Multi-source dynamic signal unified test system for core machine test

By using the combined solution of PTP clock source and NTP server in the aero-engine test system, the problem of insufficient clock synchronization accuracy of multi-source dynamic signals is solved, high-precision data alignment and system expansion are achieved, and the reliability and reliability of the test system are improved. efficiency.

CN118740305AActive Publication Date: 2024-10-01AECC SHENYANG ENGINE RES INST

Patent Information

Application Number
CN202410847471.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-27
Publication Date
2024-10-01
Estimated Expiration
2044-06-27

AI Technical Summary

Technical Problem

In traditional aero-engine test systems, the clock synchronization accuracy of multi-source dynamic signals is insufficient to meet the time accuracy requirements of high sampling rate testing, and the heterogeneity of equipment types and software platforms makes system expansion and maintenance difficult.

Method used

The PTP clock source is used for device timing in the lower computer network, and the NTP server is used for operating system timing in the host computer network to achieve hardware time stamp collection and synchronization of steady-state and dynamic data, and comprehensive data analysis is performed through the dynamic unified test system and management.

Benefits of technology

The clock synchronization accuracy is improved to the nanosecond level, ensuring the alignment and synchronization of steady-state and dynamic data, simplifying system expansion and maintenance, and improving the reliability and efficiency of the test system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118740305A_ABST
    Figure CN118740305A_ABST
Patent Text Reader

Abstract

The invention belongs to the field of engine tests, and particularly relates to a multi-source dynamic signal unified test system for a core engine test. The system comprises a lower computer network, the lower computer network comprises a plurality of steady state test devices and a plurality of dynamic test devices, and the lower computer network carries out time service on each device of the lower computer network through a PTP clock source so as to add a hardware timestamp to data collected by each device of the lower computer network; the upper computer network is connected with the lower computer network, the upper computer network comprises a steady-state test upper computer and a plurality of dynamic test upper computers, and the steady-state test upper computer is used for receiving steady-state signals collected by each steady-state test device in the lower computer network; the dynamic test upper computer is used for receiving dynamic signals collected by the dynamic test devices in the lower computer network, and the upper computer network carries out time service on the upper computer operating systems of the upper computer network through the NTP server. According to the method and the device, alignment of steady-state and dynamic acquired data is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the technical field of engine testing, and in particular relates to a multi-source dynamic signal unified testing system for core engine testing. Background Art

[0002] The core engine of the engine consists of three parts: the high-pressure compressor, the combustion chamber, and the high-pressure turbine. The importance of core engine technology verification to engine development is becoming increasingly apparent. For the core engine test bench test system, if it is to achieve the introduction and comprehensive analysis of various signal sources, data clock synchronization, and effective data flow control, etc., there are high requirements for the rationality of the test system architecture design.

[0003] In traditional aircraft engine test systems, the acquisition and management of steady-state and dynamic test signals are managed separately in their own systems. Such management is based on the traditional data acquisition architecture.

[0004] The existing core engine test system is composed as follows Figure 1 As shown. It is mainly composed of steady-state and dynamic test systems, which correspond to the steady-state data acquisition system of the lower computer, the dynamic data acquisition system and the upper computer data acquisition computer system. The bench test includes steady-state pressure test, steady-state thermocouple temperature test, steady-state transmitter signal test, whole machine vibration test, dynamic pressure pulsation test, dynamic non-contact blade tip vibration displacement test, dynamic gap test, dynamic strain gauge test, flow field test, acoustic test, etc. These test lower computers are connected to their respective upper computers through the network. These test systems are independent of each other, and data synchronization is managed based on the upper computer operating system time, such as Figure 1 The host computer operating system is synchronized with the NTP server and the collected data is timestamped.

[0005] The timestamps of steady-state test data and dynamic test data in the test system use the operating system time synchronized by NTP. A comprehensive analysis of steady and dynamic data is performed in the multi-source dynamic signal test system. This method has poor clock synchronization accuracy and can be used for steady-state acquisition within a sampling rate of less than 20Hz, but is not applicable for dynamic tests above 200kHz and 1MHz. The time accuracy of the operating system in the local area network is basically in the second level. If the timing accuracy is further improved to milliseconds, the system overhead will increase. The above results in the inability to meet the time accuracy requirements of dynamic tests.

