Temporary hanging system for replacing hanging rod of railway-crossing tied-arch bridge and hanging rod replacing method

Through the use of the temporary lifting system, the problem of difficult and high safety risks of replacement of cross-rail mount arch bridge booms is solved, and safe and efficient construction of the designated skylight points in the railway map is achieved, and it is adapted to the low clearance height and compact environment. Boom replacement requirements.

CN118911045APending Publication Date: 2024-11-08ZHENGZHOU ZHONGYUAN RAILWAY ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411326233.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-23
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

The existing boom replacement device is difficult to apply to cross-rail arch bridges, which are difficult to construct and have high safety risks, and are prone to collision with the railway contact network load-bearing cable and return line, affecting railway transportation.

Method used

A temporary hanging system for replacement of cross-rail rail arch bridge hoist booms, including a first temporary hanging boom, a second temporary hanging boom, a support assembly, a first temporary steel beam, a second temporary steel beam, a temporary anchor and a lower pocket hoist The steel plate bottom support is fitted with the bridge beam through the lower hanging steel plate bottom support, increasing the contact area and adapting to a low clearance height and compact construction environment.

Benefits of technology

It has achieved higher safety in maintaining normal operation of railways when the railway map is constructed at the railway map, adapting to the replacement of cross-rail tied arch bridge booms, reducing construction difficulty and safety risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911045A_ABST
    Figure CN118911045A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of bridge maintenance, and particularly relates to a temporary hanging system for replacing a hanging rod of a railway-crossing tied-arch bridge and a hanging rod replacing method, a lower hanging steel plate bottom support is adopted, and the lower hanging steel plate bottom support comprises a bottom plate, side plates connected to the two sides of the bottom plate and a fixing plate vertically connected to the top of each side plate. The fixing plate is used for fixing the temporary suspender and the temporary steel cross beam, the bottom plate is used for being attached to the bottom face of the under-bridge cross beam, and the side plate is used for being attached to the side face of the under-bridge cross beam. The thickness of the steel plate is smaller, the difference between the height of the steel plate and the shoulder pole beam and the length of the shoulder pole beam extending out of the two sides of the bridge lower cross beam is large, and the contact area of the lower hanging steel plate bottom support and the bridge lower cross beam is larger than that of the shoulder pole beam in the prior art. Therefore, the method can be suitable for replacing the suspender of the railway-crossing tied-arch bridge with low clearance height under the bridge and close transverse and vertical distances between a catenary carrier cable and a return line and an under-bridge cross beam.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of bridge maintenance, and in particular relates to a temporary hanging system for replacing hangers of a tie-bar arch bridge across a railway and a hanger replacement method. Background Art

[0002] The tied arch bridge is a typical type of arch bridge. It is widely used for its advantages such as external static determination, internal static overdetermination, no horizontal thrust at the arch foot under the action of lateral force, low height of the approach bridges at both ends, and low requirements for geological conditions. The hanger is one of the main load-bearing components of the tied arch bridge. The lower end is connected to the crossbeam and the upper end is connected to the arch rib. It plays an important role in transferring the bridge deck load to the arch rib. During long-term use, the hanger will have various diseases, such as cracking and falling off of the upper and lower anchor head protective concrete; loosening, failure, and slipping of the anchor; uneven force on the hanger steel strand or wire. The existence of these diseases of the tied arch bridge poses a serious hidden danger to the safety of the bridge. Therefore, the hanger should be replaced after a long period of use.

[0003] The tied arch bridge is used in many occasions, such as urban traffic arteries, highways, railways, rivers, etc. The more common tied arch bridge suspender replacement method in the prior art is the tied arch bridge suspender replacement device disclosed in the Chinese invention patent with the authorization announcement number CN102286942B, which uses threaded rods, Bailey truss beams, shoulder pole beams, distribution beams, through-type hydraulic jacks, through-type sensors and other components, wherein the shoulder pole beam is arranged below the cross beam below the suspender to be replaced, and the Bailey truss beam is located above the pad beam arranged on the bridge and is erected between adjacent suspenders. Since the shoulder pole beam is mostly made of I-beams in actual use, the height of the I-beams is relatively high. The tied arch bridge for which the suspenders need to be replaced in this application is located on a multi-track railway trunk line. The multi-track contact network load-bearing cables and return lines in the railway fence are relatively close to the horizontal and vertical distances from the cross beams under the bridge. The construction under the bridge needs to be carried out at the skylight point, which is difficult to construct and has high safety risks. The construction under the bridge in the railway fence also requires the contact network to be shut down for cooperation. The devices and methods used in the prior art are more likely to collide with the railway contact network load-bearing cables and return lines, which poses a greater safety risk and affects railway transportation. Summary of the invention

[0004] The present invention provides a temporary hanging system and a hanger replacement method for replacing hangers of a tie-arch bridge across railways, so as to solve the technical problem that the existing hanger replacement devices and structures are difficult to apply to the replacement of hangers on a tie-arch bridge across railways.

