Fabricated bridge support and bridge construction method
By using the spring-type telescopic columns and wire rope cable connection structure of the prefabricated bridge support, the problems of insufficient installation accuracy, efficiency and safety of traditional supports are solved, realizing rapid installation and efficient construction, and reducing project costs.
Patent Information
- Application Number
- CN202411228414.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-03
- Publication Date
- 2024-11-12
AI Technical Summary
Traditional scaffolding systems used in existing bridge construction have shortcomings in terms of installation accuracy, efficiency, economy, and safety. Furthermore, the recycling and reuse of materials is difficult, posing safety hazards.
The bridge supports are prefabricated, including spring-loaded telescopic columns and a cross-laid steel wire rope or steel strand cable connection structure. The support columns can be quickly installed and retracted through the connection unit.
It enables rapid installation and disassembly, improves construction efficiency and safety, reduces project investment, and minimizes material waste and construction procedures.
Smart Images

Figure CN118932872A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of bridge construction, in particular to an assembled bridge support, and also to a bridge construction method, wherein the assembled bridge support of the present invention is adopted. Background Art
[0002] During the construction of bridges, the bridge support system is an important and indispensable support system in the construction process. Traditional supports are mostly used in current bridge construction, but with the innovation of bridge construction technology, the disadvantages of traditional supports in terms of installation accuracy, installation efficiency, economy, and environmental protection in construction have gradually emerged. For example, the existing disc buckle or bowl buckle brackets are mostly assembled at multiple points, the construction process is cumbersome, the workers' installation level is high, the brackets have strict requirements on the foundation, and overall collapse safety accidents are prone to occur; the fastener-type bracket often uses redundancy to ensure the safety of the bracket node, the mechanical model is not clear, and as the number of material reversals increases, material wear is prone to occur, and material defects at the nodes are uncontrollable, posing safety hazards; pier-beam brackets are mostly welded with large-diameter steel pipe columns, the height adjustability is relatively poor and relatively bulky, the construction requires high construction machinery and tools, and the circulation is difficult, resulting in material waste. Therefore, how to design a bridge bracket with high safety, convenient disassembly and assembly, and circulation is crucial in the field of bridge construction. Summary of the invention
[0003] In view of this, the present invention proposes an assembled bridge support and a bridge construction method.
[0004] To achieve the above object, the present invention adopts the following technical solutions: The assembled bridge support of the present invention comprises a plurality of vertically arranged support columns, and also comprises a connection structure for connecting the plurality of support columns end to end in sequence, wherein the support column is a spring-type telescopic column, which comprises a lower sleeve, an upper telescopic section slidably inserted in the lower sleeve, and an energy storage spring arranged in the lower sleeve, and a pull-up switch and a compression switch are arranged on the upper part of the lower sleeve; The connection structure includes a plurality of connection units, and two adjacent support columns are connected together through one of the connection units. The connection unit includes a lower cross brace connecting the two lower sleeves together and an upper cross brace connecting the two upper telescopic sections together. The upper cross brace and the lower cross brace are telescopic structures. The connection unit also includes a pair of lower oblique members connecting two adjacent lower sleeves together and a pair of upper oblique members connecting two adjacent upper telescopic joints together. The upper oblique members and the lower oblique members are both cross-arranged, and the upper oblique members and the lower oblique members are both steel wire rope cables, steel strand cables or steel rods.
[0005] The beneficial effects are: the prefabricated bridge support of the present invention can be prefabricated, and the on-site installation is simple and convenient, which greatly reduces the support assembly steps, saves assembly space, and effectively improves the installation speed and support installation accuracy, thereby shortening the construction period and improving the assembly quality; during the construction process, it can achieve rapid installation and rapid condensation and recovery, reduce the input of personnel and machinery, achieve safe and efficient construction, and reduce project investment.
[0006] Preferably, a lower node plate is provided on the upper part of each lower sleeve, and the lower cross brace is detachably connected to the lower node plates on both sides by bolts; and an upper node plate is provided on the upper part of each upper telescopic joint, and the upper cross brace is detachably connected to the upper node plates on both sides by bolts, so as to facilitate installation.
[0007] Preferably, the upper cross brace and the lower cross brace have the same structure, both comprising a first channel steel and a second channel steel, the first channel steel being provided with a plurality of protrusions at intervals, and the second channel steel being provided with positioning holes matching the protrusions at intervals. During actual installation, the first channel steel and the second channel steel are inserted together, the protrusions and the positioning holes are provided at equal intervals, and fixation can be achieved when the protrusions are clamped in the positioning holes.
