Prefabricated UHPC (Ultra High Performance Concrete) armor structure of ship lock and construction method
Through prefabricated UHPC protective surface structure and assembly technology, the sealing and reinforcement design of UHPC boards is used to solve the problem of easy damage to the concrete on the ship lock facade, improve durability and construction efficiency, reduce costs, and promote prefabricated assembly technology. Application in ship lock engineering.
Patent Information
- Application Number
- CN202411193398.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-28
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-08-28
AI Technical Summary
During the operation of the lock, the facade concrete is susceptible to ship impact or heavy friction, resulting in surface damage and exposed steel bars, affecting durability and bringing safety hazards. The existing prefabricated assembly technology is rarely used in lock projects, resulting in High construction costs and complex processes.
Using a prefabricated UHPC surface guard structure, it is assembled by multiple UHPC board standard parts, with grooves and bumps arranged for vertical docking, and a connector and anchor rib are arranged on the back, combining the transverse seal butt structure and reinforced seal cavity, and sealing is injected into the seal through an inflatable device. glue, realize sealing and reinforcement, and simplify construction process.
It improves the resistance to ship impacts and structural durability of ships, reduces the cost of steel plate protection, reduces the use of formwork, simplifies the construction process, and promotes the application of prefabricated prefabricated technology in ship lock projects.
Smart Images

Figure CN118911101A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of ship lock construction, and in particular to a prefabricated UHPC face armor structure for a ship lock and a construction method thereof. Background Art
[0002] Inland waterway transport is an important part of the modern integrated transport system, with the unique advantages of low cost, large transport volume and low energy consumption. The ship lock is the most important navigation structure for ships to overcome the water level difference and ensure the navigation of the waterway. It is a key node of my country's high-grade waterways. my country's inland waterway transport has achieved vigorous development, and a large number of major ship lock projects have been completed, which has played a vital role in the construction of my country's waterway network.
[0003] However, during the operation of the ship lock, the concrete facades on the waterside of the lock head, lock chamber, main navigation wall and other structures are susceptible to ship impact or strong friction, resulting in surface damage and exposed steel bars, which seriously affects the durability of the ship lock and poses a safety hazard. At present, most ship locks are designed with steel guards on the concrete surface on the waterside, but their protection range is limited, and during construction, the connection between the steel guard and the formwork is prone to leakage, which affects the quality of the main structure. At the same time, some ship locks use steel plate face guards, which greatly improve the protection range compared to steel guards, but the cost of steel plates is high, and the bonding surface with concrete is prone to separation. Rust is prone to occur during the operation of the ship lock, which also affects durability.
[0004] In addition, when pouring the concrete of the ship lock, formwork needs to be supported around it, and the formwork needs to be removed after the poured concrete reaches a certain strength. The formwork is used in large quantities, with many operation processes and high costs. At present, the domestic prefabrication and assembly technology is developing rapidly, such as in the fields of bridges and docks, which has brought considerable benefits in terms of quality and work efficiency. However, the ship lock is currently mainly constructed on-site, and prefabrication and assembly technology is rarely used. The industrialized construction system of the ship lock project has not yet been established. Therefore, a prefabricated UHPC protective structure and construction method for the ship lock are proposed to solve the above problems. Summary of the invention
[0005] The main purpose of the present invention is to provide a prefabricated UHPC face structure and construction method for a ship lock, so as to solve the problem that the facade concrete is easily hit by a ship or rubbed with great force, resulting in surface damage and exposed steel bars, which seriously affects the durability of the ship lock and brings potential safety hazards.
[0006] In order to solve the above technical problems, the technical solution adopted by the present invention is: a prefabricated UHPC face structure for a ship lock, which is assembled from a plurality of UHPC plate standard parts, the upper and lower ends of the UHPC plate standard parts are respectively provided with corresponding grooves and protrusions for vertical docking of the UHPC plate standard parts, and the back of the UHPC plate standard parts is symmetrically provided with two groups of connecting parts distributed at the upper and lower edges for fixing the vertical docking of the UHPC plate standard parts, and the back of the UHPC plate standard parts is also provided with a plurality of anchor bars for combining with cast-in-place concrete.
[0007] In the preferred embodiment, corresponding transverse sealing butt joint structures are provided on the left and right sides of the UHPC board standard parts for transverse butt joint of the UHPC board standard parts.
