Gobi desert micropore cast-in-place pile hole and micropore cast-in-place pile construction method

By using auger drill rod lead holes and impact drill bits to extrude the soil in the Gobi Desert area, the low hole formation efficiency and floating soil caused by loose soil are solved, and high efficiency is achieved. Accurate pile hole construction reduces labor and costs.

CN118932987APending Publication Date: 2024-11-12NINGXIA ELECTRIC POWER CONSTR PROJECT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411128840.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

When constructing micropore filling pile holes in the Gobi Desert area, due to the dry and loose soil, the existing technology requires multiple drilling and water injection, resulting in low hole formation efficiency and floating soil on the hole wall and bottom, which affects the construction accuracy and quality. Increase labor and costs.

Method used

The initial hole is formed by using auger drill rod dry operation guide, and then the impact drill bit is used to squeeze the soil of the hole wall tightly, eliminating multiple drilling and water injection processes, and directly pouring concrete, avoiding hole cleaning operations and improving hole formation accuracy and construction efficiency.

Benefits of technology

The accuracy of pile hole formation is improved, the construction volume is reduced, manpower is saved, construction efficiency and quality is improved, and the accuracy of pile foundation position and the quality of concrete pouring are ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118932987A_ABST
    Figure CN118932987A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of pile foundation hole construction, and particularly relates to a gobi desert micropore cast-in-place pile hole and a micropore cast-in-place pile construction method. The gobi desert micropore cast-in-place pile hole construction method comprises the steps that A1, a site is leveled, and the positions of pile holes are marked after the positions of the pile holes are determined through surveying and setting out; a2, the spiral drilling machine is in place, and a spiral drilling rod on the spiral drilling machine is aligned with the pile hole marking position for dry operation hole guiding to form an initial hole; a3, the initial hole is filled with water; and A4, the percussion drill is in place, and a percussion bit is aligned with the center of the initial hole for percussion hole forming. The pile hole construction is completed in the mode that the spiral drill rod is adopted for conducting dry operation to lead the hole to form the initial hole, then the percussion drill is adopted for extruding and compacting soil on the hole wall, a protection wall is formed in the pile hole, the hole forming quality is guaranteed, and the pile hole construction efficiency is improved. According to the micropore cast-in-place pile construction method, the pile hole construction method is adopted for forming holes, soil around the pile holes is compact and free of topsoil, embedded parts can be placed for pouring without cleaning the holes, the workload is reduced, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of pile foundation hole construction, and in particular relates to a Gobi desert microporous cast-in-place pile hole and a microporous cast-in-place pile construction method. Background Art

[0002] Photovoltaic power stations are power generation systems that directly convert solar radiation energy into electrical energy. They generally include facilities such as transformers, inverters, and photovoltaic arrays. Photovoltaic arrays include multiple groups of solar panels installed on pile foundations through brackets. In order to maximize the solar panels' reception of sunlight, the installation accuracy of the solar panels should be guaranteed. Therefore, the construction accuracy requirements for the pile foundations used to support and install solar panels are relatively strict. The construction accuracy of the pile foundation is mainly determined by the position and shape of the pile hole. Therefore, the construction accuracy of the pile hole is particularly important. Most of the above-mentioned pile foundations are microporous cast-in-place piles with a pile diameter of about 20 cm and a depth of more than 1.7 m. Accordingly, the diameter of the pile foundation hole should be about 20 cm, and the hole depth should be greater than or equal to 1.7 m.

[0003] Photovoltaic power stations are mostly located in deserts or Gobi deserts with abundant sunshine and long sunshine hours. Although the terrain in these areas is relatively flat, the geology is complex and changeable, mainly composed of loose soils such as clay, silt, and sand, which brings challenges to the construction of microporous cast-in-place pile holes. At present, the construction of microporous cast-in-place piles mainly includes site leveling, pile foundation hole drilling, placement of embedded parts, and pile foundation pouring.

