A welding device and method for welding a sewage pipe and a multi-branch pipe
By designing an automated welding device, the linkage of stepper motor, servo motor and oil cylinder is used to realize automated branch pipe penetration and welding, solving the problems of increased working strength and extended welding time caused by manual operation in the existing technology, and significantly improving Welding efficiency.
Patent Information
- Application Number
- CN202411245576.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-06
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-09-06
AI Technical Summary
In the prior art, the process of welding sewage discharge pipes and multiple branch pipes requires manual operation, which leads to an increase in worker's working strength and an extended welding time, and reduces welding efficiency.
A welding device is designed, including a tooling mechanism, a feeding mechanism and a welding mechanism. Through the linkage of stepper motor, servo motor and oil cylinder, automatic branch pipe penetration and welding are realized, reducing manual manual operation.
It greatly reduces the work intensity of workers, significantly improves welding efficiency, shortens the welding time between branch pipes and sewage pipes, and improves the overall welding efficiency.
Smart Images

Figure CN118752111B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of welding a sewage pipe and multiple branch pipes together, in particular to a welding device and method for welding a sewage pipe and multiple branch pipes. Background Art
[0002] In the process of farmland wastewater treatment, farmland wastewater affected by non-point source pollution needs to be pumped through a sewage pipe into a designated treatment tank. Chemical reagents are then added to the treatment tank to treat the farmland wastewater. Because the flow area of the sewage pipe is fixed, the outflow volume of farmland wastewater is also fixed. As a result, it takes a long time to discharge farmland wastewater from farmland into the treatment tank, which reduces the discharge efficiency of farmland wastewater.
[0003] In order to solve the problem of low discharge efficiency, workers welded multiple branch pipes on a sewage pipe to increase the discharge volume of farmland sewage. The specific welding method is:
[0004] S1. The worker takes out a square tube with a rectangular cross section, punches out a plurality of left square grooves 1 on the left end face of the square tube along its length direction, and then punches out a plurality of right square grooves 2 on the right end face of the square tube along its length direction, and ensures that the right square grooves 2 are opposite to the left square grooves 1, thus processing the following: Figure 1~Figure 2 The sewage pipe 3 shown;
[0005] S2, workers take out a number of branch pipes 4 with rectangular cross sections, punch out a through groove 5 in the middle of each branch pipe 4, and thus process the following: Figure 3~Figure 4 Branch pipe 4 shown;
[0006] S3. The worker takes out a branch pipe 4 and passes it through the left square slot 1 and the right square slot 2 of the sewage pipe 3 from left to right, ensuring that the through slot 5 of the branch pipe 4 is connected to the inner cavity of the sewage pipe 3. The worker then uses the welding head of the welding machine to weld the contact seam between the branch pipe 4 and the right square slot 2, and then welds the contact seam between the branch pipe 4 and the left square slot 1, thus welding the first branch pipe 4 to the sewage pipe 3.
[0007] S4, the worker repeats the operation of step S3, thereby finally achieving welding of multiple branch pipes 4 on a sewage pipe 3, such as Figure 5 The figure shows a sewage pipe 3 and a plurality of branch pipes 4 welded together.
[0008] When in use, one end of the sewage pipe 3 is extended into the farmland, and the other end of the sewage pipe 3 is extended into the treatment pool, while ensuring that multiple branch pipes 4 are all in the treatment pool. At this time, the farmland sewage in the farmland is not only discharged into the treatment pool from the other end of the sewage pipe 3, but also discharged into the treatment pool from multiple branch pipes 4, thereby increasing the discharge volume of farmland sewage.
[0009] However, although this method can realize the welding of a sewage pipe 3 and multiple branch pipes 4, it still has the following technical defects:
[0010] I. In step S3, the branch pipe 4 needs to be manually inserted between the left square groove 1 and the right square groove 2, and then the welding machine needs to be manually operated to weld the contact seams between the branch pipe 4 and the left square groove 1 and the contact seams between the branch pipe 4 and the right square groove 2 together. The entire operation is done manually, which not only increases the workload of the workers, but also increases the welding time of the branch pipe 4 and the sewage pipe 3, thereby reducing the welding efficiency of the sewage pipe 3 and the multiple branch pipes 4.
[0011] II. Every time a worker installs a branch pipe 4 into the sewage pipe 3, he needs to weld the branch pipe 4 to the sewage pipe 3 using the welding head of the welding machine. The number of branch pipes 4 to be welded undoubtedly increases the welding process, further increases the welding time of the branch pipe 4 and the sewage pipe 3, and further reduces the welding efficiency of the sewage pipe 3 and multiple branch pipes 4.
[0012] Therefore, there is an urgent need for a welding device and method that can greatly reduce the workload of workers and greatly improve welding efficiency. Summary of the Invention
[0013] The purpose of the present invention is to overcome the shortcomings of the prior art and provide a welding device and method for welding sewage pipes and multi-branch pipes, which greatly reduces the workload of workers and greatly improves welding efficiency.