[0008] In the preferred embodiment, the transverse sealing butt joint structure is a vertical cut edge arranged at the side edge of the back of the UHPC board standard part. When two UHPC board standard parts are butt jointed transversely, the two vertical cut edges at the butt joint form a groove for filling the waterproof connection mortar.
[0009] In the preferred embodiment, the transverse sealing docking structure includes an inserted docking structure arranged on the side of the UHPC board standard part. When two UHPC board standard parts are transversely docked, the two inserted docking structures at the docking point are plugged into each other, and a reinforced sealing cavity is formed between the two, and a reinforced sealing structure is plugged into the reinforced sealing cavity.
[0010] In a preferred embodiment, the insertion docking structure includes a Z-shaped docking portion arranged on the side of the UHPC board standard part and a slot adapted to the end of the Z-shaped docking portion.
[0011] In the preferred embodiment, the reinforced sealing cavity includes a Z-shaped reinforcement cavity located between two Z-shaped docking parts at the docking point, and the Z-shaped reinforcement cavity is composed of a reinforcement groove located in the middle and sealing grooves located on both sides of the reinforcement groove. Locking grooves connected to the reinforcement grooves are also provided on the opposite sides of the two Z-shaped docking parts, and the cross-sections of the locking groove and the slot are cross-shaped, and the sealing groove is used to fill the sealant.
[0012] In a preferred embodiment, the reinforced sealing structure includes an inserted locking rod adapted to the reinforcement groove and the locking groove; The insertion locking rod is also provided with an expansion glue injection structure for injecting glue into the two sealing grooves; The expansion glue injection structure includes a accommodating cavity which is arranged in the insertion locking rod and has an open top. A plurality of slurry outlet holes which are connected to the accommodating cavity are arranged on the two side wall surfaces of the insertion locking rod. When the insertion locking rod is inserted into the reinforcement groove and the locking groove, the slurry outlet holes can be connected with the relative sealing grooves. Two slurry storage capsules are symmetrically arranged in the accommodating cavity. The slurry storage capsules store sealant. The two slurry storage capsules are respectively fitted with the slurry outlet holes on both sides, and an easy-to-open folding line is arranged on the side close to the slurry outlet hole. The outside of the slurry storage capsule is covered with an extruded rubber layer whose two ends are connected to the inner wall of the accommodating cavity. An inflatable bag is arranged between the two extruded rubber layers. The two sides of the inflatable bag are connected to the inner wall of the accommodating cavity, and an inflation port is arranged on the top of the inflatable bag.
[0013] In a preferred embodiment, two opposite inner wall surfaces of the reinforcement groove are provided with spring sheets perpendicular to the sealing groove, and a conical end is provided at the bottom end of the inserted locking rod.
[0014] In the preferred solution, the method for butting two laterally adjacent UHPC board standard parts is as follows: S1. Hoist the UHPC board standard parts to be installed to the side of the installed UHPC board standard parts, align the Z-shaped joint parts of the two UHPC board standard parts with the corresponding slots, and then lower the UHPC board standard parts to be installed to the installation position; S2. After the vertical fixation of the standard UHPC board to be installed is completed, the insertion locking rod is inserted into the reinforcement groove and the locking groove; S3. Inflate the inflation port of the inflation bag using an inflation device to expand it, and then use the extruded rubber layers on both sides to squeeze the two pulp storage capsules respectively, so that the pulp storage capsules are cracked from the easy-open folding line side, so that the sealant inside the capsules flows from the pulp outlet hole inserted into the side wall of the locking rod into the side surface and the sealing groove.
[0015] The method includes: S1. Prefabricate UHPC board standard parts in the factory and transport them to the construction site; S2, pour the lock bottom plate, and preset the fixing groove and anchor bolts for the standard parts of the bottom UHPC plate at the top; S3. Installation of the first layer of UHPC standard parts. Before hoisting, apply waterproof cement slurry on the part in contact with the lock structure. Use lifting equipment to hoist the horizontal layer of UHPC standard parts in sequence. The bottom is connected and fixed with the connector through anchor bolts. The rear of each UHPC standard part is tightened by tension bars, which are mainly used to bear the lateral force during concrete pouring. At the same time, install the conventional formwork of other parts. S4. After the other processes of the warehouse surface are completed and the warehouse is inspected and qualified, the concrete of this layer is poured. The top surface elevation of the concrete pouring is lower than the standard parts of the UHPC board of this layer, so as to connect with the standard parts of the UHPC board of the upper layer; S5. After the lower layer concrete meets the construction requirements, the upper layer UHPC board standard parts are hoisted in sequence. Before installation, a layer of waterproof mortar is first placed on the joints on the top of the lower layer UHPC board standard parts, and the upper and lower corresponding connectors are fixed by bolts during the joints. The rear of each UHPC board standard part is tightened by tensioning bars, and conventional formworks of other parts are installed at the same time. Step S4 is repeated to complete the pouring of this layer of concrete. S6. Repeat S5 until the entire ship lock construction is completed.
