer hole is insufficiently reinforced with explosives, which is prone to foundation; 4. The hole spacing is too large, resulting in over-excavation and under-excavation, and the unevenness exceeds 20cm; 5. The width of the blasting area is insufficient, resulting in the inability to arrange the main blast hole and buffer hole in some areas, and only the pre-crack hole is arranged. After blasting, the rate of large blocks increases; 6. When the rock mass is relatively broken, the half-hole rate decreases after blasting. Summary of the invention
[0004] In view of the serious over-excavation and under-excavation in the existing pre-splitting blasting of underground mining point pillar boundaries, and the serious damage to the surrounding retained rock mass, the present invention proposes a method for pre-splitting blasting of underground mining point pillar boundaries with slotted pipe interval charging. The present invention adopts a slotted pipe interval uncoupled charging structure, which greatly reduces the blasting material and labor costs and achieves the expected blasting effect.
[0005] A method for pre-splitting blasting of a slotted pipe with interval charge at the boundary of a point column in underground mining, the specific steps are as follows:
[0006] (1) The pre-blasting section of the underground mining point column is provided with pre-splitting holes, buffer holes and main blasting holes, and the main blasting holes include auxiliary holes, inner main blasting holes and roof holes; the pre-splitting holes are longitudinally equidistantly arranged on the outer edge of the pre-blasting section of the underground mining point column; the buffer holes are longitudinally equidistantly arranged on the outside of the pre-blasting section of the underground mining point column, and the distance between each buffer hole and the outer edge of the pre-blasting section of the underground mining point column is equal; the inner main blasting holes are equidistantly arranged on the pre-blasting section of the underground mining point column along the edge of the access section, and the distance between each inner main blasting hole and the edge of the access section is equal; the roof holes are equidistantly arranged on the top edge of the pre-blasting section of the underground mining point column; the auxiliary holes on the left and right blasting surfaces of the access section are equidistantly arranged between the buffer holes and the inner main blasting holes, and the auxiliary holes on the upper blasting surface of the access section are equidistantly arranged between the buffer holes and the roof holes;
[0007] (2) Use the interval uncoupled charging method to fill the roof hole with emulsion explosives, and use the continuous uncoupled charging method to fill the buffer hole, auxiliary hole, and inner main blast hole with emulsion explosives without filling with taphole mud;
[0008] (3) The pre-splitting hole is filled with emulsion explosives by using an interval uncoupled charging method, and a detonator and a reinforced emulsion explosive are installed at the bottom of the pre-splitting hole. The emulsion explosives are inserted into the slotted tube at intervals, and then the middle part of the pre-splitting hole is charged with air intervals through the slotted tube, and the hole mouth is filled with taphole mud;
[0009] (4) The pre-crack hole, the inner main blast hole, the auxiliary hole, the buffer hole and the top plate hole are detonated in sequence at the bottom of the hole, wherein the pre-crack hole, the inner main blast hole, the auxiliary hole, the buffer hole and the top plate hole are detonated simultaneously.
[0010] In the step (1), the spacing between adjacent pre-splitting holes is 0.4-0.5m, the spacing between adjacent buffer holes is 0.8-1.1m, the spacing between adjacent auxiliary holes is 0.8-1.2m, the spacing between adjacent inner main blast holes is 0.8-1.1m, and the spacing between adjacent top plate holes is 0.6-0.8m.
[0011] Preferably, the distance between the buffer hole and the outer edge of the pre-blasting section of the underground mining point column is 0.4-0.5m, the distance between the auxiliary hole and the outer edge of the pre-blasting section of the underground mining point column is 1.1-1.3m, the distance from the auxiliary hole to the inner main blasting hole connecting line is 0.7-1.0m, and the distance from the inner main blasting hole to the edge of the approach section is 0.8-1.0m; by strictly controlling the hole spacing of the pre-splitting holes on both sides and the spacing between the buffer hole and the pre-splitting hole, it is effectively avoided that the connection between the pre-splitting hole of the previous shot and the pre-splitting hole of the next shot is prone to cracking, thereby avoiding the problem of uneven rock wall or even excessive over-excavation.
[0012] Preferably, the diameter of the pre-splitting hole is 42-43 mm, and the depth is 3.0-3.2 m; the diameter of the buffer hole is 42-43 mm, and the depth is 3.0-3.2 m; the diameter of the auxiliary hole is 42-43 mm, and the depth is 3.0-3.2 m; the diameter of the inner main blast hole is 42-43 mm, and the depth is 3.0-3.2 m; the diameter of the top plate hole is 42-43 mm, and the depth is 3.0-3.2 m.
[0013] In the step (2), the charge amount of the buffer hole per hole is 2.0-2.1 kg, and the uncoupling coefficient is 1.31-1.34; the charge amount of the auxiliary hole per hole is 2.4-2.5 kg, and the uncoupling coefficient is 1.31-1.34; the charge amount of the inner main blast hole per hole is 2.4-2.5 kg, and the uncoupling coefficient is 1.31-1.34; the charge amount of the top plate hole per hole is 0.9-1.0 kg, and the uncoupling coefficient is 1.31-1.34.
[0014] The charge amount of the pre-splitting hole in step (3) is 1.4-1.5 kg, the uncoupling coefficient is 1.2-1.25, the reinforced emulsion explosive at the bottom of the pre-splitting hole accounts for 50-60% of the total charge amount, the linear charge density of the emulsion explosive in the middle of the pre-splitting hole is 300-400 g / m, and the air spacing height between adjacent emulsion explosives in the pre-splitting hole is 300-500 mm.
[0015] In the step (4), the interval time for sequentially detonating the bottom of the pre-splitting hole, the inner main blast hole, the auxiliary hole, the buffer hole and the top plate hole is 250-300 ms.
[0016] The slitting tube is an arc-shaped structure, the arc of the slitting tube is 245° to 246°, the inner diameter of the slitting tube is 31 to 32 mm, and the outer diameter is 34 to 35 mm; the material of the slitting tube is preferably PVC tube.
