New energy project large-scale site earthwork optimization method based on least square method and proportional optimization method
By combining the least squares method and the proportional optimization method, the new energy project site is divided into multiple blocks and iteratively optimized, which solves the problem of low accuracy in the calculation of earthwork volume in the traditional earthwork calculation method, and realizes the calculation of the earthwork filling and excavation engineering volume. High-precision optimization reduces project costs and environmental impact.
Patent Information
- Application Number
- CN202410738896.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-07
- Publication Date
- 2024-10-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The traditional site earthwork calculation method in new energy projects results in excessive filling and excavation heights inside the site and on the slopes, and low earthwork volume calculation accuracy, which affects project quality, progress and cost control, and increases unnecessary engineering volume and investment. cost.
The project site is divided into multiple blocks by using a combination of the least squares method and the proportional optimization method. The least squares method is used to accurately calculate the amount of earthwork filling and excavation work in each block, and the proportional optimization method is used to determine the expected amount of earthwork excavation and filling work in each block. , iterative optimization until the optimization rate of earthwork filling and excavation in all blocks meets the requirements, and the determination of the optimal site level earthwork filling and excavation engineering quantity is achieved.
It improves the high-precision optimization of earthwork filling and excavation works, reduces unnecessary earthwork moving and disposal costs, reduces project costs, ensures the rationality and accuracy of earthwork distribution, adapts to complex site conditions, and improves optimization efficiency and flexibility sex.
Smart Images

Figure CN118735040A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of site earthwork optimization calculation, and in particular to a large-scale site earthwork optimization method for new energy projects based on a least squares method and a proportional optimization method. Background Art
[0002] Site leveling is in the implementation preparation stage of new energy projects. Especially for medium and large new energy projects, if the entire site needs to be leveled, the earthwork volume is very large, which will have a great impact on the engineering cost and investment return rate of the entire project, and even affect the owner's investment decision on the entire project. Therefore, in the stage of site leveling design of the project, how to optimize the design, how to ensure the minimum amount of filling and excavation as much as possible on the basis of the balance of filling and excavation of the site earthwork, so as to minimize the site leveling volume and cost of the entire project, is particularly important.
[0003] The traditional earthwork calculation method for site leveling is: according to the original natural terrain of the site, the site leveling design is carried out in a flat slope, stepped or a combination of the two, and at the same time, combined with the horizontal and longitudinal slope design requirements of the site leveling and with the help of the current mainstream earthwork calculation software, a one-time, non-differentiated site leveling treatment and site leveling earthwork calculation is carried out. However, most of the current new energy projects are medium and large projects, especially photovoltaic or "photovoltaic + other energy" projects of large new energy bases, which cover an area of tens of square kilometers. If the entire site is calculated for a one-time, non-differentiated site leveling treatment according to the traditional site leveling earthwork calculation method, the site after leveling will often have more potential adverse effects on subsequent engineering construction due to the undulations and mutations of the local original terrain:
[0004] First, after the site is leveled, the filling and excavation heights in some areas are too large, which is not conducive to ensuring the stability of the site foundation and project quality control; after the slope treatment at the edge of the site, the filling and excavation heights of some slopes are too large, which is not conducive to ensuring the stability of the site slopes, nor is it conducive to the vertical transition between the project site and the surrounding plots. At the same time, due to the excessive filling and excavation slopes, the project will invisibly increase the amount of high slopes and retaining walls set up additionally, as well as the area of land acquisition and leasing, which is not conducive to the quality, progress and cost control of the project, and may even affect the project investment and benefits; secondly, the filling and excavation heights inside the site and on the slopes are too large, which will greatly affect the project site leveling engineering cost due to the technical requirements of layered backfilling, rolling and compaction during site leveling construction, which is not conducive to the project progress and cost control; in addition, the earthwork volume calculated by performing a one-time, undifferentiated site leveling treatment on the entire site is relatively large compared to the earthwork volume calculated after optimization, and the accuracy is not high, which affects the project earthwork engineering cost and even affects the overall investment and benefits of the project. Summary of the invention
[0005] In view of the problems existing in the prior art, the present invention provides a method for optimizing earthwork for large sites of new energy projects based on the least squares method and the proportional optimization method, which solves the problems existing in the traditional method of indiscriminate site leveling, such as excessive filling and excavation heights inside the site and on the slopes, and large deviation and low accuracy of the site leveling earthwork volume compared to the optimized earthwork volume.
