Prefabricated preliminary bracing structure for tunnel partial excavation and assembling method thereof
Through the prefabricated initial support structure and its assembly method, the problems of many tunnel construction processes, long time and large disturbances are solved, and fast and safe tunnel support is achieved, which improves the safety and durability of the tunnel structure and reduces the Construction cost.
Patent Information
- Application Number
- CN202411031625.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-11-05
AI Technical Summary
There are many initial support construction processes, long time and great disturbances in the existing tunnel, resulting in increased pressure on surrounding rocks, affecting the safety and durability of the tunnel structure.
The prefabricated initial support structure and its assembly method are adopted to simplify the construction process through sliding connections and reduce construction time. Prefabricated concrete and steel frame structures are used, combined with the advance small conduit system and the locking anchor system to quickly complete the support and reduce the Disturbance to surrounding rocks.
Shorten the total initial support time, reduce surrounding rock disturbance, improve tunnel structure safety and durability, reduce construction costs, and optimize construction quality and personnel configuration.
Smart Images

Figure CN118895987A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of tunnel engineering, and in particular relates to a prefabricated initial support structure for tunnel partial excavation and an assembly method thereof. Background Art
[0002] Tunnel excavation will disturb the surrounding rock, reduce the strength and integrity of the surrounding rock, and increase the surrounding rock pressure acting on the tunnel structure. The initial support is the main load-bearing body of the highway and railway tunnel structure. If the initial support can be carried out in sections after the excavation, it can effectively control the disturbance of the surrounding rock around the tunnel, reduce the surrounding rock pressure, and improve the safety and durability of the tunnel structure.
[0003] The existing initial support of tunnels is carried out on-site closely following excavation, involving processes such as shotcrete, erecting steel frames, welding longitudinal connecting bars, welding steel mesh, and secondary shotcrete. It requires cooperation between workers of different trades and timely material supply. The total duration of initial support is about 5-10 hours, and the construction quality is difficult to control. The support process continuously disturbs the surrounding rock around the tunnel, causing continuous deformation of the surrounding rock and continuous increase in surrounding rock pressure, which ultimately increases the surrounding rock pressure acting on the tunnel, affecting the safety and durability of the tunnel structure. There is an urgent need for a rapid construction method for the initial support structure under partial excavation to ensure construction quality and improve tunnel safety and durability. Summary of the invention
[0004] In order to overcome the problems of many construction procedures, long time, large disturbance and difficult to control construction quality of on-site initial support for tunnels, the present invention provides a prefabricated initial support structure for tunnel partial excavation and an assembly method thereof. The corresponding initial supports and connectors are prefabricated based on the partial excavation size. When the lower initial support is installed, it can be connected to the upper initial support by sliding, effectively reducing the construction procedures, time and large disturbance of the initial support, improving the quality of the initial support, and improving the safety and durability of the tunnel.
[0005] To achieve the above object, the technical solution of the present invention is as follows:
[0006] The prefabricated initial support structure used for tunnel section excavation includes an upper step initial support, an invert initial support, two middle step initial supports and two lower step initial supports assembled through connection units; each initial support includes a prefabricated concrete body and connection ends arranged at both ends of the body;
[0007] The head of the connecting end is a comb-shaped structure, and is provided with a plurality of teeth and slots of matching length and width; the tail of the connecting end is a groove, which is covered and nested in the end of the supporting unit body and is fixedly connected with the inner steel frame and the inner support of the end; the teeth of each initial support connection unit are embedded in the corresponding slot of the adjacent initial support connection unit;
[0008] The six connecting units connect the upper step initial support, the invert initial support, the middle step initial support and the lower step initial support to form a single-stage initial support structure.
[0009] In the above-mentioned prefabricated initial support structure for tunnel section excavation, the head of each connecting end is provided with 2 slots and 2 tooth heads.
[0010] In the above-mentioned prefabricated initial support structure used for partial tunnel excavation, each initial support also includes an accessory unit, and the additional unit includes an advance small conduit system and a locking foot anchor system; wherein the advance small conduit system includes an advance small conduit and a small conduit guide hole; the locking foot anchor system includes a locking foot anchor and an anchor guide hole.