[0014] The object of the present invention is achieved by the following technical solutions: A welding device for welding a sewage pipe and a multi-branch pipe, comprising a workbench, a fixture mechanism for fixing the sewage pipe, a feeding mechanism for inserting a branch pipe into the sewage pipe, located on the left side of the fixture mechanism, and a welding mechanism, located on the right side of the fixture mechanism;
[0015] The tooling mechanism includes a stepper motor fixedly mounted on the bottom surface of the workbench, the output shaft of the stepper motor passes through the workbench upward, and a main shaft is connected to the extended end, a base is fixedly mounted on the top of the main shaft, a positioning groove is formed on the top surface of the base, and a locking screw is threadedly connected to the right side wall of the base;
[0016] The feeding mechanism includes a lifting cylinder fixedly arranged on the bottom surface of the workbench, the piston rod of the lifting cylinder passes through the workbench upward, and a U-shaped part is fixed on the extended end, a material basket is welded in the U-shaped part, the bottom of the material basket is closed, a lifting cylinder is fixed on the bottom surface of the material basket, the piston rod of the lifting cylinder passes through the bottom wall of the material basket and extends into the material basket, and a lifting plate is fixed on the active end of the piston rod of the lifting cylinder; a horizontal cylinder is fixed on the left side wall of the material basket, a bracket is fixed on the active end of the piston rod of the horizontal cylinder, a clamping cylinder is fixed on the bottom wall of the bracket, and the clamping head of the clamping cylinder is downward toward the opening of the material basket;
[0017] The welding mechanism includes a vertical plate fixed on the workbench and a feed cylinder fixed on the right end surface of the vertical plate. The piston rod of the feed cylinder passes through the vertical plate to the left, and a mounting plate is fixed on the extended end. A plurality of servo motors are fixed on the left end surface of the mounting plate at intervals along its height direction. A connecting frame is welded to the output shaft of each servo motor, and a welding head is fixed on the connecting frame. The other end of each welding head is connected to a welding machine.
[0018] A plurality of supporting legs supported on the ground are fixedly provided on the bottom surface of the workbench.
[0019] The positioning groove in the base matches the outer contour of the sewage pipe.
[0020] A threaded hole communicating with the positioning groove is provided in the inner side wall of the base, and the locking screw is threadedly connected in the threaded hole.
[0021] The inner cavity of the basket matches the outer contour of the branch pipe.
[0022] A fixing plate is fixed on the upper end portion of the left side wall of the basket, the cylinder barrel of the horizontal oil cylinder is fixed on the left end surface of the fixing plate, and the piston rod of the horizontal oil cylinder is arranged to the right through the fixing plate.
[0023] Each welding head is arranged tilted to the right and upward.
[0024] The welding device also includes a controller, which is electrically connected to the stepping motor, the horizontal oil cylinder, the clamping oil cylinder, the lifting oil cylinder, the feeding oil cylinder and the servo motor via signal lines.
[0025] A method for welding a sewage pipe and a manifold, comprising the following steps:
[0026] S1. A worker takes out a plurality of square tubes with rectangular cross-sections, punches out a plurality of left-sided square grooves on the left end surface of the square tubes at intervals along the length thereof, and then punches out a plurality of right-sided square grooves on the right end surface of the square tubes at intervals along the length thereof, ensuring that the right-sided square grooves are opposite to the left-sided square grooves, thereby processing a plurality of sewage pipes;
[0027] S2. Workers take out a number of branch pipes with rectangular cross-sections and punch out a through groove in the middle of each branch pipe to form the branch pipes;
[0028] S3. The worker places the processed branch pipes into the basket from the top port. During the placement process, ensure that the through slots of the branch pipes face upwards. When all the branch pipes are placed, the branch pipes at the bottom of the basket are just supported on the lifting plate, and the top surface of the branch pipes at the top of the basket is just flush with the top surface of the basket.
[0029] S4. Fixing the sewage pipe with fixture: The worker takes out the first sewage pipe and inserts the lower end of the sewage pipe into the positioning groove of the base of the fixture from top to bottom. The worker then tightens the locking screw, and the left end of the locking screw presses against the right end face of the sewage pipe, thus completing the fixture of the sewage pipe. At this time, the left square groove on the sewage pipe faces the feeding mechanism;
[0030] S5. Insert the topmost branch pipe in the basket into the sewage pipe. The specific operation steps are as follows:
[0031] S51, the piston rod of the lifting cylinder of the control feeding mechanism is extended upward, and the piston rod drives the lifting plate to move upward, and the lifting plate drives all the branch pipes in the material basket to move upward synchronously. When the piston rod of the lifting cylinder is extended to the set distance, the controller controls the lifting cylinder to close. At this time, the branch pipe on the top layer is just pushed out of the material basket and just enters the chuck of the clamping cylinder;
[0032] S52, controlling the clamping oil cylinder to start, closing the clamping head of the clamping oil cylinder, and clamping and fixing the branch pipe on the top layer;
[0033] S53. Control the piston rod of the horizontal cylinder to extend rightward. The piston rod drives the bracket to move rightward. The bracket drives the clamping cylinder to move rightward. The clamping cylinder drives the clamped branch pipe to move rightward. The branch pipe passes through the first left square slot and the first right square slot of the sewage pipe from left to right. When the piston rod of the horizontal cylinder extends to the set distance, the controller controls the horizontal cylinder to close. At this time, the through slot of the branch pipe is connected to the inner cavity of the sewage pipe, thereby finally completing the installation of the top branch pipe in the sewage pipe.