[0005] In order to solve the above problems, the temporary hanging system for replacing the hanger rod of the tied arch bridge across the railway provided by the present invention adopts the following technical solutions: A temporary hanging system for replacing a hanger rod of a tie-bar arch bridge across a railway, characterized in that it comprises a first temporary hanger rod, a second temporary hanger rod, a support assembly, a first temporary steel crossbeam, a second temporary steel crossbeam, a temporary anchor and a bottom support of a lower hanging steel plate; the support assembly is provided with four groups, arranged at intervals along the upper chord steel pipe of the tie-bar arch bridge, and comprises a clamping member for clamping on the upper chord steel pipe and a leveling pad connected to the clamping member; Two of the first temporary steel beams are arranged in parallel and spaced apart and are located on both sides of the hanger to be replaced, and each first temporary steel beam is installed on the upper surface of two corresponding leveling pads; the second temporary steel beam is arranged correspondingly to the first temporary steel beam and extends in the same direction, and the second temporary steel beam is used to be arranged between the bridge deck and the lower chord steel pipe of the tied arch bridge; two of the first temporary hangers are connected between each first temporary steel beam and the corresponding second temporary steel beam, and the top of each first temporary hanger is connected to the temporary anchor used to tension the first temporary hanger; The lower pocket hanging steel plate bottom supports are provided with two along the extension direction of the second temporary steel beam, including a bottom plate, side plates connected to both sides of the bottom plate, and a fixed plate vertically connected to the top of each side plate, the fixed plate is located below the corresponding second temporary steel beam, the bottom plate is used to fit with the bottom surface of the beam under the bridge, and the side plate is used to fit with the side surface of the beam under the bridge; each second temporary steel beam and the two fixed plates located below it are correspondingly fastened with a second temporary hanger passing through the bridge deck, so that the second temporary hangers are distributed in a rectangular shape with the hanger to be replaced as the center.

[0006] Furthermore, a plurality of reinforcing rib plates are connected between the fixed plate and the corresponding side plate and are arranged at intervals in the extension direction of the cross beam under the bridge.

[0007] Furthermore, the fixing plate is fitted with the lower surface of the bridge deck.

[0008] Furthermore, the clamping member includes two semicircular hoop bodies, each of which is connected to a fastening plate extending along the axial direction of the semicircular hoop body on both radial sides, a plurality of reinforcing ribs arranged at intervals along the axial direction of the semicircular hoop body are connected between the fastening plate and the semicircular hoop body, and a plurality of fastening holes arranged at intervals along the axial direction of the semicircular hoop body are provided on the fastening plate.

[0009] Furthermore, the second temporary hanger is a precision-rolled threaded steel bar.

[0010] The beneficial effects of the temporary hanging system for replacing the hanger of the cross-railway tie-arch bridge of the present invention are as follows: the present invention adopts a lower hanging steel plate bottom support when fixing the second temporary steel crossbeam, and the lower hanging steel plate bottom support includes a bottom plate fitted with the bottom surface of the crossbeam under the bridge, a side plate fitted with the side of the crossbeam under the bridge, and a fixing plate for installing the second temporary hanger. Compared with the shoulder pole beam in the prior art, the thickness of the bottom plate and the side plate is thinner, and the height of the shoulder pole beam and the length of the shoulder pole beam extending out of the two sides of the crossbeam under the bridge are quite different; in addition, the contact area between the lower hanging steel plate bottom support and the crossbeam under the bridge is also larger than that of the shoulder pole beam in the prior art, so it can adapt to the replacement of the hanger of the cross-railway tie-arch bridge with low clearance height under the bridge, and the lateral and vertical distances between the contact network load-bearing cables and return lines and the crossbeam under the bridge are relatively close. When the railway is constructed at the designated skylight point, the normal operation of the railway can be maintained with higher safety.

[0011] The technical solution of the method for replacing the suspender rod of a tied arch bridge across a railway of the present invention is: The method for replacing the suspender rod of a tied arch bridge across a railway comprises the following steps: Step 1: Determine the original cable force of the suspender and the bridge deck elevation; Step 2: Build railings on the arch ribs to form a construction platform; Step 3: Use the overhead line operation ladder car to install the load-bearing cables and return line guardrails during the railway skylight time; Step 4: Installing a temporary hoisting system, wherein the temporary hoisting system is a temporary hoisting system for replacing the hanger rod of a tie arch bridge across a railway as described in any one of claims 1 to 5; Step 5: Convert the cable force of the old boom to the temporary hoisting system and remove the old boom; Step 6: Install a new boom and transfer the cable force of the temporary hoisting system to the new boom; Step 7: Adjust the cable force of the entire bridge and re-measure the elevation of the entire bridge; Step 8: Dismantle the temporary hoisting system, carry out anti-corrosion reinforcement on the arch ribs, and repair the deck and beams under the bridge.

[0012] Furthermore, in step five, four jacks are used to tension and load the four first temporary hangers in the temporary hanging system in stages, and the old hangers are cut off in steps; the first temporary hanger is loaded in stages according to 10% of the total cable force, and then a grinding wheel saw is used to cut off 10% of the steel wires. After the working condition is completed, the reference elevation points of the first temporary hanger and the two old hangers adjacent to the old hanger to be replaced are measured, and the linear change of the bridge deck after the first batch of steel wires are cut is judged by the change in relative elevation. At the same time, the cable force of the old hanger to be replaced is monitored, and the amount of cable force of the old hanger to be replaced is judged by the monitoring value, and the relationship between the lifting force of the jack and the cable force of the old hanger during the system conversion process is found. After the on-site monitoring of the bridge deck elevation and stress shows no abnormal data changes, the above steps are repeated for a total of 10 cycles until the old hanger is replaced.