[0004] The microporous cast-in-place pile holes are mainly drilled by spiral drill rods. Because the soil moisture content in the Gobi Desert is almost zero and the soil is dry and loose, it is necessary to inject water into the bottom of the hole while drilling to change the soil from a loose state to a consolidated state, thereby achieving the effect of hole formation. During this process, the drill bit needs to be lifted several times to observe the soil condition in the hole. When the soil moisture content in the hole is too low, water is injected. When the soil moisture content in the hole is too high, dry soil is filled in until the soil moisture content in the hole reaches the drilling requirement and then the drilling continues. Although the above-mentioned hole formation method can ensure the hole formation effect, it is necessary to lift the drill several times and adjust the soil moisture content in the hole in time. In addition, the soil brought out by the drill each time should be cleaned in time to prevent the loose soil from being brought into the hole again when drilling, causing the hole to collapse. The process is cumbersome, wastes manpower, and has low hole formation efficiency. There is loose soil on the hole wall and the bottom of the hole formed by the above construction method. When pouring microporous cast-in-place piles, it is necessary to clean the hole before placing the embedded parts to prevent the loose soil from falling to the bottom of the hole when the embedded parts are lowered, affecting the hole depth, and the loose soil from being entrained by the concrete during the concrete pouring operation, affecting the pouring quality. Generally, a spiral drill rod is used for hole cleaning. During the hole cleaning process, there is a risk of disturbing the soil on the hole wall and causing the hole to collapse. The loose soil at the bottom of the hole is also difficult to clean. Not only does it require multiple hole cleanings, but it also causes the hole diameter to increase, the hole position to shift, and the demand for concrete to increase, affecting the hole diameter and hole position accuracy, and then affecting the pile foundation position accuracy, bringing difficulties to the installation of solar panels. For example, when the pile foundation position deviation is too large, the solar panel can be barely installed after multiple debugging. The solar panel is easily damaged by long-term exposure to large tension or torque; if the pile foundation position deviation is too large, it will also cause the module to be unable to be installed, and the pile foundation needs to be reworked, affecting the construction progress and increasing the construction cost. Summary of the invention

[0005] The technical problem to be solved by the present invention is to provide a Gobi desert microporous cast-in-place pile hole and a microporous cast-in-place pile construction method, so as to improve the pile hole forming accuracy, reduce the construction workload, save manpower, and improve the construction efficiency and quality.

[0006] The technical solution adopted by the present invention to solve the technical problem is: a method for constructing a microporous cast-in-place pile hole in a Gobi desert, comprising the following steps:

[0007] A1. Level the site, measure and lay out the pile hole positions, and then mark the pile hole positions;

[0008] A2. The auger drill is in place, and the auger rod on the auger drill is aligned with the pile hole mark position to form the initial hole;

[0009] A3, filling the initial hole with water;

[0010] A4. The impact drill is in place, and the impact drill bit is aimed at the center of the initial hole to impact and form a hole.

[0011] Furthermore, the pile hole position marking in step A1 includes inserting a chisel into the center of the pile position to mark the center of the pile position and sprinkling white lime at the pile position for marking, and a red ribbon is provided on the chisel.

[0012] Furthermore, a scale is provided on the auger rod.

[0013] Furthermore, the step A3 comprises: inserting the outlet of the high-pressure water pipe into the soil layer at the bottom of the initial hole to start high-pressure water injection, and slowly pulling out the high-pressure water pipe after the water fills the entire initial hole.

[0014] A Gobi Desert microporous cast-in-place pile construction method comprises the following steps:

[0015] S1. Drilling a hole using any of the above-mentioned Gobi Desert microporous cast-in-place pile hole construction methods;

[0016] S2, check the hole depth, hole diameter, verticality of hole wall and thickness of sediment at the bottom of hole formed in step S1 and record them, and rework the pile holes that fail to meet the standards;

[0017] S3. Place the pile embedded parts in the pile hole, ensuring that the height from the top of the pile embedded parts to the ground meets the design requirements;

[0018] S4. Continuously pour concrete into the hole and the microporous cast-in-place pile casting is completed.

[0019] Furthermore, in step S2, a pole with an upper marking point and a lower marking point is used to detect the hole depth; during the detection, the pole is placed in the up and down direction, and the lower end of the pole is against the bottom wall of the pile hole. If the horizontal plane at the mouth of the pile hole is between the upper marking point and the lower marking point, the hole depth of the pile hole is qualified and step S3 can be performed; otherwise, the hole depth of the pile hole is unqualified and rework is required.

[0020] Furthermore, the step S4 includes: unloading the concrete in the concrete mixer truck into the lifting hopper on the loader, the bottom of the lifting hopper is provided with a pouring port, and the concrete in the lifting hopper falls into the pile hole through the pouring port to cast the pile foundation.

