An excavation method based on soft surrounding rock tunnel construction

By optimizing temporary support based on the double-sided wall pit guide method, the temporary arch support between the upper and lower pits was cancelled, and the CVD pit guide method was adopted to solve the slow construction speed and high cost of weak surrounding rock tunnels in the existing technology. The problem has achieved more efficient construction progress and structural stability.

CN118793446BActive Publication Date: 2024-11-26POWERCHINA CONSTR GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411273263.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-09-12
Publication Date
2024-11-26
Estimated Expiration
2044-09-12

AI Technical Summary

Technical Problem

The existing excavation method based on weak surrounding rock tunnel construction has insufficient construction speed and cost, especially in the environment where large section shallow buried tunnels pass through ancient building complexes, the construction speed of the double-sided wall pit method is slow and costly. CRD The pit guide method is expensive and is rarely used in mountain tunnels.

Method used

Based on the double-sided wall pit guide method, temporary support is optimized, temporary arch support between upper and lower pits is cancelled, and CVD pit guide method is adopted to set up surrounding pit guide support units and independent support components to reduce temporary support Workload to improve construction efficiency.

Benefits of technology

It reduces construction costs, simplifies processes, reduces excavation cycle time, improves construction progress and efficiency, ensures the stability and safety of the tunnel structure, and avoids the impact of rolling and vibration of temporary arches.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118793446B_ABST
    Figure CN118793446B_ABST
Patent Text Reader

Abstract

The present invention discloses an excavation method based on soft surrounding rock tunnel construction, which relates to the technical field of soil drilling. Based on the premise of ensuring safe tunnel construction, the excavation method and support method of the tunnel are creatively optimized. In terms of suppressing deformation and settlement, the settlement requirements of the tunnel passing through existing buildings can be met, and the settlement in the tunnel can be controlled within 50 mm; in terms of construction progress, the number of guide tunnels is reduced, the cycle progress time is shortened, and the excavation progress is greatly improved. The upper guide pit is divided into two left and right guide pits through the middle support, and the lower guide pit is divided into three parts, the left and right lower guide pits and the middle inverted arch part. This method realizes the continuity of the partial excavation of the guide pit, and the upper and lower guide pits can be constructed simultaneously and uninterruptedly, which improves the construction efficiency and reduces the cost; in terms of cost saving, the engineering volume of temporary support is reduced, and the construction material cost, machinery cost and labor cost are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of soil drilling, and in particular to an excavation method based on soft surrounding rock tunnel construction. Background Art

[0002] The construction methods for large-section tunnels are now relatively mature, mainly including the double-side wall pilot tunnel method, the cross-wall method, the step method, etc. The excavation and support methods for tunnel construction in different geological conditions and geographical environments are different. Each has its own advantages, but inevitably also has certain defects.

[0003] For example, the double side wall pilot method and the cross partition method are suitable for excavation of tunnels with poor geological conditions at the bottom surrounding rock. When constructing shallow buried large span tunnels, the double side wall pilot method can effectively control the surface subsidence and keep the face stable, but the construction speed of this method is slow and the cost is high; the step method is generally suitable for grade III and IV surrounding rock. The bottom surrounding rock should be excavated by the step method after the necessary advance support measures are stable. Tunnels with more than three lanes generally need to use three steps. The upper and lower steps interfere with each other during excavation, which will increase the number of disturbances of the surrounding rock. The more commonly used CRD pilot construction method, the full name of the cross partition method, is a tunnel construction method suitable for soft strata, especially for controlling surface subsidence. It has a good effect and is generally used in urban subway construction. Because of its high cost, it is rarely used in mountain tunnels, but it can also be used in special circumstances, such as expansive soil strata. On this basis, a tunnel CVD pilot method excavation construction method is proposed for specific geological conditions. Summary of the invention

[0004] In view of the above-mentioned problems existing in the existing excavation method based on soft surrounding rock tunnel construction, the present invention is proposed.

[0005] Therefore, the present invention provides an excavation method based on soft surrounding rock tunnel construction, which is proposed in the environment of solving the problem of large-section shallow buried tunnels passing through existing ancient buildings. On the basis of the double-side wall pilot pit method, combined with actual construction conditions, the temporary support of the double-side wall pilot pit method is optimized to realize tunnel construction under specific geological conditions, which is referred to as the CVD pilot pit method.