[0008] The present invention also provides a bridge construction method, which adopts an assembled bridge support, wherein the assembled bridge support includes a plurality of vertically arranged support columns, and also includes a connection structure that connects the plurality of support columns end to end in sequence, wherein the support column is a spring-type telescopic column, which includes a lower sleeve, an upper telescopic section slidably inserted in the lower sleeve, and an energy storage spring arranged in the lower sleeve, and a pull-up switch and a compression switch are arranged on the upper part of the lower sleeve; The connection structure includes a plurality of connection units, and two adjacent support columns are connected together through one of the connection units. The connection unit includes a lower cross brace connecting the two lower sleeves together and an upper cross brace connecting the two upper telescopic sections together. The upper cross brace and the lower cross brace are telescopic structures. The connection unit also includes a pair of lower oblique members connecting two adjacent lower sleeves together and a pair of upper oblique members connecting two adjacent upper telescopic joints together. The upper oblique members and the lower oblique members are both cross-arranged, and the upper oblique members and the lower oblique members are both steel wire rope cables, steel strand cables or steel rods.
[0009] The bridge construction method of the present invention specifically includes the following construction steps: S1, mark the installation position of the prefabricated bridge support on the pier foundation after construction; S2, hoisting the assembled bridge support to the installation position, opening each supporting column of the assembled bridge support so that the upper telescopic joint pops out automatically, adjusting the length of each upper cross brace and lower cross brace, adjusting the length of the upper diagonal brace and the lower diagonal brace, and locking the assembled bridge support so that it is in an expanded support state; S3, repeat S2, install the remaining assembled bridge supports on the installation positions of the pier foundation in sequence, and lock the assembled bridge supports to put them in an unfolded support state; S4, installing a bridge formwork system on top of the fabricated bridge support; S5, pre-pressing the assembled bridge support, after which the upper cross brace and the lower cross brace of each assembled bridge support are checked, and then the beam body is constructed; S6, after the beam construction is completed, the bridge formwork system is dismantled, the upper expansion joint of each prefabricated bridge support is retracted into the lower sleeve, and the upper cross brace and the lower cross brace are folded together, and then the retracted prefabricated bridge supports are moved out from the bottom of the beam body to the designated site one by one; S7, repeat this process to realize the recovery of all prefabricated bridge supports under the beam body.
[0010] Compared with the prior art, the present invention adopts assembled bridge supports during construction. On the basis of meeting the needs of bridge construction, the on-site installation is simple and convenient, which greatly reduces the steps of bracket assembly, saves assembly space, and effectively improves the installation speed and bracket installation accuracy, thereby shortening the construction period and improving the assembly quality; during the construction process, rapid installation and rapid condensation and recovery can be achieved, reducing the input of personnel and machinery, realizing safe and efficient construction, and reducing project investment. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 It is a schematic diagram of the expansion of the assembled bridge support of the present invention.
[0012] Figure 2 yes Figure 1 Top view of the .
[0013] Figure 3 It is a condensed schematic diagram of the assembled bridge support of the present invention.
[0014] Figure 4 It is a construction state diagram of the present invention. DETAILED DESCRIPTION
[0015] The following is a detailed description of an embodiment of the present invention in conjunction with the accompanying drawings. This embodiment is implemented on the premise of the technical solution of the present invention, and a detailed implementation method and a specific operation process are given, but the protection scope of the present invention is not limited to the following embodiment.
[0016] It should be noted that, in the description of the present invention, relational terms such as “first” and “second” are merely used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any actual relationship or order between these entities or operations.
