Wharf construction working platform and construction method thereof
By designing a dock construction work platform with movable hydraulic legs and vertically movable drive components, the safety of high-altitude operations is solved, flexible construction and material transportation in multiple height difference areas are realized, and construction efficiency and safety are improved.
Patent Information
- Application Number
- CN202410951285.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-16
- Publication Date
- 2024-11-12
AI Technical Summary
There are safety risks in high-altitude operations during high pile dock construction. Traditional safety measures such as safety nets and safety ropes have short service life and low safety factor, and cannot effectively solve the working conditions fixed to the low-level upward construction. The existing cantilever platform can only provide The construction area with one-directional degree of freedom is complicated to operate and can easily cause high-level fall accidents.
A dock construction work platform including the main frame, hydraulic legs, main beam, secondary beam and lifting platform was designed. The hydraulic legs can move along the four sides of the main frame, the main beam and secondary beam can move along the long side direction, and the lifting platform can Move up and down, and realize multi-directional degree of freedom of the platform through vertical shift drive components. The hydraulic legs and vertical shift drive components cooperate to realize plane movement of the platform on the structural parts.
It realizes construction work in any construction area of the dock without the need for cranes, improves construction efficiency, can carry out upward and downward construction in areas with multiple height differences, and simplifies the transportation of construction personnel and materials, strengthens the Construction safety.
Smart Images

Figure CN118932919A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of aerial work platforms, and in particular to a dock construction work platform and a construction method thereof. Background Art
[0002] High-pile docks are widely used due to their simple structure, convenient construction, low cost and especially suitable for soft soil foundations. However, with the rapid development of the national economy, the contradiction between scarce shoreline resources and the growing demand for maritime logistics and transportation has become increasingly obvious, which has led to the construction of docks, especially high-pile docks, developing in the direction of high piles, large spans and heavy loads, which has put forward high requirements on the construction technology of high-pile docks and also generated a series of construction safety issues.
[0003] Among them, high-altitude operations are one of the biggest safety issues. During the construction phase of the dock superstructure, especially during the installation and anti-corrosion coating of the upper beams and prefabricated components, there are a lot of high-altitude operations, which poses a great safety risk. For this stage of construction, the traditional solution is to lay safety nets and wear safety ropes. In recent years, due to the frequent occurrence of various safety accidents and the country's emphasis on safety issues, the high-altitude operation methods have also been improved, and temporary hanging baskets and other measures have been adopted for dock construction. For the traditional safety measures for high-altitude operations at docks, only safety nets and safety ropes are used. The safety factor is very low, and the service life of the safety nets and safety ropes is very short and they are very easy to wear out. There are also few construction focus points, making it difficult for operators to carry out construction.
[0004] When using safety measures such as hanging baskets for aerial work, although the safety factor is improved to a certain extent and it is less likely to be damaged, a hanging basket can only provide a construction fulcrum for the construction area about 50 cm around the hanging basket, which is just a drop in the bucket for the entire wharf. A large number of hanging baskets or the use of cranes to change positions are needed to solve this type of problem.
[0005] Chinese patent CN218757249U discloses a cantilever platform for dock construction, including a construction hanging basket and a platform trolley. The bottom of the platform trolley is provided with a plurality of universal brake casters for supporting the platform trolley; the construction hanging basket is arranged below one end of the platform trolley, and the other end of the platform trolley is provided with a weight-matching component for balancing the platform trolley; However, the platform can only provide operations in the construction area in the direction of freedom in which the platform trolley moves, and the counterweight device used for the movement and docking of the platform trolley is too simple and requires multiple people to operate. Poor control can easily cause height-falling accidents. For the degrees of freedom in other directions, it is still necessary to use cranes and other methods to change the position; Moreover, the above-mentioned construction measures all rely on the stable structural fixing devices at high places to carry out downward construction, and can only be constructed along the structural surface, and cannot solve the working condition of fixing at a low place to carry out upward construction.
[0006] Based on this, the present invention designs a dock construction work platform and a construction method thereof to solve the above problems. Summary of the invention
[0007] In view of the above-mentioned shortcomings of the prior art, the present invention provides a dock construction work platform and a construction method thereof.
