Railway bridge bottom inspection vehicle track dismantling tool and method

CN118932803APending Publication Date: 2024-11-12CHENGDU XINTU TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411099522.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-12
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In the prior art, there are difficulties in dismantling the railway bridge bottom inspection vehicle track system, lack of a mature construction technology system, traditional methods consume manpower and material resources, and there are many uncontrollable factors, and the cost is high.

Method used

The track transfer system, detachable load-bearing seat and temporary track combination is adopted to move along the original track through the track transfer system, and the track removal is achieved by using the traction mechanism and drive wheel set. The original inspection vehicle track is removed step by step to reduce construction costs and uncontrollable factors. Influence.

Benefits of technology

It has achieved efficient and low-cost rail removal in complex environments of railway bridges, adapted to complex geographical locations, shortened construction cycles, and improved construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118932803A_ABST
    Figure CN118932803A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of bridge inspection vehicles, aims to solve the problem that in the prior art, a railway bridge bottom inspection vehicle track system is difficult to dismantle, and provides a railway bridge bottom inspection vehicle track dismantling tool and method. The tool comprises a track transfer system, a track dismantling system, a temporary track and a plurality of sets of detachable bearing bases, and the track transfer system is installed on an original inspection vehicle track and can move along the original inspection vehicle track; the plurality of groups of detachable bearing seats are detachably mounted on the track joint seats of the original inspection vehicle respectively; the temporary track is installed on the multiple sets of detachable bearing bases, can slide relative to the detachable bearing bases and can also be locked with the detachable bearing bases; the track dismantling system is mounted on the temporary track, and the track dismantling system can transfer the dismantled original inspection car track to the track transfer system; the method is not limited by sites and working condition environments, and the inspection car track is removed forwards along the beam bottom.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of bridge inspection vehicles, and in particular to a track removal tool and method for a railway bridge bottom inspection vehicle. Background Art

[0002] The bridge bottom inspection vehicle is a bridge maintenance and repair equipment that can move under the bridge. At present, due to the long construction and operation time of some bridges, the bottom inspection vehicle and track system are seriously aged, and there are serious safety hazards. Therefore, it is necessary to dismantle the inspection vehicle system that is seriously aged and cannot operate normally. Among them, railway bridges have many problems when dismantling their inspection vehicle systems due to their special operation, complex working conditions and high safety requirements. The main problems are as follows:

[0003] 1. At present, domestic railway bridges have not yet carried out the dismantling of the beam bottom inspection vehicle and the track system, so there is no mature construction process system;

[0004] 2. Traditional construction methods usually use special equipment such as truck cranes or aerial platforms to inspect the dismantling of vehicles and track systems. However, the site and construction environment below the railway bridge are relatively complex and require coordination and cooperation from many aspects. Therefore, it consumes more manpower and material resources. The geographical location of some beam sections may not meet the construction requirements of special equipment such as truck cranes and aerial platforms. There are many uncontrollable factors and the construction cost is high. Summary of the invention

[0005] The present invention aims to provide a track dismantling tool and method for a railway bridge bottom inspection vehicle, so as to solve the problem of difficulty in dismantling the track system of the railway bridge bottom inspection vehicle in the prior art.

[0006] The present invention is achieved by adopting the following technical solutions:

[0007] The present invention provides a rail dismantling tool for a railway bridge bottom inspection vehicle, comprising a rail transfer system, a rail dismantling system, a temporary rail and a plurality of groups of detachable load-bearing seats, wherein the rail transfer system is installed on the original inspection vehicle rail, and the rail transfer system can move along the original inspection vehicle rail;

[0008] A plurality of groups of the detachable load-bearing seats are detachably mounted on the rail joint seats of the original inspection vehicle respectively;

[0009] The temporary rails are installed on a plurality of groups of the detachable load-bearing seats, and the temporary rails can slide relative to the detachable load-bearing seats and can also be locked with the detachable load-bearing seats;

[0010] The track removal system is installed on the temporary track, and the track removal system can transfer the removed original inspection vehicle track to the track transfer system.

[0011] As the preferred technical solution:

[0012] The track transfer system is equipped with a driving wheel set, which is rollingly connected to the upper flange plate of the original inspection vehicle track. The track transfer system can move along the upper flange plate of the original inspection vehicle track.