[0011] In the above-mentioned prefabricated initial support structure used for tunnel partial excavation, the small conduit guide hole is a prefabricated structure and is fixed on the steel frame, passing through the upper step initial support; the advance small conduit passes through the small conduit guide hole and is connected thereto; the anchor rod guide hole is a prefabricated structure and is fixed on the steel frame and the bottom joint, and passes through the support unit; the locking foot anchor rod passes through the anchor rod guide hole and is connected thereto.
[0012] In the above-mentioned prefabricated initial support structure used for tunnel partial excavation, the body of each initial support includes a steel frame, a steel frame support and an end internal support; the steel frame is a prefabricated structure of several rows, the steel frame support is connected to the steel frame; the end internal support is connected to the steel frame and the connecting unit.
[0013] In the above-mentioned prefabricated initial support structure for tunnel section excavation, the connection unit also includes a reinforcement plate and a latch arranged on the connection end, the reinforcement plate is welded to the inner side of the connection unit, and the latch is fixed to the reinforcement plate and the connection end.
[0014] The above-mentioned prefabricated initial support structure for tunnel partial excavation also includes a waterproof unit arranged on the periphery of the connecting unit, and the waterproof unit includes a grouting void, a grouting body, a grouting hole and an exhaust hole; the grouting void is arranged in the over-excavated part area of the surrounding rock outside the connecting unit, and after the support structure is spliced, a quick-setting and water-blocking grouting body is injected into the grouting void through the grouting hole, and the air in the grouting void is discharged from the exhaust hole.
[0015] In the above-mentioned prefabricated initial support structure for tunnel section excavation, the protrusions of the tooth heads and the grooves of the card slots at both ends of the middle step initial support are in horizontal directions, and the protrusions of the tooth heads and the grooves of the card slots at both ends of the invert initial support are in vertical directions.
[0016] The method for assembling a prefabricated initial support structure for tunnel section excavation comprises the following steps:
[0017] Step 1: After excavating the upper step of the first-stage footage according to the tunnel excavation contour line, install the initial support of the upper step and apply the locking anchor system and the advance small guide tube system;
[0018] Step 2: After excavating the upper step of the secondary footage and the middle step of the first footage respectively according to the tunnel excavation contour line, install the initial support of the middle step of the first footage and the initial support of the upper step of the secondary footage; slide the tooth head protrusion into the slot under the guidance of the slot to complete the splicing, and weld the reinforcement plate on the inner side of the connection of the connection unit; then construct the locking foot anchor system of the middle step of the first footage and the upper step of the secondary footage and the advance small guide tube system of the upper step of the secondary footage; finally, inject and form a waterproof grouting body through the grouting hole to cover the outer side of the connection unit;
[0019] Step 3: After excavating the upper step of the third-level footage, the middle step of the second-level footage and the lower step of the first-level footage respectively according to the tunnel excavation contour line, assemble the initial support of the lower step of the first-level footage, the initial support of the middle step of the second-level footage and the initial support of the upper step of the third-level footage respectively according to the methods described in Steps 1 and 2, weld the connection units, and install the reinforcement plates; then, apply the locking foot anchor system and the advance small guide tube system respectively according to the installation sequence, and finally apply the waterproof grouting body;
[0020] Step 4: After excavating the upper step of the fourth-level footage, the middle step of the third-level footage, the lower step of the second-level footage and the inverted arch of the first-level footage according to the tunnel excavation contour line, assemble the initial support of the inverted arch of the first-level footage, the initial support of the lower step of the second-level footage, the initial support of the middle step of the third-level footage and the initial support of the upper step of the fourth-level footage respectively with reference to steps 1 to 3, weld the reinforcement plate, and install the pin at the connection between the initial support of the lower step of the first-level footage and the initial support of the inverted arch; then, apply the locking foot anchor system and the advance small guide tube system respectively according to the installation sequence, and finally apply the waterproof grouting body;
[0021] Step 5: The initial support of the first advance is closed to form a complete arch, and steps 1 to 4 are repeated until the initial support is completed.
[0022] The beneficial effects of the present invention are as follows:
[0023] 1. The scheme of on-site splicing after prefabricating the support structure components of the present invention can reduce the initial support construction process and construction time, and simplify the processes of shotcrete, erecting steel frames, welding longitudinal connecting bars, welding steel mesh, secondary shotcrete, etc. into sliding splicing prefabricated initial support, shortening the total initial support time of 5-10 hours to 1-2 hours.