[0006] The present invention is achieved through the following technical solutions:
[0007] A method for optimizing earthwork at large sites of new energy projects based on least squares method and proportional optimization method comprises the following steps:
[0008] Step 1: Divide the project site into multiple blocks, and use the least squares method to calculate and determine the earthwork excavation and filling volume of each block;
[0009] Step 2: Select multiple blocks whose area deviations from the standard reference block are within a set range from all blocks, and determine the expected earthwork filling and excavation volume of the standard reference block according to the earthwork filling and excavation volumes of the selected multiple blocks;
[0010] Step 3: According to the expected earthwork filling and excavation volume of the standard reference block and the area of each block, the expected earthwork filling and excavation volume of each block is determined by combining the proportional optimization method;
[0011] Step 4: According to the expected earthwork filling and excavation engineering volume of each block and the earthwork filling and excavation engineering volume of each block in step 1, the earthwork filling and excavation optimization rate of each block is determined in combination with the proportional optimization method;
[0012] Step 5: Divide the blocks whose earthwork optimization rate does not meet the requirements into multiple blocks again, and repeat steps 1-4 until all different earthwork optimization rates meet the requirements. Determine the optimal site-leveling earthwork volume for the project based on the earthwork volume of each block that meets the requirements.
[0013] Preferably, in step 1, the project site is divided according to terrain data and restrictive design factors.
[0014] Preferably, the blocks include blocks with gentle terrain, blocks with sudden terrain changes and restricted blocks, and a buffer zone is set between two adjacent blocks;
[0015] The site-leveling transition zone is used for natural transition and connection between blocks. The width of the site-leveling transition zone can be reasonably determined based on the fill and excavation height at the boundary, site conditions, and engineering requirements.
[0016] Preferably, the method for calculating the expected earthwork excavation and filling volume of the standard reference block in step 2 is as follows:
[0017] Based on the earthwork excavation and filling quantities of multiple selected blocks and combined with the arithmetic average method, the expected earthwork excavation and filling quantities of the standard reference block are determined.
[0018] Preferably, the calculation method for obtaining the expected earthwork excavation and filling engineering volume of each block by combining the proportion optimization method in step 3 is as follows:
[0019] Q 期望 i= S i *Q 参考 / S 参考 i∈n
[0020] Among them, Q 期望 i is the expected earthwork volume of the i-th block; S i is the area of the i-th block; Q 参考 is the expected earthwork volume of the standard reference block; S 参考 is the area of the standard reference block.
[0021] Preferably, the method for determining the optimization rate of earthwork for each block in step 4 is as follows:
[0022] According to the calculated earthwork excavation and filling volume of each block and the expected earthwork excavation and filling volume of the standard reference block and combined with the proportional optimization method, the optimization rate ω of earthwork excavation and filling of each block is calculated.
[0023] Preferably, the expression of the optimized earthwork rate ω of the block is as follows:
[0024] ω=|(Q 期望 i -Q i ) / Q i |, i∈n.
[0025] Among them, Q i is the calculated earthwork excavation and filling volume of the i-th block, Q 期望 i is the expected earthwork volume of the ith block.
[0026] Preferably, in step 5, the optimization rate of earthwork filling and cutting of each block is compared with the set optimization rate floating limit α to determine whether the optimization rate of earthwork filling and cutting of each block meets the requirements;
[0027] If the optimization rate of earthwork filling and excavation of each currently divided block meets the requirements, the optimal earthwork filling and excavation volume of the project is determined based on the calculated earthwork filling and excavation volume of each final-level block.