[0006] In order to solve the above technical problems, the present invention provides the following technical solutions: an excavation method based on soft surrounding rock tunnel construction, in which a CVD pilot pit method is set on the basis of the CRD pilot pit method; the CVD pilot pit method, based on the surrounding pilot pit support unit set by the CRD pilot pit method, cancels the temporary invert support between the upper and lower pilot pits, and sets a support unit.

[0007] As a preferred solution of the excavation method based on soft surrounding rock tunnel construction described in the present invention, the support unit includes a vertical support member arranged in the upper guide pit and connected to the top of the surrounding guide pit support unit, and independent support components located on both sides of the surrounding guide pit support unit after the lower guide pit is excavated.

[0008] As a preferred solution of the excavation method based on soft surrounding rock tunnel construction described in the present invention, the independent support assembly includes a left independent support member arranged on the left side of the surrounding pilot pit support unit, and a right independent support member arranged on the right side of the surrounding pilot pit support unit.

[0009] As a preferred solution of the excavation method based on soft surrounding rock tunnel construction described in the present invention, the soft surrounding rock is set as a surrounding rock unit, and the surrounding rock unit includes the bottom surrounding rock located at the bottom of the lower pilot pit and the top surrounding rock located at the upper pilot pit.

[0010] As a preferred solution of the excavation method based on soft surrounding rock tunnel construction described in the present invention, wherein: an upper concrete pouring space is provided below the top surrounding rock; a lower concrete pouring space is provided above the bottom surrounding rock;

[0011] The guide pit includes an upper guide pit and a lower guide pit, the upper guide pit includes a first left upper guide pit and a second right upper guide pit, and the lower guide pit includes a third left lower guide pit, a fourth right lower guide pit, and a fifth lower guide pit.

[0012] As a preferred solution of the excavation method based on soft surrounding rock tunnel construction described in the present invention, the surrounding guide pit support unit includes a permanent initial support steel frame 1 arranged in the first left upper guide pit, a permanent initial support steel frame 2 connected to the permanent initial support steel frame 1 and located in the second right upper guide pit, a lower support steel frame 1 arranged at the lower part of the permanent initial support steel frame, and a lower support steel frame 2 arranged at the lower part of the permanent initial support steel frame 2.

[0013] As a preferred solution of the excavation method based on soft surrounding rock tunnel construction of the present invention, wherein: firstly, a first left upper pilot pit is excavated, a permanent initial support steel frame 1 is set, and concrete spraying of the upper concrete pouring space is completed;

[0014] The second right upper pilot pit lags behind the first left upper pilot pit by 10-15m, and the second permanent initial support steel frame is set to complete the concrete spraying of the lower concrete pouring space;

[0015] The third left lower pilot pit lags behind the first left upper pilot pit by 18-20m. After excavation, the lower support steel frame is installed, and the net spraying is carried out in time;

[0016] The fourth right lower pilot pit lags behind the third left lower pilot pit by 3-5m. The construction process is the same as the third left lower pilot pit, and the second lower support steel frame is installed, and the net spraying protection is carried out in time;

[0017] According to the monitoring and measurement data, the temporary support of the middle partition wall was removed after the tunnel deformation stabilized;

[0018] Excavate the fifth pilot pit and close the invert in time. The excavation depth of the fifth pilot pit shall not exceed 3m at a time.

[0019] Pour the upper concrete pouring space and the invert concrete. After the invert concrete has finally set, complete the corresponding lower concrete pouring space and concrete filling.

[0020] As a preferred solution of the excavation method based on soft surrounding rock tunnel construction described in the present invention, for the top surrounding rock, vertical support parts are set up while setting the permanent initial support steel frame, laying steel mesh, and installing system anchor rods and locking anchor pipes.

[0021] As a preferred solution of the excavation method based on soft surrounding rock tunnel construction described in the present invention, for the bottom surrounding rock, independent support components are added, steel mesh is laid, and system anchor rods and locking anchor pipes are installed.

[0022] As a preferred solution of the excavation method based on soft surrounding rock tunnel construction described in the present invention, in the process of removing the vertical support members and the independent support components, at least 5-8m is retained from the second right upper pilot pit.