[0024] 2. The scheme of the present invention can reduce the disturbance to the surrounding rock of the tunnel and improve the safety of the tunnel structure: by reducing the construction time, the initial support can quickly support the surrounding rock and control the deformation of the surrounding rock, which is helpful to generate soil arch effect inside the soil body, transfer the overburden of the tunnel to both sides of the tunnel, reduce the pressure of the tunnel surrounding rock, make the tunnel structure less stressed, and improve the safety of the tunnel structure.
[0025] 3. The scheme of the present invention can improve the construction quality of initial support and the durability of the structure: the processes of shotcrete, erecting steel frames, welding longitudinal connecting bars, welding steel meshes, secondary shotcrete and other processes carried out on site are changed to prefabricated initial support in the prefabrication yard, which can realize standardized prefabrication, mechanized operation and concrete curing, effectively improve the material strength, dimensional standardization and overall stiffness of the initial support, and make the tunnel structure more durable.
[0026] 4. The scheme of the present invention can reduce construction costs: by simplifying the construction process, it can effectively optimize on-site construction personnel, especially high-risk construction personnel, while reducing the requirements for material preparation, transportation, and preparation; by replacing on-site construction with prefabricated standardized construction, prefabrication time is more sufficient, reducing night construction and overtime costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 This is an overall view of the spliced prefabricated initial support structure of the present invention.
[0028] Figure 2 It is a schematic diagram of the steel frame, locking anchor rods and initial support connectors of the present invention.
[0029] Figure 3 This is a schematic diagram of the splicing process of the bottom connecting end of the upper step and the top connecting end of the middle step.
[0030] Figure 4 This is a schematic diagram of the splicing process of the bottom connecting end of the middle step and the top connecting end of the lower step.
[0031] Figure 5 This is a schematic diagram of the splicing process of the bottom connecting end of the lower step and the top connecting end of the invert arch.
[0032] Figure 6 Schematic diagram of the overall splicing process of initial support.
[0033] Figure 7 This is a schematic diagram of the initial support construction process during the excavation process.
[0034] The accompanying drawings are marked as follows: 11, initial support for upper step; 12, initial support for middle step; 13, initial support for lower step; 14, initial support for invert; 21, steel frame; 22, steel frame support; 23, end internal support; 31, top joint; 32, bottom joint; 33, tooth head; 34, slot; 35, reinforcement plate; 36, latch; 41, grouting gap; 42, grouting body; 43, grouting hole; 44, exhaust hole; 51, advance small duct system; 51-1 advance small duct; 51-2, small duct guide hole; 52, locking foot anchor rod system; 52-1, locking foot anchor rod; 52-2, anchor rod guide hole; 61, first-level footage; 62, second-level footage; 63, third-level footage; 64, fourth-level footage; 7, excavation step; 71, upper step; 72, middle step; 73, lower step; 74, invert. DETAILED DESCRIPTION
[0035] The invention patent of this article is further described below in conjunction with the accompanying drawings:
[0036] like Figure 1-6 As shown, a prefabricated initial support structure for partial tunnel excavation of the present invention includes a support unit, a structural unit, a connection unit, a waterproof unit and an additional unit.
[0037] The support unit includes a single upper step initial support 11, two symmetrically arranged middle step initial supports 12 and lower step initial supports 13, and a single invert initial support 14; the initial support is prefabricated with concrete to support and maintain the stability of the tunnel.
[0038] The structural unit is enclosed in the supporting unit, including a steel frame 21, a steel frame support 22, and an end internal support 23; the steel arch frame 11 is several rows of prefabricated components, and its bending curvature is consistent with the tunnel excavation line, which can reinforce the concrete and serve as a fulcrum for the additional unit; several steel frame supports 22 are longitudinally connected to the steel arch frame 11, which can maintain the shape, position and spacing of the steel frame 11 and enhance its lateral stiffness; the basic function of the end internal support 23 is consistent with that of the steel frame support 22, but it is connected to the connecting unit, which can enhance the connection strength and bending stiffness at the connection of the supporting unit.
