Earth and rockfill dam structure for preventing overtopping harm and construction method
By designing the structure of self-scarce waveproof wall and gutter in the earth and rock dam, the safe discharge of water flow is achieved, the flood control problem of earth and rock dam is solved, and a simple and economical solution to prevent the hazards of the flood, improving the The flood control capacity of the earth and rock dam is achieved.
Patent Information
- Application Number
- CN202411121530.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-15
- Publication Date
- 2024-11-08
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing earth and rock dam projects are difficult to effectively prevent flood hazards in flood control, and the investment in preventive measures is large, which limits its application scope.
A kind of earth and rock dam structure is designed to prevent the hazards of the flood roof, including a dam, a self-scarce type waveproof wall, a dam top drainage ditch and a gutter. Through the design of self-scarce gap and self-scarce door, the water flow can be safely discharged to the large Lower the risk of flooding caused by exceeding the standard.
The structure is simple and inexpensive, which can effectively reduce the risk of overhead of the earth and rock dam and improve the flood control capacity of the earth and rock dam. It is suitable for small and medium-sized reservoirs, with less investment and no construction difficulty increases.
Smart Images

Figure CN118911085A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of earth-rock dam engineering, and in particular to an earth-rock dam structure and construction method for preventing overtopping hazards. Background Art
[0002] The most unfavorable thing for earth-rock dams is flood overtopping. Some flood overtopping accidents that have occurred have caused considerable economic losses. For earth-rock dam projects with important flood control objects distributed downstream, it is necessary to consider the hazards of excessive floods to conduct dam break risk analysis and adopt corresponding preventive measures, such as setting up emergency spillways and increasing the safe height of the dam. However, as a low-probability event, if the corresponding measures cause a large investment, it will inevitably affect the scope of its application. Therefore, designing a simple and low-cost structural measure that can be promoted and used in general earth-rock dam projects is of great significance for preventing and reducing the hazards of earth-rock dam overtopping and improving the risk response capacity of earth-rock dams. Summary of the invention
[0003] A first aspect of an embodiment of the present application provides an earth-rock dam structure for preventing overtopping hazards. The earth-rock dam structure for preventing overtopping hazards is simple in structure and low in cost, and can also effectively improve the earth-rock dam's ability to cope with overtopping risks caused by excessive floods.
[0004] The earth-rock dam structure for preventing overtopping hazards provided in a first aspect of the embodiment of the present application comprises: a dam, wherein both sides of the dam along the length direction are combined with the bedrock of the mountain;
[0005] A self-deficient wave-breaking wall, which is arranged at the top of the dam and located at least on one side of the dam close to the bedrock of the mountain. The self-deficient wave-breaking wall comprises a self-deficient gap and a self-deficient door. The self-deficient gap is used to self-deficiently form a drainage gap, and the self-deficient door is arranged to block the position of the self-deficient gap;
[0006] A dam top drainage ditch, the dam top drainage ditch is arranged on the downstream side of the self-draining wave-breaking wall, and the dam top drainage ditch is connected to the self-draining notch;
[0007] The intercepting ditch is arranged on the downstream side of the dam, and the intercepting ditch is connected with the dam top drainage ditch.
[0008] The earth-rock dam structure for preventing overtopping hazards provided in the embodiments of the present application may also have the following additional technical features:
[0009] In an optional scheme, the self-contained door is hinged to the structural concrete of the self-contained wave-breaking wall through a door shaft sleeve and a door shaft bearing, the side of the self-contained door is fixed to the self-contained wave-breaking wall through a limiter and an anchor bolt, and the side of the self-contained door facing the dam top drainage ditch is connected to the self-contained wave-breaking wall through a locking component.
[0010] In an optional solution, the limiting member includes a steel plate and an angle steel, the steel plate is connected to the top edge and both side edges of the self-closing door, and the angle steel is connected to the bottom side of the self-closing door; the locking member includes a spring hinge or a card with elastic function.
[0011] In an optional solution, the self-contained wave-breaking walls are located on both sides of the dam close to the bedrock of the mountain, and the self-contained gap is located below the crest of the dam.