[0023] The beneficial effects of the present invention are as follows: on the basis of the double-side wall pilot pit method, combined with actual construction conditions, the temporary support of the double-side wall pilot pit method is optimized, and the original arc-shaped temporary vertical double support is optimized and adjusted to a temporary vertical single support of the upper step, which provides a larger working space for construction, and at the same time cancels the temporary invert support of the left and right guide tunnels of the double-side wall pilot pit method, avoiding the rolling, vibration and damage of the temporary invert by the walking and excavation of the excavation equipment, reducing the workload of the temporary support, saving manpower, materials and machine input, reducing the construction cost, facilitating on-site operation, simplifying the process, reducing the excavation cycle time, accelerating the construction progress, and greatly improving the construction efficiency, thereby pulling the arch frame to sink as a whole, causing deformation and cracks in the primary support of the tunnel, and even the occurrence of settlement intrusion into the secondary lining. The construction and structural safety can be guaranteed, and the settlement, convergence and deformation of the tunnel structure are controllable. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0025] Figure 1 The present invention is a construction process flow chart of the excavation method based on soft surrounding rock tunnel construction.

[0026] Figure 2 It is a schematic diagram of the support structure of the CVD pilot tunnel method based on the soft surrounding rock tunnel construction excavation method of the present invention.

[0027] Figure 3 It is a schematic diagram of the support structure of the present invention based on the soft surrounding rock tunnel construction excavation method to strengthen the CVD pilot tunnel method.

[0028] Figure 4 It is a longitudinal section diagram of the CVD pilot tunnel method process of the excavation method for soft surrounding rock tunnel construction according to the present invention.

[0029] Figure 5 It is a CVD pilot tunnel method model of the excavation method based on soft surrounding rock tunnel construction of the present invention.

[0030] Description of the drawings: 100, temporary support unit; 101, left independent support member; 102, right independent support member; 103, vertical support member; 200, surrounding pilot pit support unit; 201, permanent initial support steel frame one; 202, permanent initial support steel frame two; 300, surrounding rock unit; 301, bottom surrounding rock; 302, lower concrete pouring space; 303, top surrounding rock; 304, upper concrete pouring space. DETAILED DESCRIPTION

[0031] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific embodiments of the present invention are described in detail below in conjunction with the accompanying drawings.

[0032] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.

[0033] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not necessarily refer to the same embodiment, nor is it an embodiment that is mutually exclusive with other embodiments, either individually or selectively.

[0034] Secondly, the present invention is described in detail with reference to the schematic diagram. When describing the embodiments of the present invention in detail, for the sake of convenience, the cross-sectional diagrams showing the device structure will not be partially enlarged according to the general scale, and the schematic diagrams are only examples, which should not limit the scope of protection of the present invention. In addition, in actual production, the three-dimensional dimensions of length, width and depth should be included.

[0035] Example 1, reference Figure 1 , which is the first embodiment of the present invention, provides an excavation method based on soft surrounding rock tunnel construction, the method comprising the following steps:

[0036] Based on the design data, geological survey data and the topography and landforms around the tunnel, we conduct a detailed analysis to understand the engineering geology and local hydrogeological conditions, formulate reasonable construction plans and construction measures, formulate construction monitoring and measurement plans and settlement observation plans; assess the risks of the tunnel, identify the sources of risk and formulate response measures, and reserve necessary emergency supplies.

[0037] In combination with the construction plan, formulate a feasible monitoring and measurement plan and a surface settlement observation plan; the surface monitoring and measurement should start with actual measurement within 30~50m of the excavation face. According to the construction drawings, make full use of BIM model software to build the model in advance, which is intuitive and clear, and provide visual explanation for on-site construction.

[0038] Before construction, it is necessary to make advance geological predictions to determine the actual geological conditions of the surrounding rock and provide a basis for the selection of construction methods. This project uses SIR-4000 geological radar scanning (30m) for short distances and seismic wave transmission method (TST) (100-150m) for long distances. The geological advance prediction uses a combination of long-distance and short-distance means for comprehensive analysis, mutual verification, and verification with the surrounding rock geology of the designed tunnel to determine the actual geological conditions of the surrounding rock and provide a basis for the selection of construction methods.