[0039] The connection unit is a steel structure, and its connection is a comb-shaped structure, which is provided with a tooth head 33 and a slot 34 with matching length and width. The tail of the connection unit is a groove, which can cover the end of the nested support unit and be connected to its inner steel frame 21 and the end inner support 23; the connection unit can be divided into a top joint 31 located at the upper part of each support unit and a bottom joint 32 at the lower part. The protrusion of the tooth head 33 and the opening of the slot 34 at the top joint 31 face the outside of the tunnel; the protrusion of the tooth head 33 and the opening of the slot 34 at the bottom joint 32 face the inside of the tunnel. During installation, the tooth head 33 of the connection unit at the end of each support unit is embedded in the slot 34 of the adjacent connection unit under the guidance of the opening, so that the connection unit at the end of the to-be-installed support unit and the installed support unit is connected; the protrusion of the tooth head 33 and the grooves of the slot 34 on the two ends of the middle step initial support 12 and the adjacent connection unit 3 are all in the horizontal direction, and the protrusion of the tooth head 33 and the grooves of the slot 34 on the two ends of the inverted arch initial support 14 and the adjacent connection unit 3 are all in the vertical direction. During assembly, the middle step initial support 12 and the lower step initial support 13 are spliced by horizontal translation, and the inverted arch initial support 14 is spliced by vertical translation. After the connection is completed, the inner side of the connection of adjacent connection units is welded through the length and then the reinforcement plate 35 is welded to increase the bending stiffness and shear strength of the connection. In addition, after the inverted arch initial support 14 is spliced, the pin 36 is inserted to increase the shear strength of the connection.
[0040] The waterproof unit is coated on the outside of the connection unit to protect it from erosion by groundwater and other corrosive substances that reduce its strength; the waterproof unit includes a grouting space 41, a grouting body 42, a grouting hole 43 and an exhaust hole; during grouting, flowing, fast-setting and water-stopping grouting material is injected through the grouting hole 43 below the bottom joint 32, and the grouting material gradually fills the grouting space 41 obtained by over-excavation between the connection unit and the surrounding rock, and at the same time, the air in the grouting space 41 is discharged from the exhaust hole 44 above the top joint. After the grouting material overflows from the exhaust hole 44, it indicates that the grouting material has filled the grouting space 41, blocking the grouting hole 43 and the exhaust hole 44. After the grouting material solidifies, a grouting body is formed to coat the outside of the connection unit.
[0041] The additional unit can maintain the stability of the surrounding rock and the supporting structure, including the advance small conduit system 51 located at the arch of the upper step initial support 11 and the locking foot anchor system located at the lower part of the upper step initial support 11, the middle step initial support 12, and the lower step initial support 13. Other additional systems can also be installed according to engineering requirements; the advance small conduit system 51 includes an advance small conduit 51-1 and a small conduit guide hole 51-2; the small conduit guide hole 51-2 is a prefabricated structure and is fixed on the steel frame 21, and passes through the upper step initial support 11; when the advance small conduit 51-1 is installed, it is passed through the small conduit guide hole 51-2 and drilled Enter the surrounding rock, and after the advance small guide tube 51-1 is tightly connected to the surrounding rock, it is tightly connected to the small guide tube guide hole 51-2 to achieve connection with the steel frame 21; the locking foot anchor system includes a locking foot anchor 52-1 and an anchor guide hole 52-2; the anchor guide hole 52-2 is a prefabricated structure and is connected to the steel frame 21 and the bottom joint 32, and passes through the upper step initial support 11; when the locking foot anchor 51-1 is applied, it is passed through the anchor guide hole 52-2 and driven into the rock mass, and after the locking foot anchor 51-1 is tightly connected to the surrounding rock, it is tightly connected to the anchor guide hole 52-2 to achieve connection with the steel frame 21 and the bottom joint 32.
[0042] In addition, the initial support construction process of the entire tunnel includes 2-5 groups of prefabricated initial support structures that are spliced synchronously.
[0043] like Figure 7 As shown, the initial support construction process of the entire tunnel includes 2-5 groups of prefabricated initial support structures that are spliced synchronously. The excavation footage can be divided into a first-level footage 61, a second-level footage 62, a third-level footage 63 and a fourth-level footage 64. The excavation steps 7 are divided into an upper step 71, a middle step 72, a lower step 73 and an invert 74.
[0044] The method for assembling a prefabricated initial support structure for tunnel segment excavation of the present invention comprises the following steps:
[0045] Step 1: After excavating the upper step 71 of the first-stage footage 61 according to the tunnel excavation contour line, install the upper step initial support 1 and implement the locking foot anchor system 52 and the advance small guide tube system 51.
