Optimization processing method, device and equipment for operation path of tower crane and storage medium

By real-time detection and update of the tower crane operation path, the problems of path conflicts and obstacles in the construction environment are solved, and the safety and efficiency of the tower crane are improved.

CN118894446APending Publication Date: 2024-11-05CHINA CONSTR THIRD ENG BUREAU GRP CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411143428.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-20
Publication Date
2024-11-05

AI Technical Summary

Technical Problem

The prior art cannot plan and adjust the working path of the tower crane in a timely and accurate manner, especially in real-time changing construction environments, which lead to path conflicts and obstacles, making it difficult to ensure the safe and efficient operation of the tower crane.

Method used

By receiving the input job, determine the path to execute the tower crane, and detect other tower cranes in the working state in its operating environment, obtain their paths, calculate the intersection area and arrival time, and according to the time difference and the location of the obstacle, in real time, Update the tower crane's job path to avoid conflicts and optimize paths.

Benefits of technology

The timeliness and accuracy of tower crane path planning is achieved, the safety and efficiency of tower cranes at the construction site are improved, and the path conflicts and obstacles are avoided.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118894446A_ABST
    Figure CN118894446A_ABST
Patent Text Reader

Abstract

The invention discloses a tower crane operation path optimization processing method and device, electronic equipment and a storage medium, and the method comprises the following steps: receiving an input first operation, and carrying out path planning to obtain a first operation path of a first tower crane executing the first operation; determining whether the working environment where the first tower crane is located contains the tower crane in the working state or not, and when it is determined that the working environment contains the tower crane in the working state, obtaining a second tower crane in the working state; a second operation path of a second tower crane is obtained, and an intersection point area is obtained according to the first operation path and the second operation path; determining a first moment when the first tower crane reaches the intersection point area, and determining a second moment when the second tower crane reaches the intersection point area; and according to the first moment and the second moment, determining whether to update the first operation path, and updating the first operation path when updating is determined. And the timeliness and the accuracy of path planning and operation of the tower crane are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of tower crane control, and in particular to a method, device, electronic equipment and storage medium for optimizing a tower crane operation path. Background Art

[0002] At the construction site, the efficient and safe use of tower cranes (referred to as tower cranes) is related to the efficiency of engineering construction and the safety of personnel and equipment. Therefore, how to ensure the safe operation of tower cranes at the construction site is extremely important.

[0003] At present, the tower crane path planning solution is usually based on the A* algorithm. The global optimal path is planned by setting the cost estimation function, and then the tower crane operation is controlled based on the planned path. However, in the actual operation of the tower crane, the operating environment changes in real time, including tower cranes performing other operations in the operating environment or changes in obstacles caused by tower crane operations, such as changes in material positions, which may lead to conflicts in the planned operation path, including path conflicts between tower cranes and new obstacles appearing on the operation path. Therefore, it is very important to plan and adjust the tower crane operation path in a timely and accurate manner. Summary of the invention

[0004] The purpose of the embodiments of the present application is to provide a method, device, electronic device and storage medium for optimizing the operation path of a tower crane, so as to solve the technical problem in the related art that the operation path of a tower crane cannot be planned and adjusted in a timely and accurate manner.

[0005] In a first aspect, an embodiment of the present application provides a method for optimizing a tower crane operation path, comprising:

[0006] Receiving an input first operation, and performing path planning to obtain a first operation path of a first tower crane for performing the first operation;

[0007] Determine whether the operating environment in which the first tower crane is located includes a tower crane in an operating state, and when it is determined that the tower crane in an operating state is included, obtain a second tower crane in an operating state;

[0008] Acquire a second operating path of the second tower crane, and obtain an intersection area according to the first operating path and the second operating path;

[0009] Determine a first time when the first tower crane reaches the intersection area, and determine a second time when the second tower crane reaches the intersection area;

[0010] According to the first time and the second time, it is determined whether to update the first operation path, and when it is determined to update, the first operation path is updated.

[0011] In a second aspect, an embodiment of the present application provides a tower crane operation path optimization processing device, comprising:

[0012] A path planning module, used for receiving an input first operation, and performing path planning to obtain a first operation path of a first tower crane for performing the first operation;

[0013] An environment determination module, used to determine whether the operating environment in which the first tower crane is located includes a tower crane in an operating state, and when it is determined that the tower crane in an operating state is included, obtain a second tower crane in an operating state;

[0014] A path judgment module, used for acquiring a second operating path of the second tower crane, and obtaining an intersection area according to the first operating path and the second operating path;

[0015] A time determination module, used to determine a first time when the first tower crane arrives at the intersection area, and to determine a second time when the second tower crane arrives at the intersection area;

[0016] An update judgment module is used to determine whether to update the first operation path according to the first moment and the second moment, and to update the first operation path when it is determined to be updated.

[0017] In a third aspect, an embodiment of the present application provides an electronic device, comprising a processor, a memory, and a computer program stored in the memory and executable on the processor, wherein the processor implements the steps in any one of the above-mentioned methods for optimizing the tower crane operation path when executing the computer program.

[0018] In a fourth aspect, an embodiment of the present application provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps in any of the above-mentioned methods for optimizing the tower crane operation path are implemented.

[0019] The embodiment of the present application provides a method, device, electronic device and storage medium for optimizing the operation path of a tower crane. When performing path planning, a first operation is received as input, a first tower crane that performs the first operation is determined, and then a first operation path of the first tower crane is determined. Then, a second tower crane in an operation state in the operation environment where the first tower crane is located is determined, and a second operation path of the second tower crane is obtained, so as to obtain an intersection area according to the first operation path and the second operation path; then, a first moment when the first tower crane reaches the intersection area is determined, and a second moment when the second tower crane reaches the intersection area is determined; finally, according to the first moment and the second moment, it is determined whether to update the first operation path, and the first operation path is updated when the update is determined. In the process of tower crane path planning, the planned operation path is updated and adjusted in a timely manner according to the operation environment where the tower crane is located, so as to improve the timeliness and accuracy of tower crane path planning and operation. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a flow chart of a tower crane operation path optimization processing method provided in an embodiment of the present application;

[0021] Figure 2 This is a flow chart of the steps of obtaining the intersection area provided in an embodiment of the present application;

[0022] Figure 3 This is a schematic diagram of a scenario provided by an embodiment of the present application;

[0023] Figure 4 This is a flow chart of the steps of obtaining the first moment and the second moment provided in an embodiment of the present application;

[0024] Figure 5 It is a flowchart of the steps of determining whether to perform update processing provided by an embodiment of the present application;

[0025] Figure 6 It is another flow chart of the method for optimizing the tower crane operation path provided in the embodiment of the present application;

[0026] Figure 7 This is another scenario schematic diagram provided by an embodiment of the present application;

[0027] Figure 8 It is another flow chart of the method for optimizing the tower crane operation path provided in the embodiment of the present application;

[0028] Fig. 9 It is a structural schematic diagram of a tower crane operation path optimization processing device provided in an embodiment of the present application;

[0029] Fig.10 is a structural schematic diagram of an electronic device provided in an embodiment of the present application;

[0030] Fig.11 This is another structural schematic diagram of an electronic device provided in an embodiment of the present application. DETAILED DESCRIPTION

[0031] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0032] It should be understood that the various steps described in the method embodiments of the present disclosure may be performed in different orders and / or in parallel. In addition, the method embodiments may include additional steps and / or omit the steps shown. The scope of the present disclosure is not limited in this respect.

