LNG cabin system area division method, cabin carrying method, cabin block and ship
By adopting a functional total segment division method in the LNG cabin system of dual-fuel container ships, the cabins are divided into multiple sections according to functional, which solves the problems of late pump tower lifting time and long dock construction cycle, and achieves early loading and the integrity of the docking is improved.
Patent Information
- Application Number
- CN202411098271.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-12
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2044-08-12
AI Technical Summary
The functional area structure division of the LNG cabin system of the dual-fuel container ship resulted in the late lifting time of the pump tower, extending the dock construction cycle, and affecting the integrity of the dock and construction efficiency.
The regional functional total segment division method of the LNG cabin system is divided into the left general section, the right general section, the middle front section, the middle back lower section, the middle back upper section and the CO2 general section. The TCS area where the pump tower is located serves as a reference for division to ensure that the functional compartment is assembled and welded in the same section, making it easier to load in advance and reduce interference.
By completing the installation and assembly of various functional compartments in advance, the impact of pump tower lifting time on docking integrity is reduced, the dock construction cycle is shortened, and the cabin's docking integrity and construction efficiency are improved.
Smart Images

Figure CN118928693A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of shipbuilding, and in particular to an LNG tank system area division method, a tank loading method, a tank section and a ship. Background Art
[0002] At present, the functional area layout of the LNG tank system of dual-fuel container ships is as follows: Figure 1 As shown in the figure, the TCS (Traction Control System) room with a pump tower is located inside the LNG tank system functional area. The structural division of the LNG tank system functional area of the traditional dual-fuel container ship is to divide a large block of nearly full width in the area above the pump tower. After the pump tower is hoisted, the large block can be hoisted in the dock. However, the LNG tank construction is not ready for pump tower hoisting until a certain stage. Therefore, the pump tower is usually hoisted in the late dock stage, resulting in a very late closure time of the large block in the dock stage. The large block can often be hoisted before leaving the dock. The late hoisting and closure time of the large block hinders the integrity construction of the LNG tank system functional area of the dual-fuel container ship and prolongs the dock construction period. Summary of the invention
[0003] In view of the defects existing in the prior art, the present application provides a method for functionally dividing the LNG tank system area of a dual-fuel container ship into sections, so as to solve the technical problems such as poor undocking integrity of the LNG tank system functional area and long terminal construction period caused by the structural division of the LNG tank system functional area of the dual-fuel container ship in the prior art.
[0004] In order to achieve the purpose of the above invention, the technical solution provided by the present invention is as follows:
[0005] A method for dividing an LNG tank system area, wherein the LNG tank system area is a dual-fuel container ship LNG tank system area, and the dual-fuel LNG tank system area is divided into a front area and a rear area with an isolation bulkhead as the boundary. The front area is arranged with a left transformer room, an auxiliary equipment room and a right transformer from left to right, and a CO2 room is arranged above the auxiliary equipment room. The rear area is arranged with a gas and electrical equipment room, a safety room and a nitrogen room from left to right, and a TCS room and a gas processing room are arranged from left to right below the safety room and between the gas and electrical equipment room and the nitrogen room. The division method comprises the following steps:
[0006] S1. Considering the limitation of the production site area on the length of the sections, determine the weight of the overall structure and outfitting, and ensure that the total weight of the sections including the slings does not exceed the maximum lifting capacity of the on-site crane;
[0007] S2. According to the cabin layout diagram of the LNG tank system area, the LNG tank system area is divided into the left area, the middle area and the right area. The left area includes the complete left transformer room, the complete gas and electrical equipment room and part of the TCS room, part of the safety room and part of the auxiliary equipment room. The left area forms the left general section. The right area includes the complete right transformer room, the complete gas processing room, the complete nitrogen room and part of the auxiliary equipment room, part of the TCS room and part of the safety room. The right area forms the right general section. The middle area is between the left general section and the right general section. The section seams of the sub-general sections are all arranged in the TCS room.
