Method for installing cantilever beam on self-elevating drilling platform wharf

By utilizing floating cranes and skidding system mechanisms on jack-up drilling platforms, efficient installation of cantilever beams is achieved, which solves the problems of long installation time and low accuracy in the existing technology, and improves production efficiency and installation accuracy. sex.

CN118774099APending Publication Date: 2024-10-15SHANGHAI WAIGAOQIAO SHIP BUILDING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411143586.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-20
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

In the existing technology, the installation method of the cantilever beam of the self-elevating drilling platform has the problem that the sliding installation requires the debugging of the lifting system to be completed and the floating crane occupies the dock for a long time, which affects the construction of other projects.

Method used

The G-shaped structure is composed of a dock, a construction platform, a downstream dock and an upstream dock. The floating crane, anchor ropes and cables are used to control the cantilever beam section to be lifted from the construction platform and slid to the drilling platform. The installation is completed through the sliding system mechanism. Avoid lifting system debugging and long-term occupation of the dock.

Benefits of technology

It improves the production pace, shortens the cantilever beam installation time, avoids time conflicts with other projects, ensures installation accuracy, and avoids installation errors caused by windy weather.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774099A_ABST
    Figure CN118774099A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of cantilever beam installation, and discloses a self-elevating drilling platform wharf cantilever beam installation method which comprises the following steps: S1, hoisting preparation; s2, starting to hoist; s3, floating crane ship moving; s4, moving the ship in place; s5, starting hoisting; and S6, hoisting is completed. According to the design method for the wharf installation cantilever beam of the self-elevating drilling platform, the problems that the main hull part cannot be lifted to the required height and the cantilever beam cannot slide to the main hull in a sliding mode when installation is carried out in a dock and a pile leg lifting system and a locking system are not debugged are solved; and through a floating crane hoisting mode, a floating crane needs to enter a dock, the time of occupying the dock is long, and the construction of other projects is influenced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of cantilever beam installation, in particular to a method for installing a cantilever beam on a jack-up drilling platform wharf. Background Art

[0002] The cantilever beam is one of the important components of the offshore jack-up drilling platform. The use of the cantilever beam has significantly improved the performance of the jack-up drilling platform, greatly increasing the number of drilling operations on the platform and the flexibility of platform operation. During the use of the cantilever beam, it is required to carry drilling equipment including the drilling tower, and be able to withstand the drilling operation load of the lateral movement of the drilling platform. Therefore, the cantilever beam has high construction precision requirements and is difficult to build. It is one of the most critical parts of the entire construction platform.

[0003] The cantilever beam of a jack-up drilling platform is usually installed in a dock. One method is to slide the cantilever beam onto the main hull by sliding. If the pile leg lifting system and the locking system are not debugged, the main hull cannot be lifted to the required height and the cantilever beam cannot be slid onto the main hull by sliding. Another method is to install it by floating crane. However, in this installation method, the floating crane needs to enter the dock, which will occupy the dock for a long time and affect the construction of other projects. Therefore, a method of installing the cantilever beam at the shipyard dock is needed. Summary of the invention

[0004] In view of the shortcomings of the prior art, the present invention provides a method for installing a cantilever beam on a pier of a self-elevating drilling platform, which solves the problems mentioned in the above background.

[0005] The present invention provides the following technical solutions: a method for installing a cantilever beam at a jack-up drilling platform wharf, wherein a mechanism for installing the cantilever beam comprises: a dock, a construction platform, a downstream wharf and an upstream wharf, wherein the dock, the construction platform, the downstream wharf and the upstream wharf are connected as a whole to form a G-shaped structure, and the dock, the construction platform, the downstream wharf and the upstream wharf enclose a space to form a harbor, a flood prevention wall is built in front of the construction platform, a dock exit door is reserved in front of the dock and is connected to the harbor, a cantilever beam section is placed on the construction platform, a floating crane is floated in the harbor, an anchor rope and a first cable are respectively arranged on the floating crane, a civilian ship berthing waters are reserved in the front area of ​​the downstream wharf, a tugboat is tied to the side of the floating crane, and the cantilever beam section is suspended at the bow of the floating crane;