[0008] To achieve the above objectives, the present invention is implemented through the following technical solutions: A dock construction work platform, comprising a main frame, hydraulic legs, a main beam, a secondary beam and a lifting platform; A plurality of hydraulic legs for supporting the main frame are provided on the lower side of the main frame, and the hydraulic legs can move along the four sides of the main frame; The main beam is movably arranged above the long side of the main frame along the long side direction of the main frame; The secondary beam can be movably arranged above the long side of the main beam along the long side direction of the main beam; The lifting platform is arranged on the inner side of the secondary beam so as to be movable up and down; a vertical driving component is also arranged on the outer side of the secondary beam for controlling the lifting platform to move up and down.
[0009] Furthermore, the lifting platform is a cylindrical frame.
[0010] Furthermore, a platform for construction is provided at a certain interval inside the lifting platform.
[0011] Furthermore, the hydraulic legs are provided with eight in total.
[0012] Furthermore, a hydraulic support leg is provided at the center of each of the four sides of the main frame, and the remaining four hydraulic support legs are respectively located below the four corners of the main frame.
[0013] Furthermore, the vertical drive assembly includes a winch and a wire rope. The winch is fixedly installed on the outside of the secondary beam, the middle part of the wire rope is fixed on the rope drum of the winch, and the upper and lower ends of the wire rope are respectively fixedly connected to the upper and lower ends of the lifting platform.
[0014] Furthermore, the main frame, main beam and secondary beam are rectangular frames.
[0015] In order to better achieve the purpose of the present invention, the present invention also provides a construction method of a dock construction work platform, comprising the following steps: Step 1: The piston of the hydraulic outrigger extends to lift the main frame, and the main beam moves to the middle of the main frame to keep the main frame evenly stressed; at this time, the three rows of hydraulic outriggers under the main frame are called support one, support two and support three from front to back; Step 2: The piston of support 1 retracts and moves horizontally backward with the main frame until the main frame crosses the gap of the structural member, and then the piston of support 1 is reset and supported on the structural member again. At this time, support 1 is close to support 2, while support 2 and support 3 keep their positions fixed and are always supported on the structural member; Step 3: After the piston of support 2 retracts, support 2 moves backward until support 2 is close to support 3, and then the piston of support 2 is reset and supported on the structural member again; Step 4: After the piston of support three retracts, support three moves backward until support three moves to the rear end of the main frame, and then the piston of support three is reset and re-supported on the structural member; Step 5: Repeat steps 2, 3 and 4, and the entire platform passes over the gaps between the structural members to achieve planar movement of the entire working platform on the structural members. Compared with the prior art, the present invention has the following beneficial effects: In the present invention, the entire working platform can be controlled to move in a plane on high-pile dock structures such as pile platforms by hydraulic outriggers, thereby enabling construction operations to be carried out in any construction area of the dock without the need to use a crane to move the hanging basket or to set up a large number of hanging baskets.
[0016] In the present invention, the movably arranged main beam and secondary beam can control the lifting platform to move in the inner area of the main frame, saving time for multiple movements to change the construction position, effectively improving construction efficiency, and also realizing the high-altitude operation of the lifting platform outside the dock area.
[0017] In the present invention, the lifting platform can move up and down in the secondary beam, and the main beam, secondary beam and lifting platform can cooperate to achieve the construction work requirements at any position in the inner area of the main frame; because there are multiple platforms arranged at intervals on the lifting platform, it is possible to achieve simultaneous construction with multiple height differences such as upward construction and downward construction, and the lifting platform can be used to realize the up and down transportation of construction personnel and simple up and down transportation of construction materials. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention, and for ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0019] Figure 1It is a structural schematic diagram of a dock construction work platform of the present invention when it is working; Figure 2 A three-dimensional diagram of a dock construction work platform of the present invention; Figure 3 It is a front view of a dock construction work platform of the present invention; Figure 4 It is a right side view of a dock construction work platform of the present invention; Figure 5 is the cross-sectional view of the profile bar; Figure 6 Schematic diagram of the driving structure for moving the main beam and the secondary beam; Figure 7 Schematic diagram of the driving structure for the hydraulic outrigger movement Figure 1 ; Figure 8 Schematic diagram of the driving structure for the hydraulic outrigger movement Figure 2 .
[0020] The numbers in the figure represent: 1. Main frame; 2. Hydraulic outriggers; 3. Main beam; 4. Secondary beam; 5. Lifting platform; 6. Winch; 7. Wire rope; 8. Pulley. DETAILED DESCRIPTION
[0021] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0022] The terms “left”, “right”, “front”, “back”, “up” and “down” mentioned in the following description are oriented in the viewing direction of the front view.