[0013] Furthermore, in step six, the conversion process of gradually transferring the cable force of the temporary hoisting system to the new hanger is also carried out in stages. The relaxation of the cable force of the first temporary hanger is achieved by gradually returning the jack. The tensioning force of the new hanger reaches 10% of the design cable force, and then the temporary hoisting system is unloaded to 90% of the design cable force. After no abnormal data changes are observed in the on-site bridge deck elevation and cable force monitoring, the next step is to tension the new hanger to 20% of the design cable force, and the first temporary hanger is unloaded to 80% of the design cable force. This step-by-step loading and unloading method is used for a total of 10 times.

[0014] Furthermore, the lower hanging steel plate base support in the temporary hanging system is made of 2 cm thick steel plate bent and welded, and the lower hanging steel plate base support is coated with 3um anti-electrical insulating glue.

[0015] Furthermore, before the old boom is cut, steel sleeves are crimped on the upper and lower sides of the cut portion.

[0016] The beneficial effects of the method for replacing the hanger of a tie-arch bridge across railways of the present invention are as follows: during construction, the present invention adopts a lower hanging steel plate bottom support formed by bending and welding steel plates to fix the entire temporary hanging system. Compared with the shoulder pole beam in the prior art, the thickness of the steel plate is thinner, and is far different from the height of the shoulder pole beam and the length of the shoulder pole beam extending out of both sides of the cross beam under the bridge; and the lower hanging steel plate bottom support surrounds the outer side of the cross beam under the bridge, and the contact area with the cross beam under the bridge is also larger than that of the shoulder pole beam in the prior art, and the fixation is more secure. Therefore, it can be adapted to the replacement of the hangers of a tie-arch bridge across railways with a low clearance height under the bridge, and the lateral and vertical distances between the contact network load-bearing cables and return lines and the cross beam under the bridge are relatively close. When the railway planned skylight points are constructed, the normal operation of the railway can be maintained, and the safety is higher. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] By reading the following detailed description with reference to the accompanying drawings, the above and other objects, features and advantages of the exemplary embodiments of the present invention will become readily understood. In the accompanying drawings, several embodiments of the present invention are shown in an exemplary and non-limiting manner, and the same or corresponding reference numerals represent the same or corresponding parts, wherein: Figure 1 It is a front view of a temporary hanging system for replacing the hanger rod of a tie-arch bridge across a railway according to the present invention; Figure 2 This is a plan view of the bottom of the crossbeam under the bridge; Figure 3 for Figure 2 AA section view; Figure 4 for Figure 1 The enlarged schematic diagram of point A in the middle; Figure 5 for Figure 3The enlarged schematic diagram of point B in the middle; Figure 6 This is the main view of the first temporary beam; Figure 7 is a top view of the first temporary beam; Figure 8 for Figure 6 AA section view; Fig. 9 is a top view of the second temporary beam; Fig.10 It is a schematic diagram of the structure of the clamping member.

[0018] Description of reference numerals: 1. Upper chord steel pipe; 2. Lower chord steel pipe; 3. First temporary steel beam; 31. First channel steel; 32. First connecting plate; 33. First perforation; 34. Reinforcement plate; 4. Second temporary steel beam; 41. Second channel steel; 42. Second connecting plate; 43. Second perforation; 44. Third perforation; 5. First temporary hanger; 6. Second temporary hanger; 7. Temporary anchor; 8. Hoop; 81. Semicircular hoop; 82. Fastening plate; 83. Reinforcement rib; 9. Leveling pad; 10. Bottom support of lower hoisting steel plate; 101. Bottom plate; 102. Side plate; 103. Fixed plate; 104. Reinforcement rib plate; 105. Fifth perforation; 11. Old hanger; 12. Bridge deck; 121. Fourth perforation; 13. Bridge beam. DETAILED DESCRIPTION

[0019] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Those skilled in the art should know that the embodiments described below are part of the embodiments of the present disclosure, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.

[0020] The principle and spirit of the present invention are explained in detail below with reference to several representative embodiments of the present invention.

[0021] Embodiments of the temporary hanging system for replacing the hanger rod of a tied arch bridge across a railway provided by the present invention: like Figure 1 , Figure 2 and Figure 3 As shown, the temporary hanging system for replacing the hanger of the railway tied arch bridge includes a first temporary hanger 5, a second temporary hanger 6, a support assembly, a first temporary steel beam 3, a second temporary steel beam 4, a temporary anchor 7 and a lower hanging steel plate base 10.

[0022] Specifically, there are four groups of support assemblies, two groups are provided on each upper chord steel pipe 1 of the tied arch bridge, and the four groups of support assemblies are distributed in a rectangular shape, and the two groups of support assemblies on each upper chord steel pipe 1 are arranged at intervals. Each group of support assemblies includes a clamping member 8 for clamping on the upper chord steel pipe 1 and a leveling pad 9 connected to the clamping member 8; wherein the structure of the clamping member 8 is as follows: Fig.10 As shown, the clamping member 8 includes two semicircular hoops 81, and each semicircular hoops 81 is connected to two radial sides with a fastening plate 82 extending along the axial direction of the semicircular hoops 81, and a plurality of reinforcing ribs 83 arranged at equal intervals along the axial direction of the semicircular hoops 81 are connected between the fastening plate 82 and the semicircular hoops 81. The fastening plate 82 is provided with fastening holes at positions between any two adjacent reinforcing ribs 83. During installation, the two semicircular hoops 81 of the clamping member 8 are clamped on the upper and lower sides of the upper chord steel pipe 1 respectively, and then bolts are inserted into the fastening holes of the two semicircular hoops 81 and fastened with nuts, so that the clamping member 8 clamps the upper chord steel pipe 1. The leveling pad 9 is welded on the semicircular hoops 81, and the upper surface of the leveling pad 9 is a horizontal plane.