[0006] A drilling platform is floating in a section of water in front of the downstream wharf away from the harbor, and the drilling platform is hung on the pile of the downstream wharf by a second cable. A port wharf is arranged in a section of water separated from the end of the downstream wharf, and a sliding system mechanism is arranged on the drilling platform;

[0007] The method for installing the cantilever beam includes the following steps:

[0008] S1, preparation for hoisting: before hoisting, place the cantilever beam section on the construction platform near the flood control wall, with the centerline of the cantilever beam section at an angle of 28° to the flood control wall. Complete the installation of the cantilever beam section support on the construction platform, so that the tail end of the cantilever beam section on the starboard side of the slideway board is 1.6 meters away from the flood control wall, and the tail end of the port side of the slideway board is 5.1 meters away from the gantry crane track on the side of the construction platform;

[0009] S2, start lifting: drive the floating crane into the harbor, throw out two anchor ropes in a figure eight shape at the stern, tie the first cable at the bow to the harbor pier, adjust the position of the floating crane so that the hull of the floating crane forms an angle of 62° with the dock gate pier, the starboard bow is 2.2 meters away from the dock gate, the port side is 4.7 meters away from the end of the downstream pier, and the starboard stern is 28.1 meters away from the end of the upstream pier, tighten the anchor rope and the first cable, fix the position of the floating crane, and then lift;

[0010] S3, floating crane moving ship: by winching up the first cable and the elastic anchor rope, the floating crane is moved horizontally to the upstream wharf, a tugboat is set to be tied to the floating crane, and then the floating crane is untied and anchored, and the tugboat cooperates to turn the floating crane and tow it to the waters where the drilling platform is located;

[0011] S4, moving the ship into position: use three tugboats to tow the floating crane to the designated position, make the centerline of the floating crane hull perpendicular to the centerline of the drilling platform, the bow of the floating crane is 50.2 meters away from the centerline of the drilling platform, and the centerline of the floating crane hull is 10 meters away from the stern of the drilling platform. The first cable in the middle of the bow of the floating crane is tied to the stern bollard on the starboard side of the drilling platform, the first cable on the left side of the bow is tied to the port pier bollard, and the first cable on the right side of the bow is tied to the downstream pier bollard. The bow and stern of the floating crane are anchored outwards respectively;

[0012] S5, hoisting starts: after the floating crane has finished anchoring and cable laying, the position of the floating crane is adjusted to meet the installation conditions through the anchor winch and the mooring winch, and the 22.5-meter-long section of the cantilever beam can be directly dropped into the corresponding position at the rear of the drilling platform deck surface. The cantilever beam section and the drilling platform are connected by the sliding system mechanism, and the cantilever beam section is controlled to slide on the drilling platform;

[0013] S6, lifting completion: After the cantilever beam section is fully in place, a temporary fixing plate is immediately welded between the edge of the slideway plate and the support, the cantilever beam section is locked, and the floating crane is unhooked and moved out.

[0014] Preferably, the civilian ship berthing waters are within 150 meters in front of the downstream wharf, and the floating crane ship moving route surrounds the periphery of the civilian ship berthing waters.

[0015] Preferably, the S2, starting lifting includes: the floating crane vessel includes a floating vessel body, a boom frame is provided on the floating vessel body, a front main hook and a rear main hook are respectively hung at the ends of the boom frame, and the front main hook and the rear main hook are respectively suspended on the left and right sides of the cantilever beam total section.

[0016] Preferably, before the floating crane is lifted, it is necessary to check the layout of the cantilever beam section and confirm that the lifting horse has passed the flaw detection. The front main hook and the rear main hook are located directly above the four groups of lifting ears of the cantilever beam section. The front main hook and the rear main hook are pre-hung with designated wire ropes and shackles, which are connected to the lifting ears on the cantilever beam section. After the cantilever beam section is lifted, its bottom is 5 meters above the top of the flood control wall.