[0028] A large-scale earthwork optimization system for new energy projects based on the least squares method and proportional optimization method, including:
[0029] The module for calculating the engineering quantity of each block is used to divide the project site into multiple blocks, and use the least squares method to calculate and determine the earthwork excavation and filling engineering quantity of each block;
[0030] The standard reference block expected engineering quantity module is used to select multiple blocks whose area deviations from the standard reference block are within a set range from all blocks, and determine the expected earthwork filling and excavation engineering quantity of the standard reference block based on the earthwork filling and excavation engineering quantities of the selected multiple blocks;
[0031] The expected engineering quantity module for each block is used to determine the expected earthwork filling and excavation quantity of each block based on the expected earthwork filling and excavation quantity of the standard reference block and the area of each block in combination with the proportional optimization method;
[0032] The earthwork excavation and filling quantity optimization rate module is used to determine the earthwork excavation and filling optimization rate of each block according to the expected earthwork excavation and filling quantity of each block and the earthwork excavation and filling quantity of each block in combination with the proportional optimization method;
[0033] The total engineering quantity module is used to further divide the blocks whose earth-filling and excavation optimization rate does not meet the requirements into multiple blocks, and calculate the earth-filling and excavation optimization rate of each block after division, until the earth-filling and excavation optimization rate of all blocks meets the requirements. According to the earth-filling and excavation engineering quantities of each block that meet the requirements, the optimal total site-leveling earth-filling and excavation engineering quantity of the project is determined.
[0034] Compared with the prior art, the present invention has the following beneficial technical effects:
[0035] The earthwork optimization method for large sites of new energy projects based on the least squares method and the proportional optimization method provided by the present invention combines the least squares method with the proportional optimization method, accurately calculates the calculated earthwork filling and excavation engineering volume of each block by the least squares method, and then uses the proportional optimization method to determine the expected earthwork filling and excavation engineering volume of each block based on the area of each block in combination with the area of the standard reference block and the expected earthwork filling and excavation engineering volume, thereby realizing high-precision optimization of the earthwork filling and excavation engineering volume of each block of the site. Compared with the traditional earthwork optimization method, the method uses mathematical algorithms for accurate calculation, improves the optimization efficiency, and reduces the tediousness and errors of repeated calculations. Secondly, an iterative mechanism is used to divide the blocks that do not meet the requirements again. When the optimization rate of filling and excavation of a block does not meet the requirements, the method further divides the block into smaller blocks through the iterative optimization mechanism, and recalculates and adjusts until the optimization rate of filling and excavation of all blocks meets the requirements. This iterative method enables the optimization scheme to flexibly adapt to various complex site conditions. Through continuous iterative optimization, the final earthwork excavation scheme is more reasonable and economical, which can minimize unnecessary earthwork movement and disposal costs and reduce project costs. When selecting the standard reference block, this method comprehensively considers the deviation between the area of each block and the area of the standard reference block, as well as the earthwork excavation volume of these blocks, ensuring the representativeness and rationality of the selected standard reference block. By comprehensively considering the area deviation and earthwork excavation volume of each block compared to the standard reference block, this method can more accurately determine the expected earthwork excavation volume of each block, thereby improving the accuracy of the optimization results and the optimization efficiency.
[0036] In summary, this large-scale earthwork optimization method for new energy projects based on least squares method and proportional optimization method combines the least squares method with the proportional optimization method, adopts an iterative optimization mechanism, and comprehensively considers the area deviation and earthwork excavation and filling volume. It achieves high-precision and high-efficiency optimization of earthwork excavation and filling volume, and has significant advantages and practical application value. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] Figure 1 The present invention is a flow chart of the method for optimizing earthwork calculation. DETAILED DESCRIPTION
[0038] The present invention will be further described in detail below in conjunction with the accompanying drawings, which are intended to explain the present invention rather than to limit it.
[0039] See also Figure 1 A method for optimizing earthwork of large sites of new energy projects based on least square method and proportional optimization method comprises the following steps:
[0040] Step 1: Obtain the terrain data and restrictive design factors of the project site according to the topographic map of the project site;
[0041] First, it is necessary to obtain a high-precision topographic map of the project site. The topographic map should contain sufficient information, such as contour lines, elevation points, water systems, residential areas, existing roads, above-ground and underground pipelines, etc., so as to conduct site condition analysis before project site leveling.