[0016] The present invention provides a prefabricated UHPC face protection structure and construction method for a ship lock. By utilizing the high strength and corrosion resistance of UHPC concrete, UHPC prefabricated panels are used for the protection of the ship lock facade concrete, which can greatly improve the ability to resist ship collisions and abrasions and the durability of the structure. In addition, the cost of steel plate face protection is at least half of that of steel face protection, and the protection area is larger than that of steel and wooden protection, and the protection effect is ideal. At the same time, during the construction of the ship lock, the UHPC prefabricated panels can also be used as templates, reducing the amount of templates used, and there is no need to remove them later, which simplifies the construction process and promotes the application of prefabricated assembly technology in ship lock projects. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The present invention will be further described below in conjunction with the accompanying drawings and embodiments: Figure 1 This is a structural diagram of a standard component of a UHPC board of the present invention; Figure 2 The present invention Figure 1 A magnified view of the structure in the middle; Figure 3 The present invention Figure 1 Middle B is an enlarged view of the structure; Figure 4 This is a structural diagram of a second embodiment of the transverse sealing butt joint structure of the present invention; Figure 5 This is a structural diagram of the connection between the insertion docking structure and the reinforced sealing cavity of the present invention; Figure 6 The present invention Figure 5 A top view of the structure; Figure 7 This is a structural diagram of the connection between the insertion docking structure of the present invention and the standard parts of the UHPC board; Figure 8 The present invention Figure 7 A top view of the structure; Fig. 9 It is a structural diagram of the reinforced sealing structure of the present invention; Fig.10 The present invention Fig. 9 Half-section structure diagram; Fig.11 The present invention Fig.10 Look at the structural diagram; Fig.12 is a schematic diagram of step S2 of the method of the present invention; Fig.13 The present invention Fig.12 Middle C structure enlarged view; Fig.14 is a schematic diagram of step S3 of the method of the present invention; Fig.15 The present invention Fig.14 Middle D structure magnification; Fig.16 is a schematic diagram of step S5 of the method of the present invention; Fig.17 The present invention Fig.16 Middle E is an enlarged view of the structure; Fig.18 This is a structural diagram of the butt joint between the groove and the protrusion in the method of the present invention; Fig.19 It is a schematic diagram of the structure after construction of the present invention; In the figure: UHPC board standard part 1; anchor bolt 2; connector 3; groove 4; protrusion 5; anchor bar 6; transverse sealing docking structure 7; insertion docking structure 71; Z-shaped docking part 710; slot 711; spring piece 712; reinforced sealing cavity 72; reinforced groove 720; sealing groove 721; locking groove 722; reinforced sealing structure 73; insertion locking rod 730; accommodating cavity 731; slurry outlet hole 732; slurry storage capsule 733; extruded rubber layer 734; inflatable bag 735; inflation port 736; tapered end 737; lock bottom plate 8; fixing groove 9; tie rod 10; waterproof mortar 12. DETAILED DESCRIPTION
[0018] Example 1 like Figure 1-3 As shown, a prefabricated UHPC face structure of a ship lock is assembled from a plurality of UHPC plate standard parts 1, and the upper and lower ends of the UHPC plate standard part 1 are respectively provided with corresponding grooves 4 and protrusions 5 for vertical docking of the UHPC plate standard part 1. The vertical fit of the upper and lower UHPC plate standard parts 1 can be achieved through the docking of the grooves 4 and the protrusions 5. In this embodiment, the grooves 4 and the protrusions 5 are both trapezoidal structures, and the back of the UHPC plate standard part 1 is symmetrically provided with two groups of connectors 3 distributed at the upper and lower edges. The connectors 3 are preset during the prefabrication process of the UHPC plate standard part 1 and are used to fix the vertical docking of the UHPC plate standard part 1. The back of the UHPC plate standard part 1 is also provided with a plurality of anchor bars 6 for combining with cast-in-place concrete. The anchor bars 6 are distributed on the back of the UHPC plate standard part 1 in an array manner, and are preset during the prefabrication process of the UHPC plate standard part 1 like the connectors 3.
