Prefabricated cable trough installation tool

By designing prefabricated cable trough installation tools, using the combination of walking mechanism and fixtures, the problems of low efficiency and damage in traditional cable trough installation construction are solved, and a more efficient and safe construction process is achieved.

CN118929486APending Publication Date: 2024-11-12NO 6 ENG CO LTD OF CHINA RAILWAY NO 3 ENG GRP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411138201.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-19
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

During the installation and construction of traditional cable ducts, manual handling leads to low construction efficiency and easy damage to the cable ducts, affecting the construction progress.

Method used

Design a prefabricated cable trough installation tool, including a running mechanism, operating rod and fixture, and use cross-shaped clamping arms and suspension chains to achieve stable clamping and lifting of cable troughs. Support frames and brackets improve support effects, simplify operation and reduce Construction cost.

Benefits of technology

Improve construction efficiency and ensure construction safety. Through the automatic clamping and support mechanism of fixtures, labor intensity and cable trough damage risks are reduced, and construction safety and efficiency are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118929486A_ABST
    Figure CN118929486A_ABST
Patent Text Reader

Abstract

The invention provides a prefabricated cable trough mounting tool, and belongs to the technical field of building construction. The prefabricated cable trough installation tool comprises a walking mechanism, an operating rod and a clamp, the operating rod is installed on the walking mechanism, the two ends of the operating rod can swing up and down, the clamp is connected to the front end of the operating rod, the clamp comprises two clamping arms which are distributed in a crossed mode, and the two clamping arms are connected with the operating rod. The two clamping arms are rotationally connected, a clamping plate is arranged between the opposite sides of the bottom ends of the two clamping arms, and the top ends of the two clamping arms are both connected to the front end of the operating rod. The device has the advantages of being simple in structure and convenient to operate, reducing construction cost, improving construction efficiency and guaranteeing construction safety.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a prefabricated cable trough installation tool. Background Art

[0002] In the field of construction, the traditional cable trough installation and construction adopts manual handling and installation, which is slow and easy to cause collisions during the handling process, causing damage to the cable trough and affecting the construction progress. Therefore, a device that is easy to install, easy to operate and labor-saving is designed to solve the above problems. Summary of the invention

[0003] In order to solve the above technical problems, the present invention provides a prefabricated cable trough installation tool.

[0004] The technical solution of the present invention is achieved in this way:

[0005] A prefabricated cable trough installation tool, comprising a running mechanism, an operating rod and a clamp, wherein the operating rod is installed on the running mechanism, and both ends of the operating rod can swing up and down, and the clamp is connected to the front end of the operating rod, wherein the clamp comprises two clamping arms distributed in a cross shape, the two clamping arms are rotatably connected, a clamping plate is arranged between opposite sides of the bottom ends of the two clamping arms, and the top ends of the two clamping arms are connected to the front end of the operating rod.

[0006] Furthermore, a hook is provided at the front end of the operating rod, a suspension chain is connected between the top ends of the two clamping arms, and the suspension beam is suspended on the hook.

[0007] Furthermore, the running mechanism includes a wheel axle and wheel bodies installed on both ends of the wheel axle, a support frame is installed on the wheel axle, and the top end of the support frame is sleeved on the operating rod.

[0008] Furthermore, the inner side surface of the clamping plate is provided with a back plate that can be raised and lowered, and the outer side surface of the back plate is rotatably mounted with a support rod, one end of the support rod is rotatably connected to a connecting rod, and the top end of the connecting rod is rotatably connected to the clamping plate, wherein the clamping plate is displaced upward on the back plate so that the support rod is supported on the bottom of the side of the prefabricated cable trough.

[0009] Furthermore, the support rod includes a first rod body, a second rod body and a third rod body, the first rod body and the third rod body are perpendicular to each other, two ends of the second rod body are respectively connected to the first rod body and the third rod body, and one end of the first rod body away from the second rod body is rotatably connected to the connecting rod, wherein, when the support rod is supported on the bottom of the side of the prefabricated cable trough, the second rod body is in contact with the bottom of the side of the prefabricated cable trough, and the bottom end of the second rod body is inclined inward, and the height of the third rod body is less than the height of the prefabricated cable trough.