[0021] Compared with the prior art, the beneficial effects of the present invention are: providing a method for constructing micro-porous cast-in-place pile holes in the Gobi Desert, which completes the pile hole construction by first using a spiral drill rod to dry-drill the hole to form an initial hole, and then using an impact drill to squeeze and compact the hole wall soil, thereby eliminating the need for multiple drilling, water injection and drilling processes, forming a protective wall in the pile hole, ensuring the hole quality, and improving the pile hole construction efficiency.

[0022] Provided is a Gobi Desert micro-porous bored pile construction method. By adopting the pile hole construction method of the invention to form a hole, the soil quality of the pile hole wall is dense and free of loose soil, embedded parts can be directly placed for pouring operations, the hole cleaning process is omitted, the workload of the micro-porous bored pile is reduced, manpower is saved, and the construction efficiency of the micro-porous bored pile is improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 It is a construction flow chart of microporous cast-in-place pile holes of the present invention;

[0024] Figure 2 It is a construction flow chart of microporous cast-in-place piles of the present invention. DETAILED DESCRIPTION

[0025] In order to make those skilled in the art better understand the present invention, the present invention is further described below in conjunction with the accompanying drawings and embodiments. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. In the absence of conflict, the embodiments of the present invention and the features in the embodiments can be combined with each other.

[0026] As attached Figure 1-2 As shown, a method for constructing a microporous cast-in-place pile hole in a Gobi desert comprises the following steps:

[0027] A1. Level the site, measure and lay out the pile hole positions, and then mark the pile hole positions;

[0028] A2. The auger drill is in place, and the auger rod on the auger drill is aligned with the pile hole mark position to form the initial hole;

[0029] A3, filling the initial hole with water;

[0030] A4. The impact drill is in place, and the impact drill bit is aimed at the center of the initial hole to impact and form a hole.

[0031] The auger can drill through hard interlayers or boulders with high strength. The soil cut by the auger rod is transported to the hole mouth along the spiral blades when the auger rod is drilled downward. After the hole is drawn, the soil delivered by the auger rod at the hole mouth needs to be cleaned. Step A2 uses a auger to draw the hole in a one-time dry operation. The dry operation is completed in one time, eliminating the multiple drilling, water injection and drilling processes in the background technology construction method, and reducing the number of times the hole mouth soil is cleaned. There is loose soil in the initial hole formed in step A2, and the soil is loose at the hole wall. Impact drills are commonly used for drilling rock-embedded pile foundations in mountainous hills. The free fall of the hammer generates kinetic energy to crush the soil or rock into a hole. The present invention uses an impact drill bit to impact the hole after the initial hole is filled with water. The impact drill bit relies on its own impact force to squeeze the soil at the hole wall and the bottom of the initial hole. While the loose soil on the hole wall and the bottom of the hole is squeezed, an effective wall protection is formed under the action of the water body to avoid hole collapse, ensure the quality of the hole, and improve the efficiency of pile hole construction. In addition, there is no loose soil in the pile hole drilled by the above method, and no hole cleaning operation is required, which reduces the construction workload of microporous bored piles, saves manpower, and improves the construction efficiency of microporous bored piles.

[0032] Regarding step A1, the site is leveled to ensure the smooth entry of equipment such as drilling rigs, to ensure that the openings of multiple pile holes are located on the same horizontal plane, and to ensure that the top surfaces of multiple pile foundations poured later are flush. The pile hole position is determined by measuring and laying out according to the design drawings. GPS-RTK real-time differential positioning technology is generally used for positioning measurement. Real-time differential positioning technology is a measurement method that can obtain centimeter-level positioning accuracy in real time in the field, which improves the efficiency of measurement and layout. Step A1 can mark the pile hole position by marking lines, plugging in markers at the center of the pile position, etc. Specifically, the pile hole position marking in step A1 includes inserting a drill at the center of the pile position to mark the center of the pile position and sprinkling white lime at the pile position, and a red ribbon is provided on the drill. The red ribbon is provided on the drill to facilitate construction personnel to quickly identify it. The ribbon can also be a color that has a significant contrast with the ground, such as orange, silver, etc. Sprinkling white lime at the pile position further facilitates construction personnel to identify the pile hole position. The pile position deviation is generally one-tenth of the pile diameter and within 30 mm.