[0013] As the preferred technical solution:

[0014] The track transfer system includes a track transfer truss, on which a traction mechanism is installed. The traction mechanism is used to pull the track transfer truss to move along the upper flange plate of the original inspection vehicle track.

[0015] As the preferred technical solution:

[0016] The driving wheel set is installed on the upper part of the track transfer truss.

[0017] As the preferred technical solution:

[0018] The traction mechanism includes a traction hoist and a traction wire rope. The traction hoist is installed on the track transfer truss. One end of the traction wire rope is connected to the traction hoist, and the other end of the traction wire rope is connected to the end of the railway bridge.

[0019] As the preferred technical solution:

[0020] Two sets of inverted driving wheels are installed on the detachable load-bearing seat, and the temporary track adopts an I-shaped steel rail. The two sets of inverted driving wheels are respectively arranged on both sides of the rail waist of the temporary track and contact the bottom surface of the upper flange plate of the temporary track. The temporary track is slidably connected to the detachable load-bearing seat, and the temporary track can move forward relative to the detachable load-bearing seat.

[0021] As the preferred technical solution:

[0022] Holes are provided on the temporary track and the detachable load-bearing seat, and the temporary track is locked on the detachable load-bearing seat by installing fastening connectors in the holes.

[0023] As the preferred technical solution:

[0024] The temporary track is arranged directly below the original inspection vehicle track, and the length direction of the temporary track is the same as the length direction of the original inspection vehicle track.

[0025] As the preferred technical solution:

[0026] The track removal system comprises a track removal truss, a driving wheel set is installed on the track removal truss, the driving wheel set is in contact with the lower flange plate of the temporary track, and the track removal truss can move along the temporary track.

[0027] As the preferred technical solution:

[0028] Holes are provided on the track removal truss and the temporary track. When the track removal truss arrives at the construction site, the track removal truss is locked on the temporary track by installing fastening connectors in the holes.

[0029] As the preferred technical solution:

[0030] The fastening connection member may be a bolt.

[0031] As the preferred technical solution:

[0032] Roller brackets are provided on both sides of the track dismantling truss and the track transfer truss, and the positions of the roller brackets on the two correspond to each other. The dismantled original inspection vehicle track is transferred to the track transfer system through the roller brackets.

[0033] As the preferred technical solution:

[0034] A lifting and moving mechanism is installed on the track removal truss, and the lifting and moving mechanism is located above the original inspection vehicle track. The lifting and moving mechanism is used to connect with the original inspection vehicle track, and the original inspection vehicle track is lifted and protected in advance when the original inspection vehicle track is removed.

[0035] As the preferred technical solution:

[0036] The lifting and moving mechanism adopts a hand-pulled lifting hoist.

[0037] As the preferred technical solution:

[0038] A plurality of hand-pulled lifting hoists are installed on the track transfer truss.

[0039] As the preferred technical solution:

[0040] A track lowering mechanism is installed on the track transfer truss, and the track lowering mechanism is used to lower the original inspection vehicle track to the ground.

[0041] As the preferred technical solution:

[0042] The track lowering mechanism adopts a lifting winch.

[0043] As the preferred technical solution:

[0044] A temporary suspension seat is installed on the temporary track, and a safety stopper is arranged at the end of the temporary track.

[0045] The present invention further provides a method for removing the track of a railway bridge bottom inspection vehicle, wherein the track is removed by using the above-mentioned railway bridge bottom inspection vehicle track removal tool, and the method comprises the following steps:

[0046] S1: Install the rail removal tooling for the railway bridge bottom inspection vehicle;

[0047] Install the track transfer system on the original inspection vehicle track, install each set of detachable load-bearing seats on each original inspection vehicle track joint seat, install and lock the temporary track on each set of detachable load-bearing seats, install the track removal system and temporary suspension seat on the temporary track, and complete the installation;

[0048] S2: Dismantle the first section of the original inspection vehicle track;

[0049] The lifting and moving mechanism is connected to the first section of the original inspection vehicle track and tightened to lift and protect the first section of the original inspection vehicle track; then the first section of the original inspection vehicle track is dismantled, and after dismantling, it is lifted and placed on the roller bracket on the side of the track dismantling system by the lifting and moving mechanism, and the first section of the original inspection vehicle track is pushed to the roller bracket on the side of the track transfer system and fixed;