[0017] The principle of pre-splitting blasting by cutting seams at the boundary of underground mining points and columns according to the present invention:
[0018] 1. Rock crushing mechanism
[0019] (1) Destruction theory based on the expansion pressure of explosive gas:
[0020] Foreign scholars believe that the high-temperature and high-pressure gas generated after the explosion of explosives will directly act on the rock mass, causing the compressive stress to increase sharply and forming a stress field, thereby producing a "gas wedge effect". On the rock wall around the charge column in the hole, the gas expansion generates thrust, causing the rock mass to have a tendency to move radially. In the movement of particles inside the rock, due to the different particle stresses caused by the different distances of the explosive packages from the free surface, the movement speed of the particles inside the rock is also different. If the shear stress generated is greater than the ultimate shear strength of the rock, the rock mass will be destroyed. If the charge is too large and the degree of expansion of the explosive gas is too large, it may cause the rock mass on the hole wall to bulge or radially throw. Although the energy of the explosive gas is very large, it is actually only about 10% of the work done by the explosive, and its action time is much longer than the time of rock destruction.
[0021] (2) Explosion stress wave reverse stretching theory:
[0022] This theory, based on the perspective of detonation dynamics, proposes that the stress wave on the free surface forms a tensile wave due to reflection, which is the main factor causing rock damage. If this reverse stress wave is greater than the ultimate tensile strength of the rock, it will cause the rock mass to fail.
[0023] (3) Theory of the interaction between explosion gas and stress wave:
[0024] The combined action theory holds that the destruction of rock is the result of the combined action of the above two rock breaking theories. Experiments have shown that this theory is more practical and has been recognized by more experts. Its basic content is: the tensile stress and shear stress generated by the explosion of explosives cause cracks in the rock mass. When the explosive gas enters the cracks, it further expands the cracks. When the expansion pressure of the explosive gas reaches a certain limit, the rock is thrown out of the blast hole.
[0025] 2. Pre-splitting blasting mechanism
[0026] Pre-splitting blasting technology has been used in engineering projects as early as the 1950s. Due to its unique blasting effect, many experts and scholars have conducted in-depth research on this technology.
[0027] Weakening the blasting disturbance of the main blasthole and the buffer blasthole to form a complete and coherent pre-crack is the criterion for judging the success of pre-splitting blasting. The pre-splitting blasthole is detonated before the main blasthole, and no free surface is formed at this time. Therefore, in engineering practice, it is necessary to reasonably design the parameters of the pre-splitting blasting hole network to ensure the cracking effect of pre-splitting blasting. When pre-splitting blasting is carried out in softer rocks, the explosion stress is difficult to develop toward the connection line of the two holes, the cracking effect is not ideal, and it also has a great damage to the stability of the slope.
[0028] (1) Research on rock fracture mechanism:
[0029] Due to its heterogeneity, rock cannot be perfectly controlled in actual engineering blasting. There are many different opinions on the mechanism of pre-splitting blasting, which can be summarized as follows.
[0030] ① Stress wave superposition:
[0031] WIDuvall, RSPaine and others proposed the theory that stress waves from two adjacent blast holes are superimposed to form cracks during explosion. After the explosive charge is detonated, it propagates inside the rock in the form of a cylindrical wave. The stress waves meet at the midpoint of the line connecting the two holes. At this time, the combined force of the stress waves is perpendicular to the line, and the rock is displaced under the combined force. When the combined force of the superimposed stress waves is greater than the ultimate tensile strength of the rock, cracks are generated and continue to expand into pre-cracks and finally form a cross-section.
[0032] The key to pre-splitting blasting is to detonate two holes simultaneously, but this is an ideal state. In actual engineering, it is difficult to achieve simultaneous detonation between holes due to the time error between detonating cord and electric detonator. Generally speaking, the detonation speed of detonating cord is 5000-6000m / s, and the transmission speed of stress wave is also 4000m / s. The propagation duration of stress wave in rock is extremely short, and the time difference of detonation is larger than that in actual production.
[0033] ② Theory of the effect of explosion gas expansion pressure:
[0034] Umetaro Yamaguchi et al. proposed a theory on the effect of explosive gas expansion on the formation of pre-cracks, which mainly explained that the formation of rock cracks is mainly the result of the action of explosive gas, and the role of stress waves can be ignored.
[0035] The explosion gas expansion theory mainly focuses on the impact of air between the explosive bag and the hole wall on the rock during uncoupled charge blasting. This impact changes with the change of the uncoupled coefficient. When the uncoupled coefficient increases, the pressure on the hole wall will also decay. When the uncoupled coefficient decreases, the stress concentration becomes more obvious. The rock wall with the most concentrated stress will first produce tensile cracks. When the blasting hole network parameters are reasonable, the cracks will develop in the direction between the two holes until they penetrate each other, eventually forming a complete pre-crack surface.
[0036] After continuous exploration by blasting researchers, it was found that the stress value at the intersection of the line connecting the two blast holes and the hole wall in the tangent direction is the largest, and becomes more and more obvious as the distance between the blast holes decreases and the hole diameter increases. Therefore, scholars believe that the hole wall is the first place to break, and the hole distance plays a decisive role in the fracture and seam formation of the rock.
[0037] ③ Theory of the interaction between stress wave and explosion gas:
[0038] The combined action theory holds that rock fracture is the result of the synergistic effect of the above two theories.
[0039] In the initial stage, because the development of radial cracks requires the least energy, under the action of explosive gas, the cracks in the direction of the two blastholes are developed first. In the first stage, the stress wave generated by the explosives is concentrated on the hole wall, generating tangential tensile stress. When the tensile stress is greater than the ultimate tensile strength of the rock, cracks are generated in the rock. In the second stage, the explosive gas acts directly on the hole wall. Since the action time of the explosive gas is longer than that of the stress wave, the explosive gas directly enters the crack and expands the crack continuously, which is also called gas shearing action. The two actions work together to eventually form a pre-crack of a certain width.