[0033] The term "including" and its variations used herein are open inclusions, i.e., "including but not limited to". The term "based on" means "based at least in part on". The term "one embodiment" means "at least one embodiment"; the term "another embodiment" means "at least one additional embodiment"; the term "some embodiments" means "at least some embodiments". The relevant definitions of other terms will be given in the following description.

[0034] In the related art, the tower crane path planning is usually based on the A* algorithm. The global optimal path is planned by setting the cost estimation function, and then the tower crane operation is controlled based on the planned path. However, in the actual operation of the tower crane, the operating environment changes in real time, including tower cranes performing other operations in the operating environment or changes in obstacles caused by tower crane operations, such as changes in material positions, which may lead to conflicts in the planned operation path, including path conflicts between tower cranes and new obstacles appearing on the operation path. Therefore, it is very important to plan and adjust the tower crane operation path in a timely and accurate manner.

[0035] In order to solve the technical problems existing in the related art, the present application embodiment provides a method for optimizing the operation path of a tower crane, see Figure 1 , Figure 1 It is a flow chart of a tower crane operation path optimization processing method provided in an embodiment of the present application, and the method includes steps 101 to 105.

[0036] Step 101: receiving an input first operation, and performing path planning to obtain a first operation path of a first tower crane for executing the first operation.

[0037] In one embodiment, during the operation of the tower crane, different tower cranes are used to perform different operations. Therefore, when performing the operation path planning process of the tower crane, an input first operation is received, and path planning is performed to obtain a first operation path of the first tower crane that performs the first operation.

[0038] For example, when receiving the input of the first operation, the first tower crane for performing the first operation is first determined, and then the path planning is performed according to the operating environment, so as to obtain the first operating path of the first tower crane when performing the first operation, which may also be referred to as the initial operating path, and then the first tower crane is controlled to move based on the first operating path and complete the first operation. Of course, in the actual operation process, due to the change of the operating environment, the operating path needs to be adjusted in real time, so as to ensure that the first tower crane can operate normally.

[0039] When determining the first tower crane based on the received first job, since different jobs correspond to different tower cranes, such as different job types correspond to different tower cranes, when receiving the first job and determining the first operation path, it includes: receiving the input first job and identifying the job identifier corresponding to the first job; matching among the idle tower cranes according to the job identifier to obtain the first tower crane for executing the first job; acquiring environmental information of the operating environment in which the first tower crane is located, and performing path planning processing according to the environmental information and the first job to obtain the first operation path of the first tower crane, wherein the environmental information includes the location of obstacles, and the obstacles include tower cranes and non-tower crane objects.

[0040] Specifically, when the first job is received, the job identifier corresponding to the first job can be identified, wherein the job identifier can be a job type or a number used to determine the job type, etc., or other requirements (such as job duration, power requirements), etc., and then the first tower crane used to perform the first job is determined based on the obtained job identifier, such as using the job identifier to match among idle tower cranes to determine the first tower crane. After the first tower crane is determined, environmental information of the operating environment of the first tower crane is obtained, wherein the environmental information includes obstacle information, and the obstacle can be a tower crane or other objects other than a tower crane. Then, planning is performed based on the obtained environmental information and the first job to obtain the first operating path when the first tower crane is operating.

[0041] In the actual operation process, obstacles are particularly important information and may have a certain impact on the operation of the tower crane. For example, if an obstacle is on the first operation path of the first tower crane, the first tower crane will be unable to move. For another example, when the obstacle is a tower crane, and it is also performing different operations, there may be a conflict in the operation path, which will also affect the movement of the first tower crane. Therefore, when performing path planning, path planning is performed based on the environment in which the tower crane is located. By avoiding obstacles, the tower crane can be guaranteed to perform operations safely and efficiently.

[0042] Since the working environment of the tower crane will also change during its operation, it is necessary to consider the impact of the real-time changes in the working environment on the working path during the operation of the first tower crane, and then ensure the efficient and normal operation of the tower crane by timely and reasonably adjusting and optimizing the path. At this time, it is possible to determine whether there is a tower crane in an operating state in the working environment. Since the position of the tower crane in an operating state changes in real time, which leads to a change in the working environment, it is possible to determine whether the working environment has changed by determining whether there is a tower crane in an operating state.

[0043] Step 102: determine whether the operating environment in which the first tower crane is located includes a tower crane in an operating state, and if it is determined that the tower crane in an operating state is included, obtain a second tower crane in an operating state.

[0044] In one embodiment, after determining the first operating path of the first tower crane, in order to avoid the influence of other tower cranes operating in the operating environment on the first tower crane, it is further determined whether the operating environment where the first tower crane is located includes a tower crane in an operating state, and when it is determined that a tower crane in an operating state is included, a second tower crane in an operating state is obtained. The number of the second tower cranes may be one or more, and here the description is first made by taking the number of the second tower crane as one as an example, and the case where the number of the second tower cranes is more than one is similar to the case where the number of the second tower cranes is one.

[0045] Exemplarily, when determining a tower crane in an operating state, it can be read in the system, and images can be captured by a related image capture device set in the operating environment, and then the tower crane in an operating state can be determined by analyzing the image.

[0046] Step 103: Acquire a second operating path of the second tower crane, and obtain an intersection area according to the first operating path and the second operating path.

[0047] In one embodiment, after determining the second tower crane in the operating state in the operating environment, the second operating path of the second tower crane is obtained, and then the first operating path and the second operating path are compared and analyzed to determine the intersection area of ​​the first operating path and the second operating path.

[0048] For example, for the operation path of each tower crane, when the path planning and update processing are completed, the latest operation path corresponding to the tower crane will be recorded and stored, so as to control the corresponding tower crane to operate according to the latest recorded operation path. Therefore, after the second tower crane is determined, the tower crane identifier of the second tower crane can be queried to obtain the second operation path corresponding to the second tower crane. Since the first operation path and the second operation path may not consider the influence between the two tower cranes when planning, the first operation path and the second operation path may intersect. Since there may be mutual influence, it is necessary to further determine whether the path needs to be optimized and adjusted to ensure that the first tower crane and the second tower crane are not affected by each other.