[0012] In an optional solution, the dam top drainage ditch is connected to the self-depletion gaps on both sides respectively, the intercepting ditch is located at the junction of the dam and the mountains on both sides, and the intercepting ditch is connected to the dam top drainage ditch on both sides respectively.
[0013] In an optional scheme, the intercepting ditch includes a cross-section transition section and a standard drainage ditch section, the cross-section transition section connects the dam top drainage ditch and the standard drainage ditch section, and the structural joints connecting the dam top drainage ditch, the cross-section transition section and the standard drainage ditch section are all provided with water-stop structures, and a cover plate is provided on the top of the dam top drainage ditch.
[0014] In an optional scheme, the flow cross-section of the intercepting ditch is not less than half of the dam top drainage ditch, the intercepting ditch is provided with structural joints at preset intervals, and the structural joints are provided with water-stop structures; a retaining wall is provided downstream of the dam, and the outlet of the intercepting ditch is located downstream of the retaining wall.
[0015] A second aspect of the present application provides a construction method for an earth-rock dam structure, wherein the earth-rock dam structure is the earth-rock dam structure for preventing overtopping hazards in the first aspect of the embodiment, and the construction method comprises the following steps:
[0016] 1) During the pouring process of the self-deficient wave-breaking wall, a self-deficient notch is reserved according to the structural requirements, and a door shaft sleeve and a water-stop structure are embedded at the position of the self-deficient notch;
[0017] 2) Concrete the crest drainage ditch in the crest area of the dam and install a cover plate on the top of the crest drainage ditch;
[0018] 3) After the construction of the dam is completed, the intercepting ditch is constructed to connect the intercepting ditch with the drainage ditch on the dam top;
[0019] 4) Installing the limit plate and the locking member on the upstream surface of the self-closing door, and installing the self-closing door on the self-closing wave-breaking wall through the door shaft bearing and the door shaft sleeve;
[0020] 5) Flipping and closing the self-closing door, locking the self-closing door by means of the locking member, and then using butyl tape to stick and seal the gap formed around the self-closing door and the limiting plate.
[0021] In an optional solution, the construction of the intercepting ditch in step 3) includes the following steps:
[0022] The intercepting ditch is arranged at the junction of the dam and the mountain, and the flow cross-section of the intercepting ditch is not less than half of the drainage ditch on the dam top. Structural joints are constructed and arranged on the intercepting ditch every 12 meters or so, and then water-stopping structures are arranged in the structural joints.
[0023] The beneficial effects of the embodiments of the present application are:
[0024] In the earth-rock dam structure in the embodiment of the present application, under the set water level, the self-deficient gap of the self-deficient wave-breaking wall forms a drainage gap, and the water flows through the dam top drainage ditch and the downstream intercepting ditch to safely discharge to the downstream of the dam, reducing the risk of overtopping caused by excessive floods, etc., or after the overtopping danger occurs, it is discharged through both banks to reduce the overtopping head, thereby achieving the purpose of reducing or eliminating the risk. The structure of the earth-rock dam structure is simple and low in cost, and the investment caused by the addition of new structures or structural adjustments is small, and it will not increase the difficulty of construction. According to the estimated flow capacity of the 2m drainage ditch, 15m can be discharged per second. 3 / s flood, for some small and medium-sized reservoirs with less investment, it is a practical measure to improve the flood control capacity of excessive floods.
[0025] It should be understood that the foregoing general description and the following detailed description are exemplary only and are not restrictive of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 A schematic diagram of the plan layout of the earth-rock dam structure provided for this application;
[0027] Figure 2 for Figure 1 Longitudinal section of the earth-rock dam structure;
[0028] Figure 3 A schematic cross-sectional view of the self-deficient wave-breaking wall provided for this application in the upstream and downstream directions;
[0029] Figure 4 An upstream elevation view of the self-deficient wave-breaking wall provided for this application;
[0030] Figure 5A schematic cross-sectional view of the self-contained wave-breaking wall provided in this application in the direction of the dam axis;
[0031] Figure 6 This is a schematic diagram of the structure of the intercepting ditch provided in this application.
