Roof concrete layer divider and construction method thereof
By designing a roof concrete layer divider, using blade-shaped dividing heads and specific structures to divide and divide the partition joints on the concrete layer, the crack problem caused by temperature changes in the roof is solved, and the construction quality is improved and the cost is reduced.
Patent Information
- Application Number
- CN202411276835.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-12
- Publication Date
- 2024-11-05
AI Technical Summary
The prior art cannot effectively solve the problem of cracks caused by thermal expansion and contraction caused by temperature changes on the roof. Especially in extreme climate conditions, cracks in the roof concrete layer frequently appear, and the occurrence of cracks cannot be significantly reduced after using roof segmentation strips. .
Design a roof concrete layer divider, including smear plate, handle and division head. The lower edge of the division head is blade-shaped, which is used to divide multiple partition joints on the concrete layer, combining specific connecting parts and baffles structures to improve Cutting efficiency and accuracy reduce the appearance of cracks.
Multiple partition joints are divided into concrete layers through the splitter, which significantly reduces the occurrence of roof cracks, improves construction quality, and reduces the use of finished roof segmentation strips, saving costs.
Smart Images

Figure CN118895844A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of building concrete construction, in particular to a roof concrete layer divider and a construction method thereof. Background Art
[0002] In recent years, statistics show that thermal expansion and contraction caused by temperature changes are the most common cause of roof cracks, especially under extreme climatic conditions, where temperature changes cause material contraction and expansion, leading to a large number of cracks on the roof.
[0003] Even if the roof split strips are used, the appearance of roof cracks cannot be effectively reduced. No obvious cracks are found in the locations where the roof split strips are used, but there are a large number of irregular cracks in other locations. Comparing the tiled roof and fine stone concrete roof with the same method, the tiled roof has basically no cracks, which shows that the application of roof split joints is effective, but the roof used cannot be made into a tiled roof. A tool is needed to cut multiple split joints on the roof to prevent the appearance of roof cracks. Summary of the invention
[0004] The purpose of the present invention is to overcome the defects of the prior art, provide a roof concrete layer divider and a construction method thereof, and solve the problem that thermal expansion and contraction caused by temperature changes lead to roof cracks.
[0005] The technical solution to achieve the above-mentioned purpose is: a roof concrete layer divider, comprising: a trowel; a handle, the handle is connected to the upper end of the trowel, and is used to hold the handle and push the trowel; a dividing head, the dividing head is arranged at the bottom of the trowel, and the lower edge of the dividing head is blade-shaped and is used to divide the concrete layer.
[0006] In a roof concrete layer divider of the present invention, a plurality of dividing seams can be divided on the concrete through the dividing head of the divider, which greatly reduces the occurrence of roof cracks, improves the construction quality, and can also reduce the amount of finished roof dividing strips used, saving costs.
[0007] A further improvement of the roof concrete layer divider of the present invention is that a connecting piece is provided between the handle and the trowel, and the connecting piece is vertically supported between the handle and the trowel.
[0008] A further improvement of the roof concrete layer divider of the present invention is that a handshake space is formed between the connecting piece and the handle and the trowel.
[0009] A further improvement of the roof concrete layer divider of the present invention is that a gasket is provided between the connecting piece and the screed.
[0010] A further improvement of the roof concrete layer divider of the present invention is that the wiper plate is provided with: two first baffles, and the two first baffles are arranged at two ends of the wiper plate.
[0011] A further improvement of the roof concrete layer divider of the present invention is that the first baffle is arranged in an arc shape.
[0012] A further improvement of the roof concrete layer divider of the present invention is that the wiper plate is also provided with: two second baffles, the two second baffles are arranged on both sides of the wiper plate; the second baffles are connected to the first baffles and surround the upper end of the wiper plate.
[0013] A further improvement of the roof concrete layer divider of the present invention is that the second baffle is arranged vertically parallel to the dividing head.
[0014] A further improvement of the roof concrete layer divider of the present invention is that two sides of the dividing head are arranged in an arc shape.
[0015] A construction method for constructing a roof concrete layer using a divider comprises the following steps: when pouring the roof concrete layer, arranging dividing strips to divide the concrete layer into concrete surface blocks; planning dividing lines on the concrete surface blocks; holding the handle of the divider, moving the dividing head to divide the concrete surface blocks along the planned dividing lines to obtain dividing grooves. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 The present invention is a vertical view of a roof concrete layer divider.
[0017] Figure 2 This is a bottom view of a roof concrete layer divider according to the present invention.