[0019] It should be noted that, in this embodiment, the connecting member 3 is an L-shaped steel member, a plurality of stiffening plates are arranged between the vertical plate and the horizontal plate, and the horizontal plate is provided with holes for the bolts or anchor bolts 2 to pass through during connection.
[0020] In addition, corresponding transverse sealing butt joint structures 7 are provided on the left and right sides of the UHPC plate standard component 1 for transverse butt joint of the UHPC plate standard component 1 .
[0021] With such a design, multiple UHPC board standard parts 1 can be assembled on the facade of the water side of the ship lock to form an integral protective surface, and at the same time can be formed into an integrated structure with the cast-in-place structure of the ship lock to avoid falling off. The setting of the anchor bar 6 effectively improves the connection between the two parts, and can play the role of an inner mold during the cast-in-place process of the ship lock, reducing the use of the template.
[0022] In the preferred embodiment, a first embodiment of the transverse sealing docking structure 7 is proposed. The transverse sealing docking structure 7 is specifically a vertical cut edge set at the side edge of the back side of the UHPC board standard part 1. When two UHPC board standard parts 1 are transversely docked, the two vertical cut edges at the docking point form a groove body for filling with waterproof connecting mortar, thereby realizing the connection between the transverse UHPC board standard parts 1 and the sealing of the gap through the waterproof connecting mortar.
[0023] In the preferred embodiment, a second embodiment of the transverse sealing docking structure 7 is proposed, such as Figure 4-11 As shown, the transverse sealing docking structure 7 includes an insertion docking structure 71 arranged on the side of the UHPC board standard part 1. When two UHPC board standard parts 1 are transversely docked, the two insertion docking structures 71 at the docking point are plugged into each other, and a reinforced sealing cavity 72 is formed therebetween, and a reinforced sealing structure 73 is plugged into the reinforced sealing cavity 72.
[0024] In this embodiment, the docking stability and sealing effect of the UHPC board standard parts 1 can be effectively improved by inserting the docking structure 71 and inserting the reinforced sealing structure 73 into the reinforced sealing cavity 72.
[0025] In the preferred embodiment, the insertion docking structure 71 includes a Z-shaped docking portion 710 arranged on the side of the UHPC board standard part 1 and a slot 711 adapted to the end of the Z-shaped docking portion 710. The Z-shaped docking portion 710 and the slot 711 are integrally formed with the UHPC board standard part 1 during the prefabrication process. When two UHPC board standard parts 1 are docked, the Z-shaped docking portion 710 and the slot 711 can be docked to achieve the function of installation guidance and achieve preliminary connection.
[0026] The reinforced sealing cavity 72 includes a Z-shaped reinforced cavity located between two Z-shaped docking parts 710 at the docking position. The Z-shaped reinforced cavity is composed of a reinforcement groove 720 located in the middle and sealing grooves 721 located on both sides of the reinforcement groove 720. The two sealing grooves 721 are respectively located at the upper and lower ends of both sides of the reinforcement groove 720. Figure 6 As shown, locking grooves 722 communicating with the reinforcement grooves 720 are further provided on opposite sides of the two Z-shaped docking portions 710 . The cross-sections of the locking grooves 722 and the slots 711 are cross-shaped. The sealing grooves 721 are used to fill sealant.
[0027] The reinforcement sealing structure 73 includes an insertion locking rod 730 adapted to the reinforcement groove 720 and the locking groove 722. When the insertion locking rod 730 is inserted into the reinforcement groove 720 and the locking groove 722, it can cooperate with the docking of the two Z-shaped docking parts 710 to form a cross fastening structure to complete the connection between two adjacent UHPC board standard parts 1. Such a design can make the connection between the two adjacent UHPC board standard parts 1 stable. At the same time, the multi-fold line connection design can effectively improve the sealing of the connection. In addition, by filling the reserved sealing groove 721 with sealant, the sealing and bonding effect can be further achieved.