[0033] Before the auger is put in place in step A2, the surrounding conditions of the site should be checked to ensure the space for mechanical work: the auger should remain stable when in place without tilting or displacement. When the auger is used to lead the hole, the drill bit is aligned with the center of the pile hole according to the center of the pile hole marked in step A1, and the drill bit and the center of the pile hole are ensured to be on the same plumb line. After the drill bit used to mark the pile position is pulled out, the lead hole is drilled. While the auger is drilling, the soil is brought out to the hole mouth for accumulation. After the hole is led, the drill is lifted and the soil at the hole mouth is cleaned. The outer diameter of the auger can be equal to the designed aperture of the pile hole, or slightly smaller than the designed aperture of the pile hole. The outer diameter of the auger is generally 10 mm smaller than the designed aperture of the pile hole. In order to ensure the hole depth of the auger, preferably, a ruler is provided on the auger to observe and record the hole depth during the hole construction. The drill is lifted after the hole depth reaches the design requirements to improve the hole accuracy. It is required that the position error of the auger is generally within 10 mm, and its verticality deviation is within 20 mm.

[0034] The Gobi Desert is dry and rainless, and the underground water content is almost zero. In step A3, water is injected into the initial hole to increase the water content of the soil layer around the hole, so that the soil layer around the hole wall is more easily compacted when the impact drill is used to impact the hole in step A4. In step A3, a water pipe can be used to directly water the hole, but the water poured into the hole by this method will soon be absorbed by the hole wall, so that part of the hole wall does not fully absorb water, affecting the degree of compaction of the hole wall during impact drilling. Preferably, step A3 includes: inserting the outlet of the high-pressure water pipe into the bottom soil layer of the initial hole to start high-pressure water injection, and slowly pulling up the high-pressure water pipe after the water fills the entire initial hole. The high-pressure water can ensure that the bottom and wall of the hole are fully infiltrated by water, ensure the compaction density of the soil at the hole wall of the subsequent impact drilling, and improve the quality of the hole. The outlet end of the high-pressure water pipe is generally a steel pipe structure, which is convenient for inserting it into the soil layer.

[0035] The impact drill bit diameter in step A4 should be equal to the designed hole diameter of the pile hole to improve the dimensional accuracy of the pile hole and avoid the hole collapse caused by a smaller drill bit diameter or the hole diameter being too large due to the larger drill bit diameter. A large hole diameter will increase the amount of concrete used when pouring the pile body and increase production costs.

[0036] A Gobi Desert microporous cast-in-place pile construction method comprises the following steps:

[0037] S1. Drilling a hole using any of the above-mentioned Gobi Desert microporous cast-in-place pile hole construction methods;

[0038] S2, check the hole depth, hole diameter, verticality of hole wall and thickness of sediment at the bottom of hole formed in step S1 and record them, and rework the pile holes that fail to meet the standards;

[0039] S3. Place the pile embedded parts in the pile hole, ensuring that the height from the top of the pile embedded parts to the ground meets the design requirements;

[0040] S4. Continuously pour concrete into the hole and the microporous cast-in-place pile casting is completed.

[0041] Step S1: The inner wall of the pile hole is squeezed and compacted, and there is no loose soil in the pile hole. The embedded parts can be directly placed without cleaning the hole, which reduces the workload, saves manpower, and improves the construction efficiency of microporous cast-in-place piles.

[0042] Step S2 is mainly used to detect whether the pile hole completed in step S1 is qualified, so as to improve the pile hole accuracy and construction quality. The hole depth, hole diameter and bottom sediment thickness of the pile hole can be measured by a steel ruler, and the inclination of the pile hole can be checked by a plumb line method. In order to improve the hole depth measurement efficiency of the pile hole, preferably, a vertical pole with an upper marking point and a lower marking point is used in step S2 to detect the hole depth; during the detection, the lower end of the vertical pole abuts against the bottom wall of the pile hole. If the horizontal plane at the hole mouth of the pile hole is between the upper marking point and the lower marking point, the hole depth of the pile hole is qualified, and step S3 can be performed; otherwise, the hole depth of the pile hole is unqualified and rework is required. The distance from the upper marking point to the bottom end of the vertical pole is the upper qualified limit value of the pile hole depth, and the distance from the lower marking point to the bottom end of the vertical pole is the lower qualified limit value of the pile hole depth. The upper marking point and the lower marking point can be red tapes pasted on the outer peripheral surface of the vertical pole, or they can be marking parts protruding from the outer periphery of the vertical pole.