[0017] In the description of the present invention, unless otherwise clearly specified and limited, the terms "connected" and "connection" that may appear should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0018] like Figure 1-3 As shown, the assembled bridge support described in the present invention includes four vertically arranged support columns 1, and also includes a connection structure that connects the four support columns 1 together end to end in sequence. The four support columns 1 are all spring-type telescopic columns, including a lower sleeve 1.1, an upper telescopic section 1.2 slidably inserted in the lower sleeve 1.1 (the length of the upper telescopic section 1.2 is greater than the length of the lower sleeve 1.1, so that the upper part of the upper telescopic section 1.2 is located outside the lower sleeve in a retracted state) and an energy storage spring 1.3 arranged in the lower sleeve 1.1, and a pull-up switch K1 and a compression switch K2 are arranged on the upper part of the lower sleeve 1.1. The compression switch K2 is used to retract the upper telescopic section 1.2 into the lower sleeve 1.1. After the compression switch is turned on, the upper telescopic section 1.2 automatically moves upward under the action of the energy storage spring 1.3; when the pull-up switch K1 is turned on, the compression potential energy of the energy storage spring 1.3 increases, and under the action of the counter-tension, the upper telescopic section 1.2 returns to the initial state; Combination Figure 1-3 It can be seen that the connection unit includes a connection unit that connects the four support columns 1 end to end, that is, two adjacent support columns 1 are connected together through a connection unit, and the connection unit includes a lower cross brace 2 that connects the two lower sleeves 1.1 together and an upper cross brace 3 that connects the two upper telescopic sections 1.2 together, the lower cross brace 2 is installed on the upper part of the lower sleeve 1.1, and the upper cross brace 3 is installed on the upper part of the two upper telescopic sections 1.2; During the actual installation, a lower node plate 4 is provided on the upper part of each lower sleeve 1.1, and the two ends of the lower cross brace 2 are detachably connected to the lower node plate 4 by bolts; an upper node plate 5 is symmetrically provided on the upper part of each upper telescopic joint 1.2, and the upper cross brace 3 is detachably connected to the upper node plates 5 on both sides by bolts, so the assembly is simple; The upper cross brace 3 and the lower cross brace 2 both adopt a telescopic structure, and both include a first channel steel and a second channel steel. The size of the first channel steel is slightly larger than that of the second channel steel, so that the second channel steel can be inserted into the first channel steel. In order to ensure the reliable connection and elasticity of the two, a plurality of protrusions F1 are processed at intervals on the inner waist surface of the first channel steel, and a plurality of positioning holes F2 (equidistantly arranged) cooperating with the protrusions F1 are arranged at intervals on the waist of the second channel steel F2. The protrusions F1 are clamped in the positioning holes F2 to fix the two, and the length can be adjusted by horizontal pulling. Since the upper cross brace 3, the lower cross brace 2, and the support column 1 all adopt a telescopic structure, the support column 1 can be adjusted to the lowest state when not in use, and the upper cross brace 3 and the lower cross brace 2 can be adjusted to the shortest state, which is convenient for transportation and storage. Of course, during actual installation, the first channel steel and the second channel steel can also be connected by bolts.
[0019] Combination Figure 1 It can be seen that the connection unit also includes a pair of lower inclined members 6 connecting two adjacent lower sleeves 1.1 together and a pair of upper inclined members 7 connecting two adjacent upper telescopic joints 1.2 together. Figure 1 The upper parts of the two upper diagonal braces 7 are connected to the upper node plate 5 by bolts, and the lower parts are connected to the lower node plate 4 by bolts; a bottom node plate 8 is provided at the bottom of the lower sleeve 1.1, and the two lower diagonal braces 6 are cross-installed, the upper parts are connected to the upper node plate 5 by bolts, and the lower parts are connected to the bottom node plate 8 by bolts; The upper inclined brace 7 and the lower inclined brace 6 are both steel wire rope cables (or steel strand cables or steel pull rods), and each end of the steel wire rope cables has a thread (which can be adjusted with the help of a wrench) to facilitate the adjustment of the length of the cable, thereby locking the spacing of the supporting columns 1 and realizing the locking of the assembled bridge support.
[0020] In actual processing, both the lower sleeve 1.1 and the upper telescopic section 1.2 are made of round steel pipes, which are convenient for processing and height adjustment; a bottom steel plate 1.4 is welded to the bottom of the lower sleeve 1.2, and a mounting plate 1.5 is horizontally arranged at the bottom of the upper telescopic section 1.2, and a top steel plate 1.6 is welded to the top. In actual installation, one or two pairs of concentric lower mounting holes can be opened on the wall of the lower sleeve 1.1, and multiple pairs of concentric upper mounting holes can be opened at equal intervals on the upper telescopic section 1.2, and the upper telescopic section 1.2 and the lower sleeve 1.1 are fixedly connected by a long screw, so as to meet the flexible adjustment of the support height.
[0021] The assembled bridge support of the present invention can be prefabricated, and because it can be telescopically adjusted in both vertical and horizontal directions, it is convenient for transportation and turnover; at the construction site, it only needs to be placed in the designated installation position and unfolded and locked, which is quick to install, greatly reducing the steps of bracket assembly, effectively improving the installation speed and bracket installation accuracy, thereby shortening the construction period and improving the assembly quality; during the construction process, it can be quickly installed and disassembled, reducing the input of personnel and machinery, achieving safe and efficient construction, and reducing project investment.