[0050] S3: Dismantle the second section of the original inspection vehicle track;

[0051] Connect the temporary suspension seat to the original inspection vehicle track joint seat at the rear end, then remove the removable load-bearing seat at the rear end and put it into the track dismantling system; connect the track dismantling system with the track transfer system; release the connection between the temporary suspension seat and the original inspection vehicle track joint seat, release the connection between the unremoved removable load-bearing seat and the temporary track, push the temporary track forward, and the front end of the temporary track reaches the previous original inspection vehicle track joint seat, and lock the temporary track with the unremoved removable load-bearing seat; release the connection between the track dismantling system and the track transfer system, drive the track transfer system to the previous original inspection vehicle track joint seat, and install the removed removable load-bearing seat on the original inspection vehicle track joint seat; dismantle the second section of the original inspection vehicle track, lift the second original inspection vehicle track by the lifting and moving mechanism and place it on the roller bracket on the other side of the track dismantling system, push the second section of the original inspection vehicle track to the roller bracket on the other side of the track transfer system and fix it;

[0052] S4: Transfer the dismantled original inspection vehicle track;

[0053] Drive the rail transfer system to the other side of the railway bridge, and lower the two sections of the original inspection vehicle tracks that have been removed to the ground through the track lowering mechanism on the rail transfer system;

[0054] S5: According to the method steps of steps S2-S4, the railway bridge bottom inspection vehicle track removal tooling is gradually moved forward to perform step-by-step mobile construction to completely remove the original inspection vehicle track.

[0055] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:

[0056] 1. The rail dismantling tooling for the inspection vehicle under the railway bridge of the present invention is installed and suspended at the bottom of the railway bridge for step-by-step mobile construction, which does not require a large amount of machinery and equipment and can greatly reduce construction costs. The present invention can adapt to the complex construction environment of the railway bridge, does not require a large amount of coordination and cooperation work, and greatly reduces the impact of uncontrollable factors on the construction during on-site construction. During construction, it is not restricted by the site and working environment, and the inspection vehicle track dismantling work can be carried out along the bottom of the beam all the way forward.

[0057] 2. The present invention arranges three groups of detachable load-bearing seats at the bottom of the original track joint seat, and then installs a temporary track under the original track, so that the track removal system can move relative to the original track on the temporary track. By continuously changing the position of the detachable load-bearing seats and sliding the temporary track, the track removal tooling of the railway bridge bottom inspection vehicle of the present invention can be ensured to move forward continuously.

[0058] 3. The present invention can be arranged and constructed simultaneously on the left and right sides of the railway bridge, which greatly reduces the construction period and improves the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0059] Figure 1 The present invention is a schematic structural diagram of the track removal tooling for the railway bridge bottom inspection vehicle.

[0060] Figure 2 The figure is a top view of the track removal tooling of the railway bridge bottom inspection vehicle described in the present invention.

[0061] Figure 3 The present invention is a schematic diagram of the installation of the track removal tooling for the railway bridge bottom inspection vehicle.

[0062] Figure 4 for Figure 3 Front view of .

[0063] Figure 5 for Figure 3 Side view of.

[0064] Icons: 1-railway bridge, 2-track transfer system, 3-track dismantling system, 301-1#track dismantling system, 302-2#track dismantling system, 4-original inspection vehicle track, 5-original inspection vehicle track joint seat, 6-removable load-bearing seat, 601-1#removable load-bearing seat, 602-2#removable load-bearing seat, 603-3#removable load-bearing seat, 7-temporary suspension seat, 8-holes, 9-temporary track, 10-hand-pulled hoist, 11-safety block, 12-roller bracket, 13-hoisting winch, 14-traction hoist. DETAILED DESCRIPTION

[0065] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0066] Example 1

[0067] like Figure 1-Figure 5 As shown, this embodiment proposes a track removal tool for a railway bridge bottom inspection vehicle, including a track transfer system 2, a track removal system 3, a detachable load-bearing seat 6 and a temporary track 9.