[0023] Two first temporary steel beams 3 are arranged in parallel and spaced apart. The two first temporary steel beams are respectively fixed on two corresponding leveling pads 9 on the two upper chord steel pipes 1 and are respectively located on both sides of the old suspension rod 11. Figure 6 , Figure 7 and Figure 8 As shown, the first temporary steel beam 3 includes two first channel steels 31 arranged in parallel and spaced apart from each other and a first connecting plate 32 connected to the top and bottom of the two first channel steels 31. A plurality of reinforcing plates 34 spaced apart along the length direction of the first channel steel 31 are welded to the inner side of the first channel steel 31. A plurality of first connecting plates 32 are spaced apart along the length direction of the first channel steel 31. The two first connecting plates 32 at both ends are respectively provided with first through-holes 33, and the first through-holes 33 correspond to the gap between the two first channel steels 31 up and down. A steel pad is provided on the top of the first temporary steel beam 3, and four first temporary suspension rods 5 are provided, all of which are steel strands. The four first temporary suspension rods 5 pass through the corresponding steel pads and the first through-holes 33 respectively. A temporary anchor 7 is provided above the steel pad and connected to the corresponding first temporary suspension rod 5 to tension the first temporary suspension rod. The temporary anchor 7 is a device used for tensioning steel strands in the prior art, and will not be described in detail here.

[0024] The second temporary steel beam 4 is arranged correspondingly to the first temporary steel beam 3 and has the same extension direction and length. Figure 1 As shown, the second temporary steel beam 4 is arranged between the bridge deck 12 of the tied arch bridge and the lower chord steel tube 2, and has a certain distance from the bridge deck 12. Fig. 9As shown, the second temporary steel beam 4 includes two second channel steels 41 arranged in parallel and spaced apart from each other and a second connecting plate 42 connected to the top and bottom of the two second channel steels 41. The two second connecting plates 42 at both ends are provided with second through holes 43 corresponding to the first through holes 33, and a third through hole 44 is provided between the two second connecting plates 42 in the middle. The first temporary suspension rod 5 passes through the first through hole 33 and the corresponding second through hole 43 at the same time, and is fastened at the bottom of the second temporary steel beam 4.

[0025] The second temporary suspenders 6 are finely rolled threaded steel bars, and four of them are arranged in a rectangular arrangement with the old suspender 11 (the suspender to be replaced) as the center. The four second temporary suspenders 6 respectively pass through the corresponding third through-holes 44, and the tops of the second temporary suspenders 6 are fastened with nuts above the second temporary steel beam 4. Of course, in other embodiments, the second temporary suspenders 6 may also be steel strands, and in this case, a jack is used to pre-tighten the second temporary suspenders 6 and the second temporary steel beam 4 on the bridge deck 12.

[0026] like Figure 1 , Figure 3 , Figure 4 and Figure 5 As shown, two lower hanging steel plate base supports 10 are provided along the extension direction of the second temporary steel beam 4, and each lower hanging steel plate base support 10 is formed by bending and welding a 2 cm thick steel plate, and specifically includes a bottom plate 101, side plates 102 connected on both sides of the bottom plate 101, a fixing plate 103 vertically connected to the top of each side plate 102, and a plurality of spaced reinforcing rib plates 104 welded between the fixing plate 103 and the side plate 102. The two fixing plates 103 on the same side of the two lower hanging steel plate bottom brackets 10 are located below the corresponding second temporary steel beam 4. A fourth through hole 121 coaxially corresponding to the third through hole 44 is drilled on the bridge deck 12. A fifth through hole 105 coaxially corresponding to the third through hole 44 is opened on the fixing plate 103. The second temporary suspension rod 6 passes through the third through hole 44, the fourth through hole 121 and the fifth through hole 105 at the same time. The bottom end is fastened with a nut below the fixing plate 103, so that the first temporary steel beam 3, the second temporary steel beam 4, the lower hanging steel plate bottom bracket 10, the first temporary suspension rod 5, the second temporary suspension rod 6 and the supporting assembly are connected into a whole. During installation, if Figure 4 As shown, the bottom plate 101 is in contact with the bottom surface of the cross beam 13 under the bridge, and the side plate 102 is in contact with the side surface of the cross beam 13 under the bridge; the fixing plate 103 is spaced a certain distance from the bottom surface of the bridge deck 12. Of course, in other embodiments, the fixing plate 103 can also be in contact with the bottom surface of the bridge deck 12.

[0027] The present invention adopts a lower-pocket hanging steel plate base support 10 to replace the common shoulder-pole beam in the prior art. The lower-pocket hanging steel plate base support 10 includes a bottom plate 101 that is in contact with the bottom surface of the cross beam 13 under the bridge, a side plate 102 that is in contact with the side of the cross beam 13 under the bridge, and a fixing plate 103 for installing the second temporary hanger 6. Compared with the shoulder-pole beam in the prior art, the bottom plate 101 and the side plate 102 are thinner in thickness, and are far different from the height of the shoulder-pole beam and the length of the shoulder-pole beam extending out of both sides of the cross beam 13 under the bridge; in addition, the contact area between the lower-pocket hanging steel plate base support 10 and the cross beam 13 under the bridge is also larger than that of the shoulder-pole beam in the prior art. Therefore, it can adapt to the replacement of hangers of a tie-bar arch bridge across a railway with a low clearance height under the bridge and a close lateral and vertical distance between the contact network load-bearing cable and the return line and the cross beam 13 under the bridge. When the railway is constructed at the designated skylight point, the normal operation of the railway can be maintained with higher safety.