[0008] S3, the middle area in S2 is divided into a middle front section and a middle rear section with the isolation bulkhead as the boundary, the middle front section includes part of the auxiliary equipment room, and the complete CO2 room is divided into separate CO2 room sections, part of the auxiliary equipment room in the middle front section, part of the auxiliary equipment room in the left section and part of the auxiliary equipment room in the right section can form a complete auxiliary equipment room;
[0009] S4. Divide the middle and rear section into a middle and rear lower section and a middle and rear upper section in the height direction, wherein the middle and rear lower section includes the area where the pump tower is arranged in the TCS room, and the middle and rear upper section includes a partial safety room. The partial safety room in the middle and rear upper section, the partial safety room in the left general section and the partial safety room in the right general section can form a complete safety room, and the partial TCS room at the middle and rear lower end, the partial TCS room in the left general section and the partial TCS room in the right general section can form a complete TCS room.
[0010] In one embodiment, the broken seams are all located on the mid-side of the TCS compartment structure wall.
[0011] In one embodiment, the distance between the break seam line and the closer TCS compartment structural wall is greater than one meter.
[0012] In one embodiment, the isolation bulkhead in S3 is included in the front section.
[0013] In one embodiment, the middle and rear segments are divided in height direction by the upper wall between TCSs.
[0014] In one embodiment, the middle rear lower section and the middle rear upper section are both designed as "L"-shaped divisions.
[0015] The present invention also provides a tank loading method, wherein the tank is a dual-fuel type container ship LNG tank, and the LNG tank system area as described above is used as the dual-fuel type container ship LNG tank system area. After the structural construction of the LNG tank is completed, the left side general section and the right side general section are loaded, so that after the structural construction of the LNG tank is completed, the left transformer room, the right transformer room, the gas and electrical equipment room, the gas processing room and the nitrogen room all form closed and complete cabins. Before the pump tower is hoisted, the middle front section and the CO2 room general section are loaded in turn. After the pump tower is hoisted, the middle rear lower section and the middle rear upper section are loaded in turn to form the LNG tank structure section to complete the LNG tank loading.
[0016] The present invention also provides a dual-fuel type container ship LNG tank section, which adopts the dual-fuel type container ship LNG tank loading method.
[0017] The present invention also provides a dual-fuel type container ship, which comprises the LNG tank section of the dual-fuel type container ship.
[0018] Compared with the prior art, this application has at least the following beneficial effects:
[0019] This application uses the TCS room area where the pump tower is located as a reference for division, and divides the LNG tank system area into sections according to the functional cabin layout, and divides it into the left section, the right section, the middle front section, the middle rear lower section, the middle rear upper section and the CO2 room section. The section division facilitates assembly and welding, minimizes the interference between the structure and the outfitting units, divides the complete functional cabins into the same section, and allows the pipes, equipment, valves and iron outfitting to be installed completely, which can reduce the impact of the late hoisting time of the pump tower on the integrity of the undocking and the construction period of the wharf, and enables the functional cabins to be mounted and formed in advance, which is beneficial to the advancement of the outfitting integrity and related systems, improves the integrity of the cabin undocking, and shortens the construction period of the wharf.
[0020] The LNG tank system area division method, tank loading method, tank section and ship section division design of the same type of structure in this application have accumulated scientific and reasonable technical experience, and provided a set of mature and available section division design method ideas. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a plan view of the functional area cabin layout of the LNG tank system of a dual-fuel container ship in the prior art;
[0022] Figure 2 It is a cross-sectional view of the layout of the front area of the cabin of the LNG tank system functional area of the dual-fuel container ship in an embodiment of the present application;
[0023] Figure 3 It is a cross-sectional view of the layout of the rear area of the cabin of the functional area of the LNG tank system of the dual-fuel container ship in the embodiment of the present application;
[0024] Figure 4 It is a schematic diagram of a method for functionally dividing the LNG tank system area of a dual-fuel container ship in an embodiment of the present application.