[0040] The beneficial effects of the present invention are:
[0041] (1) The present invention adopts a slit tube interval uncoupled charge structure, and by strictly controlling the hole spacing of the pre-splitting holes on both sides and the spacing between the buffer hole and the pre-splitting hole, it is effectively avoided that the connection between the pre-splitting hole of the previous shot and the pre-splitting hole of the next shot is prone to cracking, thereby avoiding the problem of uneven rock wall or even excessive over-excavation;
[0042] (2) The present invention adopts a slotted tube interval uncoupled charge structure, and forms a pre-crack in advance before detonation in the main blasting area by means of pre-splitting blasting, thereby reducing the damage caused by blasting to the surrounding retained rock mass;
[0043] (3) The present invention adopts a slotted pipe interval uncoupled charge structure and adopts a slotted pipe pre-splitting blasting method to make the tunnel profile surface smoother after blasting, thereby reducing the amount of over-excavation and under-excavation;
[0044] (4) The present invention adopts a slit tube interval uncoupled charge structure and uses a pre-splitting blasting technology to ensure that there are no obvious large pieces in the blast pile after blasting, and the shoveling requirements of the shovel loader can be met. BRIEF DESCRIPTION OF THE DRAWINGS
[0045] Figure 1 Layout diagram of pre-splitting holes, buffer holes and main blast holes for pre-blasting sections of underground mining point columns;
[0046] Figure 2 This is a diagram of the pre-splitting charge structure of Example 1;
[0047] Figure 3 It is the cross-section diagram of the slit pipe;
[0048] Figure 4 This is a diagram of the pre-splitting charge structure of Example 2;
[0049] In the figure, 1-pre-splitting hole, 2-inner main blasting hole, 3-auxiliary hole, 4-buffer hole, 5-top plate hole. DETAILED DESCRIPTION
[0050] The present invention is further described in detail below in conjunction with specific implementation modes, but the protection scope of the present invention is not limited to the described contents.
[0051] Summary of the Invention
[0052] A method for pre-splitting blasting of a slotted pipe with interval charge at the boundary of a point column in underground mining (see Figures 1 to 3 ), the specific steps are as follows:
[0053] (1) The pre-blasting section of the underground mining point column is provided with pre-splitting holes, buffer holes and main blasting holes. The main blasting holes include auxiliary holes, inner main blasting holes and roof holes. The pre-splitting holes are longitudinally equidistantly arranged on the outer edge of the pre-blasting section of the underground mining point column. The buffer holes are longitudinally equidistantly arranged on the outside of the pre-blasting section of the underground mining point column. The distance between each buffer hole and the outer edge of the pre-blasting section of the underground mining point column is equal. The inner main blasting holes are longitudinally equidistantly arranged on the pre-blasting section of the underground mining point column along the edge of the approach section. Each buffer hole is longitudinally equidistantly arranged on the outer edge of the pre-blasting section of the underground mining point column. The distance between the inner main blasting hole and the edge of the access section is equal; the roof holes are equidistantly arranged at the top edge of the pre-blasting section of the underground mining point column; the auxiliary holes of the left and right blasting surfaces of the access section are equidistantly arranged between the buffer hole and the inner main blasting hole, and the auxiliary holes of the upper blasting surface of the access section are equidistantly arranged between the buffer hole and the roof holes; the slit pipe is an arc structure, the arc of the slit pipe is 245°~246°, the inner diameter of the slit pipe is 31~32mm, and the outer diameter is 34~35mm; the slit pipe material can be selected from PVC pipe;
[0054] The spacing between adjacent pre-splitting holes is 0.4-0.5m, the spacing between adjacent buffer holes is 0.8-1.1m, the spacing between adjacent auxiliary holes is 0.8-1.2m, the spacing between adjacent internal main blast holes is 0.8-1.1m, and the spacing between adjacent roof holes is 0.6-0.8m;
[0055] The distance between the buffer hole and the outer edge of the pre-blasting section of the underground mining point column is 0.4-0.5m, the distance between the auxiliary hole and the outer edge of the pre-blasting section of the underground mining point column is 1.1-1.3m, the distance between the auxiliary hole and the inner main blasting hole is 0.7-1.0m, and the distance between the inner main blasting hole and the edge of the access section is 0.8-1.0m; by strictly controlling the hole spacing of the pre-splitting holes on both sides and the spacing between the buffer hole and the pre-splitting hole, it is effectively avoided that the connection between the pre-splitting hole of the previous shot and the pre-splitting hole of the next shot is prone to cracking, thereby avoiding the problem of uneven rock wall or even excessive over-excavation;
[0056] The diameter of the pre-splitting hole is 42-43mm, and the depth is 3.0-3.2m; the diameter of the buffer hole is 42-43mm, and the depth is 3.0-3.2m; the diameter of the auxiliary hole is 42-43mm, and the depth is 3.0-3.2m; the diameter of the main blast hole is 42-43mm, and the depth is 3.0-3.2m; the diameter of the top plate hole is 42-43mm, and the depth is 3.0-3.2m;
[0057] (2) The emulsion explosives are filled in the roof holes by using the interval uncoupled charging method, and the emulsion explosives are filled in the buffer holes, auxiliary holes, and inner main blast holes by using the continuous uncoupled charging method without filling the gun mud; the charge of the buffer hole is 2.0-2.1 kg per hole, and the uncoupling coefficient is 1.31-1.34; the charge of the auxiliary hole is 2.4-2.5 kg per hole, and the uncoupling coefficient is 1.31-1.34; the charge of the inner main blast hole is 2.4-2.5 kg per hole, and the uncoupling coefficient is 1.31-1.34; the charge of the roof hole is 0.9-1.0 kg per hole, and the uncoupling coefficient is 1.31-1.34;
[0058] (3) The pre-splitting hole is filled with emulsion explosives by using an interval uncoupled charging method, and a detonator and a reinforced emulsion explosive are loaded at the bottom of the pre-splitting hole, and the emulsion explosives are inserted into the slit tube at intervals, and then the middle part of the pre-splitting hole is charged with air intervals through the slit tube, and the hole mouth is filled with taphole mud; the single hole charge of the pre-splitting hole is 1.4-1.5 kg, the uncoupled coefficient is 1.2-1.25, the reinforced emulsion explosive at the bottom of the pre-splitting hole accounts for 50-60% of the total charge, the linear charge density of the emulsion explosive in the middle of the pre-splitting hole is 300-400 g / m, and the air interval height between adjacent emulsion explosives in the pre-splitting hole is 300-500 mm;