[0017] Preferably, the S3, floating crane ship moving includes: the number of the tugboats is three, two of which enter the harbor when the floating crane is pulled toward the upstream wharf, and are respectively tied to the bow and stern of the port side of the floating crane to cooperate in the ship moving, and then according to the tide conditions on the day of the operation, when the floating crane exits the harbor, a tugboat is arranged at the bow or stern of the starboard side of the floating crane to cooperate in the ship moving.

[0018] Preferably, the S4, moving the ship into position, comprises: before moving the ship into position, arranging thirteen second cables on the drilling platform and sequentially tying them to the piles of the downstream wharf.

[0019] Preferably, the S5, the start of lifting includes: the sliding system mechanism includes a base, the base is installed on the drilling platform, the end of the base is provided with a sliding system mechanism, a steel strand is pulled on the sliding system mechanism, a clamping plate is provided at one end of the steel strand away from the through-core cylinder, and the clamping plate is installed on the cantilever beam total section.

[0020] Preferably, the cantilever beam overall section includes a bulkhead, a climbing frame is provided on the outer edge of the bulkhead, a mounting hole is opened on the climbing frame, and the clamping plate is installed on the mounting hole by means of a latch.

[0021] Preferably, S5, the start of lifting includes: the cantilever beam section slides 33.746 meters toward the bow of the drilling platform, the floating crane always maintains a certain force during the traction process, and the position of the floating crane is continuously adjusted by setting an anchor machine and a mooring machine, so that the floating crane moves synchronously with the cantilever beam section toward the bow of the drilling platform.

[0022] Preferably, the S5, the start of lifting includes: when the cantilever beam section is towed and slid, a total station and a positioning plumb line are used to confirm that the longitudinal axis is aligned with the longitudinal center line of the floating crane, the lateral error is ≯2.5mm, and the monitoring data is reported to the commander.

[0023] Compared with the prior art, the present invention has the following beneficial effects:

[0024] 1. The design method for installing the cantilever beam at the dock of the self-elevating drilling platform utilizes the lifting capacity of the floating crane to lift the cantilever beam section to the height of the drilling platform, and then uses the anchor rope and the first cable to control the position of the floating crane when the cantilever beam section slides. The cantilever beam section can be directly slid onto the main hull of the drilling platform to complete the installation without the need for the lifting system to be debugged, thereby improving the production rhythm.

[0025] 2. The design method of installing the cantilever beam on the wharf of the self-elevating drilling platform is to use a floating crane to lift the cantilever beam section placed on the construction platform, and transport it across the water to the wharf in the area where the drilling platform is located for installation. There is no need to occupy the dock for a long time. After the cantilever beam section is built, it can be directly placed on the construction platform. Other construction platforms can be used normally, and only the dock needs to be used briefly during the lifting, which will not affect the construction of other projects.

[0026] 3. The cantilever beam design method for installing the self-elevating drilling platform at the dock will not occupy the dock for a long time, so there is no need to conflict with the construction time of other construction projects. Therefore, the lifting time can be freely selected, and then the weather with low wind speed can be selected for lifting, which effectively avoids the situation where the dock is occupied for a long time and the installation must be carried out in strong winds, eliminates installation errors, and enables the subsequent engineering commissioning and construction to proceed normally. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 This is a schematic diagram of the lifting structure of the floating crane of the present invention;

[0028] Figure 2 This is a schematic diagram of the structure of moving a ship out of a harbor according to the present invention;

[0029] Figure 3 This is a schematic diagram of the structure of moving a ship out of a harbor according to the present invention;

[0030] Figure 4 This is a schematic diagram of the ship moving route structure of the present invention;

[0031] Figure 5 This is a schematic diagram of the floating crane in place structure of the present invention;

[0032] Figure 6 This is a schematic diagram of the cantilever beam overall section hoisting structure of the present invention;

[0033] Figure 7 It is a schematic diagram of the sliding structure of the cantilever beam overall section of the present invention;

[0034] Figure 8 This is a schematic diagram of the top view of the cantilever beam assembly of the present invention;

[0035] Fig. 9 It is a schematic diagram of the overall structure of the cantilever beam of the present invention;

[0036] Fig.10 It is a schematic diagram of the structure of the sliding system mechanism of the present invention.