[0042] Identification of restrictive design factors: According to project requirements and site conditions, identify the restrictive design factors that affect the calculation of site earthwork volume, including environmental protection areas, existing buildings and structures, above-ground and underground pipeline facilities, scenic spots and historical sites, and other unusable land in the project site. Based on the restrictive design factors, the constraints and limitation scope of earthwork volume calculation can be determined.
[0043] Step 2: Divide the project site into multiple primary blocks based on terrain data and restrictive design factors, and set up site leveling transition zones between adjacent primary blocks;
[0044] The project site is divided into multiple first-level blocks according to the gentle terrain, undulating terrain and restricted areas. Each block should have relatively consistent terrain characteristics and construction conditions. The multiple first-level blocks include blocks with gentle terrain, blocks with undulating terrain and restricted blocks, and a field leveling transition zone is set between the blocks. The width of the field leveling transition zone can be reasonably determined according to the fill and excavation height at the boundary between the blocks, the site conditions and the engineering requirements, so that the field leveling and slope pulling treatment between the blocks can be carried out on site according to the actual situation to ensure a smooth transition after the field leveling of each block.
[0045] When dividing the blocks, the project site is divided according to the set site slope and slope direction. In this embodiment, the area with an average slope less than 10% is divided into a flat terrain block, and the area with an average slope greater than or equal to 10% and a large slope change rate is divided into a sudden terrain block.
[0046] Step 3: According to the terrain data of each primary block, each primary block is divided again to form multiple secondary blocks;
[0047] According to the terrain data, each primary block is divided into two levels to form multiple secondary blocks, and the area of each secondary block is kept as uniform as possible. The flat terrain blocks are divided according to the slope and slope direction, and the terrain mutation blocks are divided according to the continuous change of the slope. A field leveling transition zone is set between each adjacent secondary block. The width of the field leveling transition zone between each block can be set according to the filling and excavation height at the boundary. It should be a gentle transition between each block and not affect the subsequent engineering construction requirements. The field leveling transition zone is determined according to the actual situation of the site.
[0048] Step 4: Use the least square method to calculate the earthwork excavation and filling volume Qi of each secondary block;
[0049] Step 5: Select multiple secondary blocks with similar areas to the standard reference block in the secondary blocks, and determine the expected earthwork excavation and filling volume of the standard reference block based on the earthwork excavation and filling volume of the selected secondary blocks.
[0050] The expected earthwork excavation and filling quantity of the standard reference block using the arithmetic mean method is calculated as follows:
[0051] Q 参考 =(Q1+Q2+Q3+......Q m ) / m, m∈n.
[0052] Among them, Q m is the calculated site leveling earthwork excavation and filling volume of the block with an area similar to the standard reference block; m is the number of blocks with an area similar to the standard reference block.
[0053] Step 6: Calculate the expected earthwork excavation and filling volume of each secondary block based on the expected earthwork excavation and filling volume of the standard reference block and in combination with the proportional optimization method.
[0054] Specifically, according to the area of the secondary block, the area of the standard reference block and the expected earthwork filling and excavation engineering volume, the expected earthwork filling and excavation engineering volume of each secondary block is calculated. The calculation method of the expected earthwork filling and excavation engineering volume of the secondary block is as follows:
[0055] Q 期望 i= S i *Q 参考 / S 参考
[0056] Among them, Q 期望 i is the expected earthwork volume of the i-th block; S i is the area of the i-th block; Q 参考 is the expected earthwork volume of the standard reference block; S 参考 is the area of the standard reference block.
[0057] Step 7: According to the earthwork filling and excavation works of each secondary block and the expected earthwork filling and excavation works of the standard reference block, combined with the proportional optimization method, the filling and excavation optimization rate ω of each secondary block is calculated. The calculation method is as follows:
[0058] ω=|(Q 期望 i -Q i ) / Q i |, i∈n.
[0059] Among them, Q i is the calculated earthwork excavation and filling volume of the i-th block, Q 期望i is the expected earthwork volume of the ith block.
[0060] Step 8: When the optimization rate of earthwork filling and excavation in each secondary block meets the requirements, the calculated earthwork filling and excavation volume Q of each secondary block is calculated. i After summarizing, the optimal site leveling earthwork excavation and filling volume of the project is obtained.