[0025] The specific descriptions of the reference numerals are as follows: 11, LNG tank; 101, left transformer room; 102, gas and electrical equipment room; 103, CO2 room; 104, auxiliary equipment room; 105, safety room; 106, TCS room; 107, gas processing room; 108, right transformer room; 109, nitrogen room; 12, left general section; 13, right general section; 14, middle front section; 15, middle rear lower section; 16, middle rear upper section; 22, CO2 room general section; 23, LNG tank structure section. DETAILED DESCRIPTION
[0026] In order to make the purpose, technical scheme and advantages of the present invention clearer, the present invention is described below by the specific embodiments shown in the accompanying drawings. However, it should be understood that these descriptions are only exemplary and are not intended to limit the scope of the present invention. In addition, in the following description, the description of well-known structures and technologies is omitted to avoid unnecessary confusion of the concept of the present invention.
[0027] The terms used in this disclosure are for the purpose of describing specific embodiments only and are not intended to limit the disclosure. The singular forms of "a", "said" and "the" used in this disclosure and the appended claims are also intended to include plural forms unless the context clearly indicates otherwise. It should also be understood that the term "and / or" used herein refers to and includes any or all possible combinations of one or more associated listed items.
[0028] It should be understood that although the terms first, second, third, etc. may be used in the present disclosure to describe various information, such information should not be limited to these terms and should not be understood as indicating or implying relative importance. These terms are only used to distinguish the same type of information from each other. For example, without departing from the scope of the present disclosure, the first information may also be referred to as the second information, and similarly, the second information may also be referred to as the first information. Depending on the context, the word "if" as used herein may be interpreted as "at the time of" or "when" or "in response to determining".
[0029] In the description of the present invention, unless otherwise specified and limited, it should be noted that the terms "installed", "connected" and "connected" should be understood in a broad sense. For example, it can be a mechanical connection or the internal connection between two components. It can be a direct connection or an indirect connection through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to the specific circumstances.
[0030] In order to better understand the technical solution of the present invention, the present invention is described in detail below with reference to the accompanying drawings.
[0031] This embodiment takes a 23,000-ton dual-fuel container ship with a tank area width of about 61 meters as an example. This embodiment provides a method for functionally dividing the LNG tank system area of a dual-fuel container ship, wherein the LNG tank system area of the dual-fuel container ship is arranged as follows: Figure 1-3 The LNG tank system area is arranged above the LNG tank 11. The LNG tank system area is divided into a front area and a rear area with the isolation bulkhead as the boundary. The front area is arranged with a left transformer room 101, an auxiliary equipment room 104 and a right transformer 108 from left to right. A CO2 room 103 is arranged above the auxiliary equipment room 104. The rear area is arranged with a gas and electrical equipment room 102, a safety room 105 and a nitrogen room 109 from left to right. Below the safety room 105 and between the gas and electrical equipment room 102 and the nitrogen room 109, a TCS room 106 and a gas processing room 107 are arranged from left to right. The division method includes the following steps:
[0032] S1. Consider the limitation of the production site area on the length of the sections, determine the weight of the overall structure and outfitting, and ensure that the total weight of the sections including the slings does not exceed the maximum lifting capacity of the on-site crane.
[0033] S2. According to the cabin layout diagram of the LNG tank system area, the LNG tank system area is divided into a left area, a middle area and a right area. The left area includes a complete left transformer room 101, a complete gas and electrical equipment room 102, and part of the TCS room, part of the safety room, and part of the auxiliary equipment room. The left area forms a left general section 12. The right area includes a complete right transformer room 108, a complete gas processing room 107, a complete nitrogen room 109, and part of the auxiliary equipment room, part of the TCS room, and part of the safety room. The right area forms a right general section 13. The middle area is between the left general section and the right general section. Figure 2 , 3 As shown by the arrow lines in FIG. 1 , the segment seams of the sub-sections are all arranged in the TCS room 106; in this embodiment, the break seams are all located on the side of the cabin structure wall of the TCS room 106 toward the middle, and the distance between the break seams and the cabin structure wall of the TCS room that is closer is greater than one meter.