[0028] Embodiment of the method for replacing the suspender rod of a tied arch bridge across a railway provided by the present invention: The method for replacing the suspenders of the tied arch bridge across the railway is mainly as follows: four first temporary suspenders are first installed on both sides of the old suspenders to be replaced, and the first temporary suspenders use steel strands; two sets of double-jointed channel steel pole beams (i.e., the first temporary steel beams) are set at the top of the arch ribs, and two sets of double-jointed channel steel pole beams (i.e., the second temporary steel beams) are set at a set distance above the bridge deck, and the four first temporary suspenders are connected to the first temporary steel beams and the second temporary steel beams, and the four second temporary suspenders pass through the second temporary steel beams and the bridge deck, and are connected to the bottom of the bridge beam with two sets of special 40Cr alloy 2cm thick lower pocket hanging steel plate bottom brackets to form a temporary pocket hanging system. During construction, the cable force of the old suspenders is first gradually transferred to the temporary pocket hanging system, and then the old suspenders are removed, and new suspenders are installed, and then the cable force of the temporary pocket hanging system is gradually transferred to the new suspenders, and finally the temporary pocket hanging system is removed and the cable force of the new suspenders is adjusted.

[0029] In general, the above method mainly includes the following steps: Step 1: Determine the original cable force of the suspender and the bridge deck elevation; Step 2: Build railings on the arch ribs to form a construction platform; Step 3: Use the overhead line operation ladder car to install the load-bearing cables and return line guardrails during the railway skylight time; Step 4: Installing a temporary hanging system. The structure of the temporary hanging system is the same as that described in the embodiment of the temporary hanging system for replacing the hanger rod of the tied arch bridge across the railway, and will not be described in detail here. Step 5: Convert the cable force of the old boom to the temporary hoisting system and remove the old boom; Step 6: Install a new boom and transfer the cable force of the temporary hoisting system to the new boom; Step 7: Adjust the cable force of the entire bridge and re-measure the elevation of the entire bridge; Step 8: Dismantle the temporary hoisting system, carry out anti-corrosion reinforcement on the arch ribs, and repair the deck and beams under the bridge.

[0030] This embodiment uses a specific construction case to explain the above replacement method in detail: 1. Construction preparation (1) Close both ends of the tied arch bridge where the hangers need to be replaced; (2) When the bridge deck is closed to traffic, a third-party monitoring unit will conduct actual measurements of the bridge deck elevation and the cable force of the hanger at each hanging point, and provide the control force and bridge deck elevation when the hanger is replaced on site; (3) After entering the site, prepare and process the first temporary hanger 5, the second temporary hanger 6, the first temporary steel beam 3 and the second temporary steel beam 4 for construction in advance, calibrate the jack, sensor and pump station, measure the arc of the arch, and determine the processing size of the arch clamp 8.

[0031] 2. Processing and production of temporary hoisting system The temporary hanging system includes the first temporary hanging rod 5, the second temporary hanging rod 6, the supporting assembly, the first temporary steel beam 3, the second temporary steel beam 4, the temporary anchor 7 and the bottom bracket 10 of the lower hanging steel plate. Among them, the second temporary steel beam 4 is welded by [40 channel steel, and the bottom bracket 10 of the lower hanging steel plate is made of 2cm thick steel plate (coated with 3um anti-electrical insulation glue) by bending and welding.

[0032] 3. Installation of temporary hoisting system above the bridge deck (1) During non-railway skylight hours (daytime), use the municipal aerial work vehicle operating platform (up to 30m) to install the protective railings of the arch work channel; The bridge deck arch rib is equipped with a fastener-type steel pipe support as a railing for the up and down passages for personnel. The strength grade of the steel is Q355, and the spacing between the vertical bars of the railing is 1.5m. The distance can be appropriately adjusted when encountering the first temporary steel crossbeam 3; the length of the vertical bar on the outside of the railing is 4.5m (the arch rib height between the upper and lower chords of the arch is 3m, and the height of the railing is 1.5m), the length of the top horizontal bar of the upper chord of the arch is 3.5m, the length of the bottom horizontal bar of the lower chord of the arch is 4m, the length of a single horizontal diagonal bar is 2.5m, the outer width of the arch ring is 0.6m, and the railing avoids the clamp 8 at the position of the first temporary hanger 5. The weight of the arch rib railing of the entire bridge is about 32t, and the average load on each hanger is about 6KN.

[0033] (2) Use the work platform of the work vehicle and the hand chain hoist to pull and install the first temporary steel beam 3, the first temporary suspension rod 5 and the temporary anchor 7 of the arch; Before installing the hoop 8 and the first temporary steel beam 3 of the arch, the top elevation of the wedge-shaped leveling pad 9 must be further confirmed. If there is a deviation in the top steel plate elevation of the leveling pads 9 on both sides, padding must be performed. During the assembly process, attention must be paid to maintaining balance on both sides to prevent the first temporary steel beam 3 from tilting. The first temporary steel beam 3 must be positioned and placed strictly according to the position marked on the design drawing. At the same time, the first connecting plate 32 at the bottom of the first temporary steel beam 3 and the contact part of the leveling pad 9 on the top of the hoop 8 must be welded firmly to ensure that the arch platform will not be deformed or tilted when the first temporary suspension rod 5 is tensioned.