[0039] The pilot pit where the soft surrounding rock tunnel is located includes an upper pilot pit and a lower pilot pit, wherein the upper pilot pit includes a first left upper pilot pit and a second right upper pilot pit, and the lower pilot pit includes a third left lower pilot pit, a fourth right lower pilot pit, and a fifth lower pilot pit.

[0040] The construction process of the tunnel CVD pilot method is as follows:

[0041] First, excavate the first left upper pilot pit, set up a permanent initial support steel frame 201, and complete the concrete spraying of the upper concrete pouring space 304;

[0042] The second right upper pilot pit lags behind the first left upper pilot pit by 10-15m, and a permanent initial support steel frame 202 is set to complete the concrete spraying of the lower concrete pouring space 302;

[0043] The third left lower pilot pit lags behind the first left upper pilot pit by 18-20m. After excavation, the lower support steel frame 203 is installed, and the net spraying is carried out in time;

[0044] The fourth right lower pilot pit lags behind the third left lower pilot pit by 3-5m. The construction process is the same as the third left lower pilot pit, and the lower support steel frame 204 is installed, and the net spraying protection is carried out in time;

[0045] According to the monitoring and measurement data, the temporary support of the middle partition wall was removed after the tunnel deformation stabilized;

[0046] Excavate the fifth pilot pit and close the invert in time. The excavation depth of the fifth pilot pit shall not exceed 3m at a time.

[0047] Pour the upper concrete pouring space 304 inverted arch concrete, and complete the corresponding lower concrete pouring space 302 concrete filling after the inverted arch concrete is finally set. For the top surrounding rock 303, set up the permanent initial support steel frame 201 and set up the vertical support member 103, lay the steel mesh, and set up the system anchor rod and the locking foot anchor pipe. For the bottom surrounding rock 301, add independent support components, lay the steel mesh, and set up the system anchor rod and the locking foot anchor pipe. In the process of dismantling the vertical support member 103 and the independent support component, at least 5-8m is retained from the second right upper guide pit.

[0048] Pour the upper concrete pouring space 304 inverted arch concrete, and complete the corresponding lower concrete pouring space 302 concrete filling after the inverted arch concrete is finally set. For the top surrounding rock 303, set the permanent initial support steel frame 201 and set the vertical support member 103, lay the steel mesh, and drive the system anchor rod and the locking foot anchor pipe. For the bottom surrounding rock 301, add independent support components, lay the steel mesh, and drive the system anchor rod and the locking foot anchor pipe. In the process of dismantling the vertical support member 103 and the independent support component, at least 5-8m is retained from the second right upper guide pit.

[0049] For large-section tunnel excavation, it is very important to arrange the sequence and safety steps of each pilot tunnel construction reasonably, which is very important for the safety of construction personnel and the project itself. The "Technical Specification for Highway Engineering Construction Safety" (JTG F90-2015) is formulated for highway projects using conventional drilling and blasting methods. Conventional mechanical excavation methods are used to reduce the vibration impact of blasting on the surrounding rock. Because there are many construction trolleys and equipment in the tunnel, the safety step distance of 70m required by the specification will increase the occurrence of equipment injury accidents. For this reason, after repeated demonstrations by industry experts, the distance between the secondary lining concrete and the heading face can be appropriately relaxed, but the maximum shall not exceed 110m.

[0050] The common CRD pilot pit excavation method uses the method of reserving core soil to divide the large-section tunnel into 4 relatively independent small caverns for construction. The CRD method follows the construction principle of "small division, short steps, short circulation, fast closure, frequent measurement, and strong support". It is divided into blocks from top to bottom into rings, and supports as it is excavated, and the initial support is done in time. After the settlement and convergence of the arch of the initial support structure are basically stable, the temporary middle partition wall and temporary invert in the initial support structure are removed from top to bottom before construction. The CRD method is suitable for excavation with a large span and strict control over the settlement and deformation of the surrounding rock. When the CRD method is used for excavation, each step of the excavation is closed into a ring, which has the advantages of the step method and the double-side wall pilot pit method, which is conducive to the stability of the surrounding rock and ensures construction safety.