[0037] In the figure: 1. Dock; 2. Construction platform; 3. Downstream wharf; 4. Floating crane; 41. Floating vessel body; 42. Boom frame; 43. Front main hook; 44. Rear main hook; 5. Cantilever beam section; 51. Bulkhead; 52. Climbing frame; 53. Mounting hole; 6. First cable; 7. Harbor; 8. Anchor rope; 9. Flood control wall; 10. Dock door; 11. Berthing area for civilian ships; 12. Tugboat; 13. Drilling platform; 14. Second cable; 15. Port wharf; 16. Sliding system mechanism; 161. Base; 162. Through-core cylinder; 163. Steel strand; 164. Pallet; 165. Latch; 17. Upstream wharf. DETAILED DESCRIPTION

[0038] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0039] See also Figure 1-10 , a method for installing a cantilever beam at a jack-up drilling platform wharf, wherein a mechanism for installing the cantilever beam comprises: a dock 1, a construction platform 2, a downstream wharf 3 and an upstream wharf 17, wherein the dock 1, the construction platform 2, the downstream wharf 3 and the upstream wharf 17 are connected as a whole to form a G-shaped structure, and the dock 1, the construction platform 2, the downstream wharf 3 and the upstream wharf 17 enclose a space to form a harbor 7, a flood prevention wall 9 is built in front of the construction platform 2, a dock exit door 10 is reserved in front of the dock 1 and is connected to the harbor 7, a cantilever beam section 5 is placed on the construction platform 2, a floating crane 4 is floating in the harbor 7, an anchor rope 8 and a first cable 6 are respectively arranged on the floating crane 4, a civilian ship berthing water area 11 is reserved in the front area of ​​the downstream wharf 3, a tugboat 12 is tied to the side of the floating crane 4, and the cantilever beam section 5 is suspended at the bow of the floating crane 4;

[0040] A drilling platform 13 is floating in a section of water in front of the downstream wharf 3 away from the harbor 7. The drilling platform 13 is hung on the pile of the downstream wharf 3 by a second cable 14. A port wharf 15 is set in a section of water separated from the end of the downstream wharf 3. A sliding system mechanism 16 is set on the drilling platform 13.

[0041] The method for installing the cantilever beam includes the following steps:

[0042] S1, preparation for hoisting: before hoisting, place the cantilever beam section 5 at a position close to the flood control wall 9 on the construction platform 2, with the center line of the cantilever beam section 5 forming an angle of 28° with the flood control wall 9, and complete the corresponding work of the cantilever beam section 5 support on the construction platform 2, so that the tail end of the cantilever beam section 5 on the starboard side of the slideway board is 1.6 meters away from the flood control wall 9, and the tail end of the port side of the slideway board is 5.1 meters away from the gantry crane track on the side of the construction platform 2;

[0043] S2, start lifting: drive the floating crane 4 into the harbor 7, throw out two anchor ropes 8 in a figure eight shape at the stern, hang the first cable 6 at the bow to the pier of the harbor 7, adjust the position of the floating crane 4, make the hull of the floating crane 4 and the pier of the dock gate 10 form an angle of 62°, the starboard bow is 102.2 meters away from the dock gate, the port side is 4.7 meters away from the end of the downstream dock 3, and the starboard stern is 28.1 meters away from the end of the upstream dock 17, tighten the anchor rope 8 and the first cable 6, fix the position of the floating crane 4, and then lift;