[0049] Further, when determining whether there is an intersection area between the first operation path and the second operation path, it is possible to refer to Figure 2 , Figure 2 It is a flowchart diagram of the steps of obtaining the intersection area provided in an embodiment of the present application, wherein the steps include steps 201 to 203.

[0050] Step 201, constructing environmental coordinates corresponding to the working environment, and obtaining a first coordinate curve corresponding to the first working path and a second coordinate curve corresponding to the second working path in the environmental coordinates;

[0051] Step 202, determining whether there is an intersection coordinate between the first coordinate curve and the second coordinate curve;

[0052] Step 203, when it is determined that there are intersection coordinates, a coordinate area in the environment coordinates is obtained according to a preset area acquisition standard and the intersection coordinates, and an intersection area in the working environment is obtained according to the coordinate area.

[0053] Specifically, corresponding environmental coordinates can be constructed according to the working environment, and then the first working path and the second working path can be coordinateized in the environmental coordinates to obtain a first coordinate curve corresponding to the first working path and a second coordinate curve corresponding to the second working path, and then it is determined in the environmental coordinates whether the first coordinate curve and the second coordinate curve intersect to determine the existence of intersection coordinates, and then when it is determined that there are intersection coordinates, the intersection area is obtained according to the set area selection method.

[0054] For example, when the first operation path and the second operation path have an intersection, it means that the first tower crane and the second tower crane may encounter each other during the operation. Of course, there may be a situation where they do not meet. In this case, it is necessary to determine the intersection based on the actual operation conditions of the first tower crane and the second tower crane. When the intersection is determined in the environmental coordinates, the world coordinate position of the intersection in the operating environment can be determined based on the proportional relationship between the coordinates and the environment. Then, when determining the intersection area, a circle or a square can be taken based on the world coordinate position to obtain a circular area or a square area, such as Figure 3 As shown, the first working path 1 and the second working path 2 intersect at point A. At this time, when determining the intersection area, a circular area with point A as the center can be obtained, and a rectangular area with point A as the center can also be obtained.

[0055] Of course, in actual applications, the first operating path and the second operating path may not have an intersection, and thus there will be no intersection area. At this time, since there is no other tower crane affecting the operation of the first tower crane, there is no need to optimize and adjust the first operating path of the first tower crane.

[0056] Step 104, determining a first time when the first tower crane reaches the intersection area, and determining a second time when the second tower crane reaches the intersection area.

[0057] In one embodiment, after determining that the first operation path and the second operation path have an intersection area, the first time when the first tower crane reaches the intersection area and the second time when the second tower crane reaches the intersection area are further determined. The obtained first time and second time can be used to determine whether there is an operation conflict between the first tower crane and the second tower crane during the operation process, specifically whether they will meet.

[0058] Furthermore, when determining the first moment and the second moment, reference may be made to Figure 4 , Figure 4 It is a flowchart of the steps of obtaining the first moment and the second moment provided in an embodiment of the present application, wherein the steps include steps 401 to 403.

[0059] Step 401, obtaining the operation start time of the first tower crane, and determining the stay time at each operation point in the first operation;

[0060] Step 402, determining a first time when the first tower crane reaches the intersection area according to the operation start time, the dwell time and the first operation path;

[0061] Step 403, obtaining the current operation information of the second tower crane, and obtaining the second time when the second tower crane reaches the intersection area according to the current operation information.

[0062] Specifically, the first tower crane may be a tower crane that has not started to perform the operation. In this case, an operation start time may be set for the first tower crane, and then when the operation start time is reached, the first tower crane is controlled to start the operation. Therefore, when the first tower crane moves to the intersection area, the operation start time of the first tower crane and the length of stay of each operation point in the first operation may be obtained, such as the length of stay at each sub-operation point when the first operation includes multiple sub-operations, and the stay time of each operation point may be tabulated, such as "operation point A: 10 minutes, operation point B: 15 minutes, ...", etc., and then the first moment when the first tower crane reaches the intersection area is determined according to the operation start time, the length of stay and the first operation path. Obviously, when determining the moment when the tower crane arrives at the intersection area, the moving speed of the tower crane also needs to be considered. By accumulating the length of stay of each operation point and the path moving time (based on the path length and the moving speed) from the operation start time, the specific time when the first tower crane arrives at the intersection area, i.e., the first moment, is obtained.

[0063] Similarly, when the second moment when the second tower crane moves to the intersection area is obtained, the current operation information of the second tower crane is obtained to determine the second moment when it reaches the intersection area according to the information. In practical applications, the second tower crane may be a tower crane in operation, that is, different from the operation start time of the first tower crane. Then, when determining the second moment when the second tower crane moves to the intersection area, the current operation information of the second tower crane can be obtained to query the operation status, position, current operation point and other information of the second tower crane in real time, and then the specific time when the second tower crane reaches the intersection area, that is, the second moment, is calculated.

[0064] Step 105: Determine whether to update the first operation path according to the first moment and the second moment, and update the first operation path when it is determined to be updated.

[0065] In one embodiment. After obtaining the first moment when the first tower crane reaches the intersection area and the second moment when the second tower crane reaches the intersection area through analysis and processing, the first moment and the second moment will be used to determine whether to update the first operation path, and then when determining the update, the operation of the first tower crane is controlled based on the updated first operation path. Specifically, the first moment and the second moment represent the specific time when the first tower crane and the second tower crane reach the intersection area. When the two are the same, it means that the two reach the intersection area at the same time, that is, the first tower crane and the second tower crane meet in the intersection area. At this time, the operation of the first tower crane and the second tower crane will be affected, otherwise the two will not affect each other.

[0066] Exemplarily, when determining whether to update the first operation path according to the first moment and the second moment, it is possible to refer to Figure 5 , Figure 5It is a schematic flowchart of a step for determining whether to perform an update process provided by an embodiment of the present application. Among them, this step includes Step 501 to Step 503.

[0067] Step 501, calculate the difference based on the first moment and the second moment to obtain the corresponding time difference, and compare the time difference with a preset threshold.

[0068] Step 502, if the time difference is less than the preset threshold, perform an update process on the first operation path.

[0069] Step 503, if the time difference is greater than or equal to the preset threshold, determine whether to perform an update process on the first operation path according to whether there are operation points of the first tower crane and the second tower crane in the intersection area.

[0070] Specifically, when determining whether to perform an update process on the first operation path, calculate the time difference between the first moment and the second moment, compare the calculated time difference with the preset threshold, and then make a further judgment based on the comparison result.