[0010] Furthermore, a roller is provided on the lower surface of the third rod.

[0011] Furthermore, a support plate is vertically arranged at the bottom end of the backing plate.

[0012] Furthermore, the clamping plate is provided with longitudinally distributed through grooves, and a sliding rod penetrating the through grooves and capable of sliding in the through grooves along the height direction is vertically mounted on the outer side surface of the support plate.

[0013] The present invention has the following beneficial effects:

[0014] 1. The prefabricated cable trough installation tool of the present application has a simple structure, is easy to operate, reduces construction costs, improves construction efficiency, and ensures construction safety.

[0015] 2. The prefabricated cable trough installation tool of the present application, after the prefabricated cable trough is lifted, the towing rods on both sides are respectively supported at the corners of the bottom of the side walls of the prefabricated cable trough, thereby improving the supporting effect of the prefabricated cable trough and further ensuring construction safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 This is a schematic diagram of the present invention when clamping a prefabricated cable trough;

[0017] Figure 2 The present invention Figure 1 Enlarged view of point A in the middle.

[0018] In the figure: 1. Traveling mechanism; 1.1. Axle; 1.2. Wheel body; 2. Operating lever; 3. Clamp; 3.1. Clamping arm; 3.2. Clamping plate; 4. Hook; 5. Suspension chain; 6. Support frame; 7. Back plate; 8. Support rod; 8.1. First rod body; 8.2. Second rod body; 8.3. Third rod body; 9. Connecting rod; 10. Roller; 11. Support plate; 12. Through groove; 13. Sliding rod. DETAILED DESCRIPTION

[0019] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0020] like Figure 1 and Figure 2As shown, this embodiment provides a prefabricated cable trough installation tool, including a running mechanism 1, an operating rod 2 and a clamp 3, the operating rod 2 is installed on the running mechanism 1, and the two ends of the operating rod 2 can swing up and down, the clamp 3 is connected to the front end of the operating rod 2, wherein the clamp 3 includes two clamping arms 3.1 distributed in a cross shape, the two clamping arms 3.1 are rotatably connected, a clamping plate 3.2 is arranged between the opposite sides of the bottom ends of the two clamping arms 3.1, and the top ends of the two clamping arms 3.1 are connected to the front end of the operating rod 2.

[0021] The running mechanism 1 serves as the mobile carrier of the entire prefabricated cable trough installation tool. The clamp 3 rotates relative to each other at the bottom ends of the two clamping arms 3.1, so that the two clamping plates 3.2 can automatically clamp the prefabricated cable trough from both sides under the action of gravity. The worker presses down the tail end of the operating rod 2, so that the operating rod 2 uses the running mechanism 1 as a fulcrum and its front end tilts upward. At this time, the clamp 3 lifts the clamped prefabricated cable trough off the ground, and then adjusts the position of the lifted prefabricated cable trough by using the displacement of the running mechanism 1. When lowering the prefabricated cable trough to the preset installation position, the front end of the operating rod 2 is directly swung downward to place the prefabricated cable trough to the preset installation position. At this time, the clamp 3 automatically removes the clamping force on the prefabricated cable trough, so that the clamp 3 can release the prefabricated cable trough.

[0022] The front end of the operating rod 2 is provided with a hook 4, and a suspension chain 5 is connected between the top ends of the two clamping arms 3.1, and the suspension chain 5 is suspended on the hook 4. The clamp 3 is suspended on the hook 4 at the front end of the operating rod 2 by the suspension chain 5. After the prefabricated cable trough is clamped by the clamp 3, when the front end of the operating rod 2 swings upward to lift the prefabricated cable trough, the two ends of the suspension chain 5 are subjected to inward pulling force under the action of gravity, so that the clamp 3 tends to clamp the prefabricated cable trough. Then, when the prefabricated cable trough is transferred, the clamp 3 can stably clamp the prefabricated cable trough under the action of gravity of the prefabricated cable trough.