[0068] The rail transfer system 2 is installed on the original inspection vehicle track 4, and a driving wheel group is installed on the rail transfer system 2. The driving wheel group is rollingly connected to the upper flange plate of the original inspection vehicle track 4, and the rail transfer system 2 can move along the upper flange plate of the original inspection vehicle track 4.

[0069] The rail transfer system 2 includes a rail transfer truss, the driving wheel group is installed on the upper part of the rail transfer truss, and a traction mechanism is also installed on the upper part of the rail transfer truss. The traction mechanism is used to pull the rail transfer truss to move along the upper flange plate of the original inspection vehicle track 4.

[0070] In this embodiment, the traction mechanism includes a traction hoist 14 and a traction wire rope. The traction hoist 14 is installed on the rail transfer truss. One end of the traction wire rope is connected to the traction hoist 14, and the other end of the traction wire rope is connected to the end of the railway bridge 1. The traction hoist 14 is started, and the rail transfer truss is pulled toward the other side of the railway bridge 1 by the traction wire rope.

[0071] Furthermore, two traction hoists 14 are installed on the track transfer truss, and the two traction hoists 14 are respectively installed at the front and rear ends of the track transfer truss to facilitate traction of the track transfer truss to move in different directions.

[0072] It should be noted that the traction mechanism is not limited to the above-mentioned one, and other mechanisms capable of providing traction may also be used.

[0073] The detachable bearing seat 6 is installed on the original inspection vehicle track joint seat 5, and the original inspection vehicle track joint seat 5 is installed at the bottom of the railway bridge 1. In this embodiment, three groups of detachable bearing seats 6 are arranged at the bottom of the railway bridge 1, but it is not limited to three groups, and it can also be multiple groups. Three groups are a more preferred solution, which saves costs while ensuring construction safety. The detachable bearing seat 6 can be connected to the original inspection vehicle track joint seat 5 by bolts, which is convenient for installation and removal.

[0074] Two groups of inverted driving wheels are installed on the detachable load-bearing seat 6, and the temporary track 9 adopts an I-shaped steel rail. The two groups of inverted driving wheels are respectively arranged on both sides of the rail waist of the temporary track 9 and contact the bottom surface of the upper flange plate of the temporary track 9. The temporary track 9 is lifted by multiple groups of detachable load-bearing seats 6, and the temporary track 9 can be moved forward relative to the detachable load-bearing seat 6 through the inverted driving wheels.

[0075] Holes 8 are provided on both the temporary rail 9 and the detachable load-bearing seat 6 , and bolts can be installed in the holes 8 to lock the temporary rail 9 on the detachable load-bearing seat 6 .

[0076] The temporary track 9 is arranged directly below the original inspection vehicle track 4 , and the length direction of the temporary track 9 is the same as the length direction of the original inspection vehicle track 4 .

[0077] The track removal system 3 is installed on the temporary track 9 , and the track removal system 3 is movable on the temporary track 9 .

[0078] The track removal system 3 includes a track removal truss, on which a driving wheel set is also installed. The driving wheel set is in contact with the lower flange plate of the temporary track 9 , and the track removal truss can move along the temporary track 9 .

[0079] Holes 8 are provided on the track removal truss and the temporary track 9. When the track removal truss arrives at the construction site, the track removal truss can be locked on the temporary track 9 by installing bolts in the holes 8 to ensure construction safety.

[0080] Roller brackets 12 are provided on both sides of the track removal truss for placing the dismantled original inspection vehicle track 4 .

[0081] A lifting and moving mechanism is installed on the track removal truss, and the lifting and moving mechanism is located above the original inspection vehicle track 4. The lifting and moving mechanism is used to connect with the original inspection vehicle track 4. When the original inspection vehicle track 4 is removed, the track can be lifted and protected in advance to avoid falling or dropping after the track bolts are loosened, and the disassembled original inspection vehicle track 4 can be lifted and placed on the roller bracket 12 on one side of the track removal truss.

[0082] Roller brackets 12 are also provided on both sides of the track transfer truss and correspond to the positions of the roller brackets 12 on the track dismantling truss. When the disassembled original inspection vehicle track 4 is placed on the roller bracket 12 on the track dismantling truss, the original inspection vehicle track 4 can be pushed onto the roller bracket 12 on the track transfer truss. After the original inspection vehicle track 4 is fixed, it can be transported by the track transfer truss.