[0059] (4) The pre-splitting hole, the inner main blasting hole, the auxiliary hole, the buffer hole and the top plate hole are detonated at the bottom of the hole in sequence, wherein the pre-splitting hole, the inner main blasting hole, the auxiliary hole, the buffer hole and the top plate hole are detonated simultaneously; the interval time for detonating the pre-splitting hole, the inner main blasting hole, the auxiliary hole, the buffer hole and the top plate hole in sequence is 250-300ms;
[0060] Principle of pre-splitting blasting with interval charge in the cut-slit pipe at the boundary of underground mining point column:
[0061] 1. Rock crushing mechanism
[0062] (1) Destruction theory based on the expansion pressure of explosive gas:
[0063] Foreign scholars believe that the high-temperature and high-pressure gas generated after the explosion of explosives will directly act on the rock mass, causing the compressive stress to increase sharply and forming a stress field, thereby producing a "gas wedge effect". On the rock wall around the charge column in the hole, the gas expansion generates thrust, causing the rock mass to have a tendency to move radially. In the movement of particles inside the rock, due to the different particle stresses caused by the different distances of the explosive packages from the free surface, the movement speed of the particles inside the rock is also different. If the shear stress generated is greater than the ultimate shear strength of the rock, the rock mass will be destroyed. If the charge is too large and the degree of expansion of the explosive gas is too large, it may cause the rock mass on the hole wall to bulge or radially throw. Although the energy of the explosive gas is very large, it is actually only about 10% of the work done by the explosive, and its action time is much longer than the time of rock destruction.
[0064] (2) Explosion stress wave reverse stretching theory:
[0065] This theory, based on the perspective of detonation dynamics, proposes that the stress wave on the free surface forms a tensile wave due to reflection, which is the main factor causing rock damage. If this reverse stress wave is greater than the ultimate tensile strength of the rock, it will cause the rock mass to fail.
[0066] (3) Theory of the interaction between explosion gas and stress wave:
[0067] The combined action theory holds that the destruction of rock is the result of the combined action of the above two rock breaking theories. Experiments have shown that this theory is more practical and has been recognized by more experts. Its basic content is: the tensile stress and shear stress generated by the explosion of explosives cause cracks in the rock mass. When the explosive gas enters the cracks, it further expands the cracks. When the expansion pressure of the explosive gas reaches a certain limit, the rock is thrown out of the blast hole.
[0068] 2. Pre-splitting blasting mechanism
[0069] Pre-splitting blasting technology has been used in engineering projects as early as the 1950s. Due to its unique blasting effect, many experts and scholars have conducted in-depth research on this technology.
[0070] Weakening the blasting disturbance of the main blasthole and the buffer blasthole to form a complete and coherent pre-crack is the criterion for judging the success of pre-splitting blasting. The pre-splitting blasthole is detonated before the main blasthole, and no free surface is formed at this time. Therefore, in engineering practice, it is necessary to reasonably design the parameters of the pre-splitting blasting hole network to ensure the cracking effect of pre-splitting blasting. When pre-splitting blasting is carried out in softer rocks, the explosion stress is difficult to develop toward the connection line of the two holes, the cracking effect is not ideal, and it also has a great damage to the stability of the slope.
[0071] (1) Research on rock fracture mechanism:
[0072] Due to its heterogeneity, rock cannot be perfectly controlled in actual engineering blasting. There are many different opinions on the mechanism of pre-splitting blasting, which can be summarized as follows.
[0073] ① Stress wave superposition:
[0074] WIDuvall, RSPaine and others proposed the theory that stress waves from two adjacent blast holes are superimposed to form cracks during explosion. After the explosive charge is detonated, it propagates inside the rock in the form of a cylindrical wave. The stress waves meet at the midpoint of the line connecting the two holes. At this time, the combined force of the stress waves is perpendicular to the line, and the rock is displaced under the combined force. When the combined force of the superimposed stress waves is greater than the ultimate tensile strength of the rock, cracks are generated and continue to expand into pre-cracks and finally form a cross-section.
[0075] The key to pre-splitting blasting is to detonate two holes simultaneously, but this is an ideal state. In actual engineering, it is difficult to achieve simultaneous detonation between holes due to the time error between detonating cord and electric detonator. Generally speaking, the detonation speed of detonating cord is 5000-6000m / s, and the transmission speed of stress wave is also 4000m / s. The propagation duration of stress wave in rock is extremely short, and the time difference of detonation is larger than that in actual production.
[0076] ② Theory of the effect of explosion gas expansion pressure:
[0077] Umetaro Yamaguchi et al. proposed a theory on the effect of explosive gas expansion on the formation of pre-cracks, which mainly explained that the formation of rock cracks is mainly the result of the action of explosive gas, and the role of stress waves can be ignored.
[0078] The explosion gas expansion theory mainly focuses on the impact of air between the explosive bag and the hole wall on the rock during uncoupled charge blasting. This impact changes with the change of the uncoupled coefficient. When the uncoupled coefficient increases, the pressure on the hole wall will also decay. When the uncoupled coefficient decreases, the stress concentration becomes more obvious. The rock wall with the most concentrated stress will first produce tensile cracks. When the blasting hole network parameters are reasonable, the cracks will develop in the direction between the two holes until they penetrate each other, eventually forming a complete pre-crack surface.
[0079] After continuous exploration by blasting researchers, it was found that the stress value at the intersection of the line connecting the two blast holes and the hole wall in the tangent direction is the largest, and becomes more and more obvious as the distance between the blast holes decreases and the hole diameter increases. Therefore, scholars believe that the hole wall is the first place to break, and the hole distance plays a decisive role in the fracture and seam formation of the rock.