[0006] Although the data acquisition equipment used in the dynamic test of the test system has achieved network access, the different types of equipment and software platforms make system expansion and maintenance difficult. For example, when a system device fails, due to different software platforms and device types, the acquisition equipment with the same function lacks interchangeability and cannot be replaced immediately, which increases the system operation and maintenance costs. Summary of the invention

[0007] In order to solve the above problems, the present application provides a multi-source dynamic signal unified testing system for core engine testing to solve the clock synchronization problem when multi-source dynamic signals are accessed in the core engine testing system, as well as the problem of synchronous analysis of steady-state and dynamic data on the same platform.

[0008] The multi-source dynamic signal unified test system for core engine testing of the present application mainly includes:

[0009] A lower-machine network, wherein the lower-machine network includes a plurality of steady-state test devices and a plurality of dynamic test devices, and the lower-machine network is connected to a PTP clock source, and each device in the lower-machine network is timed by the PTP clock source, so as to add a hardware timestamp to the data collected by each device in the lower-machine network;

[0010] The host computer network is connected to the lower computer network. The host computer network includes a steady-state test host computer and multiple dynamic test host computers. The steady-state test host computer is used to receive steady-state signals collected by each steady-state test device in the lower computer network, and the dynamic test host computer is used to receive dynamic signals collected by each dynamic test device in the lower computer network. The host computer network is connected to an NTP server, and the timing of each host computer operating system in the host computer network is performed through the NTP server.

[0011] Preferably, the dynamic test equipment in the lower computer network is divided into continuous acquisition equipment and discontinuous acquisition equipment. The dynamic signals collected by the continuous acquisition equipment are connected to the dynamic unified test system. The dynamic unified test system is timed externally through a PTP clock source and internally synchronized between the dynamic test equipment through an independent data clock synchronization bus. The discontinuous acquisition equipment is directly timed through the PTP clock source.

[0012] Preferably, the continuous acquisition equipment includes whole machine vibration test equipment, dynamic pressure pulsation test equipment, dynamic strain gauge test equipment, flow field test equipment and acoustic test equipment, and the non-continuous acquisition equipment includes dynamic non-contact blade tip vibration displacement test equipment and dynamic clearance test equipment.

[0013] Preferably, the dynamic test host computer in the host computer network is divided into a continuous dynamic signal processing system architecture and a discontinuous dynamic signal processing system architecture. The continuous dynamic signal processing system architecture includes a dynamic test master control server and multiple dynamic test host computer sub-machines whose tasks are scheduled by the dynamic test master control server. The dynamic test master control server is used to collect dynamic signals uploaded by the dynamic unified test system in the lower computer network. The discontinuous dynamic signal processing system architecture includes multiple dynamic test host computers, which are used to collect and process dynamic signals collected by discontinuous collection devices in the lower computer network.

[0014] Preferably, the dynamic test master control server is also used to transmit the steady-state data periodically analyzed by the steady-state test host computer and the dynamic data periodically analyzed by each dynamic test host computer in the non-continuous dynamic signal processing system architecture to the dynamic test host computer sub-computer for comprehensive data analysis.

[0015] Preferably, the dynamic test host computer sub-machines include at least three.

[0016] This application ensures the alignment of steady-state and dynamic acquisition data, and realizes the synchronous acquisition, display, analysis and management functions of multi-source dynamic signal data on the same software platform. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 This is a schematic diagram of the existing core machine test system architecture.

[0018] Figure 2 It is a schematic diagram of the core engine test system architecture of a preferred embodiment of the multi-source dynamic signal unified test system for core engine testing of the present application. DETAILED DESCRIPTION

[0019] In order to make the purpose, technical scheme and advantages of the implementation of this application clearer, the technical scheme in the implementation of this application will be described in more detail in combination with the drawings in the implementation of this application. In the drawings, the same or similar reference numerals throughout represent the same or similar elements or elements with the same or similar functions. The described implementation is a part of the implementation of this application, not all of the implementations. The implementation described below with reference to the drawings is exemplary and is intended to be used to explain this application, and cannot be understood as a limitation on this application. Based on the implementation in this application, all other implementations obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application. The implementation of this application is described in detail below in combination with the drawings.

[0020] The present application provides a unified test system for multi-source dynamic signals for core engine testing, such as Figure 2 As shown, it mainly includes:

[0021] A lower-machine network, wherein the lower-machine network includes a plurality of steady-state test devices and a plurality of dynamic test devices, and the lower-machine network is connected to a PTP clock source, and each device in the lower-machine network is timed by the PTP clock source, so as to add a hardware timestamp to the data collected by each device in the lower-machine network;

[0022] The host computer network is connected to the lower computer network. The host computer network includes a steady-state test host computer and multiple dynamic test host computers. The steady-state test host computer is used to receive steady-state signals collected by each steady-state test device in the lower computer network, and the dynamic test host computer is used to receive dynamic signals collected by each dynamic test device in the lower computer network. The host computer network is connected to an NTP server, and the timing of each host computer operating system in the host computer network is performed through the NTP server.