[0022] The present invention also provides a bridge construction method, comprising the following construction steps: S1, first construct the pier foundation, level the site after the construction is completed, and mark the position of each assembled bridge support on the pier to ensure the high-precision installation of each support. Figure 4 A; S2, lift multiple assembled bridge supports to the corresponding installation positions respectively, see Figure 4 B. Expand and lock each prefabricated bridge support separately. Take the expansion and locking of the support as an example: adjust the length of each support column 1. During the adjustment, the upper telescopic section 1.2 pops up under the action of the energy storage spring 1.3; adjust the length of each lower cross brace 2 and upper cross brace 3. During the adjustment, pull the support column 1 to both sides; use a wrench to adjust each thread, tighten the cable, and then achieve the locking of the expanded state. For details, see Figure 4 C; Of course, in actual construction, the construction process of lifting and unfolding can also be carried out simultaneously; S3, installing the bridge formwork system on the top of the assembled bridge support, and after the bridge formwork system is installed, inspecting and accepting the support system consisting of multiple supports on the pier; S4, after acceptance, pre-press the support system, and check the upper cross brace 3 and lower cross brace 2 of each support again to ensure that they meet the requirements of the specification, and then construct the beam body. For details, see Figure 4 D; S6, after the beam construction is completed, the bridge formwork system is removed, and each bracket is adjusted to the retracted state one by one and lifted to the specified position. Take one of the brackets as an example: turn on the pull-up switch, the potential energy of the energy storage spring 1.3 increases, so that the upper telescopic section 1.2 automatically retracts into the lower sleeve 1.1, and the upper cross brace 3 and the lower cross brace 2 are condensed together (see Figure 4 E) Move the retracted prefabricated bridge supports one by one from the bottom of the beam to the designated site; S7, further compress the upper telescopic section 1.2 of each bracket to the bottom and lock it with the compression switch. Figure 2 It is transported to a dedicated storage site in the compressed state shown and awaits use in the next bridge project.
[0023] Finally, it should be emphasized that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions recorded in the aforementioned embodiments without creative work, or replace some of the technical features therein with equivalents. Therefore, any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. An assembled bridge support, comprising a plurality of vertically arranged support columns, Features: It also includes a connection structure that connects the plurality of support columns end to end in sequence, wherein the support column is a spring-type telescopic column, which includes a lower sleeve, an upper telescopic section slidably inserted in the lower sleeve, and an energy storage spring arranged in the lower sleeve, and a pull-up switch and a compression switch are arranged on the upper part of the lower sleeve; The connection structure includes a plurality of connection units, and two adjacent support columns are connected together through one of the connection units. The connection unit includes a lower cross brace connecting the two lower sleeves together and an upper cross brace connecting the two upper telescopic sections together. The upper cross brace and the lower cross brace are telescopic structures. The connection unit also includes a pair of lower oblique members connecting two adjacent lower sleeves together and a pair of upper oblique members connecting two adjacent upper telescopic joints together. The upper oblique members and the lower oblique members are both cross-arranged, and the upper oblique members and the lower oblique members are both steel wire rope cables, steel strand cables or steel rods.
2. The assembled bridge support according to claim 1, Features: A lower node plate is provided on the upper part of each lower sleeve, and the lower cross brace is detachably connected to the lower node plates on both sides by bolts; an upper node plate is provided on the upper part of each upper telescopic joint, and the upper cross brace is detachably connected to the upper node plates on both sides by bolts.
3. The assembled bridge support according to claim 1, Features: The upper cross brace and the lower cross brace have the same structure, and both include a first channel steel and a second channel steel. The first channel steel is provided with a plurality of protrusions at intervals, and the second channel steel is provided with positioning holes matching with the protrusions at intervals.
4. A bridge construction method, Features: The assembled bridge support according to any one of claims 1 to 3 is used, and specifically comprises the following construction steps: S1, mark the installation position of the prefabricated bridge support on the pier foundation after construction; S2, hoisting the assembled bridge support to the installation position, opening each supporting column of the assembled bridge support so that the upper telescopic joint pops out automatically, adjusting the length of each upper cross brace and lower cross brace, adjusting the length of the upper diagonal brace and the lower diagonal brace, and locking the assembled bridge support so that it is in an expanded support state; S3, repeat S2, install the remaining assembled bridge supports on the installation positions of the pier foundation in sequence, and lock the assembled bridge supports to put them in an unfolded support state; S4, installing a bridge formwork system on top of the fabricated bridge support; S5, pre-pressing the assembled bridge support, after which the upper cross brace and the lower cross brace of each assembled bridge support are checked, and then the beam body is constructed; S6, after the beam construction is completed, the bridge formwork system is dismantled, the upper expansion joint of each prefabricated bridge support is retracted into the lower sleeve, and the upper cross brace and the lower cross brace are folded together, and then the retracted prefabricated bridge supports are moved out from the bottom of the beam body to the designated site one by one; S7, repeat this process to realize the recovery of all prefabricated bridge supports under the beam body.