[0018] Figure 3 The present invention is a cross-sectional view of a roof concrete layer divider.
[0019] Figure 4 The present invention is a schematic flow chart of a construction method for constructing a roof concrete layer using a divider.
[0020] Figure 5 It is a top view of the roof concrete layer constructed by using a divider according to the present invention.
[0021] In the figure: 10, divider; 11, spatula; 12, handle; 13, dividing head; 14, connecting piece; 15, gasket; 16, first baffle; 17, second baffle; 20, concrete surface block; 21, dividing groove. DETAILED DESCRIPTION
[0022] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.
[0023] See also Figure 1 , showing a vertical view of a roof concrete layer divider of the present invention. The present invention provides a roof concrete layer divider, comprising: a wiper plate 11.
[0024] Among them, the trowel plate 11 can be selected from the common trowel bottom plate in construction to reduce costs.
[0025] The handle 12 is connected to the upper end of the wiping board 11 and is used for pushing the wiping board 11 by holding the handle 12 .
[0026] The handle 12 is arranged parallel to the end surface of the spatula 11, so that the construction workers can push the spatula 11 by hand.
[0027] The dividing head 13 is arranged at the bottom of the screed 11, and the lower edge of the dividing head 13 is in the shape of a blade, and is used to divide the concrete layer.
[0028] The dividing head 13 is configured to be boat-shaped, so that the lower edge of the dividing head 13 can cut concrete more easily.
[0029] In this embodiment, the dividing head 13 and the bottom of the trowel plate 11 can be detachably connected, and a plurality of dividing heads 13 with different groove depths and widths are provided. Corresponding to the thickness of the concrete layer on different roofs, dividing grooves 21 with different depths and widths need to be opened. The selection is made according to actual construction requirements and is not limited here.
[0030] See also Figure 1 , showing a vertical view of a roof concrete layer divider of the present invention. The present invention provides a roof concrete layer divider, wherein a connecting member 14 is provided between a handle 12 and a trowel plate 11, and the connecting member 14 is vertically supported between the handle 12 and the trowel plate 11.
[0031] Among them, in this embodiment, the number of connecting parts 14 is two, which are respectively arranged at the two ends of the handle 12 to connect the handle 12 with the wiping plate 11. The number of connecting parts 14 can also be set to one, which is arranged at one end of the handle 12 to connect the handle 12 with the wiping plate 11. The number and setting position of the connecting parts 14 are selected according to specific needs and are not limited here.
[0032] See also Figure 1 , showing a vertical view of a roof concrete layer divider of the present invention. The present invention provides a roof concrete layer divider, wherein a handshake space is formed between the connecting member 14 and the handle 12 and the trowel 11.
[0033] The handshake space is a rectangular space, which is convenient for construction workers to operate the divider 10.
[0034] See also Figure 1, showing a vertical view of a roof concrete layer divider of the present invention. The present invention provides a roof concrete layer divider, wherein a gasket 15 is provided between a connecting member 14 and a screed plate 11.
[0035] The gasket 15 is attached to the upper end surface of the wipe board 11 , and the gasket 15 is arranged at the connection between the connecting member 14 and the wipe board 11 , so as to strengthen the connection between the connecting member 14 and the wipe board 11 .
[0036] See also Figure 1 and Figure 2 , Figure 1 A vertical view showing a roof concrete layer divider of the present invention, Figure 2 The bottom view of a roof concrete layer divider of the present invention is shown. The present invention provides a roof concrete layer divider, and the wiper plate 11 is provided with: two first baffles 16, and the two first baffles 16 are arranged at both ends of the wiper plate 11.
[0037] The first baffle 16 can reduce the resistance during operation of the divider 10 and prevent the concrete from affecting the screed 11, thereby further ensuring the quality of the construction.
[0038] See also Figure 2 , showing a bottom view of a roof concrete layer divider of the present invention. The present invention provides a roof concrete layer divider, wherein the first baffle 16 is arranged in an arc shape.
[0039] The arc-shaped first baffle 16 does not affect the sight of construction workers and can also prevent concrete mud from splashing and affecting construction quality.
[0040] See also Figure 1 , showing a vertical view of a roof concrete layer divider of the present invention. The present invention provides a roof concrete layer divider, and the wiper plate 11 is further provided with: two second baffles 17, and the two second baffles 17 are arranged on both sides of the wiper plate 11.
[0041] The second baffle 17 further protects the screed 11 from two sides to prevent the concrete from affecting the divider 10 during construction.