[0080] ③ Theory of the interaction between stress wave and explosion gas:
[0081] The combined action theory holds that rock fracture is the result of the synergistic effect of the above two theories.
[0082] In the initial stage, because the energy required for the development of radial cracks is the smallest, under the action of the explosive gas, the cracks in the direction of the line connecting the two blastholes develop first. In the first stage, the stress wave generated by the explosives is concentrated on the hole wall, generating tangential tensile stress. When the tensile stress is greater than the ultimate tensile strength of the rock, cracks appear in the rock. In the second stage, the explosive gas acts directly on the hole wall. Because the action time of the explosive gas is longer than that of the stress wave, the explosive gas directly enters the crack and causes the crack to continue to expand, which is also called gas shearing effect. The two effects work synergistically to eventually form a pre-crack of a certain width;
[0083] The uncoupled charging structure with slotted tube intervals is adopted. By strictly controlling the hole spacing of the pre-splitting holes on both sides and the spacing between the buffer hole and the pre-splitting hole, it is effectively avoided that the connection between the pre-splitting hole of the previous shot and the pre-splitting hole of the next shot is prone to cracking, thereby avoiding the problem of uneven rock wall or even excessive over-excavation.
[0084] Example 1: The point-pillar mining method adopted by a mine is carried out in two steps. The small-section approach is excavated by driving and blasting. The tunnel bottom width is 4m, the top height is 3.6m, the cross-section perimeter is 30.52m, and the cross-section area is 28.03m 2 After the approach section is formed, it is expanded to the boundary of the point column. The pre-blasting section of the underground mining point column has a bottom width of 10m, a top height of 6m, a section circumference of 44.84m, and a section area of 61.66m 2 During the expansion and brushing construction, a total of 70 blastholes were set up, including 20 pre-crack holes, 8 buffer holes, 14 top plate holes, 14 auxiliary holes, 8 inner circle holes, and 6 bottom plate holes;
[0085] A method for pre-splitting blasting of a slotted pipe with interval charge at the boundary of a point column in underground mining (see Figure 1 ), the specific steps are as follows:
[0086] (1) The pre-blasting section of the underground mining point column is provided with pre-splitting holes, buffer holes and main blasting holes, and the main blasting holes include auxiliary holes, inner main blasting holes and roof holes; the pre-splitting holes are longitudinally equidistantly arranged at the outer edge of the pre-blasting section of the underground mining point column, the buffer holes are longitudinally equidistantly arranged outside the pre-blasting section of the underground mining point column, and the distance between each buffer hole and the outer edge of the pre-blasting section of the underground mining point column is equal; the inner main blasting holes are longitudinally equidistantly arranged at the outer edge of the pre-blasting section of the underground mining point column along the edge of the approach section. On the broken section, the distance between each inner main blast hole and the edge of the access section is equal; the roof holes are equidistantly arranged at the top edge of the pre-blasting section of the underground mining point column; the auxiliary holes of the left and right blasting surfaces of the access section are equidistantly arranged between the buffer hole and the inner main blast hole, and the auxiliary holes of the upper blasting surface of the access section are equidistantly arranged between the buffer hole and the roof hole; the slit pipe is an arc structure, the arc of the slit pipe is 246°, the inner diameter of the slit pipe is 32mm, and the outer diameter is 35mm; the slit pipe is made of PVC pipe;
[0087] The spacing between adjacent pre-splitting holes is 0.4m, the spacing between adjacent buffer holes is 1.0m, the spacing between adjacent auxiliary holes is 1.2m, the spacing between adjacent internal main blasting holes is 1.1m, and the spacing between adjacent top plate holes is 0.7m;
[0088] The distance between the buffer hole and the outer edge of the pre-blasting section of the underground mining point column is 0.5m, the distance between the auxiliary hole and the outer edge of the pre-blasting section of the underground mining point column is 1.3m, the distance between the auxiliary hole and the inner main blasting hole is 0.8m, and the distance between the inner main blasting hole and the edge of the access section is 0.9m; by strictly controlling the hole spacing of the pre-splitting holes on both sides and the spacing between the buffer hole and the pre-splitting hole, it is effectively avoided that the connection between the pre-splitting hole of the previous shot and the pre-splitting hole of the next shot is prone to cracking, thereby avoiding the problem of uneven rock wall or even excessive over-excavation;
[0089] The diameter of the pre-splitting hole is 42mm and the depth is 3.2m; the diameter of the buffer hole is 42mm and the depth is 3.2m; the diameter of the auxiliary hole is 42mm and the depth is 3.2m; the diameter of the inner main blast hole is 42mm and the depth is 3.2m; the diameter of the top plate hole is 42mm and the depth is 3.2m;
[0090] (2) The emulsion explosives are filled in the roof hole by using the interval uncoupled charging method, and the emulsion explosives are filled in the buffer hole, auxiliary hole, and inner main blast hole by using the continuous uncoupled charging method without filling the gun mud; the charge of the buffer hole is 2.1kg per hole, and the uncoupling coefficient is 1.31; the charge of the auxiliary hole is 2.4kg per hole, and the uncoupling coefficient is 1.31; the charge of the inner main blast hole is 2.4kg per hole, and the uncoupling coefficient is 1.31; the charge of the roof hole is 0.9kg per hole, and the uncoupling coefficient is 1.31;
[0091] (3) The pre-splitting hole is filled with emulsion explosives by using an interval uncoupled charging method, and a detonator and a reinforced emulsion explosive are loaded at the bottom of the pre-splitting hole, and the emulsion explosives are inserted into the slit tube at intervals, and then the middle part of the pre-splitting hole is charged with air intervals through the slit tube, and the hole mouth is filled with gun mud; the single hole charge of the pre-splitting hole is 1.5 kg, the uncoupled coefficient is 1.2, the reinforced emulsion explosive at the bottom of the pre-splitting hole accounts for 60% of the total charge, the linear charge density of the emulsion explosive in the middle of the pre-splitting hole is 300 g / m, the air interval height between the bottom of the pre-splitting hole and the middle emulsion explosive is 400 mm, and the interval height between the middle and the hole mouth emulsion explosive is 500 mm;
[0092] (4) The pre-splitting hole, the inner main blasting hole, the auxiliary hole, the buffer hole and the top plate hole are detonated at the bottom of the hole in sequence, wherein the pre-splitting hole, the inner main blasting hole, the auxiliary hole, the buffer hole and the top plate hole are detonated simultaneously; the interval time for the pre-splitting hole, the inner main blasting hole, the auxiliary hole, the buffer hole and the top plate hole to be detonated at the bottom of the hole in sequence is 250ms;
[0093] From the half-hole marks remaining on the left and right sides of the scene in this embodiment, it can be seen that the use of pre-splitting blasting technology can make the wall of the pillar smooth, the average over-excavation and under-excavation is less than 10 cm, the half-hole marks are kept intact, and the contour is smoother and straighter, and there are no obvious large pieces in the blast pile, meeting the loading requirements of the shovel loader.