[0034] S6. The worker controls the clamping cylinder to close, and the chuck is separated from the branch pipe; then controls the piston rod of the horizontal cylinder to retract to the left, and the piston rod drives the clamping cylinder and the chuck to reset to the left; then controls the piston rod of the lifting cylinder to retract downward, and the piston rod drives the U-shaped piece to move downward, and the U-shaped piece drives the material basket to move downward, and the material basket drives the multiple branch pipes inside it to move downward synchronously. At the same time, the material basket also drives the horizontal cylinder, the clamping cylinder and the lifting cylinder to move downward synchronously; when the piston rod of the lifting cylinder retracts to the set stroke, the controller controls the lifting cylinder to close, and at this time, the feeding mechanism enters the second feeding station;
[0035] S7. The worker repeats steps S5 to S6 twice, thereby installing a branch pipe between the second left square groove and the second right square groove, and between the third left square groove and the third right square groove.
[0036] S8. Welding of the three branch pipes to the sewage pipe. The specific steps are as follows:
[0037] S81. The worker controls the piston rod of the welding mechanism's feed cylinder to extend leftward. The piston rod drives the mounting plate to the left, which in turn drives the three servo motors mounted thereon to the left. The servo motors drive the corresponding connecting brackets to the left, which in turn drives the corresponding welding heads to the left. When the piston rod of the feed cylinder is fully extended, the welding head is positioned close to the contact seam formed between the branch pipe and the right square groove.
[0038] S82. Turn on the welding machine connected to the welding head; then control the three servo motors to start, which drive the connecting frame to rotate, and the connecting frame drives the welding head to rotate. The welding head rotates around the axis of the servo motor. During the rotation process, the welding head welds the contact seam formed between the branch pipe and the right square groove, thereby welding the branch pipe and the right square groove into one.
[0039] S83. After the branch pipe and the right square groove of the sewage pipe are welded together, the worker first controls the servo motor and the welding machine to shut down. Then, the worker controls the piston rod of the feed cylinder to retract to the right. The piston rod drives the mounting plate to the right, which in turn drives the servo motors to the right, thereby resetting the welding head.
[0040] S84: The worker controls the stepper motor to start, which drives the main shaft to rotate, which in turn drives the base to rotate, which in turn drives the sewage pipe to rotate synchronously. When the sewage pipe rotates 180°, the controller controls the stepper motor to stop. At this point, the left square groove on the sewage pipe enters the welding station of the welding mechanism. The worker repeats steps S81 to S82 once, thereby welding the branch pipe to the left square groove, thereby finally achieving the goal of welding multiple branch pipes to the sewage pipe.
[0041] S9. After welding, the worker loosens the locking screws and then removes the sewage pipe and branch pipe welded together on the base.