[0071] Assume that the first moment is T1 and the second moment is T2. These two moments respectively represent the times when the first tower crane and the second tower crane reach the intersection area. By calculating |T2 - T1|, the time difference ΔT between the two tower cranes when reaching the intersection area is obtained. Then, compare the time difference ΔT with the preset threshold T. Among them, the preset threshold T is a safe and efficient standard used to judge whether there is a meeting conflict between the two tower cranes in the intersection area.

[0072] When making a comparison, if ΔT < T, it means that the time interval between the two tower cranes in the intersection area is too short, and there is a potential meeting conflict. At this time, the first operation path of the first tower crane can be adjusted or optimized to avoid a conflict with the second tower crane in the intersection area. Usually, the first operation path is re-planned. Of course, in actual processing, it can also be to adjust the operation speed or change the operation order, etc.

[0073] If ΔT ≥ T, further judgment is required to determine whether to perform an update process on the first operation path. Specifically, further judgment is made according to whether there are operation points of the first tower crane and the second tower crane in the intersection area.

[0074] Furthermore, when the obtained time difference is greater than or equal to a preset threshold, when performing further judgment and processing, it also includes: if it is determined that both the first tower crane and the second tower crane have working points in the intersection area, then it is determined that the first working path is updated; if it is determined that neither the first tower crane nor the second tower crane has working points in the intersection area, then it is determined not to update the first working path; if it is determined that the first tower crane or the second tower crane has working points in the intersection area, then it is determined whether to update the first path according to the timing relationship between the first moment and the second moment; wherein, if it is determined that the first tower crane has a first working point in the intersection area, then it is determined not to update the first working path; if it is determined that the second tower crane has a second working point in the intersection area, then when the first moment is before the second moment, it is determined not to update the first working path, and when the second moment is before the first moment, it is determined to update the first working path.

[0075] Exemplarily, when determining whether the first tower crane and the second tower crane have an operating point in the intersection area, there may be multiple situations, including: both the first tower crane and the second tower crane have an operating point, neither the first tower crane nor the second tower crane has an operating point, and only one of the first tower crane and the second tower crane has an operating point.

[0076] When processing the above-mentioned situations, if neither the first tower crane nor the second tower crane has an operation point in the intersection area, since the two tower cranes do not conflict in time, the first operation path may not be updated at this time.

[0077] If both the first tower crane and the second tower crane have operating points in the intersection area, since the length of time the first tower crane and / or the second tower crane stay in the intersection area is unknown, it can be directly determined that the first operating path is to be updated. Of course, in addition to directly determining that the update process is to be performed, further judgment can be made based on the operating time of the first tower crane and the second tower crane in the intersection area, and at this time, the order in which the first tower crane and the second tower crane reach the intersection area also needs to be considered. Based on this situation, when processing, the order of the first moment and the second moment is determined based on the time sequence. Taking the first moment in front and the second moment in the back as an example, the departure time of the first tower crane leaving the intersection area can be calculated at this time, that is, the first moment plus the stay time, and then the time difference between the departure time and the second moment is calculated, so as to compare the time difference obtained at this time with the preset threshold value. If the time difference obtained at this time is less than the preset threshold value, it is determined that the first operating path is to be updated, otherwise the first operating path is not to be updated. In addition, for the case where the first moment is in the back and the second moment is in the front, the processing method is the same.

[0078] If only the first tower crane has an operation point in the intersection area, it can be determined that the first operation path does not need to be updated. Of course, the order of the first moment and the second moment can also be determined based on the time sequence to determine whether the update process is required, and the specific processing method is the same as the processing method of "taking the first moment in front and the second moment in the back as an example".

[0079] If only the second tower crane has an operating point in the intersection area, the time sequence relationship of the time when the first tower crane and the second tower crane arrive at the intersection area is compared, that is, the time sequence relationship of the first moment and the second moment is compared. If the first moment is earlier than the second moment, the first operation path may not be updated, and similarly, the processing method of "taking the first moment in front and the second moment in the back as an example" may be used for further determination. If the second moment is earlier than the first moment, the first operation path may be updated, and at this time, the processing method of "the first moment in the back and the second moment in the front" may also be used.

[0080] Based on the above description, when determining whether the first tower crane and the second tower crane have an operating point in the intersection area, the time sequence relationship between the first moment and the second moment can be introduced. At the same time, when determining that there is an operating point, the residence time of the first operating point of the first tower crane and the second operating point of the second tower crane in the intersection area is determined. Then, when determining whether to update the first operating path, after considering the introduction of the residence time, it is determined whether the first tower crane and the second tower crane have an encounter conflict, and then it is more accurately determined whether the first operating path needs to be updated.

[0081] Furthermore, the above-mentioned optimization and adjustment of the first operating path of the first tower crane is a planning process performed before the operation of the first tower crane. By considering and predicting changes in the operating environment in advance, which is specifically reflected in the operation and movement of other tower cranes, timely and accurate avoidance is performed to avoid the situation where tower cranes encounter each other, thereby making the tower crane operation efficiency lower.

[0082] In actual applications, during the operation of the tower crane, there will also be situations where real-time optimization and adjustment are required. In addition to the movement of the tower crane, there are also changes in the environment caused by the tower crane operation (such as transportation), such as fixed obstacles. Therefore, Figure 6 , Figure 6 This is another flow chart of the tower crane operation path optimization processing method provided in the embodiment of the present application, wherein the step includes steps 601 to 604.

[0083] Step 601, determining whether there is a change in the position of an obstacle in the working environment;

[0084] Step 602, when it is determined that there is a position change of the obstacle, determining whether the obstacle with the position change is located on the first operation path;

[0085] Step 603, when it is determined that the first operation path is in progress, obtaining a moving distance difference between the current position of the first tower crane and the position of the obstacle;

[0086] Step 604: If the moving distance difference is equal to the preset distance difference, the first operation path is updated.

[0087] Specifically, during the operation of the first tower crane, it is determined in real time whether there is a change in the position of an obstacle in the operating environment. When it is determined that there is a change in the position of the obstacle, it is determined whether the obstacle with a changed position is on the first operating path. When it is determined that the obstacle is on the first operating path, the difference in moving distance between the current position of the first tower crane and the position of the obstacle is obtained. When it is determined that the moving distance difference is equal to a preset distance difference, the first operating path is updated.

[0088] For example, during the operation of the first tower crane, the operating environment is monitored in real time, and an image acquisition device disposed in the operating environment can be used to acquire images or videos, and then by analyzing and processing the images or videos, it is determined whether there is a change in the position of the obstacle, and whether the obstacle is in the unreachable part of the first operating path, and then by calculating the distance difference between the first tower crane and the obstacle, it is determined whether the first operating path needs to be updated. Figure 7 , during the movement of the first tower crane, when the first tower crane moves from point X to point Y, it is detected that obstacle 1 moves from point X to point Y, and point Y is in the unreached part of the first working path. At this time, the moving distance between point Y and point y is calculated, that is, the distance of the working path between point Y and point y, as the distance difference between the first tower crane and the obstacle.