[0094] Example 2: The point-pillar mining method adopted by a mine is carried out in two steps. The small-section approach is excavated by driving and blasting. The tunnel bottom width is 4m, the top height is 3.6m, the cross-section perimeter is 30.52m, and the cross-section area is 28.03m. 2 After the approach section is formed, it is expanded to the boundary of the point column. The pre-blasting section of the underground mining point column has a bottom width of 10m, a top height of 6m, a section circumference of 44.84m, and a section area of 61.66m 2 ;During the expansion and brushing construction, a total of 68 blastholes were set up, including 18 pre-splitting holes, 8 buffer holes, 14 top plate holes, 14 auxiliary holes, 8 inner circle holes, and 6 bottom plate holes;;
[0095] A method for pre-splitting blasting of a slotted pipe with interval charge at the boundary of a point column in underground mining (see Figures 1 to 3 ), the specific steps are as follows:
[0096] (1) The pre-blasting section of the underground mining point column is provided with pre-splitting holes, buffer holes and main blasting holes, and the main blasting holes include auxiliary holes, inner main blasting holes and roof holes; the pre-splitting holes are longitudinally equidistantly arranged at the outer edge of the pre-blasting section of the underground mining point column, the buffer holes are longitudinally equidistantly arranged outside the pre-blasting section of the underground mining point column, and the distance between each buffer hole and the outer edge of the pre-blasting section of the underground mining point column is equal; the inner main blasting holes are longitudinally equidistantly arranged at the outer edge of the pre-blasting section of the underground mining point column along the edge of the approach section. On the broken section, the distance between each inner main blast hole and the edge of the access section is equal; the roof holes are equidistantly arranged at the top edge of the pre-blasting section of the underground mining point column; the auxiliary holes of the left and right blasting surfaces of the access section are equidistantly arranged between the buffer hole and the inner main blast hole, and the auxiliary holes of the upper blasting surface of the access section are equidistantly arranged between the buffer hole and the roof hole; the slit pipe is an arc structure, the arc of the slit pipe is 246°, the inner diameter of the slit pipe is 32mm, and the outer diameter is 35mm; the slit pipe is made of PVC pipe;
[0097] The spacing between adjacent pre-splitting holes is 0.45m, the spacing between adjacent buffer holes is 0.9m, the spacing between adjacent auxiliary holes is 1.0m, the spacing between adjacent internal main blasting holes is 1.0m, and the spacing between adjacent roof holes is 0.6m;
[0098] The distance between the buffer hole and the outer edge of the pre-blasting section of the underground mining point column is 0.48m, the distance between the auxiliary hole and the outer edge of the pre-blasting section of the underground mining point column is 1.2m, the distance from the auxiliary hole to the inner main blasting hole is 0.7m, and the distance from the inner main blasting hole to the edge of the access section is 0.8m; by strictly controlling the hole spacing of the pre-splitting holes on both sides and the spacing between the buffer hole and the pre-splitting hole, it is effectively avoided that the connection between the pre-splitting hole of the previous shot and the pre-splitting hole of the next shot is prone to cracking, thereby avoiding the problem of uneven rock wall or even excessive over-excavation;
[0099] The diameter of the pre-splitting hole is 42mm and the depth is 3.1m; the diameter of the buffer hole is 42mm and the depth is 3.1m; the diameter of the auxiliary hole is 42mm and the depth is 3.1m; the diameter of the inner main blast hole is 42mm and the depth is 3.1m; the diameter of the top plate hole is 42 and the depth is 3.1m;
[0100] (2) The emulsion explosives are filled in the roof hole by using the interval uncoupled charging method, and the emulsion explosives are filled in the buffer hole, auxiliary hole, and inner main blast hole by using the continuous uncoupled charging method without filling the gun mud; the charge of the buffer hole is 2.0 kg per hole, and the uncoupling coefficient is 1.32; the charge of the auxiliary hole is 2.45 kg per hole, and the uncoupling coefficient is 1.32; the charge of the inner main blast hole is 2.41 kg per hole, and the uncoupling coefficient is 1.32; the charge of the roof hole is 1.0 kg per hole, and the uncoupling coefficient is 1.32;
[0101] (3) The pre-splitting hole is filled with emulsion explosives by using an interval uncoupled charging method, and a detonator and a reinforced emulsion explosive are loaded at the bottom of the pre-splitting hole. The emulsion explosives are inserted into the slit tube at intervals, and then the middle part of the pre-splitting hole is charged with air intervals through the slit tube, and the hole mouth is filled with gun mud; the single hole charge of the pre-splitting hole is 1.45 kg, the uncoupled coefficient is 1.22, the reinforced emulsion explosive at the bottom of the pre-splitting hole accounts for 50% of the total charge, the linear charge density of the emulsion explosive in the middle part of the pre-splitting hole is 400 g / m, and the air interval heights between the emulsion explosives in the pre-splitting hole are 300 mm, 400 mm, and 500 mm, respectively. Figure 4 ;
[0102] (4) The pre-splitting hole, the inner main blasting hole, the auxiliary hole, the buffer hole and the top plate hole are detonated at the bottom of the hole in sequence, wherein the pre-splitting hole, the inner main blasting hole, the auxiliary hole, the buffer hole and the top plate hole are detonated simultaneously; the interval time for the pre-splitting hole, the inner main blasting hole, the auxiliary hole, the buffer hole and the top plate hole to be detonated at the bottom of the hole in sequence is 300ms;
[0103] This embodiment adopts the slit tube interval charging pre-splitting blasting technology. From the half-hole marks remaining on the left and right sides of the scene, it can be seen that the half-hole rate after the blasting is increased, the excavation contour surface is relatively flat and neat, the over-excavation and under-excavation are small, and there are no obvious large blocks in the blasting pile, which meets the shoveling requirements of the forklift and reduces the damage to the retained rock mass.