[0051] This method is based on the CRD pilot pit excavation method. Under the premise of ensuring the safe construction of the tunnel, the excavation method and support method of the tunnel are optimized. In terms of suppressing deformation and settlement, it can meet the settlement requirements of tunnels passing through existing buildings, and the settlement in the tunnel can be controlled within 50mm; in terms of construction progress, the number of pilot tunnels is reduced, the cycle progress time is shortened, and the excavation progress is greatly improved. Compared with the tunnel pilot pit method of the prior art, the pilot pit division method is different. The upper pilot pit is divided into two left and right pilot pits through the middle support, and the lower pilot pit is divided into three parts, the left and right lower pilot pits and the middle invert part. This method realizes the continuity of the pilot pit division excavation. The upper and lower pilot pits can be constructed simultaneously and uninterruptedly, which improves construction efficiency and reduces costs; in terms of cost saving, it reduces the amount of temporary support engineering, construction material costs, machinery costs and labor costs.

[0052] Example 2, reference Figure 1-Figure 3 and Figure 5 , which is the second embodiment of the present invention, provides a supporting structure based on the excavation method for soft surrounding rock tunnel construction in Embodiment 1.

[0053] The support structure is used in combination with the CVD pilot pit method. The support structure is based on a surrounding pilot pit support unit 200 set up based on the CRD pilot pit method, the temporary invert support between the upper and lower pilot pits is cancelled, and a temporary support unit 100 is set up.

[0054] The CVD pilot tunnel method is a tunnel section separation excavation support method, which mainly uses the middle column support or double middle column support to ensure the stability of the arch.

[0055] Compared with the CRD pilot pit method, the CVD pilot pit method cancels the temporary inverted arch support between the upper and lower pilot pits, and optimizes the arc-shaped steel structure of the upper pilot pit into a vertical support form, which can effectively reduce the difficulty of excavation and enhance the force of the middle support structure. The third left lower pilot pit and the fourth right lower pilot pit are excavated and supported independently, and only the lower pilot pit is permanently supported. After the deformation is stable, the fifth lower pilot pit is excavated and supported to form an arch frame closed loop.

[0056] Among them, the temporary support unit 100 includes a vertical support member 103 arranged in the upper guide pit and connected to the top of the surrounding guide pit support unit 200, and independent support components located on both sides of the surrounding guide pit support unit 200 after the lower guide pit is excavated.

[0057] Furthermore, the independent support assembly includes a left independent support member 101 arranged on the left side of the surrounding pilot pit support unit 200, and a right independent support member 102 arranged on the right side of the surrounding pilot pit support unit 200.

[0058] Preferably, the vertical support member 103 is configured as a drug coil anchor rod with a diameter of 22 cm, a length of 2.5 m, and a longitudinal distance of 1.2 m*0.5 m in the x-axis direction. At the same time, a steel mesh with a diameter of 8 cm and a cross-sectional size of 200 mm*200 mm is arranged in a plum blossom shape. At the same time, an I25b I-beam frame is provided with a longitudinal spacing of 0.5 m. The lower part is filled with C25 shotcrete, and the thickness of the upper concrete pouring space 304 is 100 mm.

[0059] Preferably, the left independent support component 101 and the right independent support component 102 in the independent support assembly have the same structure, and four are arranged on each side. The left independent support component 101 and the right independent support component 102 both adopt locking foot steel pipes with a diameter of 42mm*4mm. The steel pipes are 4m long and form an angle of 30° with the horizontal plane.

[0060] Example 3, reference Figure 1-Figure 5 , which is the third embodiment of the present invention, provides a support structure based on the excavation method for soft surrounding rock tunnel construction in Embodiment 1. This embodiment is different from the second embodiment in that a horizontal support rod 104 is provided on one side of the vertical support member 103.

[0061] Compared with Example 2, further, the horizontal support rod 104 adopts an I-beam frame with a diameter of 8mmI25b, and multiple groups of horizontal support rods 104 are arranged. The longitudinal spacing between each group of horizontal support rods 104 is 0.5m, and a 200mm*200mm steel mesh is arranged.

[0062] The horizontal support rod 104 with the above structure can be used to divide the upper guide pit into two left and right guide pits through the middle support during the partial excavation of the guide pit. The first left upper guide pit and the second right upper guide pit provide mutual support force, and a higher strength guide pit reinforcement effect is achieved compared with the support method in Example 2. At the same time, the guide pit is divided into upper and lower parts from the large span line of the guide pit, and the lower guide pit is divided into three parts, the third left lower guide pit, the fourth right lower guide pit and the fifth lower guide pit, so as to form the left and right lower guide pits and the middle inverted arch part, so as to achieve the continuity of the partial excavation of the guide pit, and the upper and lower guide pits can be constructed simultaneously and uninterruptedly, thereby improving the construction efficiency and reducing the cost.