[0042] The present invention has the following advantages: greatly reducing the work intensity of workers and greatly improving welding efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0043] Figure 1 This is the axonometric drawing of the sewage pipe;
[0044] Figure 2 for Figure 1 The main cross-sectional diagram of
[0045] Figure 3 This is the axonometric drawing of the branch pipe;
[0046] Figure 4 for Figure 3 The main cross-sectional diagram of
[0047] Figure 5 This is a schematic diagram of a sewage pipe and multiple branch pipes welded together;
[0048] Figure 6 It is a structural schematic diagram of the present invention;
[0049] Figure 7 for Figure 6 The main cross-sectional diagram of
[0050] Figure 8 It is a structural diagram of the tooling mechanism;
[0051] Figure 9 This is the axonometric drawing of the base;
[0052] Figure 10 for Figure 9 The main cross-sectional diagram of
[0053] Figure 11 It is a structural diagram of the feeding mechanism;
[0054] Figure 12 for Figure 11 AA cross-sectional view;
[0055] Figure 13 It is a schematic diagram of the connection between the basket and the U-shaped piece;
[0056] Figure 14 It is a structural diagram of the welding mechanism;
[0057] Figure 15 A schematic diagram of placing multiple branch pipes into a basket from its top port;
[0058] Figure 16 for Figure 15 BB cross-sectional view;
[0059] Figure 17 Schematic diagram for fixing the sewage pipe fixture;
[0060] Figure 18 This is a schematic diagram of the top-level branch pipe entering the chuck of the clamping cylinder;
[0061] Figure 19 for Figure 18 CC cross-sectional view;
[0062] Figure 20 Schematic diagram of the clamp holding the topmost branch pipe;
[0063] Figure 21 This is a schematic diagram of installing the top-level branch pipe inside the sewage pipe;
[0064] Figure 22 This is a schematic diagram of the feeding mechanism entering the second feeding station;
[0065] Figure 23 This is a schematic diagram of the second branch pipe in the basket being passed through the sewage pipe;
[0066] Figure 24 Schematic diagram for installing three branch pipes on the sewage pipe;
[0067] Figure 25 This is a schematic diagram of welding the branch pipe and the right square groove together;
[0068] Figure 26 for Figure 25 A partial enlarged view of part I;
[0069] Figure 27 This is a schematic diagram of welding the branch pipe to the left square groove;
[0070] In the picture:
[0071] 1-left square groove, 2-right square groove, 3-drain pipe, 4-branch pipe, 5-through groove;
[0072] 7- workbench, 8- tooling mechanism, 9- feeding mechanism, 10- welding mechanism, 11- stepping motor, 12- spindle, 13- base, 14- positioning slot, 15- locking screw;
[0073] 16-lifting cylinder, 17-U-shaped piece, 18-material basket, 19-lifting cylinder, 20-lifting plate, 21-horizontal cylinder, 22-bracket, 23-clamping cylinder, 24-chuck;
[0074] 25-vertical plate, 26-feed cylinder, 27-mounting plate, 28-servo motor, 29-connecting frame, 30-welding head, 31-fixed plate. DETAILED DESCRIPTION
[0075] The present invention will be further described below with reference to the accompanying drawings, and the protection scope of the present invention is not limited to the following:
[0076] like Figures 6 to 14As shown, a welding device for welding a sewage pipe and a multi-branch pipe comprises a workbench 7, on which a fixture mechanism 8 for fixing the sewage pipe 3 is provided, a feeding mechanism 9 for inserting the branch pipe 4 into the sewage pipe 3 is provided on the left side of the fixture mechanism 8 on the workbench 7, and a welding mechanism 10 is provided on the right side of the fixture mechanism 8 on the workbench 7; a plurality of support legs supported on the ground are fixed on the bottom surface of the workbench 7.
[0077] The fixture mechanism 8 includes a stepper motor 11 fixed to the bottom surface of the workbench 7. The output shaft of the stepper motor 11 extends upward through the workbench 7, and a spindle 12 is connected to the extended end. A base 13 is fixed to the top of the spindle 12. A positioning groove 14 is defined on the top surface of the base 13, and a locking screw 15 is threadedly connected to the right side wall of the base 13. The positioning groove 14 in the base 13 matches the outer contour of the sewage pipe 3. A threaded hole is defined in the inner side wall of the base 13, which communicates with the positioning groove 14, and the locking screw 15 is threadedly connected to the threaded hole.
[0078] The feeding mechanism 9 includes a lifting cylinder 16 fixed on the bottom surface of the workbench 7, the piston rod of the lifting cylinder 16 passes through the workbench 7 upward, and a U-shaped part 17 is fixed on the extended end, a material basket 18 is welded in the U-shaped part 17, the bottom of the material basket 18 is closed, and a lifting cylinder 19 is fixed on the bottom surface of the material basket 18, the piston rod of the lifting cylinder 19 passes through the bottom wall of the material basket 18 and extends into the material basket 18, and a lifting plate 20 is fixed on the active end of the piston rod of the lifting cylinder 19; a horizontal cylinder 21 is fixed on the left side wall of the material basket 18, a bracket 22 is fixed on the active end of the piston rod of the horizontal cylinder 21, a clamping cylinder 23 is fixed on the bottom wall of the bracket 22, and the clamping head 24 of the clamping cylinder 23 is downward toward the opening of the material basket 18; the inner cavity of the material basket 18 is matched with the outer contour of the branch pipe 4. A fixing plate 31 is fixed on the upper end of the left side wall of the basket 18 , the cylinder barrel of the horizontal oil cylinder 21 is fixed on the left end surface of the fixing plate 31 , and the piston rod of the horizontal oil cylinder 21 is arranged to penetrate the fixing plate 31 to the right.
[0079] The welding mechanism 10 includes a vertical plate 25 fixed on the workbench 7, a feed cylinder 26 fixed on the right end surface of the vertical plate 25, the piston rod of the feed cylinder 26 passes through the vertical plate 25 to the left, and a mounting plate 27 is fixed on the extended end, and a plurality of servo motors 28 are fixed on the left end surface of the mounting plate 27 at intervals along its height direction, and a connecting frame 29 is welded to the output shaft of each servo motor 28, and a welding head 30 is fixed on the connecting frame 29, each welding head 30 is tilted to the right and upward, and the other end of each welding head 30 is connected to a welding machine.