[0043] The upper end of the embedded part is generally a steel pipe structure for installing the solar panel bracket, and the lower end of the embedded part is a steel bar structure to ensure the rigidity and strength of the pile. When installing the embedded parts, it is necessary to ensure that the top surfaces of multiple embedded parts are flush, and the hanging wire lamp method can also be used to ensure that the positions of multiple embedded parts meet the design requirements. When placing the embedded parts, avoid colliding with the hole wall. After the embedded parts are in place, fix them immediately to prevent increasing the installation error.

[0044] In step S4, a concrete mixer truck can be directly used for pouring. However, due to the special construction environment, the concrete mixer truck has a large load capacity, which is generally 30-40 tons. The pile hole is easily crushed during movement, resulting in rework of the pile hole and increasing construction costs. In addition, the height of the concrete mixer truck discharge port is about 1.5m, which is relatively high from the ground. When the concrete is lowered to the pile hole for pouring, the concrete falls and impacts the hole wall of the pile hole, which easily impacts the hole wall soil into the concrete. The soil is mixed into the concrete to form pile body slag, which affects the quality of the finished microporous cast-in-place pile. Preferably, step S4 includes: unloading the concrete in the concrete mixer truck into the lifting hopper on the loader, and the bottom of the lifting hopper is provided with a pouring port, and the concrete in the lifting hopper falls into the pile hole through the pouring port for pile foundation pouring. The loader is small in size and load capacity, with a total weight of about 15-20 tons, which can effectively prevent the pile hole from being crushed. In addition, the loader's lifting hopper is height-adjustable, which can drive the pouring port at its bottom to rise and fall synchronously, reducing the impact potential energy generated when the concrete falls, and preventing the soil on the wall of the pile hole from being entrained into the pile body by the concrete, thereby ensuring the quality of the pile casting.

[0045] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A method for constructing microporous cast-in-place pile holes in the Gobi Desert, characterized in that: The following steps are involved: A1. Level the site, measure and lay out the pile hole positions, and then mark the pile hole positions; A2. The auger drill is in place, and the auger rod on the auger drill is aligned with the pile hole mark position to form the initial hole; A3, filling the initial hole with water; A4. The impact drill is in place, and the impact drill bit is aimed at the center of the initial hole to impact and form a hole.

2. The Gobi Desert microporous cast-in-place pile hole construction method according to claim 1, characterized in that: The pile hole position marking in step A1 includes inserting a chisel into the center point of the pile position to mark the center point of the pile position and sprinkling white lime at the pile position for marking, and a red ribbon is provided on the chisel.

3. The Gobi Desert microporous cast-in-place pile hole construction method according to claim 1, characterized in that: A ruler is arranged on the spiral drill rod.

4. The Gobi Desert microporous cast-in-place pile hole construction method according to claim 1, characterized in that: The step A3 comprises: inserting the outlet of the high-pressure water pipe into the soil layer at the bottom of the initial hole to start high-pressure water injection, and slowly pulling out the high-pressure water pipe after the water fills the entire initial hole.

5. A Gobi Desert microporous cast-in-place pile construction method, characterized in that: The following steps are involved: S1. Drilling a hole using the Gobi Desert microporous cast-in-place pile hole construction method as described in any one of claims 1 to 4; S2, check the hole depth, hole diameter, verticality of hole wall and thickness of sediment at the bottom of hole formed in step S1 and record them, and rework the pile holes that fail to meet the standards; S3. Place the pile embedded parts in the pile hole, ensuring that the height from the top of the pile embedded parts to the ground meets the design requirements; S4. Continuously pour concrete into the hole and the microporous cast-in-place pile casting is completed.

6. The Gobi Desert microporous cast-in-place pile construction method according to claim 5, characterized in that: In step S2, a vertical pole with an upper marking point and a lower marking point is used to detect the hole depth. During the detection, the vertical pole is placed in the up-down direction, and the lower end of the vertical pole abuts against the bottom wall of the pile hole. If the horizontal plane at the hole mouth of the pile hole is between the upper marking point and the lower marking point, the hole depth of the pile hole is qualified and step S3 can be performed; otherwise, the hole depth of the pile hole is unqualified and rework is required.

7. The Gobi Desert microporous cast-in-place pile construction method according to claim 5, characterized in that: The step S4 comprises: unloading the concrete in the concrete mixer truck into the lifting hopper on the loader, the bottom of the lifting hopper is provided with a pouring port, and the concrete in the lifting hopper falls into the pile hole through the pouring port to cast the pile foundation.