[0044] S3, floating crane moving ship: by winching up the first cable 6 and the elastic anchor rope 8, the floating crane 4 is horizontally moved to the upstream dock 17, and the tugboat 12 is set to be tied to the floating crane 4. Then the floating crane 4 is untied and anchored, and the tugboat 12 cooperates to turn the floating crane 4 and tow it to the waters where the drilling platform 13 is located;

[0045] S4, moving the ship into position: using three tugboats 12 to tow the floating crane 4 to the designated position, so that the centerline of the floating crane 4 hull is perpendicular to the centerline of the drilling platform 13, the bow of the floating crane 4 is 50.2 meters away from the centerline of the drilling platform 13, and the centerline of the floating crane 4 hull is 10 meters away from the stern of the drilling platform 13, the first cable 6 in the middle of the bow of the floating crane 4 is hung on the starboard stern bollard of the drilling platform 13, the first cable 6 on the left side of the bow is hung on the 15 bollards of the port terminal, and the first cable 6 on the right side of the bow is hung on the 3 bollards of the downstream terminal, and the bow and stern of the floating crane 4 are anchored outward respectively;

[0046] S5, hoisting starts: after the floating crane 4 drops anchor and cables, the position of the floating crane 4 is adjusted to meet the installation conditions through the anchor winch and the mooring winch, and the 22.5-meter-long section of the cantilever beam section 5 can directly fall into the corresponding position at the rear of the deck surface of the drilling platform 13. The cantilever beam section 5 and the drilling platform 13 are connected by the sliding system mechanism 16 to control the sliding of the cantilever beam section 5 on the drilling platform 13;

[0047] S6, lifting completion: After the cantilever beam section 5 is fully in place, a temporary fixing plate is immediately welded between the edge of the lower slideway plate and the support, the cantilever beam section 5 is locked, and the floating crane is unhooked and moved out.

[0048] Among them; the civilian ship berthing waters 11 are within 150 meters in front of the downstream wharf 3, and the floating crane 4 ship moving route is around the periphery of the civilian ship berthing waters 11. During the lifting process of the cantilever beam section 5, the floating crane 4 route travels along the periphery of the civilian ship berthing waters 11 to ensure that it will not affect the normal berthing of civilian ships.

[0049] Among them; S2, start lifting includes: the floating crane 4 includes a floating crane body 41, and the floating crane body 41 is provided with a boom frame 42, and the ends of the boom frame 42 are respectively hung with a front main hook 43 and a rear main hook 44, and the front main hook 43 and the rear main hook 44 are respectively suspended on the left and right sides of the cantilever beam total section 5, and a trial lift is carried out before lifting, and after confirming that the rigging connection is correct, the front main hook 43 and the rear main hook 44 are lifted, and the cantilever beam total section 5 is lifted by about 500mm, the reading of the floating crane 4 is tracked, and it stops for about 5 minutes to check the changes in the structure and the reading of the floating crane 4, and confirm safety.

[0050] Among them; before the floating crane 4 is lifted, it is necessary to check the layout of the cantilever beam section 5, confirm that the lifting horse flaw detection is qualified, the front main hook 43 and the rear main hook 44 are located directly above the four groups of lifting ears of the cantilever beam section 5, and the front main hook 43 and the rear main hook 44 are pre-hung with designated wire ropes and shackles, which are connected to the lifting ears on the cantilever beam section 5, and the bottom of the cantilever beam section 5 is 5 meters higher than the top of the flood control wall 9 after the lifting. After the formal lifting, the lifting situation is debugged and controlled to ensure that the floating crane 4 will not cause the cantilever beam section 5 to bump or scratch the bottom when moving the ship after lifting.

[0051] Among them; S3, floating crane ship moving includes: the number of tugboats 12 is three, two tugboats 12 enter the harbor 7 when the floating crane 4 is pulled toward the upstream dock 17, and are respectively tied to the bow and stern of the port side of the floating crane 4 to cooperate with the ship moving, and then according to the tide conditions on the day of the operation, when the floating crane 4 exits the harbor 7, a tugboat 12 is arranged at the bow or stern of the starboard side of the floating crane 4 to cooperate with the ship moving, and the tugboat 12 is set to provide power for the floating crane 4, and work in cooperation to complete the ability of the floating crane 4 to move forward and turn, so that the floating crane 4 can smoothly arrive at the waters where the drilling platform 13 is located, and the floating crane 4 is controlled to calibrate the distance position from the drilling platform 13.