[0028] The insertion locking rod 730 is also provided with an expansion glue injection structure for injecting glue into the two sealing grooves 721. The sealant can be set in the insertion locking rod 730 in advance without adding corresponding glue injection equipment on site.
[0029] The expansion glue injection structure includes a accommodating cavity 731 which is arranged in the insertion locking rod 730 and has an open top. A plurality of slurry outlet holes 732 which are connected to the accommodating cavity 731 are arranged on both side wall surfaces of the insertion locking rod 730. When the insertion locking rod 730 is inserted into the reinforcement groove 720 and the locking groove 722, the slurry outlet holes 732 can be connected to the relative sealing groove 721. Two slurry storage capsules 733 are symmetrically arranged in the accommodating cavity 731. The slurry storage capsules 733 store sealant. The two slurry storage capsules 733 are respectively fitted with the slurry outlet holes 732 on both sides, and an easy-to-open folding line is arranged on the side close to the slurry outlet holes 732. The outside of the slurry storage capsule 733 is covered with an extruded rubber layer 734 whose two ends are connected to the inner wall of the accommodating cavity 731. An inflatable bag 735 is arranged between the two extruded rubber layers 734. The two sides of the inflatable bag 735 are connected to the inner wall of the accommodating cavity 731, and an inflation port 736 is arranged on the top of the inflatable bag 735.
[0030] In this embodiment, the sealant may be epoxy resin, and the pulp storage capsule 733 may be made of soft plastic, with a thin aluminum foil for retaining the sealant attached to the inner wall.
[0031] With such a design, when the inflatable bag 735 is inflated, its own expansion can be used to squeeze the pulp storage capsule 733, and at the same time, the easy-open fold line set thereon can cause it to crack, so that the sealant inside can be squeezed out and then flow out through the pulp outlet hole 732.
[0032] In the preferred embodiment, spring sheets 712 perpendicular to the sealing groove 721 are provided on the two opposite inner wall surfaces of the reinforcement groove 720, and a conical end head 737 is provided at the bottom end of the insertion locking rod 730. The conical end head 737 and the insertion locking rod 730 are integrally formed. One end of the spring sheet 712 is fixedly connected to the side wall of the reinforcement groove 720, and the other end is free. The two spring sheets 712 can limit the insertion locking rod 730 to a certain extent, and at the same time, the spacing difference between the two can be sealed. The setting of the conical end head 737 facilitates the insertion of the insertion locking rod 730.
[0033] It should be noted that when the spring sheet 712 is compressed and stretched, care should be taken not to block the sealing groove 721 .
[0034] In the preferred solution, the method for butting two laterally adjacent UHPC board standard parts 1 is as follows: S1, hoisting the UHPC board standard component 1 to be installed to the side of the installed UHPC board standard component 1, and aligning the Z-shaped docking parts 710 of the two UHPC board standard components 1 with the corresponding slots 711, and then lowering the UHPC board standard component 1 to be installed to the installation position; S2. After the UHPC board standard part 1 to be installed is vertically fixed, the insertion locking rod 730 is inserted into the reinforcement groove 720 and the locking groove 722; S3. Inflate the inflation port 736 of the inflation bag 735 using an inflation device to expand it, and then use the extrusion rubber layers 734 on both sides to squeeze the two pulp storage capsules 733 respectively, so that the pulp storage capsules 733 are cracked from the easy-to-open fold line side, so that the sealant inside it flows from the pulp outlet hole 732 on the side wall of the inserted locking rod 730 into its side and the sealing groove 721.
[0035] Example 2 Further illustrate with reference to Example 1, Figure 12-19 The structure shown is a construction method for a prefabricated UHPC facing structure of a ship lock, the method comprising: S1. Prefabricate UHPC board standard parts 1 in the factory and transport them to the construction site; S2, pouring the ship lock bottom plate 8, and presetting the fixing groove 9 and anchor bolt 2 for inserting the bottom UHPC plate standard part 1 at the top; S3. Installation of the first layer of UHPC standard plate parts 1. Before hoisting, apply waterproof cement slurry on the part in contact with the lock structure. Use lifting equipment to hoist the horizontal layer of UHPC standard plate parts 1 in sequence. The bottom is connected and fixed with the connecting parts 3 through anchor bolts 2. The rear of each UHPC standard plate part 1 is tightened by tie bars 10, which are mainly used to bear the lateral force during concrete pouring. At the same time, install conventional formworks in other parts; S4. After the other processes of the warehouse surface are completed and the warehouse is inspected and qualified, the concrete of this layer is poured. The top surface elevation of the concrete pouring is about 15 cm lower than the UHPC board standard part 1 of this layer, so as to connect with the UHPC board standard part 1 of the upper layer; S5. After the lower layer concrete meets the construction requirements, the upper layer UHPC board standard parts 1 are hoisted in sequence. Before installation, a layer of waterproof mortar 12 is first set on the joint at the top of the lower layer UHPC board standard parts 1, and the upper and lower corresponding connectors 3 are fixed by bolts during the joint. The rear of each UHPC board standard part 1 is tightened by the tie rod 10, and the conventional formwork of other parts is installed at the same time. Step S4 is repeated to complete the concrete pouring of this layer. S6. Repeat S5 until the entire ship lock construction is completed.