[0080] The welding device also includes a controller, which is electrically connected to the stepper motor 11, the horizontal cylinder 21, the clamping cylinder 23, the lifting cylinder 19, the feed cylinder 26 and the servo motor 28 via a signal line. Workers can use the controller to control the extension or retraction of the piston rods of the horizontal cylinder 21, the lifting cylinder 19 and the feed cylinder 26, and can also control the start or stop of the stepper motor 11, the clamping cylinder 23 and the servo motor 28, which facilitates the workers' operation and has the characteristics of a high degree of automation.
[0081] A method for welding a sewage pipe and a manifold, comprising the following steps:
[0082] S1. The worker takes out a plurality of square tubes with rectangular cross sections, and punches out a plurality of left square grooves 1 on the left end surface of the square tube along its length direction, and then punches out a plurality of right square grooves 2 on the right end surface of the square tube along its length direction, and ensures that the right square grooves 2 are opposite to the left square grooves 1, thereby processing a plurality of square tubes as follows: Figure 1~Figure 2 The sewage pipe 3 shown;
[0083] S2, workers take out a number of branch pipes 4 with rectangular cross sections, punch out a through groove 5 in the middle of each branch pipe 4, and thus process the following: Figure 3~Figure 4 Branch pipe 4 shown;
[0084] S3, workers put the processed multiple branch pipes 4 into the basket 18 from the top port, as shown in FIG. Figure 15-16 As shown, during the insertion process, ensure that the through slots 5 of the branch pipes 4 face upwards; after all the branch pipes 4 are inserted, the branch pipes 4 at the bottom layer of the basket 18 are just supported on the lifting plate 20, and at the same time, the top surface of the branch pipes 4 at the top layer of the basket 18 is just flush with the top surface of the basket 18;
[0085] S4. Fixing the sewage pipe 3: The worker takes out the first sewage pipe 3 and inserts the lower end of the sewage pipe 3 into the positioning groove 14 of the base 13 of the fixture mechanism 8 from top to bottom. Then the worker tightens the locking screw 15. The left end of the locking screw 15 presses against the right end surface of the sewage pipe 3, thereby achieving the fixture fixation of the sewage pipe 3. Figure 17 As shown, at this time, the left square groove 1 on the sewage pipe 3 faces the feeding mechanism 9;
[0086] S5. Insert the topmost branch pipe 4 in the basket 18 into the sewage pipe 3. The specific operation steps are as follows:
[0087] S51, control the piston rod of the jacking cylinder 19 of the feeding mechanism 9 to extend upward, the piston rod drives the jacking plate 20 to move upward, and the jacking plate 20 drives all the branch pipes 4 in the basket 18 to move upward synchronously. When the piston rod of the jacking cylinder 19 extends to the set distance, the controller controls the jacking cylinder 19 to close. At this time, the branch pipe 4 on the top layer is just pushed out to the outside of the basket 18 and just enters the chuck 24 of the clamping cylinder 23, as shown in FIG. Figure 18-19 As shown;
[0088] S52, control the clamping oil cylinder 23 to start, the clamping head 24 of the clamping oil cylinder 23 is closed, and the clamping head 24 clamps and fixes the top branch pipe 4, such as Figure 20 As shown;
[0089] S53, control the piston rod of the horizontal oil cylinder 21 to extend to the right, the piston rod drives the bracket 22 to move to the right, the bracket 22 drives the clamping oil cylinder 23 to move to the right, the clamping oil cylinder 23 drives the clamped branch pipe 4 to move to the right, and the branch pipe 4 passes through the first left square slot 1 and the first right square slot 2 of the sewage pipe 3 from left to right. When the piston rod of the horizontal oil cylinder 21 extends to the set distance, the controller controls the horizontal oil cylinder 21 to close. At this time, the through slot 5 of the branch pipe 4 is just connected to the inner cavity of the sewage pipe 3, thereby finally realizing the topmost branch pipe 4 to be passed through the sewage pipe 3, as shown in FIG. Figure 21 As shown;
[0090] S6, the worker controls the clamping cylinder 23 to close, and the chuck 24 is separated from the branch pipe 4; then controls the piston rod of the horizontal cylinder 21 to retract to the left, and the piston rod drives the clamping cylinder 23 and the chuck 24 to reset to the left; then controls the piston rod of the lifting cylinder 16 to retract downward, and the piston rod drives the U-shaped part 17 to move downward, and the U-shaped part 17 drives the material basket 18 to move downward, and the material basket 18 drives the multiple branch pipes 4 therein to move downward synchronously. At the same time, the material basket 18 also drives the horizontal cylinder 21, the clamping cylinder 23 and the lifting cylinder 19 to move downward synchronously; when the piston rod of the lifting cylinder 16 retracts to the set stroke, the controller controls the lifting cylinder 16 to close. At this time, the feeding mechanism 9 enters the second feeding station, as shown in FIG. Figure 22 As shown;
[0091] S7, the worker repeats the operation of steps S5-S6 twice, thereby installing a branch pipe 4 between the second left square groove 1 and the second right square groove 2, and between the third left square groove 1 and the third right square groove 2. Figure 23-24 As shown;
[0092] S8, welding of the three branch pipes 4 and the sewage pipe 3, the specific operation steps are as follows:
[0093] S81. The worker controls the piston rod of the feed cylinder 26 of the welding mechanism 10 to extend leftward. The piston rod drives the mounting plate 27 to move leftward. The mounting plate 27 drives the three servo motors 28 thereon to move leftward. The servo motors 28 drive the corresponding connecting frames 29 to move leftward. The connecting frames 29 drive the corresponding welding heads 30 to move leftward. When the piston rod of the feed cylinder 26 is fully extended, the welding head 30 is just close to the contact gap formed between the branch pipe 4 and the right square groove 2.