[0034] 4. Installation of load-bearing cables and return line protection lines In order to prevent the bottom of the bridge deck 12 from falling off and scratching the existing contact network load-bearing cables and return lines during construction, it is necessary to use the contact network operation ladder car within the railway fence to install YJKZ (C) type pre-twisted armored wire strips on the load-bearing cables and return lines within the projection range of the bridge at the railway skylight point, and arrange 2 groups of ladder cars for each skylight point of each track for simultaneous construction.

[0035] 5. Bridge deck opening Within the scope of the railway fence, four holes with a diameter of 6 cm are drilled in the bridge deck (20 cm thick) around the existing hangers using a core drilling machine, with a hole spacing of 1.4 m*0.7 m.

[0036] 6. Installation of temporary hoisting system below the bridge deck A simple movable rubber wheel assembled ladder cage is used as the construction platform under the bridge. The plane size of the ladder cage is 1.2m*2m, the plane size of the projection of the four corner diagonal braces is 3.2m*4.5m, and a 1.2m high fence is set on the top of the ladder cage. Prepare 4 sets of movable decoration ladder cages (3 sections with a total height of 5.4m), the lower pocket hanging steel plate bottom bracket 10 and related tools in advance to reach the operation door position. The lower pocket hanging system in the railway fence needs to be within the skylight point. The ladder cage, the lower pocket hanging steel plate bottom bracket 10 and the tools are manually transported to the position of the second temporary hanging rod 6. Using the ladder cage as a construction platform, the winch wire rope is first lowered at the position of the fourth perforation 121 drilled in the bridge deck 12 to lift the lower pocket hanging steel plate bottom bracket 10 to the construction platform, and then 2m long 40 fine rolled threaded steel (second temporary hanging rod 6) is lowered from the bridge deck 12 to fix the lower pocket hanging steel plate bottom bracket 10 to the cross beam 13 under the bridge by bolts.

[0037] 7. Temporary suspender cable force conversion The tensioning end of the first temporary hanger 5 is set at the upper end of the upper chord steel pipe 1. It is installed with four jacks with support legs and bolted to the first temporary steel beam 3. A set of safety tool anchors is installed in the support legs. The jacks are equipped with automatic hydraulic locks. The four jacks are synchronously controlled to tension or unload and relax through the shut-off valve.

[0038] According to the bridge deck control elevation and cable force control value provided by the third-party monitoring unit, the oil gauge readings of the corresponding tensioning equipment and the corresponding tensioning control values ​​of each level were calculated. The original design maximum constant load of the hanger was 688.7 KN, and the first temporary hanger 5 was tensioned using four 100t jacks.

[0039] In the process of gradually transferring the cable force of the old suspender rod to the temporary hoisting system, the construction process of simultaneously tensioning and loading the four first temporary suspenders 5 of the temporary hoisting system in stages and cutting the old suspenders (with 120 steel wires) in steps is adopted: that is, the first temporary suspender rod 5 is loaded in stages according to 10% of the total cable force (each stage takes about 2-3 minutes), and then the 12 steel wires on the old suspender rod 11 are cut by a grinding wheel saw (it takes about 2-3 minutes). After the working condition is completed, the benchmark elevation points of the old suspender rod and the old suspender rods adjacent to it are measured, and the linear changes of the bridge deck after the first batch of steel wires are cut are understood through the change value of the relative elevation. At the same time, the cable force of the old suspender rod 11 is monitored, and the amount of cable force of the old suspender rod 11 is judged by the monitoring value, and the relationship between the lifting force of the jack and the cable force of the suspender rod during the system conversion process is found. After the bridge deck elevation and stress are monitored on site without abnormal data changes (it takes about 5 minutes), the above steps are repeated.

[0040] Continue to load the first temporary hanger 5 to 20% of the total cable force, and then cut 12 steel wires. A total of 10 cycles are required to completely cut the entire old hanger 11, so that the cable force of the old hanger 11 is fully transferred to the temporary hanging system. Each cycle takes about 11 minutes, and the conversion of a single temporary hanging system takes about 110 minutes. Due to the complex stress conversion of the rods during the tensioning and unloading process, the tensioning and unloading of the jacks for replacing the hangers in the railway fence are considered to be constructed within the skylight point.

[0041] During the cable force conversion process, when the cable force of each level of the replaced hanger is transferred to the first temporary hanger 5, it is necessary to anchor the first temporary hanger 5, and at the same time track and monitor the cable force and the elevation change at the location where the replacement hanger is located, observe whether there are cracks in the bridge deck, and measure the elevation of the bridge deck at the adjacent point to determine whether the cable force needs to be adjusted. After confirming that there is no problem, start cutting the steel wire along the outside of the old hanger cable until the old hanger 11 is completely cut off. In order to prevent accidents caused by sudden breakage of the steel wire, steel sleeves are first used for crimping above and below the cutting position to play a damping role. The upper and lower changes in the bridge deck and the elevation change difference of the adjacent span suspension point are controlled within the range of ±2mm, and shall not exceed the specified value of ±1cm. The cutting position of the original hanger is 1.5m above the bridge deck.

[0042] 8. Remove the old boom After the suspender at 12 of the bridge deck is fixed above the bridge deck, it is pulled and tied with a wire rope, and then cut directly with a grinding wheel saw. The arch anchor head is pulled back with a 100t jack to remove the upper anchor head. The old suspender anchor head at the beam end below the bridge deck is cut and removed in the railway skylight point using a ladder cage construction work platform.