[0036] The above embodiments are only preferred technical solutions of the present invention and should not be regarded as limiting the present invention. The protection scope of the present invention shall be the technical solutions recorded in the claims, including equivalent replacement solutions of the technical features in the technical solutions recorded in the claims. That is, equivalent replacement improvements within this scope are also within the protection scope of the present invention.
Claims
1. A prefabricated UHPC face structure for a ship lock, characterized by: A plurality of UHPC plate standard parts (1) are assembled; the upper and lower ends of the UHPC plate standard parts (1) are respectively provided with corresponding grooves (4) and protrusions (5) for vertically butting the UHPC plate standard parts (1); the back of the UHPC plate standard parts (1) are symmetrically provided with two groups of connecting parts (3) distributed at the upper and lower edges for fixing the vertical butt joint of the UHPC plate standard parts (1); and the back of the UHPC plate standard parts (1) are also provided with a plurality of anchor bars (6) for combining with cast-in-place concrete.
2. According to claim 1, a prefabricated UHPC face structure for a ship lock is characterized by: Corresponding transverse sealing butt joint structures (7) are provided on the left and right sides of the UHPC plate standard component (1) for transverse butt joint of the UHPC plate standard component (1).
3. According to claim 2, a prefabricated UHPC facing structure for a ship lock is characterized by: The transverse sealing butt joint structure (7) is a vertical cut edge provided at the side edge of the back side of the UHPC board standard component (1). When two UHPC board standard components (1) are butt jointed transversely, two vertical cut edges at the butt joint form a groove for filling with waterproof connection mortar.
4. According to claim 2, a prefabricated UHPC face structure for a ship lock is characterized by: The transverse sealing docking structure (7) comprises an insertion docking structure (71) arranged on the side of the UHPC plate standard part (1); when two UHPC plate standard parts (1) are transversely docked, the two insertion docking structures (71) at the docking position are plugged into each other, and a reinforced sealing cavity (72) is formed between the two, and a reinforced sealing structure (73) is plugged into the reinforced sealing cavity (72).
5. The prefabricated UHPC facing structure for a ship lock according to claim 4 is characterized by: The insertion docking structure (71) comprises a Z-shaped docking portion (710) arranged on the side of the UHPC board standard part (1) and a slot (711) adapted to the end of the Z-shaped docking portion (710).
6. The prefabricated UHPC facing structure for a ship lock according to claim 5 is characterized by: The reinforced sealing cavity (72) comprises a Z-shaped reinforced cavity located between two Z-shaped butt joints (710) at the butt joint, the Z-shaped reinforced cavity comprising a reinforcing groove (720) located in the middle, and sealing grooves (721) located on both sides of the reinforcing groove (720), and locking grooves (722) connected to the reinforcing grooves (720) are further provided on opposite sides of the two Z-shaped butt joints (710), the cross-sections of the locking grooves (722) and the slots (711) being in a cross shape, and the sealing grooves (721) are used to fill the sealant.