[0032] Figure numerals: dam 1, self-contained wave-breaking wall 2, self-contained notch 3, self-contained door 4, dam top drainage ditch 5, intercepting ditch 6, door shaft sleeve 7, door shaft bearing 8, limit piece 9, anchor bolt 10, locking member 11, section transition section 12, drainage ditch standard section 13, water-stop structure 14, cover plate 15, retaining wall 16.
[0033] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present application and, together with the description, serve to explain the principles of the present application. DETAILED DESCRIPTION
[0034] In order to better understand the technical solution of the present application, the embodiments of the present application are described in detail below with reference to the accompanying drawings.
[0035] It should be clear that the described embodiments are only part of the embodiments of the present application, rather than all the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present application.
[0036] The terms used in the embodiments of the present application are only for the purpose of describing specific embodiments, and are not intended to limit the present application. The singular forms "a", "said" and "the" used in the embodiments of the present application and the appended claims are also intended to include plural forms, unless the context clearly indicates other meanings.
[0037] It should be understood that the term "and / or" used in this article is only a description of the association relationship of associated objects, indicating that there can be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In addition, the character " / " in this article generally indicates that the associated objects before and after are in an "or" relationship.
[0038] It should be noted that the directional words such as "upper", "lower", "left", and "right" described in the embodiments of the present application are described at the angles shown in the accompanying drawings and should not be understood as limiting the embodiments of the present application. In addition, in the context, it is also necessary to understand that when it is mentioned that an element is connected to another element "upper" or "lower", it can not only be directly connected to another element "upper" or "lower", but also indirectly connected to another element "upper" or "lower" through an intermediate element.
[0039] like Figure 1-6As shown, the first aspect of the embodiment of the present application provides an earth-rock dam structure for preventing overtopping hazards, and the earth-rock dam structure for preventing overtopping hazards includes a dam 1, a self-depleting wave-breaking wall 2, a dam top drainage ditch 5 and a water interception ditch 6. Among them, the dam 1 is a concrete panel rockfill dam, and the two sides of the dam 1 along the length direction are combined with the mountain bedrock; the self-depleting wave-breaking wall 2 is arranged at the dam top of the dam 1, and the self-depleting wave-breaking wall 2 is located at least on one side of the dam 1 close to the mountain bedrock, the self-depleting wave-breaking wall 2 includes a self-depleting gap 3 and a self-depleting door 4, the self-depleting gap 3 is used to self-deplete to form a drainage gap, and the self-depleting door 4 is arranged to block the position of the self-depleting gap 3; the dam top drainage ditch 5 is arranged on the downstream side of the self-depleting wave-breaking wall 2, and the dam top drainage ditch 5 is connected with the self-depleting gap 3; the water interception ditch 6 is arranged on the downstream side of the dam 1, and the water interception ditch 6 is connected with the dam top drainage ditch 5.
[0040] In the earth-rock dam structure of this embodiment, under the set water level, the self-deficient gap 3 of the self-deficient wave-breaking wall 2 forms a drainage gap, and the water flows through the dam top drainage ditch 5 and the downstream interception ditch 6 to safely drain to the downstream of the dam 1, reducing the risk of overtopping caused by excessive floods, etc., or after the overtopping danger occurs, it is drained through both banks to reduce the overtopping head, thereby achieving the purpose of reducing or eliminating the risk. The structure of the earth-rock dam structure is simple and low in cost, with little investment in new structures or structural adjustments, and will not increase the difficulty of construction. According to the estimated flow capacity of the 2m drainage ditch, 15m can be discharged per second. 3 / s flood, for some small and medium-sized reservoirs with less investment, it is a practical measure to improve the flood control capacity of excessive floods.
[0041] like Figure 3-5 As shown, in a specific embodiment, the self-deficient door 4 is hinged to the structural concrete of the self-deficient wave-breaking wall 2 through the door shaft sleeve 7 and the door shaft bearing 8, the side of the self-deficient door 4 is fixed to the self-deficient wave-breaking wall 2 through the limiter 9 and the anchor bolt 10, and the side of the self-deficient door 4 facing the dam top drainage ditch 5 is connected to the self-deficient wave-breaking wall 2 through the locking member 11. Specifically, the limiter 9 includes a steel plate and an angle steel, the steel plate is connected and arranged on the top edge and both sides of the self-deficient door 4, and the angle steel is connected and arranged on the bottom side of the self-deficient door 4; the locking member 11 includes a spring hinge or a card with elastic function.