[0023] The present application adds a PTP clock source as the main clock source in the lower computer network of the test system to provide time for the lower computers. At the same time, the original NTP server is retained and only provides time for the operating systems of each upper computer in the upper computer network. In the lower computer network, the PTP timing accuracy can reach nanosecond accuracy, and two groups of slave devices can be timed at the same time, that is, the steady-state test equipment and dynamic test equipment in the lower computer network can be timed at the same time. In this way, the data collected by the lower computer can be hardware timestamped, which is more accurate than the operating system timestamp in the original architecture, ensuring the alignment of steady-state and dynamic collected data.

[0024] In some optional embodiments, the dynamic test equipment in the lower computer network is divided into continuous acquisition equipment and discontinuous acquisition equipment. The dynamic signals collected by the continuous acquisition equipment are connected to the dynamic unified test system. The dynamic unified test system is timed externally through a PTP clock source and internally through an independent data clock synchronization bus to synchronize the timing between the dynamic test devices. The discontinuous acquisition equipment is directly timed through the PTP clock source.

[0025] In this embodiment, in order to ensure dynamic data alignment and improve clock synchronization accuracy, continuous acquisition devices are merged, such as Figure 2 As shown in the figure, a dynamic unified test system is built in the lower computer network. The system architecture connects the dynamic signals collected continuously with a sampling frequency of 200kHz or 1MHz. The system consists of multiple subsystems, which can realize the continuous collection task of variable sampling rate of each subsystem. The hardware of each subsystem adopts the same specification and variable sampling rate, which can be interchanged to ensure the scalability and easy maintenance of the system. The dynamic unified test system uses the PTP clock source for timing externally and the independent data clock synchronization bus for timing synchronization between subsystems internally, which ensures the stability of the system and the accuracy of continuous working timing to the greatest extent. For the non-continuously collected dynamic signals in the lower computer network, due to the large difference in sampling rate with the continuously collected dynamic test signals, such as the 20MHz~80MHz counter to collect blade tip vibration and gap test, it will no longer be connected to the dynamic unified test system but directly perform PTP timing operation, and the data will be transmitted back to the upper computer through the network.

[0026] In some optional embodiments, the continuous acquisition equipment includes whole machine vibration testing equipment, dynamic pressure pulsation testing equipment, dynamic strain gauge testing equipment, flow field testing equipment and acoustic testing equipment, and the non-continuous acquisition equipment includes dynamic non-contact blade tip vibration displacement testing equipment and dynamic clearance testing equipment.

[0027] In some optional embodiments, the dynamic test host computer in the host computer network is divided into a continuous dynamic signal processing system architecture and a discontinuous dynamic signal processing system architecture. The continuous dynamic signal processing system architecture includes a dynamic test master control server and multiple dynamic test host computer sub-machines whose tasks are scheduled by the dynamic test master control server. The dynamic test master control server is used to collect dynamic signals uploaded by the dynamic unified test system in the lower computer network. The discontinuous dynamic signal processing system architecture includes multiple dynamic test host computers, which are used to collect and process dynamic signals collected by discontinuous collection devices in the lower computer network.

[0028] In this embodiment, just as the lower computer network is divided into continuous and discontinuous dynamic signal acquisition, different upper computers are used to process continuous and discontinuous dynamic signals in the upper computer network. The continuous dynamic signal processing system architecture is used to process continuous dynamic signals. A dynamic test master control server is deployed in the upper computer network to manage the dynamic unified test data analysis and scheduling uploaded by the lower computers. The data can be distributed to multiple dynamic test upper computer sub-machines through the dynamic test master control server for analysis and real-time display. In some optional implementations, the dynamic test upper computer sub-machines include at least three, for example, Figure 2 The dynamic test host computer (1), dynamic test host computer (2), and dynamic test host computer (3) are respectively configured with analysis interfaces of different combination parameters, and only analyze one type of dynamic data or extract other types of data for comprehensive analysis and display as needed. The utilization efficiency of the system is greatly improved compared with the single analysis function of the original system. Since the continuously collected dynamic data has been synchronously collected and analyzed on this platform, the software is actually distributed and deployed through the same platform, which is conducive to the expansion of the system and the universality of data. For the non-continuous dynamic signal processing system architecture, the number of host computers configured is consistent with the non-continuous acquisition equipment in the lower computer network, that is, it includes a dynamic non-contact blade tip vibration displacement host computer for receiving dynamic data collected by the dynamic non-contact blade tip vibration displacement test equipment in the lower computer network, and a dynamic gap host computer for receiving dynamic data collected by the dynamic gap test equipment in the lower computer network.