[0046] Step 2: After excavating the upper step 71 of the secondary footage 62 and the middle step 72 of the first footage 61 respectively according to the tunnel excavation contour line, install the initial support 12 of the middle step of the first footage 61 and the initial support 11 of the upper step of the secondary footage 62; during installation, the protrusion of the tooth head 33 slides and fits into the slot 34 under the guidance of the slot 34 to complete the installation, and welds the inner side of the connection of adjacent connection units through the length, and then welds the reinforcement plate 35; then, the locking foot anchor system 52 of the middle step of the first footage and the upper step of the secondary footage and the advance small guide tube system 51 of the upper step of the secondary footage are constructed; finally, the waterproof grouting body 42 is injected through the grouting hole 43 to cover the outer side of the connection unit.
[0047] Step 3: After excavating the upper step 71 of the third-level footage 63, the middle step 72 of the second-level footage 62 and the lower step 73 of the first-level footage 61 according to the tunnel excavation contour line, install the initial support 13 of the lower step of the first-level footage 61, the initial support 12 of the middle step of the second-level footage 62 and the initial support 11 of the upper step of the third-level footage 63 respectively with reference to the methods described in steps 1 and 2, and weld the connection unit and the reinforcement plate 35 in the order of initial support installation; then apply the locking foot anchor system 52 and the advance small guide tube system 51 in the order of installation, and finally apply the waterproof grouting body 42.
[0048] Step 4: After excavating the upper step 71 of the fourth-level footage 64, the middle step 72 of the third-level footage 63, the lower step 73 of the second-level footage 62 and the invert 74 of the first-level footage 61 according to the tunnel excavation contour line, install the initial support 14 of the invert of the first-level footage 61, the initial support 13 of the lower step of the second-level footage 62, the initial support 12 of the middle step of the third-level footage 63 and the initial support 11 of the upper step of the fourth-level footage 64 respectively with reference to steps 1 to 3; weld the connecting unit and the reinforcing plate 35 according to the installation sequence of the support units, and install the pin 36 at the connection between the initial support 13 of the lower step of the first-level footage 61 and the initial support 14 of the invert; then apply the locking foot anchor system 52 and the advance small guide tube system 51 respectively according to the installation sequence, and finally apply the waterproof grouting body 42.
[0049] Step 5: The initial support of the first advance is closed to form a complete arch, and steps 1 to 4 are repeated until the initial support is completed.
Claims
1. Prefabricated initial support structure for tunnel section excavation, characterized by: It comprises an upper step initial support (11), an inverted arch initial support (14), two middle step initial supports (12) and two lower step initial supports (13) assembled through connection units; each initial support comprises a prefabricated concrete body and connection ends arranged at both ends of the body; The head of the connecting end is a comb-shaped structure and is provided with a plurality of teeth (33) and slots (34) of matching length and width; the tail of the connecting end is a groove, which covers and nests in the end of the supporting unit body and is fixedly connected with the inner steel frame (21) and the inner support (23) of the end; the teeth (33) of each initial supporting connecting unit are embedded in the corresponding slot (34) of the adjacent initial supporting connecting unit; Six connection units connect the upper step initial support (11), the invert initial support (14), the middle step initial support (12) and the lower step initial support (13) to form a single-stage initial support structure.
2. The prefabricated initial support structure for tunnel partial excavation according to claim 1 is characterized in that: The head of each connecting end is provided with two clamping grooves (34) and two tooth heads (33).
3. The prefabricated initial support structure for tunnel partial excavation according to claim 1 is characterized in that: Each initial support also includes an accessory unit, wherein the accessory unit includes an advanced small catheter system (51) and a locking foot anchor rod system (52); wherein the advanced small catheter system (51) includes an advanced small catheter (51-1) and a small catheter guide hole (51-2); and the locking foot anchor rod system (52) includes a locking foot anchor rod (52-1) and an anchor rod guide hole (52-2).
4. The prefabricated initial support structure for tunnel partial excavation according to claim 3 is characterized in that: The small conduit guide hole (51-2) is a prefabricated structure and is fixed on the steel frame (21), and passes through the upper step initial support (11); the advance small conduit (51-1) passes through the small conduit guide hole (51-2) and is connected thereto; the anchor rod guide hole (52-2) is a prefabricated structure and is fixed on the steel frame (21) and the bottom joint (32), and passes through the support unit; the locking foot anchor rod (51-1) passes through the anchor rod guide hole (52-2) and is connected thereto.