[0042] The second blocking piece 17 is connected with the first blocking piece 16 and surrounds the upper end of the wiper plate 11 .
[0043] The first blocking piece 16 and the second blocking piece 17 are both disposed along the edge of the wipe board 11 to protect the wipe board 11 .
[0044] See also Figure 1 , showing a vertical view of a roof concrete layer divider of the present invention. The present invention provides a roof concrete layer divider, wherein the second baffle 17 and the dividing head 13 are arranged vertically and parallelly.
[0045] Among them, the second baffle 17 is arranged perpendicular to the upper end surface of the squeegee 11, and a groove is formed between the second baffle 17 and the squeegee 11 to protect the middle handle 12, and the dividing head 13 is arranged directly below the handle 12 for the convenience of construction workers.
[0046] See also Figure 3 , showing a cross-sectional view of a roof concrete layer divider of the present invention. The present invention provides a roof concrete layer divider, and the two sides of the dividing head 13 are arranged in an arc shape.
[0047] Among them, the arc-shaped side can reduce working resistance, and the cutting surface formed on the concrete is very smooth and presents a beautiful effect.
[0048] See also Figure 4 and Figure 5 , Figure 4 A schematic flow chart of a construction method for constructing a roof concrete layer using a divider according to the present invention is shown. Figure 5 The present invention provides a method for constructing a roof concrete layer using a divider 10, comprising the following steps:
[0049] Execute step S210: when pouring the roof concrete layer, arrange the dividing strips to divide the concrete layer into concrete surface blocks 20.
[0050] The dividing strips need to be placed on the concrete layer until the concrete is completely solidified, and then step S220 is performed.
[0051] Execute step S220: plan a dividing line on the concrete surface block 20 .
[0052] The dividing lines are arranged horizontally and vertically on the concrete surface block 20 to further divide the concrete surface block 20. The planning of the dividing lines should consider the density according to the thickness of the concrete in the actual construction. The number and density of the dividing lines are not specifically set here. Then, step S230 is executed.
[0053] Execute step S230 : hold the handle 12 of the divider 10 , and use the dividing head 13 to divide the concrete surface block 20 along the planned dividing line to obtain the dividing groove 21 .
[0054] In the process of dividing by holding the divider 10, it is necessary to level it and keep the divider 10 in a balanced state so that the cut dividing grooves 21 have a uniform depth and a smooth groove wall.
[0055] The present invention is described in detail above in conjunction with the embodiments of the drawings. A person skilled in the art can make various changes to the present invention according to the above description. Therefore, certain details in the embodiments should not be construed as limiting the present invention, and the scope of protection of the present invention shall be the scope defined by the attached claims.
Claims
1. A roof concrete layer divider, It is characterized in that include: Wipe board; A handle connected to the upper end of the wiper and used for holding the handle to push the wiper; A dividing head is arranged at the bottom of the screed, and the lower edge of the dividing head is in the shape of a blade and is used to divide the concrete layer.
2. A roof concrete layer divider according to claim 1, It is characterized in that A connecting piece is provided between the handle and the wiping board, and the connecting piece is vertically supported between the handle and the wiping board.
3. A roof concrete layer divider according to claim 2, It is characterized in that A handshake space is formed between the connecting piece, the handle and the wiping board.
4. A roof concrete layer divider according to claim 2, It is characterized in that A gasket is provided between the connecting piece and the wiping plate.
5. A roof concrete layer divider according to claim 1, It is characterized in that The wipe board is provided with: Two first blocking pieces are arranged at two ends of the wiper.
6. A roof concrete layer divider according to claim 5, It is characterized in that The first blocking piece is arranged in an arc shape.
7. A roof concrete layer divider according to claim 5, It is characterized in that The wipe board is also provided with: Two second blocking pieces, the two second blocking pieces are arranged on both sides of the wiper; The second blocking piece is connected to the first blocking piece and surrounds the upper end of the wiper plate.
8. A roof concrete layer divider according to claim 7, It is characterized in that The second baffle is arranged vertically and parallelly to the dividing head.
9. A roof concrete layer divider according to claim 1, It is characterized in that The two sides of the dividing head are arranged in an arc shape.
10. A method for constructing a roof concrete layer using a divider, It is characterized in that The steps include: When pouring the roof concrete layer, arranging the dividing strips to divide the concrete layer into concrete face blocks; Planning a dividing line on the concrete surface block; Holding the handle of the divider, the dividing head is moved along the planned dividing line to divide the concrete surface block to obtain a dividing groove.