[0089] When determining whether the first operating path needs to be updated, the moving distance between the first tower crane and the obstacle is constantly decreasing. At this time, the first operating path can be updated when the moving distance difference reaches the set value. Since the obstacle can also be moved away, when determining whether the first operating path needs to be updated based on the moving distance difference, the obstacle is monitored in real time to determine whether it still exists on the first operating path.

[0090] Further, refer to Figure 8 , Figure 8 This is another flow chart of the method for optimizing the tower crane operation path provided in the embodiment of the present application, wherein the steps include S1 to S4.

[0091] S1, environmental perception and information collection.

[0092] Use sensors and other data sources (such as the Beidou network) to collect real-time information about the environment around the tower crane, including the location, speed, acceleration, etc. of obstacles. Convert the collected information into a processable format, such as digital signals or image data.

[0093] S2, coordinate transformation and positioning.

[0094] The tower crane operation status monitoring and positioning module is used to locate the tower crane hoisting position and obtain the global coordinates of the construction site. The global coordinates are converted into polar coordinates with the tower crane as the origin, which facilitates subsequent path planning and obstacle avoidance calculations.

[0095] S3, global path planning.

[0096] Based on GIS technology and intelligent algorithms (such as A* algorithm, Dijkstra algorithm, etc.), the global motion trajectory of the tower crane is planned according to the target location and obstacle information. Taking into account the specific conditions of the construction site (such as the layout of buildings around the tower crane, road conditions, etc.), the planned path is optimized to improve operational efficiency.

[0097] S4, dynamic obstacle avoidance and path adjustment.

[0098] During the operation of the tower crane, the changes in the surrounding environment are monitored in real time, including new obstacles or changes in the position of obstacles (such as new vehicles). Then, using the group tower anti-collision algorithm and tower crane control experience, the movement trajectory of the tower crane is dynamically adjusted to avoid obstacles and ensure safety. If an obstacle that cannot be avoided is encountered, the operation of the tower crane can be suspended to wait for the obstacle to be eliminated or the path can be replanned.

[0099] Specifically, when performing dynamic obstacle avoidance, the tower crane is controlled to run according to the planned path and real-time environmental information. At the same time, the tower crane's operation status monitoring and positioning module is used to monitor the tower crane's position, speed and other status information in real time to ensure that the tower crane can run accurately and stably according to the planned path.

[0100] For example, at a construction site, a tower crane needs to complete the task of lifting materials from point A to point B. When planning the path, the system finds that there is an existing road from point A to point B, but there is a moving obstacle on the road (such as another construction vehicle).

[0101] At this point, you can first use GIS technology and intelligent algorithms to plan a global path from point A to point B, and try to avoid obstacles on the road. Then, during the operation of the tower crane, monitor the position and speed information of the obstacle in real time. If the obstacle approaches the tower crane or enters the movement trajectory of the tower crane, the system will dynamically adjust the movement trajectory of the tower crane based on the group tower anti-collision algorithm and tower crane control experience, such as offsetting a certain distance to the left or right to avoid the obstacle. Finally, when the tower crane successfully avoids the obstacle and approaches point B, the system will fine-tune the path based on real-time environmental information to ensure that the tower crane can accurately and stably reach point B and complete the lifting task.

[0102] In actual applications, obstacles can be fixed or other tower cranes in operation. Therefore, during the operation of the tower crane, the position and status information of other tower cranes can be monitored in real time (multiple tower cranes can be monitored in real time through monitoring equipment such as high-definition cameras and sensors to ensure that they run according to the predetermined trajectory). Once a collision risk is found, the dynamic obstacle avoidance strategy is immediately activated. According to the type and degree of collision risk, appropriate obstacle avoidance measures are taken, such as changing speed, direction or height, to avoid obstacles (i.e. other tower cranes). If the obstacle cannot be avoided, the operation of the tower crane can be suspended to wait for the obstacle to be eliminated or the path can be replanned.

[0103] When planning the path of a new tower crane, you can also first query and consider the information of the tower cranes on the planned path, and use advanced algorithms (such as heuristic search algorithms, collision detection algorithms, etc.) to plan the path of the new tower crane to ensure that it will not conflict with the tower cranes on the planned path.

[0104] During the planning process and during the operation of the tower crane, collision detection is continuously performed. If a potential collision risk is detected, the early warning mechanism is immediately triggered to warn the operator through sound, light or display. The path planning of the new tower crane is dynamically adjusted based on the real-time collision detection results and early warning information. If necessary, the operation of the tower crane with the planned path can be suspended to avoid potential collisions.

[0105] For example, on a large construction site, the paths of two cranes (Crane A and Crane B) have been planned, and now a path needs to be planned for the third crane (Crane C). At this point, the real-time position, speed, direction and other information of Crane A and Crane B are first obtained and integrated into the construction site model. When planning the path of Crane C, a collision detection algorithm can be used to detect whether the candidate path of Crane C conflicts with the planned paths of Crane A and Crane B. If a conflict is detected, the candidate path of Crane C will be adjusted until a path is found that does not conflict with Crane A and Crane B. This adjustment process may involve changing the speed, direction or selecting a new start / end point for Crane C.

[0106] In addition, during the operation of tower crane C, collision detection will continue. If a potential collision risk is detected (for example, the position of tower crane A or tower crane B is offset due to wind or other factors), the cab control terminal device will immediately trigger the early warning mechanism and warn the operator. At the same time, the path of tower crane C will be dynamically adjusted or the operation of tower crane A / B will be suspended according to the real-time situation to avoid collision.

[0107] In summary, the present application discloses a method for optimizing the operation path of a tower crane. When performing path planning, a first operation is received as input, a first tower crane that performs the first operation is determined, and then a first operation path of the first tower crane is determined. Then, a second tower crane that is in an operation state in the operation environment where the first tower crane is located is determined, and a second operation path of the second tower crane is obtained, so as to obtain an intersection area according to the first operation path and the second operation path; then, a first moment when the first tower crane reaches the intersection area is determined, and a second moment when the second tower crane reaches the intersection area is determined; finally, according to the first moment and the second moment, it is determined whether to update the first operation path, and the first operation path is updated when the update is determined. In the process of tower crane path planning, the planned operation path is updated and adjusted in a timely manner according to the operation environment where the tower crane is located, so as to improve the timeliness and accuracy of tower crane path planning and operation.

[0108] According to the method described in the above embodiment, this embodiment will be further described from the perspective of the optimization processing device of the tower crane operation path. The optimization processing device of the tower crane operation path can be implemented as an independent entity or integrated in an electronic device, such as a terminal. The terminal may include a mobile phone, a tablet computer, etc.