[0063] The remaining structure is the same as that of Example 2.

[0064] Additionally, in order to provide a concise description of exemplary embodiments, all features of an actual embodiment may not be described (ie, those features that are not relevant to the best mode presently contemplated for carrying out the invention or those features that are not relevant to implementing the invention).

[0065] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present invention, which should all be included in the scope of the claims of the present invention.

Claims

1. An excavation method based on soft surrounding rock tunnel construction, characterized by: The CVD pilot method is set up on the basis of the CRD pilot method; The CVD pilot pit method is based on the surrounding pilot pit support unit (200) set up by the CRD pilot pit method, and the temporary invert support between the upper and lower pilot pits is cancelled, and a temporary support unit (100) is set up inside the soft surrounding rock pilot pit; the temporary support unit (100) comprises a vertical support member (103) set up in the upper pilot pit and connected to the top of the surrounding pilot pit support unit (200), and independent support components located on both sides of the surrounding pilot pit support unit (200) after the lower pilot pit is excavated; the independent support components comprise a left independent support member (101) set up on the left side of the surrounding pilot pit support unit (200), and a right independent support member (102) set up on the right side of the surrounding pilot pit support unit (200); The weak surrounding rock is set as a surrounding rock unit (300), and the surrounding rock unit (300) includes a bottom surrounding rock (301) located at the bottom of the lower pilot pit, and a top surrounding rock (303) located at the upper pilot pit; an upper concrete pouring space (304) is provided below the top surrounding rock (303); and a lower concrete pouring space (302) is provided above the bottom surrounding rock (301); The pilot pit is divided from the pilot pit large span line, including an upper pilot pit and a lower pilot pit, the upper pilot pit includes a first left upper pilot pit and a second right upper pilot pit, and the lower pilot pit includes a third left lower pilot pit, a fourth right lower pilot pit, and a fifth lower pilot pit; The surrounding guide pit support unit (200) comprises a permanent initial support steel frame 1 (201) arranged on the first left upper guide pit, a permanent initial support steel frame 2 (202) connected to the permanent initial support steel frame 1 (201) and located on the second right upper guide pit, a lower support steel frame 1 (203) arranged at the lower part of the permanent initial support steel frame 1 (201), and a lower support steel frame 2 (204) arranged at the lower part of the permanent initial support steel frame 2 (202); The excavation method comprises the following steps: First, a first left upper pilot pit is excavated, the permanent initial support steel frame 1 (201) is installed, and concrete spraying of the upper concrete pouring space (304) is completed; The second right upper pilot pit lags behind the first left upper pilot pit by 10-15m, and the second permanent initial support steel frame (202) is set to complete the concrete spraying of the lower concrete pouring space (302); The third left lower pilot pit lags behind the first left upper pilot pit by 18-20m. After excavation, the lower support steel frame 1 (203) is installed and sprayed with mesh; The fourth right lower guide pit lags behind the third left lower guide pit by 3-5m, and the construction process is the same as the third left lower guide pit, and the second lower support steel frame (204) is installed, and the mesh spraying is carried out; According to the monitoring and measurement data, the temporary support of the middle partition wall was removed after the tunnel deformation stabilized; Excavate the fifth lower pilot pit and close the invert in time. The excavation distance of the fifth lower pilot pit shall not exceed 3m at a time. The upper concrete pouring space (304) is poured with inverted arch concrete, and after the inverted arch concrete is finally set, the corresponding lower concrete pouring space (302) is filled with concrete.

2. The excavation method based on soft surrounding rock tunnel construction according to claim 1 is characterized in that: The vertical support member (103) is arranged at the same time as the permanent initial support steel frame 1 (201) is arranged on the top surrounding rock (303).

3. The excavation method based on soft surrounding rock tunnel construction according to claim 2 is characterized in that: The independent support assembly is arranged on the bottom surrounding rock (301).

4. The excavation method based on soft surrounding rock tunnel construction according to claim 3 is characterized in that: During the process of removing the vertical support member (103) and the independent support assembly, at least 5-8 m is retained starting from the second right upper guide pit.