[0061] When the earth-filling and cutting optimization rates of several secondary blocks do not meet the requirements, repeat steps 3-7, divide the secondary blocks that do not meet the requirements into multiple tertiary blocks again, and calculate the earth-filling and cutting optimization rates of each tertiary block until the earth-filling and cutting optimization rates meet the requirements.
[0062] The optimal site-leveling earthwork excavation and filling volume for the project is determined by summarizing the earthwork excavation and filling volumes of each block whose optimization rate meets the requirements.
[0063] In the process of determining the optimization rate of earthwork, the optimization rate floating limit α is first set, and then the optimization rate of earthwork of each secondary block is compared with the optimization rate floating limit α. If the optimization rate of earthwork of each secondary block ω is less than or equal to the floating limit α, then the secondary block is the optimal final block, and the earthwork volume Q of this block is calculated. i That is, the optimal earthwork filling and excavation volume, where the optimization rate floating limit α is determined based on the actual engineering situation and engineering project experience.
[0064] If the optimization rate ω of the earthwork filling and excavation volume of each secondary block is greater than the floating limit α, steps 3-7 need to be repeated for the secondary blocks that do not meet the requirements until the optimization rate ω of the earthwork filling and excavation volume of the divided block is less than the floating limit α. At this time, the block is the final block, and the earthwork filling and excavation volume of each block that meets the requirements is summed up to obtain the optimal total earthwork filling and excavation volume of the project.
[0065] This large-scale site earthwork optimization method for new energy projects based on the least squares method and the proportional optimization method can accurately calculate the calculated earthwork filling and excavation volume of each block through the least squares method, and then determine the expected earthwork filling and excavation volume of each block according to the standard reference block area and its expected earthwork filling and excavation volume according to the proportional method, so that the earthwork filling and excavation volume allocation of the entire project site is more accurate. Secondly, when the filling and excavation optimization rate of a block does not meet the requirements, the method allows the block to be further divided into smaller blocks, and recalculated and adjusted. This iterative processing method can adapt to various complex site conditions and improve the flexibility of the optimization scheme. Through the proportional optimization method, the filling and excavation optimization rate of each block can be quickly and effectively determined, thereby reducing unnecessary earthwork movement, reducing construction costs, and improving construction efficiency. Due to the accurate calculation and reasonable allocation of earthwork filling and excavation volume, unnecessary earthwork transportation and disposal costs can be reduced, thereby reducing the total cost of the project. The optimized earthwork filling and excavation scheme can make better use of the natural terrain and landforms of the project site, reduce the impact on the environment, and at the same time, it can also maximize the utilization of resources through reasonable allocation of resources. By optimizing the earthwork filling and excavation scheme, the damage to the original terrain can be reduced, the interference to the surrounding environment can be reduced, and it is beneficial to protect the ecological environment. Due to the use of mathematical methods for calculation and optimization, the results obtained are highly predictable and can provide a reliable basis for project decision-making. The method has clear steps, simple operation, easy implementation and promotion in the project, and has good practicality and operability.
[0066] In summary, the earthwork optimization method for large sites of new energy projects based on the least squares method and proportional optimization method has the advantages of high accuracy, strong flexibility, improved efficiency, cost savings, resource optimization, environmental friendliness, strong predictability and easy implementation.
[0067] Example 1
[0068] The present invention also provides a large-scale site earthwork optimization system for new energy projects based on the least squares method and the proportional optimization method, comprising:
[0069] The module for calculating the engineering quantity of each block is used to divide the project site into multiple blocks, and use the least squares method to calculate and determine the earthwork excavation and filling engineering quantity of each block;
[0070] The standard reference block expected engineering quantity module is used to select multiple blocks whose area deviations from the standard reference block are within a set range from all blocks, and determine the expected earthwork filling and excavation engineering quantity of the standard reference block based on the earthwork filling and excavation engineering quantities of the selected multiple blocks;
[0071] The expected engineering quantity module for each block is used to determine the expected earthwork filling and excavation quantity of each block based on the expected earthwork filling and excavation quantity of the standard reference block and the area of each block in combination with the proportional optimization method;
[0072] The earthwork excavation and filling quantity optimization rate module is used to determine the earthwork excavation and filling optimization rate of each block according to the expected earthwork excavation and filling quantity of each block and the calculated earthwork excavation and filling quantity of each block in combination with the proportional optimization method;
[0073] The total engineering quantity module is used to further divide the blocks whose earth-filling and excavation optimization rate does not meet the requirements into multiple blocks, and calculate the earth-filling and excavation optimization rate after division until the earth-filling and excavation optimization rate of all blocks meets the requirements. According to the earth-filling and excavation engineering quantities of each block that meets the requirements, the optimal total site-leveling earth-filling and excavation engineering quantity of the project is determined.