[0104] Example 3: The point-pillar mining method adopted by a certain mine is carried out in two steps. The small-section approach is excavated by driving and blasting. The tunnel bottom width is 4m, the top height is 3.6m, the cross-section perimeter is 30.52m, and the cross-section area is 28.03m 2 After the approach section is formed, it is expanded to the boundary of the point column. The pre-blasting section of the underground mining point column has a bottom width of 10m, a top height of 6m, a section circumference of 44.84m, and a section area of 61.66m 2 ;During the expansion and brushing construction, a total of 66 blast holes were set up, including 16 pre-splitting holes, 8 buffer holes, 14 top plate holes, 14 auxiliary holes, 8 inner circle holes, and 6 bottom plate holes;;
[0105] A method for pre-splitting blasting of a slotted pipe with interval charge at the boundary of a point column in underground mining (see Figures 1 to 3 ), the specific steps are as follows:
[0106] (1) The pre-blasting section of the underground mining point column is provided with pre-splitting holes, buffer holes and main blasting holes, and the main blasting holes include auxiliary holes, inner main blasting holes and roof holes; the pre-splitting holes are longitudinally equidistantly arranged at the outer edge of the pre-blasting section of the underground mining point column, the buffer holes are longitudinally equidistantly arranged outside the pre-blasting section of the underground mining point column, and the distance between each buffer hole and the outer edge of the pre-blasting section of the underground mining point column is equal; the inner main blasting holes are longitudinally equidistantly arranged at the outer edge of the pre-blasting section of the underground mining point column along the edge of the approach section. On the broken section, the distance between each inner main blast hole and the edge of the access section is equal; the roof holes are equidistantly arranged at the top edge of the pre-blasting section of the underground mining point column; the auxiliary holes of the left and right blasting surfaces of the access section are equidistantly arranged between the buffer hole and the inner main blast hole, and the auxiliary holes of the upper blasting surface of the access section are equidistantly arranged between the buffer hole and the roof hole; the slit pipe is an arc structure, the arc of the slit pipe is 246°, the inner diameter of the slit pipe is 31mm, and the outer diameter is 34mm; the slit pipe is made of PVC pipe;
[0107] The spacing between adjacent pre-splitting holes is 0.5m, the spacing between adjacent buffer holes is 1.05m, the spacing between adjacent auxiliary holes is 0.9m, the spacing between adjacent internal main blasting holes is 0.9m, and the spacing between adjacent roof holes is 0.7m;
[0108] The distance between the buffer hole and the outer edge of the pre-blasting section of the underground mining point column is 0.45m, the distance between the auxiliary hole and the outer edge of the pre-blasting section of the underground mining point column is 1.25m, the distance from the auxiliary hole to the inner main blasting hole is 0.9m, and the distance from the inner main blasting hole to the edge of the access section is 0.95m; by strictly controlling the hole spacing of the pre-splitting holes on both sides and the spacing between the buffer hole and the pre-splitting hole, it is effectively avoided that the connection between the pre-splitting hole of the previous shot and the pre-splitting hole of the next shot is prone to cracking, thereby avoiding the problem of uneven rock wall or even excessive over-excavation;
[0109] The diameter of the pre-splitting hole is 42mm and the depth is 3.0m; the diameter of the buffer hole is 42mm and the depth is 3.0m; the diameter of the auxiliary hole is 42mm and the depth is 3.0m; the diameter of the inner main blast hole is 42mm and the depth is 3.0m; the diameter of the top plate hole is 42mm and the depth is 3.0m;
[0110] (2) The emulsion explosives are filled in the roof hole by using the interval uncoupled charging method, and the emulsion explosives are filled in the buffer hole, auxiliary hole, and inner main blast hole by using the continuous uncoupled charging method without filling the gun mud; the charge of the buffer hole is 2.05kg per hole, and the uncoupling coefficient is 1.34; the charge of the auxiliary hole is 2.42kg per hole, and the uncoupling coefficient is 1.34; the charge of the inner main blast hole is 2.45kg per hole, and the uncoupling coefficient is 1.34; the charge of the roof hole is 0.92kg per hole, and the uncoupling coefficient is 1.34;
[0111] (3) The pre-splitting hole is filled with emulsion explosives by using an interval uncoupled charging method, and a detonator and a reinforced emulsion explosive are loaded at the bottom of the pre-splitting hole, and the emulsion explosives are inserted into the slotted tube at intervals, and then the middle part of the pre-splitting hole is charged with air intervals through the slotted tube, and the hole mouth is filled with gun mud; the single hole charge of the pre-splitting hole is 1.4 kg, the uncoupled coefficient is 1.25, the reinforced emulsion explosive at the bottom of the pre-splitting hole accounts for 60% of the total charge, the linear charge density of the emulsion explosive in the middle of the pre-splitting hole is 400 g / m, the air interval height between the bottom of the pre-splitting hole and the middle emulsion explosive is 400 mm, and the air interval height between the middle and the hole mouth emulsion explosive is 500 mm;
[0112] (4) The pre-splitting hole, the inner main blasting hole, the auxiliary hole, the buffer hole and the top plate hole are detonated at the bottom of the hole in sequence, wherein the pre-splitting hole, the inner main blasting hole, the auxiliary hole, the buffer hole and the top plate hole are detonated simultaneously; the interval time for the pre-splitting hole, the inner main blasting hole, the auxiliary hole, the buffer hole and the top plate hole to be detonated at the bottom of the hole in sequence is 300ms;
[0113] After blasting in this embodiment, the hole wall is relatively flat, the half-hole marks are obvious, and there are no obvious large pieces of blast pile, which meets the requirements for shoveling by scraper, and the over-excavation and under-excavation of the surrounding retained rock mass is less than 10 cm.