[0083] In this embodiment, the lifting and moving mechanism adopts a hand-pulled lifting hoist 10, and four hand-pulled lifting hoists 10 are installed on the track transfer truss. The four hand-pulled lifting hoists 10 are symmetrically arranged on the track transfer truss.

[0084] The track transfer truss is equipped with a track lowering mechanism, which is used to lower the original inspection vehicle track 4 on the roller brackets 12 on both sides of the track transfer truss to the ground. When the track transfer system 2 moves to the other side of the railway bridge 1, the original inspection vehicle track 4 is lowered to the ground by the track lowering mechanism.

[0085] In this embodiment, the track lowering mechanism adopts a lifting winch 13, and two lifting winches 13 are symmetrically installed on the track transfer truss, which are respectively used to lower the original inspection vehicle track 4 on the roller brackets 12 on both sides of the track transfer truss.

[0086] It should be noted that the present invention is not limited to the hand-pulled lifting hoist 10 and the hoisting winch 13 , and other mechanisms capable of lifting or lowering the original inspection vehicle track 4 may also be used.

[0087] In this embodiment, two track removal systems 3 are installed on the temporary track 9 , namely, a 1# track removal system 301 and a 2# track removal system 302 .

[0088] A temporary suspension seat 7 is also installed on the temporary track 9, and the temporary suspension seat 7 is arranged at the rear end of the temporary track 9. When the current section of the original inspection vehicle track 4 is dismantled and the next section of the original inspection vehicle track 4 is to be dismantled, the railway bridge bottom inspection vehicle track dismantling tooling needs to be moved forward (towards the other side of the railway bridge 1), and the track transfer system 2 can be moved directly on the original inspection vehicle track 4. The movement method of the detachable load-bearing seat 6 and the temporary track 9 is: first, the temporary suspension seat 7 is connected to the original inspection vehicle track joint seat 5 at the rear end by a steel wire rope, and a group of detachable load-bearing seats 6 at the rear end are dismantled; then the dismantled detachable load-bearing seats 6 are placed in the 2# track dismantling system 302, the 2# track dismantling system 302 is moved to the side of the 1# track dismantling system 301, and the 1# track The dismantling system 301 and the 2# track dismantling system 302 are connected to the track transfer system 2; then the connection between the temporary suspension seat 7 and the original inspection vehicle track joint seat 5 is released, the connection between the undisassembled detachable load-bearing seat 6 and the temporary track 9 is released, the temporary track 9 is pushed forward, the front end of the temporary track 9 is pushed to the front end of the original inspection vehicle track joint seat 5, and the temporary track 9 is fixed to the undisassembled detachable load-bearing seat 6; the connection between the track dismantling system 3 and the track transfer system 2 is released, and the disassembled detachable load-bearing seat 6 is transported to the front end of the original inspection vehicle track joint seat 5 through the track transfer system 2, and the disassembled detachable load-bearing seat 6 is installed on the front end of the original inspection vehicle track joint seat 5, and then the detachable load-bearing seat 6 is fixed to the temporary track 9. At this time, the dismantling of the next section of the original inspection vehicle track 4 can be carried out.

[0089] A safety stopper 11 is provided at the rear end of the temporary track 9 to prevent the temporary track 9 from sliding out and falling when the temporary track 9 is pushed forward.

[0090] When the track removal work is actually carried out, the track removal tooling of the railway bridge bottom inspection vehicle of the present invention can be arranged on the left and right sides of the railway bridge 1 at the same time, and the construction can be carried out at the same time, which greatly reduces the construction period and improves the construction efficiency.