[0052] Among them; S4, moving the ship into position includes: before moving the ship into position, thirteen second cables 14 are set on the drilling platform 13 and hung on the piles of the downstream dock 3 in sequence, and the thirteen second cables 14 are used to fasten the parts of the drilling platform 13 that are not related to the lifting to the downstream dock 3, which plays a positioning role and avoids the drilling platform 13 from moving during the lifting process and affecting the lifting.

[0053] Among them; S5, the start of lifting includes: the sliding system mechanism 16 includes a base 161, the base 161 is installed on the drilling platform 13, the sliding system mechanism 16 is arranged at the end of the base 161, the sliding system mechanism 16 is pulled with a steel strand 163, and the end of the steel strand 163 away from the through-core cylinder 162 is provided with a clamping plate 164, and the clamping plate 164 is installed on the cantilever beam section 5. By installing the sliding system mechanism 16, the sliding system mechanism 16 is used to synchronously pull the cantilever beam section 5 to slide toward the head of the drilling platform 13, and the sliding system mechanism 16 provides a pulling force for the cantilever beam section 5, so that the cantilever beam section 5 moves along the fixed track, completing the sliding assembly of the cantilever beam section 5 and the drilling platform 13.

[0054] Among them; the cantilever beam section 5 includes a bulkhead 51, and a climbing frame 52 is arranged on the outer edge of the bulkhead 51. A mounting hole 53 is opened on the climbing frame 52. The clamping plate 164 is installed on the mounting hole 53 through the pin 165. The clamping plate 164 is temporarily installed on the cantilever beam section 5 by using the pin 165 to provide traction force for the cantilever beam section 5. After the cantilever beam section 5 is hoisted, it is convenient to directly disassemble the sliding system mechanism 16.

[0055] Among them; S5, the beginning of lifting includes: the cantilever beam section 5 slides 33.746 meters toward the bow of the drilling platform 13. During the traction process, the floating crane 4 always maintains a certain force. At the same time, the position of the floating crane 4 is continuously adjusted by setting the anchor machine and the cable winch, so that the floating crane 4 moves synchronously with the cantilever beam section 5 toward the bow of the drilling platform 13. The floating crane 4 is used to move synchronously according to the sliding of the cantilever beam section 5. At the same time, the drilling platform 13 continuously adjusts the ballast to ensure that the deck surface is always in a horizontal state. It can not only provide support for the part of the cantilever beam section 5 that is not in contact with the drilling platform 13, so that the cantilever beam section 5 remains balanced, but also avoid pulling and deflection during the sliding of the cantilever beam section 5.

[0056] Among them; S5, the start of lifting includes: when the cantilever beam section 5 is towed and slipped, a total station and a positioning plumb line are used to confirm that the longitudinal axis is aligned with the longitudinal center line of the floating crane 4, and the lateral error is ≯2.5mm, and the monitoring data is reported to the commander. The total station and the positioning plumb line are used to confirm multiple times that the relative positions of the longitudinal center lines of the cantilever beam section 5 and the drilling platform 13 meet the requirements, so that the towing direction of the cantilever beam section 5 is on a matching track, thereby improving the accuracy of the cantilever beam section 5 during lifting.