[0114] The specific implementation modes of the present invention are described in detail above, but the present invention is not limited to the above implementation modes, and various changes can be made within the knowledge scope of ordinary technicians in this field without departing from the purpose of the present invention.
Claims
1. A method for pre-splitting blasting of a slit pipe with interval charge at the boundary of a point column in underground mining, It is characterized in that The specific steps are as follows: (1) The pre-blasting section of the underground mining point column is provided with pre-splitting holes, buffer holes and main blasting holes, and the main blasting holes include auxiliary holes, inner main blasting holes and roof holes; the pre-splitting holes are longitudinally equidistantly arranged on the outer edge of the pre-blasting section of the underground mining point column; the buffer holes are longitudinally equidistantly arranged on the outside of the pre-blasting section of the underground mining point column, and the distance between each buffer hole and the outer edge of the pre-blasting section of the underground mining point column is equal; the inner main blasting holes are equidistantly arranged on the pre-blasting section of the underground mining point column along the edge of the access section, and the distance between each inner main blasting hole and the edge of the access section is equal; the roof holes are equidistantly arranged on the top edge of the pre-blasting section of the underground mining point column; the auxiliary holes on the left and right blasting surfaces of the access section are equidistantly arranged between the buffer holes and the inner main blasting holes, and the auxiliary holes on the upper blasting surface of the access section are equidistantly arranged between the inner main blasting holes and the roof holes; (2) Use the interval uncoupled charging method to fill the roof hole with emulsion explosives, and use the continuous uncoupled charging method to fill the buffer hole, auxiliary hole, and inner main blast hole with emulsion explosives without filling with taphole mud; (3) The pre-splitting hole is filled with emulsion explosives by using an interval uncoupled charging method, and a detonator and a reinforced emulsion explosive are installed at the bottom of the pre-splitting hole. The emulsion explosives are inserted into the slotted tube at intervals, and then the middle part of the pre-splitting hole is charged with air intervals through the slotted tube, and the hole mouth is filled with taphole mud; (4) The pre-crack hole, the inner main blast hole, the auxiliary hole, the buffer hole and the top plate hole are detonated in sequence at the bottom of the hole, wherein the pre-crack hole, the inner main blast hole, the auxiliary hole, the buffer hole and the top plate hole are detonated simultaneously.
2. The method for pre-splitting blasting of the slit pipe with interval charge at the boundary of underground mining point column according to claim 1, Features: In step (1), the spacing between adjacent pre-splitting holes is 0.4-0.5 m, the spacing between adjacent buffer holes is 0.8-1.1 m, the spacing between adjacent auxiliary holes is 0.8-1.2 m, the spacing between adjacent inner main blast holes is 0.8-1.1 m, and the spacing between adjacent top plate holes is 0.6-0.8 m.
3. The method for pre-splitting blasting of the slit pipe with interval charge at the boundary of underground mining point column according to claim 2, Features: The distance between the buffer hole and the outer edge of the pre-blasting section of the underground mining point column is 0.4~0.5m, the distance between the auxiliary hole and the outer edge of the pre-blasting section of the underground mining point column is 1.1~1.3m, the distance from the auxiliary hole to the inner main blasting hole is 0.7~1.0m, and the distance from the inner main blasting hole to the edge of the access section is 0.8~1.0m.
4. The method for pre-splitting blasting of the slit pipe with interval charge at the boundary of underground mining point column according to claim 2, Features: The diameter of the pre-cracking hole is 42-43mm, and the depth is 3.0-3.2m; the diameter of the buffer hole is 42-43mm, and the depth is 3.0-3.2m; the diameter of the auxiliary hole is 42-43mm, and the depth is 3.0-3.2m; the diameter of the inner main blast hole is 42-43mm, and the depth is 3.0-3.2m; the diameter of the top plate hole is 42-43mm, and the depth is 3.0-3.2m.
5. The method for pre-splitting blasting of the slit pipe with interval charge at the boundary of underground mining point column according to claim 1, Features: In step (2), the charge amount of the buffer hole is 2.0-2.1 kg, and the uncoupling coefficient is 1.31-1.34; the charge amount of the auxiliary hole is 2.4-2.5 kg, and the uncoupling coefficient is 1.31-1.34; the charge amount of the inner main blast hole is 2.4-2.5 kg, and the uncoupling coefficient is 1.31-1.34; the charge amount of the top plate hole is 0.9-1.0 kg, and the uncoupling coefficient is 1.31-1.
34.
6. The method for pre-splitting blasting of the slit pipe with interval charge at the boundary of underground mining point column according to claim 1, Features: The charge amount of each pre-splitting hole in step (3) is 1.4-1.5 kg, the uncoupling coefficient is 1.2-1.25, the reinforced emulsion explosive at the bottom of the pre-splitting hole accounts for 50-60% of the total charge amount, the linear charge density of the emulsion explosive in the middle of the pre-splitting hole is 300-400 g / m, and the air spacing height between adjacent emulsion explosives in the pre-splitting hole is 300-500 mm.
7. The method for pre-splitting blasting of the slit pipe with interval charge at the boundary of underground mining point column according to claim 1, Features: In step (4), the interval time for detonating the pre-splitting hole, the inner main blast hole, the auxiliary hole, the buffer hole and the top plate hole in sequence at the bottom of the hole is 250 to 300 ms.