[0042] like Figure 1-2 As shown, in a specific embodiment, the self-draining wave-breaking wall 2 is located on both sides of the dam 1 near the bedrock of the mountain, and the self-draining gap 3 is located below the dam top of the dam 1. It is in the shape of a square gap and is blocked by the self-draining door 4 during normal operation. The dam top drainage ditch 5 is respectively connected with the self-draining gap 3 on both sides, and the intercepting ditch 6 is located at the junction of the dam 1 and the mountains on both sides, and the intercepting ditch 6 is respectively connected with the dam top drainage ditch 5 on both sides.
[0043] like Figure 2-3As shown, in a specific embodiment, the intercepting ditch 6 includes a cross-section transition section 12 and a drainage ditch standard section 13, the cross-section transition section 12 connects the dam top drainage ditch 5 and the drainage ditch standard section 13, and the structural joints connecting the dam top drainage ditch 5, the cross-section transition section 12 and the drainage ditch standard section 13 are all provided with a water-stop structure 14, and a cover plate 15 is provided on the top of the dam top drainage ditch 5.
[0044] In addition, the flow cross-section of the intercepting ditch 6 is not less than half of the dam top drainage ditch 5. The intercepting ditch 6 is provided with structural joints at preset intervals, and the structural joints are provided with water-stop structures 14. A retaining wall 16 is provided downstream of the dam 1, and the outlet of the intercepting ditch 6 is located downstream of the retaining wall 16.
[0045] A second aspect of the embodiments of the present application provides a construction method of an earth-rock dam structure, wherein the earth-rock dam structure is the earth-rock dam structure for preventing overtopping hazards in the embodiment of the first aspect, and the construction method comprises the following steps:
[0046] 1) During the pouring process of the self-deficient wave-breaking wall 2, according to the structural requirements, a self-deficient notch 3 is reserved, a door shaft sleeve 7 is pre-embedded at the position of the self-deficient notch 3, and a water-stop structure 14 is pre-embedded;
[0047] 2) pouring the dam crest drainage ditch 5 in the dam crest area of the dam 1, and setting a cover plate 15 on the top of the dam crest drainage ditch 5;
[0048] 3) After the construction of the dam 1 is completed, the intercepting ditch 6 is constructed to connect the intercepting ditch 6 with the dam top drainage ditch 5; when constructing the intercepting ditch 6, it is necessary to set the intercepting ditch 6 at the junction of the dam 1 and the mountain, and the flow cross section of the intercepting ditch 6 is not less than half of the dam top drainage ditch 5, and a structural joint is constructed and set on the intercepting ditch 6 every 12 meters or so, and then a water stop structure 14 is set in the structural joint;
[0049] 4) Install the limit plate and locking member 11 on the upstream surface of the self-closing door 4, and install the self-closing door 4 on the self-closing wave-breaking wall 2 through the door shaft bearing 8 and the door shaft sleeve 7;
[0050] 5) Flip and close the self-closing door 4, lock the self-closing door 4 by means of the locking member 11, and then use butyl tape to stick and seal the gap formed between the self-closing door 4 and the limiting plate.
[0051] The above are only preferred embodiments of the present application and are not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. An earth-rock dam structure for preventing overtopping hazards. It is characterized in that include: A dam, wherein both sides of the dam along the length direction are combined with the bedrock of the mountain; A self-deficient wave-breaking wall, which is arranged at the top of the dam and located at least on one side of the dam close to the bedrock of the mountain. The self-deficient wave-breaking wall comprises a self-deficient gap and a self-deficient door. The self-deficient gap is used to self-deficiently form a drainage gap, and the self-deficient door is arranged to block the position of the self-deficient gap; A dam top drainage ditch, the dam top drainage ditch is arranged on the downstream side of the self-draining wave-breaking wall, and the dam top drainage ditch is connected to the self-draining notch; The intercepting ditch is arranged on the downstream side of the dam, and the intercepting ditch is connected with the dam top drainage ditch.