[0043] During the original construction, cement slurry was poured into the old suspender conduits in the arch ribs and tie beams for protection. After the old suspenders were cut off, the cement mortar in the conduits was not easy to remove. The old suspenders at the beam ends and arch ends could not be directly removed. The old suspenders were removed by coring: that is, after the old suspenders were cut off, a special extended coring machine (110mm) was used to coring along the old suspenders until the old suspenders were completely loosened and removed. The drilled hole was also used as the installation hole for the new suspender conduit. When coring the hole, the hole axis should be controlled to coincide with the old suspender axis. After coring, the existing embedded pipes were re-anticorrosive.

[0044] 9. Install new boom The anchor end of the 12th hanger on the bridge deck is designed to pass through the embedded steel pipe in the form of a connecting steel tie rod, anchored at the bottom of the beam at the railway skylight point and sealed. The inner diameter of the embedded steel pipe on the anchor end of the original hanger on the bridge top arch rib is only 143mm, and it is difficult for ordinary anchor heads (outer diameter 140mm) to pass through. Therefore, before installing the new hanger, it is necessary to remove the embedded steel pipe on the anchor end of the old hanger, expand the hole, and re-install a seamless steel pipe with an inner diameter of 152mm.

[0045] The new hanger on the bridge deck is installed by lowering the wire rope from the arch winch to pull the new hanger (outside the skylight point). The traction wire rope should pass through the conduit from the arch rib end to the bridge deck and connect to the new hanger. Since the inner diameter of the original conduit is small, the traction wire rope should be located at the center of the hanger. The traction hanger is inserted into the conduit from bottom to top to avoid friction and jamming between the hanger and the conduit due to eccentricity. When the traction cable body passes through the upper end of the arch rib anchor pad, the cable body tensioning end member is installed. The hanger cable must not be damaged during transportation, especially the HDPE protective layer. The traction wire rope is connected to the new hanger through a sling.

[0046] 10. New boom cable force conversion The second system conversion is to transfer the force of the first temporary suspender 5 to the new suspender by alternately tensioning the new suspender and unloading the first temporary suspender 5, and the new suspender replaces the force of the first temporary suspender 5. According to the control elevation and cable force control value provided by the third-party monitoring unit, the oil gauge readings of the tensioning equipment corresponding to the tension control values ​​of each level of the new suspender tension and the tension control values ​​of each level of the temporary suspender unloading are calculated, and the new suspender is tensioned by a 200t jack.

[0047] The conversion process of the temporary hoisting system gradually transferring the cable force to the new suspender is also carried out in stages. The relaxation of the cable force of the first temporary suspender 5 is achieved by the gradual return of the jack: that is, the tension of the new suspender reaches 10% of the design cable force (about 3 minutes), and then the temporary hoisting system is unloaded to 90% (about 2 minutes). After 5 minutes of observation of the on-site bridge deck elevation and cable force monitoring without abnormal data changes, the next step is to tension the new suspender to 20% of the design cable force, and the first temporary suspender 5 is unloaded to 80% of the design cable force. This step-by-step loading and unloading method is used for a total of 10 times. Each cycle takes about 10 minutes, and the conversion of the temporary hoisting system takes about 100 minutes in total.

[0048] Also during the whole process of cable replacement, the cable force and the change of deflection at the location of the replacement hanger should be tracked and monitored, and the cracks in the bridge deck should be detected to determine whether the cable force needs to be adjusted. During the entire tensioning process, it is necessary to monitor the elevation of the bridge deck at the hanger to keep its changes within the design control range, monitor the stress of the new hanger throughout the process, and monitor the three data indicators of tensioning force, elongation and bridge deck elevation in a timely manner. After the construction is completed, the bridge deck elevation should be consistent with that before replacement. Due to the complex stress conversion of the rods during tensioning and unloading, the tensioning and unloading of the jacks for replacing the hangers inside the railway fence are considered to be constructed within the skylight point.

[0049] 11. Adjust the cable force, dismantle the temporary hoisting system, carry out anti-corrosion reinforcement on the arch ribs, and repair the deck and beams under the bridge. After the first temporary suspender 5 cable force is unloaded, the final cable force is adjusted in time according to the control elevation and cable force monitoring instructions provided by the third-party monitoring unit. After the new suspender is tensioned and the cable force of the entire bridge is adjusted, the upper and lower shock absorbers of the new suspender, related components of the health detection system, waterproof cover, protective cover and other facilities are installed according to the design requirements. After that, the temporary hoisting system is dismantled, the arch ribs are reinforced for corrosion protection, and the lower deck and beams of the bridge are repaired.

[0050] The method for replacing the hanger rods of a tie-arch bridge across railways of the present invention can be adapted to the replacement of the hanger rods of a tie-arch bridge across railways with a low clearance height under the bridge and a close lateral and vertical distance between the contact network load-bearing cables and return lines and the crossbeams under the bridge. The construction has high safety and does not affect the operation of the railway.