[0029] In some optional implementations, the dynamic test master control server is also used to transmit the steady-state data periodically analyzed by the steady-state test host computer and the dynamic data periodically analyzed by each dynamic test host computer in the non-continuous dynamic signal processing system architecture to the dynamic test host computer sub-computer for comprehensive data analysis.

[0030] In this embodiment, steady-state data and non-continuously acquired dynamic system (blade tip vibration, clearance) host computer data can be published to the dynamic test main control server through fixed-cycle analysis for comprehensive analysis of steady-state data and dynamic data, thereby realizing the synchronous acquisition, display, analysis and management functions of multi-source dynamic signal data on the same software platform.

[0031] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed in the present application should be included in the protection scope of the present application. Therefore, the protection scope of the present application shall be based on the protection scope of the claims.

Claims

1. A multi-source dynamic signal unified test system for core engine testing, characterized in that: include: A lower-machine network, wherein the lower-machine network includes a plurality of steady-state test devices and a plurality of dynamic test devices, and the lower-machine network is connected to a PTP clock source, and each device in the lower-machine network is timed by the PTP clock source, so as to add a hardware timestamp to the data collected by each device in the lower-machine network; The host computer network is connected to the lower computer network. The host computer network includes a steady-state test host computer and multiple dynamic test host computers. The steady-state test host computer is used to receive steady-state signals collected by each steady-state test device in the lower computer network, and the dynamic test host computer is used to receive dynamic signals collected by each dynamic test device in the lower computer network. The host computer network is connected to an NTP server, and the timing of each host computer operating system in the host computer network is performed through the NTP server.

2. The multi-source dynamic signal unified test system for core engine testing according to claim 1, characterized in that: The dynamic test equipment in the lower computer network is divided into continuous acquisition equipment and discontinuous acquisition equipment. The dynamic signals collected by the continuous acquisition equipment are connected to the dynamic unified test system. The dynamic unified test system is timed externally through a PTP clock source and internally synchronized between the dynamic test equipment through an independent data clock synchronization bus. The discontinuous acquisition equipment is directly timed through the PTP clock source.

3. The multi-source dynamic signal unified test system for core engine testing as claimed in claim 2, characterized in that: The continuous acquisition equipment includes whole machine vibration test equipment, dynamic pressure pulsation test equipment, dynamic strain gauge test equipment, flow field test equipment and acoustic test equipment, and the non-continuous acquisition equipment includes dynamic non-contact blade tip vibration displacement test equipment and dynamic clearance test equipment.

4. The multi-source dynamic signal unified test system for core engine testing as claimed in claim 2, characterized in that: The dynamic test host computer in the host computer network is divided into a continuous dynamic signal processing system architecture and a discontinuous dynamic signal processing system architecture. The continuous dynamic signal processing system architecture includes a dynamic test master control server and multiple dynamic test host computer sub-machines whose tasks are scheduled by the dynamic test master control server. The dynamic test master control server is used to collect dynamic signals uploaded by the dynamic unified test system in the lower computer network. The discontinuous dynamic signal processing system architecture includes multiple dynamic test host computers, which are used to collect and process dynamic signals collected by discontinuous collection devices in the lower computer network.

5. The multi-source dynamic signal unified test system for core engine testing as claimed in claim 4, characterized in that: The dynamic test master control server is also used to transmit the steady-state data periodically analyzed by the steady-state test host computer and the dynamic data periodically analyzed by each dynamic test host computer in the non-continuous dynamic signal processing system architecture to the dynamic test host computer sub-computer for comprehensive data analysis.

6. The multi-source dynamic signal unified test system for core engine testing as claimed in claim 4, characterized in that: The dynamic test host computer sub-machines include at least three.

Citation Information

Patent Citations

  • Dynamic property tracing method based on dynamic electric energy calibrator

    CN107861091A

  • Whole-network clock feedback method and system

    CN113114450A

  • Clock synchronization implementation method of wind tunnel pressure measurement system

    CN114785445A

  • Aero-engine compressor blade vibration frequency measurement method

    CN117968829A

  • Time information transmitter

    JP2013243651A

Cited By

  • Beam line station synchronous data acquisition device and method

    CN119225271A