[0034] Since the pump tower is in the TCS room 106, the loading of the left main section 12 and the right main section 13 is not affected by the hoisting time of the pump tower and can be loaded earlier than the existing technology. After the structural construction of the LNG tank 11 is completed, the left and right transformer rooms, gas and electrical equipment rooms, gas processing rooms and nitrogen rooms all form closed and complete cabins, and the outfitting integrity construction is greatly advanced, which is conducive to improving the integrity of the undocking.
[0035] S3, the middle area in S2 is divided into the middle front section 14 and the middle rear section by the isolation bulkhead, the middle front section includes part of the auxiliary equipment room, since the CO2 room 103 is located above the main deck, the complete CO2 room 103 is divided into a separate CO2 room section 22, and part of the auxiliary equipment room in the middle front section 14, part of the auxiliary equipment room in the left section and part of the auxiliary equipment room in the right section can form a complete auxiliary equipment room 104. Among them, the isolation bulkhead is included in the front section 14, so that after the middle front section 14 is loaded, the CO2 room section can be continuously hoisted.
[0036] S4. The middle and rear sections are divided into the middle and rear lower sections 15 and the middle and rear upper sections 16 in the height direction. The middle and rear lower sections include the area where the pump tower is set in the TCS room, and the middle and rear upper sections include part of the safety room. The part of the safety room at the middle and rear upper end, the part of the safety room in the left main section, and the part of the safety room in the right main section can form a complete safety room 105; the part of the TCS room at the middle and rear lower end, the part of the TCS room in the left main section, and the part of the TCS room in the right main section can form a complete TCS room 106. The height direction division is bounded by the upper wall of the TCS room. The middle and rear lower sections 15 and the middle and rear upper sections 16 are both "L"-shaped division designs.
[0037] This embodiment uses the TCS area where the pump tower is located as a reference for division, and divides the LNG tank system area into sections according to the functional cabin layout. The section division facilitates assembly and welding, minimizes the interference between the structure and outfitting units, and divides the complete functional cabins into the same section, so that pipes, equipment, valves, and iron outfittings are installed completely, which can reduce the impact of the late hoisting time of the pump tower on the undocking integrity and the wharf construction period. The functional cabins are mounted and formed in advance, which is beneficial to the advancement of outfitting integrity and related systems, improves the undocking integrity, and shortens the wharf construction period.
[0038] This embodiment also provides a dual-fuel container ship LNG tank loading method, using the above-mentioned dual-fuel container ship LNG tank system area functional division method, such as Figure 4 As shown, after the structural construction of the LNG tank 11 is completed, the left main section 12 and the right main section 13 are loaded, so that after the structural construction of the LNG tank 11 is completed, the left transformer room 101, the right transformer room 108, the gas and electrical equipment room 102, the gas processing room 107 and the nitrogen room 109 all form closed and complete cabins. Before the pump tower is hoisted, the middle front section 14 and the CO2 room main section 22 are loaded in turn. After the pump tower is hoisted, the middle rear lower section 15 and the middle rear upper section 16 are loaded in turn to form the LNG tank structure section 23 to complete the LNG tank loading.
[0039] This embodiment also provides a dual-fuel container ship LNG tank section, which adopts the dual-fuel container ship LNG tank loading method described above.
[0040] This embodiment also provides a dual-fuel type container ship, which includes the above-mentioned dual-fuel type container ship LNG tank section.
[0041] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the specific implementation methods of the invention can still be modified or some technical features can be replaced by equivalents without departing from the spirit of the technical solution of the present invention, which should be included in the scope of the technical solution for protection of the present invention.