[0094] S82, turn on the welding machine connected to the welding head 30; then control the three servo motors 28 to start, the servo motors 28 drive the connecting frame 29 to rotate, the connecting frame 29 drives the welding head 30 to rotate, and the welding head 30 rotates around the axis of the servo motor 28. During the rotation process, the welding head 30 welds the contact seam formed between the branch pipe 4 and the right square groove 2, thereby welding the branch pipe 4 and the right square groove 2 into one body. Figure 25-26 As shown;
[0095] S83. After the branch pipe 4 is welded to the right square groove 2 of the sewage pipe 3, the worker first controls the servo motor 28 and the welding machine to shut down. Then, the worker controls the piston rod of the feed cylinder 26 to retract rightward. The piston rod drives the mounting plate 27 to move rightward, and the mounting plate 27 drives each servo motor 28 to move rightward, thereby resetting the welding head 30.
[0096] S84, the worker controls the stepper motor 11 to start, the stepper motor 11 drives the main shaft 12 to rotate, the main shaft 12 drives the base 13 to rotate, and the base 13 drives the sewage pipe 3 to rotate synchronously. When the sewage pipe 3 rotates 180 degrees, the controller controls the stepper motor 11 to turn off. At this time, the left square groove 1 on the sewage pipe 3 enters the welding station of the welding mechanism 10; the worker repeats the operations of steps S81 to S82 once, thereby welding the branch pipe 4 and the left square groove 1 into one body. Figure 27 As shown, the multiple branch pipes 4 are finally welded to the sewage pipe 3, and the structure after welding is as shown in FIG. Figure 5 As shown;
[0097] Among them, from steps S5 to S8, it can be seen that the present welding device first continuously and automatically inserts the multiple branch pipes 4 in the material basket 18 into the sewage pipe 3 in sequence through the linkage of the jacking cylinder 19, the clamping cylinder 23, the horizontal cylinder 21, and the lifting cylinder 16 of the feeding mechanism 9; then, through the linkage of the feed cylinder 26 and the servo motor 28 of the welding mechanism 10, the multiple branch pipes 4 are automatically welded to the sewage pipe 3. It can be seen that the present welding device automatically inserts the multiple branch pipes 4 into the sewage pipe 3 and automatically welds the multiple branch pipes 4 to the sewage pipe 3. Compared with traditional welding methods, the present welding device does not require manual operation, which not only greatly reduces the workload of workers, but also shortens the welding time of the multiple branch pipes 4 and the sewage pipe 3, thereby greatly improving the welding efficiency of the multiple branch pipes 4 and the sewage pipe 3.
[0098] Furthermore, as can be seen from step S8, the present welding device can weld the branch pipe 4 to the right square groove 2 and the left square groove 1 together through the welding mechanism 10, thereby automatically welding multiple branch pipes 4 to the sewage pipe 3 at one time. It can be seen that, compared to traditional manual welding methods, the present welding device greatly reduces the welding process, thereby shortening the welding time of the branch pipe 4 and the sewage pipe 3, and further greatly improving the welding efficiency of the sewage pipe 3 and multiple branch pipes 4.
[0099] S9. After welding, the worker loosens the locking screw 15 and then removes the sewage pipe 3 and the branch pipe 4 welded together on the base 13.
[0100] Finally, it should be noted that the above descriptions are merely preferred embodiments of the present invention and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art will be able to modify the technical solutions described in the aforementioned embodiments or substitute equivalents for some of the technical features. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention shall be included within the scope of protection of the present invention.