[0074] Example 2
[0075] Taking the site leveling calculation of a large photovoltaic base project as an example, the land area within the red line of the project is 2116.737hm 2 According to the needs of the project, the slope after the site is leveled is no more than 8%. With the help of Feishida GPCAD V5.0 earthwork calculation software, according to the optimization design ideas of the present invention, the site is divided into multiple levels and the earthwork volume and optimization rate are summarized as shown in the following table:
[0076]
[0077]
[0078] As mentioned above: According to the optimization design idea of the present invention, after the four-level block division, compared with the feasibility study stage (first-level block), the earthwork volume of the site leveling and filling is increased from 125 million m in the feasibility study stage to 3 Optimized to 51.3034 million m 3 The total optimized earthwork volume is 73.6966 million m 3 The overall earthwork optimization rate was 58.96%, saving 294.7864 million yuan in site leveling project costs.
[0079] The present invention provides a large-scale site earthwork optimization method for new energy projects, which obtains the optimal site leveling engineering quantity by performing multiple optimization calculations on the site. At this time, the filling and excavation engineering quantities of the entire site are basically balanced and the engineering quantity is minimal. The entire site is flat as a whole under the condition of meeting the horizontal and vertical design slopes, and the terrain changes evenly and gently. Especially for medium and large new energy project sites, the site leveling earthwork engineering quantity can be optimized to the greatest extent, which has a good effect on saving the engineering investment in the project site leveling stage.
[0080] The above contents are only for explaining the technical idea of the present invention and cannot be used to limit the protection scope of the present invention. Any changes made on the basis of the technical solution in accordance with the technical idea proposed by the present invention shall fall within the protection scope of the claims of the present invention.
Claims
1. A method for optimizing earthwork at large sites of new energy projects based on the least squares method and proportional optimization method, characterized in that: The following steps are involved: Step 1: Divide the project site into multiple blocks, and use the least squares method to calculate and determine the earthwork excavation and filling volume of each block; Step 2: Select multiple blocks whose area deviations from the standard reference block are within a set range from all blocks, and determine the expected earthwork filling and excavation volume of the standard reference block according to the earthwork filling and excavation volumes of the selected multiple blocks; Step 3: According to the expected earthwork filling and excavation volume of the standard reference block and the area of each block, the expected earthwork filling and excavation volume of each block is determined by combining the proportional optimization method; Step 4: According to the expected earthwork filling and excavation engineering volume of each block and the earthwork filling and excavation engineering volume of each block in step 1, the earthwork filling and excavation optimization rate of each block is determined in combination with the proportional optimization method; Step 5: Divide the blocks whose earthwork optimization rate does not meet the requirements into multiple blocks again, and repeat steps 1-4 until all different earthwork optimization rates meet the requirements. Determine the optimal site-leveling earthwork volume for the project based on the earthwork volume of each block that meets the requirements.
2. According to claim 1, a method for optimizing earthwork of large sites of new energy projects based on least squares method and proportional optimization method is characterized in that: In step 1, the project site is divided according to terrain data and restrictive design factors.
3. The method for optimizing earthwork of large sites of new energy projects based on least square method and proportional optimization method according to claim 1 is characterized in that: The blocks include blocks with gentle terrain, blocks with sudden terrain changes and restricted blocks, and a buffer zone is set between two adjacent blocks; The site-leveling transition zone is used for natural transition and connection between blocks. The width of the site-leveling transition zone can be reasonably determined based on the fill and excavation height at the boundary, site conditions, and engineering requirements.