[0109] See also Fig. 9 , Fig. 9 is a structural schematic diagram of a tower crane operation path optimization processing device provided in an embodiment of the present application, such as Fig. 9 As shown, the tower crane operation path optimization processing device 900 provided in the embodiment of the present application includes:

[0110] A path planning module 901 is used to receive an input first operation and perform path planning to obtain a first operation path of a first tower crane performing the first operation;

[0111] The environment determination module 902 is used to determine whether the operating environment of the first tower crane includes a tower crane in an operating state, and when it is determined that the tower crane in an operating state is included, obtain a second tower crane in an operating state;

[0112] A path judgment module 903 is used to obtain a second operating path of the second tower crane, and obtain an intersection area according to the first operating path and the second operating path;

[0113] The time determination module 904 is used to determine a first time when the first tower crane arrives at the intersection area, and to determine a second time when the second tower crane arrives at the intersection area;

[0114] The update determination module 905 is used to determine whether to update the first operation path according to the first moment and the second moment, and to update the first operation path when it is determined to be updated.

[0115] In one embodiment, the path planning module 901 is further used to:

[0116] receiving an input first job and identifying a job identifier corresponding to the first job;

[0117] Matching among idle tower cranes according to the operation identifier to obtain a first tower crane for performing the first operation;

[0118] Environmental information of an operating environment of a first tower crane is obtained, and path planning is performed according to the environmental information and a first operation to obtain a first operating path of the first tower crane, wherein the environmental information includes obstacle positions, and the obstacles include tower cranes and non-tower crane objects.

[0119] In one embodiment, the path determination module 903 is further used to:

[0120] Constructing environmental coordinates corresponding to the working environment, and obtaining a first coordinate curve corresponding to the first working path and a second coordinate curve corresponding to the second working path in the environmental coordinates;

[0121] Determine whether there is an intersection coordinate between the first coordinate curve and the second coordinate curve;

[0122] When it is determined that the intersection coordinates exist, the coordinate area in the environment coordinates is obtained according to the preset area acquisition standard and the intersection coordinates, and the intersection area in the working environment is obtained according to the coordinate area.

[0123] In one embodiment, the time determination module 904 is further configured to:

[0124] Obtaining the operation start time of the first tower crane, and determining the stay time at each operation point in the first operation;

[0125] Determine the first time when the first tower crane reaches the intersection area according to the operation start time, the dwell time and the first operation path;

[0126] The current operation information of the second tower crane is obtained, and according to the current operation information, the second time when the second tower crane reaches the intersection area is obtained.

[0127] In one embodiment, the update determination module 905 is further used to:

[0128] Calculate the difference between the first moment and the second moment to obtain a corresponding time difference, and compare the time difference with a preset threshold;

[0129] If the time difference is less than a preset threshold, the first operation path is updated;

[0130] If the time difference is greater than or equal to a preset threshold, it is determined whether to update the first operation path according to whether there is an operation point between the first tower crane and the second tower crane in the intersection area.

[0131] In one embodiment, the update determination module 905 is further used to:

[0132] If it is determined that both the first tower crane and the second tower crane have operating points in the intersection area, then it is determined to update the first operating path;

[0133] If it is determined that neither the first tower crane nor the second tower crane has an operating point in the intersection area, it is determined that the first operating path is not updated;

[0134] If it is determined that the first tower crane or the second tower crane has an operating point in the intersection area, determining whether to update the first path according to the time sequence relationship between the first moment and the second moment;

[0135] If it is determined that the first tower crane has a first operating point in the intersection area, it is determined not to update the first operating path;

[0136] If it is determined that the second tower crane has a second operating point in the intersection area, when the first moment is before the second moment, it is determined not to update the first operating path, and when the second moment is before the first moment, it is determined to update the first operating path.

[0137] In one embodiment, the update determination module 905 is further used to:

[0138] Determine whether there are any changes in the position of obstacles in the working environment;

[0139] When it is determined that there is a position change of the obstacle, determining whether the obstacle with the position change is located on the first working path;

[0140] When it is determined that the first operation path is in place, obtaining a moving distance difference between a current position of the first tower crane and a position of the obstacle;

[0141] If the moving distance difference is equal to the preset distance difference, the first operation path is updated.

[0142] Also, see Fig.10 , Fig.10is a schematic diagram of the structure of an electronic device provided in an embodiment of the present application, and the electronic device may be a mobile terminal such as a smart phone, a tablet computer, or the like. Fig.10 As shown, the electronic device 1000 includes a processor 1001 and a memory 1002. The processor 1001 and the memory 1002 are electrically connected.

[0143] Processor 1001 is the control center of electronic device 1000. It uses various interfaces and lines to connect various parts of the entire electronic device. It executes various functions of electronic device 1000 and processes data by running or loading applications stored in memory 1002 and calling data stored in memory 1002, thereby monitoring electronic device 1000 as a whole.

[0144] In this embodiment, the processor 1001 in the electronic device 1000 will load the instructions corresponding to the processes of one or more applications into the memory 1002 according to the following steps, and the processor 1001 will run the application stored in the memory 1002, thereby implementing any step in the tower crane operation path optimization processing method provided in the above embodiment.

[0145] The electronic device 1000 can implement the steps in any embodiment of the method for optimizing the operating path of a tower crane provided in the embodiments of the present application. Therefore, it can achieve the beneficial effects that can be achieved by any method for optimizing the operating path of a tower crane provided in the embodiments of the present application. For details, please refer to the previous embodiments and will not be repeated here.

[0146] See also Fig.11 , Fig.11 is another structural schematic diagram of an electronic device provided in an embodiment of the present application, such as Fig.11 As shown, Fig.11 The specific structural block diagram of the electronic device provided in the embodiment of the present application is shown, and the electronic device can be used to implement the optimization processing method of the tower crane operation path provided in the above embodiment. The electronic device 1100 can be a mobile terminal such as a smart phone or a laptop computer.

[0147] The RF circuit 1110 is used to receive and send electromagnetic waves, realize the mutual conversion between electromagnetic waves and electrical signals, and thus communicate with a communication network or other devices. The RF circuit 1110 may include various existing circuit elements for performing these functions, such as antennas, radio frequency transceivers, digital signal processors, encryption / decryption chips, user identity module (SIM) cards, memories, etc. The RF circuit 1110 can communicate with various networks such as the Internet, corporate intranets, wireless networks, or communicate with other devices through wireless networks. The above-mentioned wireless networks may include cellular telephone networks, wireless local area networks, or metropolitan area networks. The above-mentioned wireless networks can use various communication standards, protocols and technologies, including but not limited to Global System for Mobile Communication (GSM), Enhanced Data GSM Environment (EDGE), Wideband Code Division Multiple Access (WCDMA), Code Division Multiple Access (CDMA), Time Division Multiple Access (TDMA), Wireless Fidelity (Wi-Fi) (such as Institute of Electrical and Electronics Engineers standards IEEE 802.11a, IEEE 802.11b, IEEE802.11g and / or IEEE802.11n), Voice over Internet Protocol (VoIP), Worldwide Interoperability for Microwave Access (Wi-Max), other protocols for email, instant messaging and short messages, and any other suitable communication protocols, even those that have not yet been developed.