[0023] Embodiment 1 In some embodiments, please refer to the attached instructions. Figure 1-4 , a dock construction work platform, comprising a main frame 1, hydraulic legs 2, a main beam 3, a secondary beam 4 and a lifting platform 5; The main frame 1 is a rectangular frame, which serves as the main load-bearing component and can ensure the overall stability of the entire working platform; The hydraulic legs 2 are arranged at the lower side of the main frame 1, and the pistons of the hydraulic legs 2 can be raised and lowered slightly to ensure that the main frame 1 is stably placed on a stable structure or ground; there are eight hydraulic legs 2 in total, and each hydraulic leg 2 is arranged in the middle of the four sides of the main frame 1, and the remaining four hydraulic legs 2 are respectively located below the four corners of the main frame 1, and the hydraulic legs 2 can move along the four sides of the main frame 1, and the hydraulic legs 2 cooperate with each other to complete the plane movement of the main frame 1; The main beam 3 is a rectangular frame, and can be movably arranged above the long side of the main frame 1 along the long side direction of the main frame 1; The secondary beam 4 is a rectangular frame and can be movably arranged above the long side of the main beam 3 along the long side direction of the main beam 3; The lifting platform 5 is a columnar frame, which is arranged inside the secondary beam 4 so as to be movable up and down; a platform is arranged inside the lifting platform 5 at a certain interval to facilitate the installation of the wharf beam formwork, steel bar welding, anti-corrosion coating construction and other related construction; a vertical driving assembly is also arranged outside the secondary beam 4 to control the lifting platform 5 to move up and down; The vertical movement drive assembly includes a winch 6 and a wire rope 7. The winch 6 is fixedly installed on the outer side of the secondary beam 4. The middle part of the wire rope 7 is fixed on the rope drum of the winch 6. The upper and lower ends of the wire rope 7 are respectively fixedly connected to the upper and lower ends of the lifting platform 5. By controlling the retraction and extension of the wire rope 7 by the winch 6, the lifting platform 5 can be controlled to move up and down on the inner side of the secondary beam 4.
[0024] In the present invention, the main beam 3, the secondary beam 4, the lifting platform 5, the winch 6, and the wire rope 7 cooperate with each other to realize the construction work requirements at any position in the inner area of the main frame 1. Cooperating with the hydraulic support legs 2, high-altitude construction work as well as personnel up and down and material transportation in any area, any part, and any working condition of the high-pile wharf can be realized.
[0025] Embodiment 2 In some embodiments, Figure 1-4 As shown, as a preferred embodiment of the present invention, a slide rail structure is provided on the lower side of the main frame 1, and the entire working platform moves along the track by laying the track at a specific position in the dock construction area.
[0026] The main frame 1, main beam 3 and secondary beam 4 are configured in other shapes, such as arched or circular. When the main frame 1 and main beam 3 are arched, the load capacity and working height of the working platform can be improved to a certain extent.
[0027] The lifting platform 5 may not be cylindrical, and may be provided with a certain curvature, so that the working area of the working platform can extend to the curved area of the lifting platform 5 to meet the construction requirements of scenes such as the outside of a high-pile dock.
[0028] Embodiment 3 In some embodiments, as a preferred embodiment of the present invention, the main frame 1, the main beam 3, the secondary beam 4 and the lifting platform 5 can be adopted as follows: Figure 5 The profile rod of the cross section shown has grooves or gaps on the outside of the rod.
[0029] like Figure 6 As shown, by arranging a pulley under the secondary beam 4, the secondary beam 4 can slide along the gap or groove above the main beam 3; the secondary beam 4 can be pushed to slide by manual drive, or a winch 6 can be added above the secondary beam 4, and the rotation of the winch 6 drives the wire rope 7 to pull the secondary beam 4 to make it move along the length direction of the main beam 3; the movement of the main beam 3 on the main frame 1 is the same as above.
[0030] like Figure 7 and 8 As shown, four fixed pulleys 8 are arranged on the side below the main frame 1 and a winch 6 is arranged outside the corner of the main frame. The rotation of the winch 6 drives the wire rope 7 to pull the hydraulic leg 2 to slide under the main frame 1, and can also be pushed by manual drive to make the hydraulic leg 2 and the main frame 1 move relative to each other.