[0091] The track removal is performed by using the above-mentioned railway bridge bottom inspection vehicle track removal tooling, and the railway bridge beam bottom inspection vehicle track removal method includes the following steps:

[0092] S1: Install the rail removal tooling for the railway bridge bottom inspection vehicle;

[0093] Install the track transfer system 2 on the original inspection vehicle track 4, install the three sets of detachable bearing seats 6 on the 1# original inspection vehicle track joint seat, the 2# original inspection vehicle track joint seat, and the 3# original inspection vehicle track joint seat, respectively, install and lock the temporary track 9 on the three sets of detachable bearing seats 6, install the track removal system 3 and the temporary suspension seat 7 on the temporary track 9, and complete the installation;

[0094] S2: dismantle the first section of the original inspection vehicle track 4;

[0095] The hand-pulled lifting hoist 10 is hooked to the first section of the original inspection vehicle track 4 in advance through the sling, and the hand-pulled lifting hoist 10 is tightened to lift and protect the first section of the original inspection vehicle track 4; then the first section of the original inspection vehicle track 4 is dismantled, and after dismantling, it is lifted by the hand-pulled lifting hoist 10 and placed on the roller bracket 12 on the side of the track dismantling system 3, and the first section of the original inspection vehicle track 4 is pushed to the roller bracket 12 on the side of the track transfer system 2 and fixed;

[0096] S3: dismantle the second section of the original inspection vehicle track 4;

[0097] Connect the temporary suspension seat 7 to the 1# original inspection vehicle track joint seat by a steel wire rope, then remove the 1# detachable load-bearing seat 601 and put it into the 2# track removal system 302; move the 2# track removal system 302 to the side of the 1# track removal system 301, and connect the 1# track removal system 301 and the 2# track removal system 302 with the track transfer system 2; release the connection between the temporary suspension seat 7 and the original inspection vehicle track joint seat 5, release the connection between the 2# detachable load-bearing seat 602 and the 3# detachable load-bearing seat 603 and the temporary track 9, and push the temporary track 9 forward until the safety block 11 at the rear end of the temporary track 9 contacts the 2# detachable load-bearing seat 602, and the temporary track 9 is The front end reaches the 4# original inspection vehicle track joint seat, and the temporary track 9 is locked with the 2# detachable load-bearing seat 602 and the 3# detachable load-bearing seat 603; the connection between the 1# track removal system 301, the 2# track removal system 302 and the track transfer system 2 is released, and the track transfer system 2 is driven to the 4# original inspection vehicle track joint seat, and the 1# detachable load-bearing seat 601 is installed on the 4# original inspection vehicle track joint seat; the second section of the original inspection vehicle track 4 is removed, and the second original inspection vehicle track 4 is lifted by the hand-pulled lifting hoist 10 and placed on the roller bracket 12 on the other side of the track removal system 3, and the second section of the original inspection vehicle track 4 is pushed to the roller bracket 12 on the other side of the track transfer system 2 and fixed;

[0098] S4: Transfer the dismantled original inspection vehicle track 4;

[0099] Drive the rail transfer system 2 to the other side of the railway bridge 1, and lower the two sections of the original inspection vehicle rails 4 that have been removed to the ground through the hoisting winch 13 on the rail transfer system 2;

[0100] S5: According to the method steps of steps S2-S4, the railway bridge bottom inspection vehicle track removal tooling is gradually moved forward to perform step-by-step mobile construction to completely remove the original inspection vehicle track 4.

[0101] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A track removal tool for a railway bridge bottom inspection vehicle, characterized in that: It includes a track transfer system, a track removal system, a temporary track and multiple sets of detachable load-bearing seats, wherein the track transfer system is installed on the original inspection vehicle track, and the track transfer system can move along the original inspection vehicle track; A plurality of groups of the detachable load-bearing seats are detachably mounted on the rail joint seats of the original inspection vehicle respectively; The temporary rails are installed on a plurality of groups of the detachable load-bearing seats, and the temporary rails can slide relative to the detachable load-bearing seats and can also be locked with the detachable load-bearing seats; The track removal system is installed on the temporary track, and the track removal system can transfer the removed original inspection vehicle track to the track transfer system.

2. The rail dismantling tool for the railway bridge bottom inspection vehicle according to claim 1 is characterized by: The track transfer system includes a track transfer truss, on which a traction mechanism is installed. The traction mechanism is used to pull the track transfer truss to move along the upper flange plate of the original inspection vehicle track.

3. The track removal tool for the railway bridge bottom inspection vehicle according to claim 1 is characterized by: Two sets of inverted driving wheels are installed on the detachable load-bearing seat, and the temporary track adopts an I-shaped steel rail. The two sets of inverted driving wheels are respectively arranged on both sides of the rail waist of the temporary track and contact the bottom surface of the upper flange plate of the temporary track. The temporary track is slidably connected to the detachable load-bearing seat, and the temporary track can move forward relative to the detachable load-bearing seat.