[0148] The memory 1120 can be used to store software programs and modules, such as the program instructions / modules corresponding to the optimization processing method for the tower crane operating path in the above-mentioned embodiment. The processor 1180 executes various functional applications and the optimization processing method for the tower crane operating path by running the software programs and modules stored in the memory 1120.

[0149] The memory 1120 may include a high-speed random access memory, and may also include a non-volatile memory, such as one or more magnetic storage devices, flash memory, or other non-volatile solid-state memory. In some examples, the memory 1120 may further include a memory remotely arranged relative to the processor 1180, and these remote memories may be connected to the electronic device 1100 via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.

[0150] The input unit 1130 can be used to receive uploaded digital or character information, and generate keyboard, mouse, joystick, optical or trackball signal input related to user settings and function control. Specifically, the input unit 1130 may include a touch-sensitive surface 1131 and other input devices 1132. The touch-sensitive surface 1131, also known as a touch display screen or touchpad, can collect user touch operations on or near it (such as operations performed by users using fingers, styluses, or any other suitable objects or accessories on or near the touch-sensitive surface 1131), and drive corresponding connection devices according to a pre-set program. Optionally, the touch-sensitive surface 1131 may include a touch detection device and a touch controller. Among them, the touch detection device detects the user's touch orientation, detects the signal brought by the touch operation, and transmits the signal to the touch controller; the touch controller receives the touch information from the touch detection device, converts it into touch point coordinates, and then sends it to the processor 1180, and can receive and execute commands sent by the processor 1180. In addition, the touch-sensitive surface 1131 may be implemented in various types such as resistive, capacitive, infrared, and surface acoustic wave. In addition to the touch-sensitive surface 1131, the input unit 1130 may further include other input devices 1132. Specifically, the other input devices 1132 may include, but are not limited to, one or more of a physical keyboard, a function key (such as a volume control key, a switch key, etc.), a trackball, a mouse, a joystick, and the like.

[0151] The display unit 1140 can be used to display information input by the user or information provided to the user and various graphical user interfaces of the electronic device 1100, which can be composed of graphics, text, icons, videos and any combination thereof. The display unit 1140 may include a display panel 1141, and optionally, the display panel 1141 may be configured in the form of LCD (Liquid Crystal Display), OLED (Organic Light-Emitting Diode), etc. Further, the touch-sensitive surface 1131 may cover the display panel 1141, and when the touch-sensitive surface 1131 detects a touch operation on or near it, it is transmitted to the processor 1180 to determine the type of the touch event, and then the processor 1180 provides a corresponding visual output on the display panel 1141 according to the type of the touch event. Although in the figure, the touch-sensitive surface 1131 and the display panel 1141 are implemented as two independent components to implement input and output functions, in some embodiments, the touch-sensitive surface 1131 and the display panel 1141 can be integrated to implement input and output functions.

[0152] The electronic device 1100 may also include at least one sensor 1150, such as a light sensor, a motion sensor, and other sensors. Specifically, the light sensor may include an ambient light sensor and a proximity sensor, wherein the ambient light sensor may adjust the brightness of the display panel 1141 according to the brightness of the ambient light, and the proximity sensor may generate an interrupt when the flip cover is closed or closed. As a type of motion sensor, the gravity acceleration sensor can detect the magnitude of acceleration in each direction (generally three axes), and can detect the magnitude and direction of gravity when stationary. It can be used for applications that identify the posture of the mobile phone (such as horizontal and vertical screen switching, related games, magnetometer posture calibration), vibration recognition related functions (such as pedometer, tapping), etc.; as for other sensors such as gyroscopes, barometers, hygrometers, thermometers, infrared sensors, etc. that can also be configured in the electronic device 1100, they will not be repeated here.

[0153] The audio circuit 1160, the speaker 1161, and the microphone 1162 can provide an audio interface between the user and the electronic device 1100. The audio circuit 1160 can transmit the electrical signal converted from the received audio data to the speaker 1161, which is converted into a sound signal for output; on the other hand, the microphone 1162 converts the collected sound signal into an electrical signal, which is received by the audio circuit 1160 and converted into audio data, and then the audio data is processed by the output processor 1180 and sent to another terminal through the RF circuit 1110, or the audio data is output to the memory 1120 for further processing. The audio circuit 1160 may also include an earplug jack to provide communication between an external headset and the electronic device 1100.

[0154] The electronic device 1100 can help the user receive requests, send information, etc. through the transmission module 1170 (such as a Wi-Fi module), which provides the user with wireless broadband Internet access. Although the transmission module 1170 is shown in the figure, it is understandable that it is not a necessary component of the electronic device 1100 and can be omitted as needed without changing the essence of the invention.

[0155] The processor 1180 is the control center of the electronic device 1100. It uses various interfaces and lines to connect various parts of the entire mobile phone. By running or executing software programs and / or modules stored in the memory 1120, and calling data stored in the memory 1120, it executes various functions of the electronic device 1100 and processes data, thereby monitoring the electronic device as a whole. Optionally, the processor 1180 may include one or more processing cores; in some embodiments, the processor 1180 may integrate an application processor and a modem processor, wherein the application processor mainly processes the operating system, user interface, and application programs, and the modem processor mainly processes wireless communications. It can be understood that the above-mentioned modem processor may not be integrated into the processor 1180.

[0156] The electronic device 1100 also includes a power supply 1190 (such as a battery) for supplying power to various components. In some embodiments, the power supply can be logically connected to the processor 1180 through a power management system, so that the power management system can manage charging, discharging, and power consumption management. The power supply 1190 can also include any components such as one or more DC or AC power supplies, recharging systems, power failure detection circuits, power converters or inverters, and power status indicators.

[0157] Although not shown, the electronic device 1100 also includes a camera (such as a front camera, a rear camera), a Bluetooth module, etc., which will not be described in detail here. Specifically in this embodiment, the display unit of the electronic device is a touch screen display, and the mobile terminal also includes a memory, and one or more programs, wherein one or more programs are stored in the memory, and are configured to be executed by one or more processors to implement any step of the optimization processing method of the tower crane operation path provided in the above embodiment.

[0158] In specific implementation, the above modules can be implemented as independent entities, or can be arbitrarily combined and implemented as the same or several entities. The specific implementation of the above modules can be found in the previous method embodiments, which will not be repeated here.