Claims
1. A method for welding a sewage pipe and a multi-branch pipe, the method using a welding device for welding a sewage pipe and a multi-branch pipe, the welding device comprising a workbench (7), the workbench (7) being provided with a tooling mechanism (8) for tooling and fixing the sewage pipe (3), a feeding mechanism (9) for inserting a branch pipe (4) into the sewage pipe (3) being provided on the left side of the tooling mechanism (8) on the workbench (7), and a welding mechanism (10) being provided on the right side of the tooling mechanism (8) on the workbench (7); The tooling mechanism (8) comprises a stepper motor (11) fixedly mounted on the bottom surface of the workbench (7), the output shaft of the stepper motor (11) passing through the workbench (7) upwards, and a main shaft (12) is connected to the extended end, a base (13) is fixedly mounted on the top of the main shaft (12), a positioning groove (14) is formed on the top surface of the base (13), and a locking screw (15) is threadedly connected to the right side wall of the base (13); The feeding mechanism (9) comprises a lifting cylinder (16) fixedly arranged on the bottom surface of the workbench (7), the piston rod of the lifting cylinder (16) passing through the workbench (7) upwards, and a U-shaped part (17) is fixedly arranged on the extended end, a material basket (18) is welded inside the U-shaped part (17), the bottom of the material basket (18) is closed, a lifting cylinder (19) is fixedly arranged on the bottom surface of the material basket (18), the piston rod of the lifting cylinder (19) passes through the bottom wall of the material basket (18) and extends into the material basket (18), and a lifting plate (20) is fixedly arranged on the active end of the piston rod of the lifting cylinder (19); a horizontal cylinder (21) is fixedly arranged on the left side wall of the material basket (18), a bracket (22) is fixedly arranged on the active end of the piston rod of the horizontal cylinder (21), a clamping cylinder (23) is fixedly arranged on the bottom wall of the bracket (22), and a clamping head (24) of the clamping cylinder (23) faces downward toward the opening of the material basket (18); The welding mechanism (10) comprises a vertical plate (25) fixedly mounted on a workbench (7), and a feed oil cylinder (26) fixedly mounted on a right end surface of the vertical plate (25); a piston rod of the feed oil cylinder (26) penetrates the vertical plate (25) to the left, and a mounting plate (27) is fixedly mounted on the extended end; a plurality of servo motors (28) are fixedly mounted on the left end surface of the mounting plate (27) at intervals in the height direction thereof; a connecting frame (29) is welded to the output shaft of each servo motor (28); a welding head (30) is fixedly mounted on the connecting frame (29); and the other end of each welding head (30) is connected to a welding machine; A plurality of supporting legs supported on the ground are fixedly provided on the bottom surface of the workbench (7); a positioning groove (14) in the base (13) matches the outer contour of the sewage pipe (3); a threaded hole connected to the positioning groove (14) is provided in the inner side wall of the base (13), and the locking screw (15) is threadedly connected in the threaded hole; the inner cavity of the material basket (18) matches the outer contour of the branch pipe (4); a fixing plate is fixedly provided on the upper end of the left side wall of the material basket (18); (31), the cylinder barrel of the horizontal oil cylinder (21) is fixedly arranged on the left end surface of the fixed plate (31), and the piston rod of the horizontal oil cylinder (21) is arranged to penetrate the fixed plate (31) to the right; each welding head (30) is arranged to tilt upward to the right; the welding device also includes a controller, and the controller is electrically connected to the stepping motor (11), the horizontal oil cylinder (21), the clamping oil cylinder (23), the lifting oil cylinder (19), the feeding oil cylinder (26) and the servo motor (28) via a signal line, characterized in that: It includes the following steps: S1. A worker takes out a plurality of square tubes with rectangular cross-sections, punches out a plurality of left-side square grooves (1) at intervals along the length direction of the square tube on the left end surface, and then punches out a plurality of right-side square grooves (2) at intervals along the length direction of the square tube on the right end surface, and ensures that the right-side square grooves (2) and the left-side square grooves (1) are opposite to each other on the left and right, thereby processing a plurality of sewage pipes (3); S2, the worker takes out a plurality of branch pipes (4) with rectangular cross-sections, and punches out a through groove (5) in the middle of each branch pipe (4), thereby processing the branch pipe (4); S3, the worker places the processed multiple branch pipes (4) into the material basket (18) from the top port thereof, and during the placing process, ensures that the through slots (5) of the branch pipes (4) face upwards; when all the multiple branch pipes (4) are placed, the branch pipes (4) at the bottom layer of the material basket (18) are just supported on the lifting plate (20), and at the same time, the top surface of the branch pipes (4) at the top layer of the material basket (18) is just flush with the top surface of the material basket (18); S4, fixture fixing of the sewage pipe (3): the worker takes out the first sewage pipe (3), and inserts the lower end of the sewage pipe (3) from top to bottom into the positioning groove (14) of the base (13) of the fixture mechanism (8), and then the worker tightens the locking screw (15), and the left end of the locking screw (15) presses against the right end surface of the