4. The method for optimizing earthwork of large sites of new energy projects based on least square method and proportional optimization method according to claim 1 is characterized in that: The expected earthwork volume for the standard reference area in step 2 is calculated as follows: Based on the earthwork excavation and filling quantities of multiple selected blocks and combined with the arithmetic average method, the expected earthwork excavation and filling quantities of the standard reference block are determined.
5. The method for optimizing earthwork of large sites of new energy projects based on least square method and proportional optimization method according to claim 1 is characterized in that: The calculation method for obtaining the expected earthwork excavation and filling volume of each block by combining the proportional optimization method described in step 3 is as follows: Q 期望 i =S i *Q 参考 / S 参考 i∈n Among them, Q 期望 i is the expected earthwork volume of the i-th block; S i is the area of the i-th block; Q 参考 is the expected earthwork volume of the standard reference block; S 参考 is the area of the standard reference block.
6. The method for optimizing earthwork of large sites of new energy projects based on least square method and proportional optimization method according to claim 1 is characterized in that: The method for determining the optimization rate of earthwork for each block in step 4 is as follows: According to the calculated earthwork excavation and filling volume of each block and the expected earthwork excavation and filling volume of the standard reference block and combined with the proportional optimization method, the optimization rate ω of earthwork excavation and filling of each block is calculated.
7. A method for optimizing earthwork of large sites of new energy projects based on least square method and proportional optimization method according to claim 6, characterized in that: The expression of the optimization rate ω of earthwork filling and cutting in the block is as follows: ω=|(Q 期望 i -Q i ) / Q i |,i∈n Among them, Q i is the calculated earthwork excavation and filling volume of the i-th block, Q 期望 i is the expected earthwork volume of the ith block.
8. The method for optimizing earthwork of large sites of new energy projects based on least square method and proportional optimization method according to claim 1 is characterized in that: In step 5, the optimization rate of earthwork filling and cutting of each block is compared with the set optimization rate floating limit α to determine whether the optimization rate of earthwork filling and cutting of each block meets the requirements; If the optimization rate of earthwork filling and excavation of each currently divided block meets the requirements, the optimal earthwork filling and excavation volume of the project is determined based on the calculated earthwork filling and excavation volume of each final-level block.
9. A system for executing the method for optimizing earthwork of large sites of new energy projects based on least square method and proportional optimization method as described in any one of claims 1 to 6, characterized in that: include: The module for calculating the engineering quantity of each block is used to divide the project site into multiple blocks and use the least squares method to determine the earthwork excavation and filling quantity of each block; The standard reference block expected engineering quantity module is used to select multiple blocks whose area deviations from the standard reference block are within a set range from all blocks, and determine the expected earthwork filling and excavation engineering quantity of the standard reference block based on the earthwork filling and excavation engineering quantities of the selected multiple blocks; The expected engineering quantity module for each block is used to determine the expected earthwork filling and excavation quantity of each block based on the expected earthwork filling and excavation quantity of the standard reference block and the area of each block in combination with the proportional optimization method; The earthwork excavation and filling quantity optimization rate module is used to determine the earthwork excavation and filling optimization rate of each block according to the expected earthwork excavation and filling quantity of each block and the earthwork excavation and filling quantity of each block in combination with the proportional optimization method; The total engineering quantity module is used to further divide the blocks whose earth-filling and excavation optimization rate does not meet the requirements into multiple blocks, and calculate the earth-filling and excavation optimization rate of each divided block until the earth-filling and excavation optimization rate of all blocks meets the requirements. According to the earth-filling and excavation engineering quantities of each block that meets the requirements, the optimal site-leveling earth-filling and excavation engineering quantity of the project is determined.
Citation Information
Patent Citations
Method for improving sampling ratio precision of core germplasm of crops
CN102915408A
Mountainous road earth volume calculation method based on oblique photography technology
CN111783191A
Earthwork amount calculation method based on improved constraint irregular triangulation network construction method
CN112733215A
Large-scale site earthwork optimization method and system for new energy project
CN117709742A
Calculation method for temporary occupied area of tower footing earthwork of power transmission line and application