4. The track removal tool for the railway bridge bottom inspection vehicle according to claim 3 is characterized by: Holes are provided on the temporary track and the detachable load-bearing seat, and the temporary track is locked on the detachable load-bearing seat by installing fastening connectors in the holes.

5. The track removal tool for the railway bridge bottom inspection vehicle according to claim 2 is characterized by: The track removal system comprises a track removal truss, a driving wheel set is installed on the track removal truss, the driving wheel set is in contact with the lower flange plate of the temporary track, and the track removal truss can move along the temporary track.

6. The rail dismantling tool for the railway bridge bottom inspection vehicle according to claim 5 is characterized by: Roller brackets are provided on both sides of the track dismantling truss and the track transfer truss, and the positions of the roller brackets on the two correspond to each other. The dismantled original inspection vehicle track is transferred to the track transfer system through the roller brackets.

7. The track removal tool for the railway bridge bottom inspection vehicle according to claim 6 is characterized by: A lifting and moving mechanism is installed on the track removal truss, and the lifting and moving mechanism is located above the original inspection vehicle track. The lifting and moving mechanism is used to connect with the original inspection vehicle track, and the original inspection vehicle track is lifted and protected in advance when the original inspection vehicle track is removed.

8. The track removal tool for the railway bridge bottom inspection vehicle according to claim 7 is characterized by: A track lowering mechanism is installed on the track transfer truss, and the track lowering mechanism is used to lower the original inspection vehicle track to the ground.

9. The rail dismantling tool for the railway bridge bottom inspection vehicle according to claim 8 is characterized by: A temporary suspension seat is installed on the temporary track, and a safety stopper is arranged at the end of the temporary track.

10. A method for removing the track of a railway bridge bottom inspection vehicle, characterized in that: Track removal is performed by using the track removal tooling for the railway bridge bottom inspection vehicle according to claim 9, comprising the following steps: S1: Install the rail removal tooling for the railway bridge bottom inspection vehicle; Install the track transfer system on the original inspection vehicle track, install each set of detachable load-bearing seats on each original inspection vehicle track joint seat, install and lock the temporary track on each set of detachable load-bearing seats, install the track removal system and temporary suspension seat on the temporary track, and complete the installation; S2: Dismantle the first section of the original inspection vehicle track; The lifting and moving mechanism is connected to the first section of the original inspection vehicle track and tightened to lift and protect the first section of the original inspection vehicle track; then the first section of the original inspection vehicle track is dismantled, and after dismantling, it is lifted and placed on the roller bracket on the side of the track dismantling system by the lifting and moving mechanism, and the first section of the original inspection vehicle track is pushed to the roller bracket on the side of the track transfer system and fixed; S3: Dismantle the second section of the original inspection vehicle track; Connect the temporary suspension seat to the original inspection vehicle track joint seat at the rear end, then remove the removable load-bearing seat at the rear end and put it into the track dismantling system; connect the track dismantling system with the track transfer system; release the connection between the temporary suspension seat and the original inspection vehicle track joint seat, release the connection between the unremoved removable load-bearing seat and the temporary track, push the temporary track forward, and the front end of the temporary track reaches the previous original inspection vehicle track joint seat, and lock the temporary track with the unremoved removable load-bearing seat; release the connection between the track dismantling system and the track transfer system, drive the track transfer system to the previous original inspection vehicle track joint seat, and install the removed removable load-bearing seat on the original inspection vehicle track joint seat; dismantle the second section of the original inspection vehicle track, lift the second original inspection vehicle track by the lifting and moving mechanism and place it on the roller bracket on the other side of the track dismantling system, push the second section of the original inspection vehicle track to the roller bracket on the other side of the track transfer system and fix it; S4: Transfer the dismantled original inspection vehicle track; Drive the rail transfer system to the other side of the railway bridge, and lower the two sections of the original inspection vehicle tracks that have been removed to the ground through the track lowering mechanism on the rail transfer system; S5: According to the method steps of steps S2-S4, the railway bridge bottom inspection vehicle track removal tooling is gradually moved forward to perform step-by-step mobile construction to completely remove the original inspection vehicle track.