7. The prefabricated UHPC facing structure for a ship lock according to claim 5 is characterized by: The reinforcement sealing structure (73) comprises an insertion locking rod (730) adapted to the reinforcement groove (720) and the locking groove (722); The insertion locking rod (730) is also provided with an expansion glue injection structure for injecting glue into the two sealing grooves (721); The expansion glue injection structure comprises a receiving cavity (731) which is arranged in the insertion locking rod (730) and has an open top. A plurality of slurry outlet holes (732) which are connected to the receiving cavity (731) are arranged on two side wall surfaces of the insertion locking rod (730). When the insertion locking rod (730) is inserted into the reinforcement groove (720) and the locking groove (722), the slurry outlet holes (732) can be connected to the corresponding sealing groove (721). Two slurry storage capsules (733) are symmetrically arranged in the receiving cavity (731). The sealant is stored therein, and the two pulp storage capsules (733) are respectively fitted with the pulp outlet holes (732) on both sides, and an easy-to-open folding line is provided on the side close to the pulp outlet hole (732). The outside of the pulp storage capsule (733) is provided with an extruded rubber layer (734) whose two ends are connected to the inner wall of the accommodating cavity (731), and an inflatable bag (735) is provided between the two extruded rubber layers (734). The two sides of the inflatable bag (735) are connected to the inner wall of the accommodating cavity (731), and the top of the inflatable bag (735) is provided with an inflation port (736).
8. The prefabricated UHPC facing structure for a ship lock according to claim 7 is characterized by: Two opposite inner wall surfaces of the reinforcement groove (720) are provided with spring sheets (712) perpendicular to the sealing groove (721), and a conical end (737) is provided at the bottom end of the inserted locking rod (730).
9. A prefabricated UHPC facing structure for a ship lock according to claim 7 or 8, characterized in that: The method for butting two UHPC plate standard parts (1) adjacent to each other laterally is as follows: S1, hoisting the UHPC board standard component (1) to be installed next to the installed UHPC board standard component (1), aligning the Z-shaped docking parts (710) at the docking points of the two UHPC board standard components (1) with the corresponding slots (711), and then lowering the UHPC board standard component (1) to be installed to the installation position; S2. After the UHPC board standard part (1) to be installed is vertically fixed, the insertion locking rod (730) is inserted into the reinforcement groove (720) and the locking groove (722); S3. Inflate the inflation port (736) of the inflation bag (735) using an inflation device to expand it, and then use the extrusion rubber layers (734) on both sides of the inflation bag (735) to squeeze the two pulp storage capsules (733) respectively, so that the pulp storage capsules (733) are cracked from the easy-open folding line side, thereby allowing the sealant inside the capsules to flow from the pulp outlet hole (732) on the side wall of the insertion locking rod (730) into its side and the sealing groove (721).
10. A construction method for a prefabricated UHPC facing structure for a ship lock using any one of claims 1 to 9, characterized in that: The method includes: S1. Prefabricate UHPC panel standard parts (1) in the factory and transport them to the construction site; S2, pouring the ship lock bottom plate (8), and presetting the fixing groove (9) and anchor bolt (2) for inserting the bottom UHPC plate standard part (1) at the top; S3. Install the first layer of UHPC standard plate parts (1). Before lifting, apply waterproof cement slurry to the part in contact with the ship lock structure. Use lifting equipment to lift the horizontal layer of UHPC standard plate parts (1) in sequence. The bottom is connected and fixed to the connecting piece (3) by anchor bolts (2). The rear of each UHPC standard plate part (1) is tightened by a tie rod (10), which is mainly used to bear the lateral force during concrete pouring. At the same time, conventional formworks of other parts are installed; S4, after the other construction processes of the warehouse surface of this layer are completed and the warehouse is inspected and qualified, the concrete of this layer is poured, and the top surface elevation of the concrete pouring is lower than the UHPC board standard part (1) of this layer, so as to connect with the UHPC board standard part (1) of the upper layer; S5, after the lower layer of concrete meets the construction requirements, the upper layer of UHPC board standard parts (1) are hoisted in sequence. Before installation, a layer of waterproof mortar (12) is first provided on the joint of the top of the lower layer of UHPC board standard parts (1), and the upper and lower corresponding connecting parts (3) are fixed by bolts during the jointing. The rear of each UHPC board standard part (1) is tightened by a tie bar (10), and conventional formworks are installed at other parts at the same time. Step S4 is repeated to complete the pouring of the concrete of this layer. S6. Repeat S5 until the entire ship lock construction is completed.
Citation Information
Patent Citations
Inter-pile greening assembled retaining wall structure
CN108166514A
Fabricated cement concrete pavement slab and construction method
CN113584981A
Prefabricated UHPC pool
CN116752823A
Ship lock water delivery gallery and construction method thereof
CN117027052A
Small prefabricated concrete assembly type gradient-adjustable trapezoidal canal
CN214656819U