[0051] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A temporary hanging system for replacing the hanger rod of a tied arch bridge across a railway, characterized in that: It includes a first temporary hanging rod, a second temporary hanging rod, a supporting assembly, a first temporary steel beam, a second temporary steel beam, a temporary anchor and a bottom support of a lower hanging steel plate; The support assembly is provided with four groups, which are arranged at intervals along the upper chord steel pipe of the tied arch bridge, and include a clamping member for clamping on the upper chord steel pipe and a leveling pad connected to the clamping member; Two of the first temporary steel beams are arranged in parallel and spaced apart and are located on both sides of the hanger to be replaced, and each first temporary steel beam is installed on the upper surface of two corresponding leveling pads; the second temporary steel beam is arranged correspondingly to the first temporary steel beam and extends in the same direction, and the second temporary steel beam is used to be arranged between the bridge deck and the lower chord steel pipe of the tied arch bridge; two of the first temporary hangers are connected between each first temporary steel beam and the corresponding second temporary steel beam, and the top of each first temporary hanger is connected to the temporary anchor used to tension the first temporary hanger; The bottom brackets of the lower hanging steel plate are provided with two bottom brackets along the extension direction of the second temporary steel beam, including a bottom plate, side plates connected to both sides of the bottom plate, and a fixing plate vertically connected to the top of each side plate, the fixing plate is located below the corresponding second temporary steel beam, the bottom plate is used to fit with the bottom surface of the beam under the bridge, and the side plates are used to fit with the side surfaces of the beam under the bridge; A second temporary hanger passing through the bridge deck is fastened and connected correspondingly between each second temporary steel cross beam and the two fixed plates located therebelow, so that the second temporary hangers are distributed in a rectangular shape with the hanger to be replaced as the center.

2. The temporary hanging system for replacing the hanger rod of the tied arch bridge across the railway according to claim 1 is characterized in that: A plurality of reinforcing rib plates are connected between the fixed plate and the corresponding side plate and are arranged at intervals in the extending direction of the cross beam under the bridge.

3. The temporary hanging system for replacing the hanger rod of the tied arch bridge across the railway according to claim 1 is characterized in that: The fixing plate is fitted with the lower surface of the bridge deck.

4. The temporary hanging system for replacing the hanger rod of a tie-arch bridge across a railway according to any one of claims 1 to 3, characterized in that: The clamping member includes two semicircular hoop bodies, each of which is connected to a fastening plate extending along the axial direction of the semicircular hoop body on both radial sides, a plurality of reinforcing ribs arranged at intervals along the axial direction of the semicircular hoop body are connected between the fastening plate and the semicircular hoop body, and a plurality of fastening holes arranged at intervals along the axial direction of the semicircular hoop body are provided on the fastening plate.

5. The temporary hanging system for replacing the hanger rod of a tie-arch bridge across a railway according to any one of claims 1 to 3, characterized in that: The second temporary hanger is a precision-rolled threaded steel bar.

6. A method for replacing the suspender rod of a tied arch bridge across a railway, characterized in that: The following steps are involved: Step 1: Determine the original cable force of the suspender and the bridge deck elevation; Step 2: Build railings on the arch ribs to form a construction platform; Step 3: Use the overhead line operation ladder car to install the load-bearing cables and return line guardrails during the railway skylight time; Step 4: installing a temporary hoisting system, wherein the temporary hoisting system is a temporary hoisting system for replacing the hanger rod of a tie arch bridge across a railway as described in any one of claims 1 to 5; Step 5: Convert the cable force of the old boom to the temporary hoisting system and remove the old boom; Step 6: Install a new boom and transfer the cable force of the temporary hoisting system to the new boom; Step 7: Adjust the cable force of the entire bridge and re-measure the elevation of the entire bridge; Step 8: Dismantle the temporary hoisting system, carry out anti-corrosion reinforcement on the arch ribs, and repair the deck and beams under the bridge.

7. The method for replacing the suspender rod of a tied arch bridge across a railway according to claim 6, characterized in that: In step five, four jacks are used to tension and load the four first temporary hangers in the temporary hanging system at the same time, and the old hangers are cut off in steps; the first temporary hanger is loaded in stages according to 10% of the total cable force, and then a grinding wheel saw is used to cut off 10% of the steel wires. After this working condition is completed, the reference elevation points of the first temporary hanger and the two old hangers adjacent to the old hanger to be replaced are measured, and the linear change of the bridge deck after the first batch of steel wires are cut is judged by the change in relative elevation. At the same time, the cable force of the old hanger to be replaced is monitored, and the amount of cable force of the old hanger to be replaced is judged by the monitoring value, and the relationship between the lifting force of the jack and the cable force of the old hanger during the system conversion process is found. After no abnormal data changes in the bridge deck elevation and stress are monitored on site, the above steps are repeated for a total of 10 cycles until the old hanger is replaced.

8. The method for replacing the suspender rod of a tied arch bridge across a railway according to claim 7, characterized in that: In step six, the conversion process of the temporary hoisting system cable force gradually transferred to the new hanger is also carried out in stages. The relaxation of the cable force of the first temporary hanger is achieved by gradually returning the jack. The tensioning force of the new hanger reaches 10% of the design cable force, and then the temporary hoisting system is unloaded to 90% of the design cable force. After no abnormal data changes are observed in the on-site bridge deck elevation and cable force monitoring, the next step is to tension the new hanger to 20% of the design cable force, and the first temporary hanger is unloaded to 80% of the design cable force. This step-by-step loading and unloading method is used for a total of 10 times.

9. The method for replacing the suspender rod of a tied arch bridge across a railway according to claim 6, characterized in that: The lower hanging steel plate base in the temporary hanging system is made of 2cm thick steel plate bent and welded, and the outer surface of the lower hanging steel plate base is coated with 3um anti-electrical insulating glue.

10. The method for replacing the suspender rod of a tied arch bridge across a railway according to claim 6, characterized in that: Before cutting the old boom, crimp the upper and lower sides of the cut part with steel sleeves.