[0023] The running mechanism 1 includes a wheel axle 1.1 and a wheel body 1.2 installed at both ends of the wheel axle 1.1. A support frame 6 is installed on the wheel axle 1.1, and the top end of the support frame 6 is sleeved on the operating rod 2. After the prefabricated cable trough is hoisted, the operating rod 2 is directly pushed, and the position of the prefabricated cable trough can be adjusted by using the running mechanism 1 to walk on the ground. After the clamp 3 clamps the prefabricated cable trough, the support frame 6 is used as the rotation fulcrum of the operating rod 2, and combined with the lever formed by the operating rod 2, the hoisting process of the prefabricated cable trough is more labor-saving.

[0024] The inner side surface of the clamping plate 3.2 is provided with a lifting and lowering back plate 7, and the outer side surface of the back plate 7 is rotatably installed with a supporting rod 8, one end of the supporting rod 8 is rotatably connected to a connecting rod 9, and the top end of the connecting rod 9 is rotatably connected to the clamping plate 3.2, wherein the clamping plate 3.2 is displaced upward on the back plate 7 so that the supporting rod 8 is supported on the bottom of the side of the prefabricated cable trough.

[0025] Specifically, when the clamp 3 clamps the prefabricated cable trough, the clamping plate 3.2 makes the back plate 7 close to the side wall of the prefabricated cable trough. In the process of lifting the prefabricated cable trough, the clamping plate will move upward on the back plate 7, and the connecting rod 9 will pull the supporting rod 8 upward. The end of the supporting rod 8 away from the connecting rod 9 will swing inward, and finally the supporting rod 8 will be supported on the bottom of the side wall of the prefabricated cable trough, that is, supported on the corner of the bottom side of the prefabricated cable trough, so that in the process of transferring the prefabricated cable trough, the supporting rod 8 assists in supporting the prefabricated cable trough, thereby improving the stability of the prefabricated cable trough when hoisting.

[0026] Among them, the supporting rod 8 includes a first rod body 8.1, a second rod body 8.2 and a third rod body 8.3. The first rod body 8.1 and the third rod body 8.3 are perpendicular to each other. The two ends of the second rod body 8.2 are respectively connected to the first rod body 8.1 and the third rod body 8.3. The end of the first rod body 8.1 away from the second rod body 8.2 is rotatably connected to the connecting rod 9. When the supporting rod 8 is supported at the bottom of the side of the prefabricated cable trough, the second rod body 8.2 is in contact with the bottom of the side of the prefabricated cable trough, and the second rod body 8.2 is in a state where the bottom end is tilted inward, and the height of the third rod body 8.3 is less than the height of the prefabricated cable trough.

[0027] When the prefabricated cable trough is lowered to the preset position, the third rod 8.3 contacts the ground first. In the subsequent process of continuously lowering the prefabricated cable trough, the prefabricated cable trough is squeezed downward into the second rod 8.2 in an inclined state, so that the support rod 8 is displaced outward as a whole. At this time, the support rod 8 causes the clamp 3 to be displaced outward as a whole to loosen the prefabricated cable trough.

[0028] The lower surface of the third rod 8.3 is provided with a roller 10. By providing the roller 10, when the third rod 8.3 is subjected to the pressure of the prefabricated cable trough during the lowering of the cable trough, the roller 10 enables the support rod 8 to move outward more smoothly and be pulled away from the bottom of the prefabricated cable trough, and enables the clamp 3 to open and release the prefabricated cable trough.

[0029] A support plate 11 is vertically arranged at the bottom of the support plate 7. When the clamp 3 is lowered to clamp the prefabricated cable trough, the support plate 11 will first support the ground on both sides of the prefabricated cable trough to support the support plate 7. As the clamp 3 continues to be lowered, the slide bar 13 will move upward to a higher position in the through slot 12, so that the top of the connecting rod 9 will drop, and the connecting rod 9 will make the top of the supporting rod 8 rotate inward, so that the supporting rod 8 is in a horizontal state, so that the clamp 3 can better clamp the prefabricated cable trough.

[0030] Furthermore, when the prefabricated cable trough is lifted, the clamping plate 3.2 moves upward outside the support plate 7, so that the connecting rod 9 is pulled upward, and the connecting rod 9 pulls the supporting rod 8, so that the supporting rod 8 swings inward to the bottom supported on the side of the prefabricated cable trough.