[0057] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. Method for installing cantilever beam on jack-up drilling platform wharf. The mechanism for installing cantilever beam includes: A dock (1), a construction platform (2), a downstream wharf (3) and an upstream wharf (17), wherein the dock (1), the construction platform (2), the downstream wharf (3) and the upstream wharf (17) are connected as a whole to form a G-shaped structure, and the dock (1), the construction platform (2), the downstream wharf (3) and the upstream wharf (17) enclose a space to form a harbor (7), a flood prevention wall (9) is built in front of the construction platform (2), and a undocking space is reserved in front of the dock (1). The door (10) is connected to the harbor (7), a cantilever beam section (5) is placed on the construction platform (2), a floating crane (4) floats in the harbor (7), an anchor rope (8) and a first cable (6) are respectively arranged on the floating crane (4), a berthing area (11) for civilian ships is reserved in the front area of ​​the downstream wharf (3), a tugboat (12) is tied to the side of the floating crane (4), and the cantilever beam section (5) is suspended at the bow of the floating crane (4); A drilling platform (13) is floating in a section of water in front of the downstream wharf (3) away from the harbor (7); the drilling platform (13) is hung on the pile of the downstream wharf (3) by a second cable (14); a port wharf (15) is arranged in a section of water separated from the end of the downstream wharf (3); and a sliding system mechanism (16) is arranged on the drilling platform (13); The method for installing the cantilever beam comprises the following steps: S1, preparation for lifting: before lifting, the cantilever beam section (5) is placed on the construction platform (2) at a position close to the flood control wall (9), with the center line of the cantilever beam section (5) and the flood control wall (9) forming an angle of 28°. The corresponding work of the cantilever beam section (5) support is installed on the construction platform (2), so that the tail end of the right side of the cantilever beam section (5) is 1.6 meters away from the flood control wall (9), and the tail end of the port side of the cantilever beam section (5) is 5.1 meters away from the gantry crane track on the side of the construction platform (2); S2, start lifting: drive the floating crane (4) into the harbor (7), throw out two anchor ropes (8) in a figure eight shape from the stern, hang the first cable (6) from the bow to the pier of the harbor (7), adjust the position of the floating crane (4), make the hull of the floating crane (4) form an angle of 62° with the dock gate (10) pier, the starboard bow is 2.2 meters away from the dock gate (10), the port side is 4.7 meters away from the end of the downstream dock (3), and the starboard stern is 28.1 meters away from the end of the upstream dock (17), tighten the anchor rope (8) and the first cable (6), fix the position of the floating crane (4), and then lift; S3, floating crane ship movement: by winching up the first cable (6) and the elastic anchor rope (8), the floating crane (4) is horizontally moved to the upstream dock (17), a tugboat (12) is arranged and tied to the floating crane (4), then the floating crane (4) is untied and anchored, and the tugboat (12) cooperates to turn the floating crane (4) and tow it to the waters where the drilling platform (13) is located; S4, moving the ship into position: using three tugboats (12) to tow the floating crane (4) to the designated position, so that the centerline of the floating crane (4) is perpendicular to the centerline of the drilling platform (13), the distance between the bow of the floating crane (4) and the centerline of the drilling platform (13) is 50.2 meters, and the distance between the centerline of the floating crane (4) and the stern of the drilling platform (13) is 10 meters. The first cable (6) in the middle of the bow of the floating crane (4) is tied to the stern mooring pile on the starboard side of the drilling platform (13), the first cable (6) on the left side of the bow is tied to the mooring pile of the port terminal (15), and the first cable (6) on the right side of the bow is tied to the mooring pile of the downstream terminal (3), and the bow and stern of the floating crane (4) are anchored outward respectively; S5, the lifting starts: after the floating crane (4) has finished dropping anchor and cable, the position of the floating crane (4) is adjusted to meet the installation conditions by means of the anchor winch and the mooring winch, and the 22.5-meter-long section of the cantilever beam section (5) can be directly dropped into the corresponding position at the rear of the deck surface of the drilling platform (13). The cantilever beam section (5) and the drilling platform (13) are connected by means of the sliding system mechanism (16), and the cantilever beam section (5) is controlled to slide on the drilling platform (13); S6, hoisting completion: after the cantilever beam section (5) is completely in place, a temporary fixing plate is immediately welded between the edge of the lower slideway plate and the support, the cantilever beam section (5) is locked, and the floating crane is unhooked and removed.