5. The prefabricated initial support structure for tunnel partial excavation according to claim 1, characterized in that: The body of each initial support includes a steel frame (21), a steel frame support (22) and an end inner support (23); the steel frame (21) is a prefabricated structure of several rows, the steel frame support (22) is connected to the steel frame (21); the end inner support (23) is connected to the steel frame (21) and the connection unit.
6. The prefabricated initial support structure for tunnel partial excavation according to claim 1, characterized in that: The connection unit also includes a reinforcing plate (35) and a latch (36) arranged at the connection end. The reinforcing plate (35) is welded to the inner side of the connection unit, and the latch (36) is fixed to the reinforcing plate (35) and the connection end.
7. The prefabricated initial support structure for tunnel partial excavation according to claim 1 is characterized in that: It also includes a waterproof unit arranged on the periphery of the connection unit, the waterproof unit including a grouting space (41), a grouting body (42), a grouting hole (43) and an exhaust hole (44); the grouting space (41) is arranged in the over-excavated part of the surrounding rock outside the connection unit, and after the support structure is spliced, a quick-setting and water-blocking grouting body (42) is injected into the grouting space (41) through the grouting hole (43), and the air in the grouting space (41) is exhausted through the exhaust hole (44).
8. The prefabricated initial support structure for tunnel partial excavation according to claim 1, characterized in that: The protrusions of the tooth heads (33) at both ends of the middle step initial support (12) and the grooves of the clamping groove (34) are both in the horizontal direction, and the protrusions of the tooth heads (33) at both ends of the inverted arch initial support (14) and the grooves of the clamping groove (34) are both in the vertical direction.
9. A method for assembling a prefabricated initial support structure using the prefabricated initial support structure for tunnel partial excavation according to any one of claims 1 to 8, characterized in that: The following steps are involved: Step 1: After excavating the upper step (71) of the first-stage footage (61) according to the tunnel excavation contour line, install the upper step initial support (1) and apply the locking foot anchor system (52) and the advance small guide tube system (51); Step 2: After excavating the upper step (71) of the secondary footage (62) and the middle step (72) of the primary footage (61) respectively according to the tunnel excavation contour line, install the initial support (12) of the middle step of the primary footage (61) and the initial support (11) of the upper step of the secondary footage (62); slide the protrusion of the tooth head (33) into the slot (34) under the guidance of the slot (34) to complete the splicing, and weld the reinforcement plate (35) on the inner side of the connection of the connection unit; then construct the locking foot anchor rod system (52) of the middle step of the primary footage and the upper step of the secondary footage and the advance small guide tube system (51) of the upper step of the secondary footage; finally, inject and form a waterproof grouting body (42) through the grouting hole (43) to cover the outer side of the connection unit; Step 3: After excavating the upper step (71) of the third-level footage (63), the middle step (72) of the second-level footage (62) and the lower step (73) of the first-level footage (61) according to the tunnel excavation contour line, assemble the initial support (13) of the lower step of the first-level footage (61), the initial support (12) of the middle step of the second-level footage (62) and the initial support (11) of the upper step of the third-level footage (63) according to the methods described in Steps 1 and 2, weld the connection units, and install the reinforcement plate (35); then, apply the locking foot anchor system (52) and the advance small guide tube system (51) respectively according to the installation sequence, and finally apply the waterproof grouting body (42); Step 4: after excavating the upper step (71) of the fourth-level footage (64), the middle step (72) of the third-level footage (63), the lower step (73) of the second-level footage (62) and the inverted arch (74) of the first-level footage (61) according to the tunnel excavation contour line, assemble the initial support (14) of the inverted arch of the first-level footage (61), the initial support (13) of the lower step of the second-level footage (62), the initial support (12) of the middle step of the third-level footage (63) and the initial support (11) of the upper step of the fourth-level footage (64) respectively with reference to steps 1 to 3, weld the reinforcing plate (35), install the latch (36) at the connection between the initial support (13) of the lower step of the first-level footage (61) and the initial support (14) of the inverted arch; then, apply the locking foot anchor system (52) and the advance small guide tube system (51) respectively according to the installation sequence, and finally apply the waterproof grouting body (42); Step 5: The initial support of the first advance is closed to form a complete arch, and steps 1 to 4 are repeated until the initial support is completed.