[0031] A longitudinally distributed through slot 12 is formed on the clamping plate 3 . A sliding rod 13 penetrating through the through slot 12 and capable of sliding in the through slot 12 along the height direction is vertically mounted on the outer side of the support plate 7 .

[0032] Specifically, the clamp 3 is in the initial state, and it is in the suspended state. At this time, the slide bar 13 cooperates with the through slot 12 to stably suspend the support plate 7 on the clamping plate 3.2. The outer end of the slide bar 13 passes through the through slot 12 and extends outward. In this way, when the prefabricated cable trough is lowered, when the support rod 8 is displaced outward by the pressure of the prefabricated cable trough, the clamp 3 will release the prefabricated cable trough. At this time, the clamping arm 3.1 drives the clamping plate 3.2 to swing outward. Then, the length of the slide bar 13 can be well used in the process of the clamping arm 3.1 swinging outward, so as to keep the through slot 12 always effectively sleeved on the slide bar 13.

[0033] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A prefabricated cable trough installation tool, characterized in that: The invention comprises a running mechanism (1), an operating rod (2) and a clamp (3), wherein the operating rod (2) is mounted on the running mechanism (1), and the two ends of the operating rod (2) can swing up and down, and the clamp (3) is connected to the front end of the operating rod (2), wherein the clamp (3) comprises two clamping arms (3.1) distributed in a cross shape, the two clamping arms (3.1) are rotatably connected to each other, a clamping plate (3.2) is arranged between opposite sides of the bottom ends of the two clamping arms (3.1), and the top ends of the two clamping arms (3.1) are connected to the front end of the operating rod (2).

2. A prefabricated cable trough installation tool as claimed in claim 1, characterized in that: A hook (4) is provided at the front end of the operating rod (2), a suspension chain (5) is connected between the top ends of the two clamping arms (3.1), and the suspension beam is suspended on the hook (4).

3. A prefabricated cable trough installation tool as claimed in claim 1, characterized in that: The running mechanism (1) comprises a wheel axle (1.1) and wheel bodies (1.2) mounted at both ends of the wheel axle (1.1); a support frame (6) is mounted on the wheel axle (1.1), and the top end of the support frame (6) is sleeved on the operating rod (2).

4. A prefabricated cable trough installation tool as claimed in claim 1, characterized in that: The inner side surface of the clamping plate (3.2) is provided with a lifting support plate (7), and the outer side surface of the support plate (7) is rotatably mounted with a supporting rod (8), one end of the supporting rod (8) is rotatably connected to a connecting rod (9), and the top end of the connecting rod (9) is rotatably connected to the clamping plate (3.2), wherein the clamping plate (3.2) is displaced upward on the support plate (7) so that the supporting rod (8) is supported on the bottom of the side surface of the prefabricated cable trough.

5. A prefabricated cable trough installation tool as claimed in claim 4, characterized in that: The support rod (8) comprises a first rod body (8.1), a second rod body (8.2) and a third rod body (8.3); the first rod body (8.1) and the third rod body (8.3) are perpendicular to each other; two ends of the second rod body (8.2) are respectively connected to the first rod body (8.1) and the third rod body (8.3); one end of the first rod body (8.1) away from the second rod body (8.2) is rotatably connected to a connecting rod (9); when the support rod (8) is supported on the bottom of the side of the prefabricated cable trough, the second rod body (8.2) contacts the bottom of the side of the prefabricated cable trough, and the bottom end of the second rod body (8.2) is inclined inwardly; and the height of the third rod body (8.3) is less than the height of the prefabricated cable trough.

6. A prefabricated cable trough installation tool as claimed in claim 5, characterized in that: A roller (10) is provided on the lower surface of the third rod body (8.3).

7. A prefabricated cable trough installation tool as claimed in claim 5, characterized in that: A supporting plate (11) is vertically arranged at the bottom end of the backing plate (7).

8. A prefabricated cable trough installation tool as claimed in claim 4, characterized in that: The clamping plate (3.2) is provided with a longitudinally distributed through slot (12), and a sliding rod (13) penetrating the through slot (12) and capable of sliding in the through slot (12) along the height direction is vertically mounted on the outer side surface of the support plate (7).