[0031] Embodiment 4 In some embodiments, Figure 1-4 As shown, as a preferred embodiment of the present invention, a construction method of a dock construction work platform is also provided, comprising the following steps: Step 1: The piston of the hydraulic outrigger 2 extends to lift the main frame 1, and the main beam 3 moves to the middle of the main frame 1 to keep the main frame 1 evenly stressed; at this time, the three rows of hydraulic outriggers 2 under the main frame 1 are called support one, support two and support three from front to back; Step 2: The piston of support 1 retracts and moves horizontally backward with the main frame 1 until the main frame 1 crosses the gap of the structural member, and then the piston of support 1 is reset and supported on the structural member again. At this time, support 1 is close to support 2, while support 2 and support 3 keep their positions fixed and are always supported on the structural member; Step 3: After the piston of support 2 retracts, support 2 moves backward until support 2 is close to support 3, and then the piston of support 2 is reset and supported on the structural member again; Step 4: After the piston of support 3 retracts, support 3 moves backward until support 3 moves to the rear end of the main frame 1, and then the piston of support 3 is reset and re-supported on the structural member; Step 5: Repeat steps 2, 3 and 4, and the entire platform passes over the gaps between the structural members to achieve planar movement of the entire working platform on the structural members.
[0032] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements will not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A dock construction work platform, comprising a main frame (1), hydraulic legs (2), a main beam (3), a secondary beam (4) and a lifting platform (5), Features: A plurality of hydraulic legs (2) for supporting the main frame (1) are provided on the lower side of the main frame (1); the hydraulic legs (2) are movable along four sides of the main frame (1); The main beam (3) is movably arranged above the long side of the main frame (1) along the long side direction of the main frame (1); The secondary beam (4) is movably arranged above the long side of the main beam (3) along the long side direction of the main beam (3); The lifting platform (5) is arranged on the inner side of the secondary beam (4) so as to be movable up and down; a vertical drive component is also arranged on the outer side of the secondary beam (4) for controlling the lifting platform (5) to move up and down.
2. The dock construction work platform according to claim 1, It is characterized in that The lifting platform (5) is a columnar frame.
3. The dock construction work platform according to claim 2, It is characterized in that A platform for construction is provided at regular intervals on the inner side of the lifting platform (5).
4. The dock construction work platform according to claim 3, It is characterized in that The hydraulic legs (2) are provided with eight in total.
5. The dock construction work platform according to claim 4, It is characterized in that A hydraulic support leg (2) is provided at the center of each of the four sides below the main frame (1), and the remaining four hydraulic support legs (2) are respectively located below the four corners of the main frame (1).
6. The dock construction work platform according to claim 5, It is characterized in that The vertical movement drive assembly comprises a winch (6) and a steel wire rope (7), the winch (6) being fixedly mounted on the outside of the secondary beam (4), the middle portion of the steel wire rope (7) being fixed on a rope drum of the winch (6), and the upper and lower ends of the steel wire rope (7) being fixedly connected to the upper and lower ends of the lifting platform (5) respectively.
7. The dock construction work platform according to claim 6, It is characterized in that The main frame (1), the main beam (3) and the secondary beam (3) are rectangular frames.
8. A method for constructing a dock construction work platform, using the dock construction work platform according to claim 7, It is characterized in that The following steps are involved: Step 1: The piston of the hydraulic support leg (2) is extended to lift the main frame (1), and the main beam (3) is moved to the middle of the main frame (1) to keep the main frame (1) evenly stressed; at this time, the three rows of hydraulic support legs (2) below the main frame (1) are called support one, support two and support three from front to back; Step 2: The piston of support 1 retracts and moves horizontally backward along with the main frame (1) until the main frame (1) crosses the gap of the structural member, and then the piston of support 1 is reset and supported on the structural member again. At this time, support 1 is close to support 2, while support 2 and support 3 remain in a fixed position and are always supported on the structural member; Step 3: After the piston of support 2 retracts, support 2 moves backward until support 2 is close to support 3, and then the piston of support 2 is reset and supported on the structural member again; Step 4: After the piston of support three is retracted, support three moves backward until support three moves to the rear end of the main frame (1), and then the piston of support three is reset and supported on the structural member again; Step 5: Repeat steps 2, 3 and 4, and the entire platform passes over the gaps between the structural members to achieve planar movement of the entire working platform on the structural members.