[0159] Those skilled in the art can understand that all or part of the steps in the various methods of the above embodiments can be completed by instructions, or by controlling related hardware through instructions, and the instructions can be stored in a computer-readable storage medium and loaded and executed by a processor. To this end, an embodiment of the present application provides a storage medium, which stores multiple instructions, and when the instructions are executed by the processor, any step in the optimization processing method for the tower crane operation path provided in the above embodiments can be implemented.

[0160] The storage medium may include: a read-only memory (ROM), a random access memory (RAM), a magnetic disk or an optical disk, etc.

[0161] Since the instructions stored in the storage medium can execute the steps in any embodiment of the tower crane operating path optimization processing method provided in the embodiments of the present application, the beneficial effects that can be achieved by any tower crane operating path optimization processing method provided in the embodiments of the present application can be achieved. Please refer to the previous embodiments for details and will not be repeated here.

[0162] The above is a detailed introduction to the optimization processing method, device, electronic device and storage medium for the tower crane operation path provided by the embodiment of the present application. The principles and implementation methods of the present application are explained in this article using specific examples. The description of the above embodiments is only used to help understand the method and its core idea of ​​the present application. At the same time, for those skilled in the art, according to the idea of ​​the present application, there will be changes in the specific implementation method and application scope. In summary, the content of this specification should not be understood as a limitation on the present application. Moreover, for those of ordinary skill in the art, without departing from the principles of the present application, several improvements and modifications can be made, and these improvements and modifications are also regarded as the protection scope of the present application.

Claims

1. A tower crane operation path optimization processing method, characterized in that: include: Receiving an input first operation, and performing path planning to obtain a first operation path of a first tower crane for performing the first operation; Determine whether the operating environment in which the first tower crane is located includes a tower crane in an operating state, and when it is determined that the tower crane in an operating state is included, obtain a second tower crane in an operating state; Acquire a second operating path of the second tower crane, and obtain an intersection area according to the first operating path and the second operating path; Determine a first time when the first tower crane reaches the intersection area, and determine a second time when the second tower crane reaches the intersection area; According to the first time and the second time, it is determined whether to update the first operation path, and when it is determined to update, the first operation path is updated.

2. The method according to claim 1, characterized in that The step of receiving an input first operation and performing path planning to obtain a first operation path of a first tower crane that performs the first operation includes: receiving a first job as input, and identifying a job identifier corresponding to the first job; Matching among idle tower cranes according to the operation identifier to obtain a first tower crane for performing the first operation; Environmental information of an operating environment in which the first tower crane is located is obtained, and path planning processing is performed according to the environmental information and the first operation to obtain a first operating path of the first tower crane, wherein the environmental information includes obstacle positions, and obstacles include tower cranes and non-tower crane objects.

3. The method according to claim 1, characterized in that The acquiring the second operating path of the second tower crane and obtaining an intersection area according to the first operating path and the second operating path includes: Constructing environmental coordinates corresponding to the working environment, and obtaining a first coordinate curve corresponding to the first working path and a second coordinate curve corresponding to the second working path in the environmental coordinates; Determine whether there are intersection coordinates between the first coordinate curve and the second coordinate curve; When it is determined that there are intersection coordinates, a coordinate area in the environment coordinates is obtained according to a preset area acquisition standard and the intersection coordinates, and an intersection area in the working environment is obtained according to the coordinate area.

4. The method according to claim 1, characterized in that The determining of a first time when the first tower crane reaches the intersection area, and the determining of a second time when the second tower crane reaches the intersection area, comprises: Obtaining the operation start time of the first tower crane, and determining the stay time at each operation point in the first operation; Determine a first time when the first tower crane reaches the intersection area according to the operation start time, the stay time and the first operation path; The current operation information of the second tower crane is acquired, and according to the current operation information, a second time when the second tower crane reaches the intersection area is obtained.

5. The method according to claim 1, characterized in that The determining whether to update the first operation path according to the first moment and the second moment includes: Calculate the difference between the first moment and the second moment to obtain a corresponding time difference, and compare the time difference with a preset threshold; If the time difference is less than the preset threshold, updating the first operation path; If the time difference is greater than or equal to the preset threshold, it is determined whether to update the first operation path according to whether there are operation points of the first tower crane and the second tower crane in the intersection area.

6. The method according to claim 5, characterized in that The determining whether to update the first operation path according to whether there is an operation point in the intersection area between the first tower crane and the second tower crane includes: If it is determined that both the first tower crane and the second tower crane have operating points in the intersection area, determining to update the first operating path; If it is determined that neither the first tower crane nor the second tower crane has an operating point in the intersection area, determining not to update the first operating path; If it is determined that the first tower crane or the second tower crane has an operating point in the intersection area, determining whether to update the first path according to the time sequence relationship between the first moment and the second moment; If it is determined that the first tower crane has a first operating point in the intersection area, it is determined not to update the first operating path; If it is determined that the second tower crane has a second operating point in the intersection area, when the first moment is before the second moment, it is determined not to update the first operating path, and when the second moment is before the first moment, it is determined to update the first operating path.

7. The method according to claim 1, characterized in that The method further comprises: Determining whether there is a change in the position of an obstacle in the working environment; When it is determined that there is a change in the position of the obstacle, determining whether the obstacle with the changed position is located on the first working path; When it is determined that the first operation path is in place, obtaining a moving distance difference between a current position of the first tower crane and a position of the obstacle; If the moving distance difference is equal to the preset distance difference, the first operation path is updated.

8. A tower crane operation path optimization processing device, characterized in that: include: A path planning module, used for receiving an input first operation, and performing path planning to obtain a first operation path of a first tower crane for performing the first operation; An environment determination module, used to determine whether the operating environment in which the first tower crane is located includes a tower crane in an operating state, and when it is determined that the tower crane in an operating state is included, obtain a second tower crane in an operating state; A path judgment module, used for acquiring a second operating path of the second tower crane, and obtaining an intersection area according to the first operating path and the second operating path; A time determination module, used to determine a first time when the first tower crane arrives at the intersection area, and to determine a second time when the second tower crane arrives at the intersection area; An update judgment module is used to determine whether to update the first operation path according to the first moment and the second moment, and to update the first operation path when it is determined to be updated.

9. An electronic device, characterized in that: The electronic device comprises a processor, a memory, and a computer program stored in the memory and executable on the processor, and the processor implements the steps in the method according to any one of claims 1 to 7 when executing the computer program.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps in the method according to any one of claims 1 to 7 are implemented.

Citation Information

Cited By

  • Intelligent construction-oriented tower crane obstacle avoidance trajectory planning and self-adaptive tracking control method

    CN119200410A