Claims
1. A method for dividing the regions of an LNG tank system, characterized in that: The LNG tank system area is a dual-fuel container ship LNG tank system area, and the dual-fuel LNG tank system area is divided into a front area and a rear area with the isolation bulkhead as the boundary. The front area is arranged with a left transformer room, an auxiliary equipment room and a right transformer from left to right, and a CO2 room is arranged above the auxiliary equipment room. The rear area is arranged with a gas and electrical equipment room, a safety room and a nitrogen room from left to right, and a TCS room and a gas processing room are arranged from left to right below the safety room and between the gas and electrical equipment room and the nitrogen room. The division method comprises the following steps: S1. Considering the limitation of the production site area on the length of the sections, determine the weight of the overall structure and outfitting, and ensure that the total weight of the sections including the slings does not exceed the maximum lifting capacity of the on-site crane; S2. According to the cabin layout diagram of the LNG tank system area, the LNG tank system area is divided into the left area, the middle area and the right area. The left area includes the complete left transformer room, the complete gas and electrical equipment room and part of the TCS room, part of the safety room and part of the auxiliary equipment room. The left area forms the left general section. The right area includes the complete right transformer room, the complete gas processing room, the complete nitrogen room and part of the auxiliary equipment room, part of the TCS room and part of the safety room. The right area forms the right general section. The middle area is between the left general section and the right general section. The section seams of the sub-general sections are all arranged in the TCS room. S3, the middle area in S2 is divided into a middle front section and a middle rear section with the isolation bulkhead as the boundary, the middle front section includes part of the auxiliary equipment room, and the complete CO2 room is divided into separate CO2 room sections, part of the auxiliary equipment room in the middle front section, part of the auxiliary equipment room in the left section and part of the auxiliary equipment room in the right section can form a complete auxiliary equipment room; S4. Divide the middle and rear section into a middle and rear lower section and a middle and rear upper section in the height direction, wherein the middle and rear lower section includes the area where the pump tower is arranged in the TCS room, and the middle and rear upper section includes a partial safety room. The partial safety room in the middle and rear upper section, the partial safety room in the left general section and the partial safety room in the right general section can form a complete safety room, and the partial TCS room at the middle and rear lower end, the partial TCS room in the left general section and the partial TCS room in the right general section can form a complete TCS room.
2. The method for dividing the LNG tank system into sections according to claim 1 is characterized in that: The broken seams are all located on the mid-section side of the TCS compartment structure wall.
3. The LNG tank system area division method according to claim 2 is characterized in that: The distance between the break seam line and the nearby TCS compartment structure wall is greater than one meter.
4. The LNG tank system area division method according to claim 1, characterized in that: The isolation bulkhead described in S3 is included in the front section.
5. The LNG tank system area division method according to claim 1, characterized in that: In step S4, the middle and rear segments are divided in height direction with the upper wall between TCSs as the boundary.
6. The LNG tank system area division method according to claim 1, characterized in that: The middle rear lower section and the middle rear upper section are both designed in an "L" shape.
7. A cabin loading method, characterized in that: The tank is a dual-fuel container ship LNG tank, which adopts the LNG tank system area division method as described in any one of claims 1 to 6. After the structural construction of the LNG tank is completed, the left and right general sections are started to be loaded, so that after the structural construction of the LNG tank is completed, the left transformer room, the right transformer room, the gas and electrical equipment room, the gas processing room and the nitrogen room all form closed and complete cabins. Before the pump tower is hoisted, the middle front section and the CO2 room general section are loaded in turn. After the pump tower is hoisted, the middle rear lower section and the middle rear upper section are loaded in turn to form the LNG tank structure section to complete the LNG tank loading.
8. A cabin section, characterized in that: The tank section is a dual-fuel type container ship LNG tank section, and adopts the dual-fuel type container ship LNG tank loading method as described in claim 7.
9. A ship, characterized in that: The ship is a dual-fuel tank ship, and the dual-fuel tank ship comprises the dual-fuel tank ship LNG tank section as claimed in claim 8.
Citation Information
Patent Citations
Construction method of deep oil tank area of container ship
CN112550626A
Block carrying method for an LNG cabin of container ship, LNG cabin block and container ship
CN113955044A
Novel segmented division method for LNG (Liquefied Natural Gas) cabins of container ship
CN115285308A
Block carrying method of liquefied gas carrier
CN116443207A
Construction method for liquid dome area of dual-fuel container ship
CN116620505A
Cited By
Module block division method of container ship
CN120423018A
Integral construction method for methanol cabin of ultra-large methanol dual-fuel ore carrier
CN121224941A
LNG fuel ship
CN122464000A