2. The method for installing a cantilever beam on a jack-up drilling platform pier according to claim 1, characterized in that: The civilian ship berthing waters (11) are located within a range of 150 meters in front of the downstream wharf (3), and the ship moving route of the floating crane (4) surrounds the periphery of the civilian ship berthing waters (11).

3. The method for installing a cantilever beam on a jack-up drilling platform pier according to claim 1, characterized in that: The S2, starting the lifting, comprises: the floating crane vessel (4) comprises a floating vessel body (41), the floating vessel body (41) is provided with a boom frame (42), the ends of the boom frame (42) are respectively hung with a front main hook (43) and a rear main hook (44), and the front main hook (43) and the rear main hook (44) are respectively hung on the left and right sides of the cantilever beam total section (5).

4. The method for installing a cantilever beam on a jack-up drilling platform pier according to claim 3, characterized in that: Before the floating crane (4) is lifted, it is necessary to check the arrangement of the cantilever beam section (5) and confirm that the hoisting horse has passed the flaw detection. The front main hook (43) and the rear main hook (44) are located directly above the four groups of lifting ears of the cantilever beam section (5). The front main hook (43) and the rear main hook (44) are pre-hung with designated wire ropes and shackles, which are connected to the lifting ears on the cantilever beam section (5). After the cantilever beam section (5) is lifted, its bottom is 5 meters above the top of the flood control wall (9).

5. The method for installing a cantilever beam on a jack-up drilling platform pier according to claim 1, characterized in that: The S3, floating crane ship moving includes: the number of the tugboats (12) is three, two of which enter the harbor (7) when the floating crane (4) is pulled toward the upstream dock (17), and are respectively tied to the port bow and stern of the floating crane (4) to cooperate with the ship moving; then, according to the tidal conditions on the day of the operation, when the floating crane (4) exits the harbor (7), a tugboat (12) is arranged at the starboard bow or stern of the floating crane (4) to cooperate with the ship moving.

6. The method for installing a cantilever beam on a jack-up drilling platform pier according to claim 1, characterized in that: The S4, moving the ship into position, includes: before moving the ship into position, thirteen second cables (14) are arranged on the drilling platform (13) and are sequentially hung on the piles of the downstream dock (3).

7. The method for installing a cantilever beam on a jack-up drilling platform pier according to claim 1, characterized in that: The S5, the start of lifting includes: the sliding system mechanism (16) includes a base (161), the base (161) is installed on the drilling platform (13), the sliding system mechanism (16) is arranged at the end of the base (161), a steel strand (163) is pulled on the sliding system mechanism (16), a clamping plate (164) is arranged at one end of the steel strand (163) away from the through-core cylinder (162), and the clamping plate (164) is installed on the cantilever beam total section (5).

8. The method for installing a cantilever beam on a jack-up drilling platform pier according to claim 7, characterized in that: The cantilever beam total section (5) comprises a bulkhead (51), a climbing frame (52) is arranged on the outer edge of the bulkhead (51), a mounting hole (53) is opened on the climbing frame (52), and the clamping plate (164) is installed on the mounting hole (53) through a latch (165).

9. The method for installing a cantilever beam on a jack-up drilling platform pier according to claim 1, characterized in that: The S5, the start of lifting, includes: the cantilever beam section (5) slides 33.746 meters towards the bow of the drilling platform (13), the floating crane (4) always maintains a certain force during the traction process, and at the same time, the position of the floating crane (4) is continuously adjusted by setting an anchor machine and a mooring machine, so that the floating crane (4) moves synchronously with the cantilever beam section (5) towards the bow of the drilling platform (13).

10. The method for installing a cantilever beam on a jack-up drilling platform pier according to claim 1, characterized in that: The S5, the start of the lifting includes: when the cantilever beam section (5) is towed and slid, a total station and a positioning plumb line are used to confirm that the longitudinal axis is aligned with the longitudinal center line of the floating crane (4), the lateral error is ≯2.5mm, and the monitoring data is reported to the commander.