sewage pipe (3), thereby achieving fixture fixing of the sewage pipe (3). At this time, the left square groove (1) on the sewage pipe (3) faces the feeding mechanism (9); S5. Insert the branch pipe (4) at the top layer in the material basket (18) into the sewage pipe (3). The specific operation steps are as follows: S51, controlling the piston rod of the lifting cylinder (19) of the feeding mechanism (9) to extend upward, the piston rod drives the lifting plate (20) to move upward, and the lifting plate (20) drives all the branch pipes (4) in the material basket (18) to move upward synchronously. When the piston rod of the lifting cylinder (19) extends to a set distance, the controller controls the lifting cylinder (19) to close. At this time, the branch pipe (4) at the top layer is just pushed out to the outside of the material basket (18) and just enters the clamping head (24) of the clamping cylinder (23); S52, controlling the clamping cylinder (23) to start, the clamping head (24) of the clamping cylinder (23) to close, and the clamping head (24) clamps and fixes the branch pipe (4) at the top layer; S53, control the piston rod of the horizontal oil cylinder (21) to extend to the right, the piston rod drives the bracket (22) to move to the right, the bracket (22) drives the clamping oil cylinder (23) to move to the right, the clamping oil cylinder (23) drives the clamped branch pipe (4) to move to the right, the branch pipe (4) passes through the first left square groove (1) and the first right square groove (2) of the sewage pipe (3) from left to right in sequence, when the piston rod of the horizontal oil cylinder (21) extends to the set distance, the controller controls the horizontal oil cylinder (21) to close, at this time, the through groove (5) of the branch pipe (4) is just connected to the inner cavity of the sewage pipe (3), so that the topmost branch pipe (4) is finally inserted into the sewage pipe (3); S6, the worker controls the clamping cylinder (23) to close, and the clamp (24) is separated from the branch pipe (4); then the piston rod of the horizontal cylinder (21) is controlled to retract to the left, and the piston rod drives the clamping cylinder (23) and the clamp (24) to return to the left; then the piston rod of the lifting cylinder (16) is controlled to retract downward, and the piston rod drives the U-shaped member (17) to move downward, and the U-shaped member (17) drives the material basket (18) to move downward, and the material basket (18) drives the multiple branch pipes (4) therein to move downward synchronously. At the same time, the material basket (18) also drives the horizontal cylinder (21), the clamping cylinder (23) and the lifting cylinder (19) to move downward synchronously; when the piston rod of the lifting cylinder (16) is retracted to the set stroke, the controller controls the lifting cylinder (16) to close, and at this time, the feeding mechanism (9) enters the second feeding station; S7, the worker repeats the operations of steps S5 to S6 twice, thereby installing a branch pipe (4) between the second left square groove (1) and the second right square groove (2), and between the third left square groove (1) and the third right square groove (2); S8. Welding of the three branch pipes (4) and the sewage pipe (3). The specific operation steps are as follows: S81. The worker controls the piston rod of the feed cylinder (26) of the welding mechanism (10) to extend to the left, and the piston rod drives the mounting plate (27) to move to the left. The mounting plate (27) drives the three servo motors (28) thereon to move to the left. The servo motors (28) drive the corresponding connecting frame (29) to move to the left. The connecting frame (29) drives the corresponding welding head (30) to move to the left. When the piston rod of the feed cylinder (26) is fully extended, the welding head (30) is just close to the contact seam formed between the branch pipe (4) and the right square groove (2). S82, turning on the welding machine connected to the welding head (30); then controlling the three servo motors (28) to start, the servo motors (28) drive the connecting frame (29) to rotate, the connecting frame (29) drives the welding head (30) to rotate, the welding head (30) rotates around the axis of the servo motor (28), and during the rotation process, the welding head (30) welds the contact seam formed between the branch pipe (4) and the right square groove (2), thereby welding the branch pipe (4) and the right square groove (2) into one body; S83. After the branch pipe (4) and the right square groove (2) of the sewage pipe (3) are welded together, the worker first controls the servo motor (28) and the welding machine to be turned off, and then controls the piston rod of the feed cylinder (26) to retract to the right, so that the piston rod drives the mounting plate (27) to move to the right, and the mounting plate (27) drives each servo motor (28) to move to the right, thereby resetting the welding head (30); S84, the worker controls the stepper motor (11) to start, the stepper motor (11) drives the main shaft (12) to rotate, the main shaft (12) drives the base (13) to rotate, and the base (13) drives the sewage pipe (3) to rotate synchronously. When the sewage pipe (3) rotates 180 degrees, the controller controls the stepper motor (11) to turn off. At this time, the left square groove (1) on the sewage pipe (3) enters the welding position of the welding mechanism (10); the worker repeats the operation of steps S81 to S82 once, thereby welding the branch pipe (4) and the left square groove (1) into one body, thereby finally realizing the welding of multiple branch pipes (4) to the sewage pipe (3); S9. After welding, the worker loosens the locking screw (15) and then removes the sewage pipe (3) and the branch pipe (4) welded together on the base (13).