2. The earth-rock dam structure for preventing overtopping hazards according to claim 1, It is characterized in that The self-confining door is hinged to the structural concrete of the self-confining wave-breaking wall through a door shaft sleeve and a door shaft bearing. The side of the self-confining door is fixed to the self-confining wave-breaking wall through a limit piece and an anchor bolt. The side of the self-confining door facing the dam top drainage ditch is connected to the self-confining wave-breaking wall through a locking component.
3. The earth-rock dam structure for preventing overtopping hazards according to claim 2, It is characterized in that The limiting part includes a steel plate and an angle steel, the steel plate is connected to the top edge and both side edges of the self-closing door, and the angle steel is connected to the bottom side of the self-closing door; the locking component includes a spring hinge or a card with elastic function.
4. The earth-rock dam structure for preventing overtopping hazards according to any one of claims 1 to 3, It is characterized in that The self-contained wave-breaking walls are located on both sides of the dam close to the bedrock of the mountain, and the self-contained gap is located below the crest of the dam.
5. The earth-rock dam structure for preventing overtopping hazards according to claim 4, It is characterized in that The dam top drainage ditch is communicated with the self-depletion gaps on both sides respectively, the intercepting ditch is located at the junction of the dam and the mountains on both sides, and the intercepting ditch is communicated with the dam top drainage ditch on both sides respectively.
6. The earth-rock dam structure for preventing overtopping hazards according to any one of claims 1 to 3 or claim 5, It is characterized in that The intercepting ditch includes a cross-section transition section and a standard drainage ditch section, the cross-section transition section connects the dam top drainage ditch and the standard drainage ditch section, and the structural joints connecting the dam top drainage ditch, the cross-section transition section and the standard drainage ditch section are all provided with water-stop structures, and a cover plate is provided on the top of the dam top drainage ditch.
7. The earth-rock dam structure for preventing overtopping hazards according to claim 6, It is characterized in that The flow cross-section of the intercepting ditch is not less than half of the dam top drainage ditch, the intercepting ditch is provided with structural joints at preset intervals, and the structural joints are provided with water-stop structures; a retaining wall is provided downstream of the dam, and the outlet of the intercepting ditch is located downstream of the retaining wall.
8. A construction method for an earth-rock dam structure, It is characterized in that The earth-rock dam structure is an earth-rock dam structure for preventing overtopping hazards as described in any one of claims 1 to 7, and the construction method comprises the following steps: 1) During the pouring process of the self-deficient wave-breaking wall, a self-deficient notch is reserved according to the structural requirements, and a door shaft sleeve and a water-stop structure are embedded at the position of the self-deficient notch; 2) Concrete the crest drainage ditch in the crest area of the dam and install a cover plate on the top of the crest drainage ditch; 3) After the construction of the dam is completed, the intercepting ditch is constructed to connect the intercepting ditch with the drainage ditch on the dam top; 4) Installing the limit plate and the locking member on the upstream surface of the self-closing door, and installing the self-closing door on the self-closing wave-breaking wall through the door shaft bearing and the door shaft sleeve; 5) Flipping and closing the self-closing door, locking the self-closing door by means of the locking member, and then using butyl tape to stick and seal the gap formed around the self-closing door and the limiting plate.
9. The construction method of the earth-rock dam structure according to claim 8, It is characterized in that The construction of the intercepting ditch in step 3) includes the following steps: The intercepting ditch is set at the junction of the dam and the mountain, and the flow section of the intercepting ditch is not less than half of the drainage ditch on the dam top. Structural joints are constructed and set on the intercepting ditch every 12 meters or so, and then water-stopping structures are set in the structural joints.
Citation Information
Patent Citations
Novel dam body with automatic storage and discharge device
CN105625275A
Multi-power full-automatic water stop gate and preparation and installation method thereof
CN116446334A
Medium and low earth and rockfill dam overtopping protection drainage structure and design method thereof
CN117005369A
Flood control structure of closed tailing pond
CN214574437U
Novel composite overflow cofferdam structure