Draught fan bearing platform pouring method

By using auxiliary devices to perform forward surface treatment in the fan platform casting process, the problems of inconvenience of staff and concrete damage are solved, the operation convenience and concrete quality are improved, and labor intensity and thermal stress risks are reduced.

CN118933012APending Publication Date: 2024-11-12THE 5TH ENGINEERING CO LTD OF CHINA RAILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411410457.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-10
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In the existing fan platform casting process, the staff cannot operate during surface treatment, which can easily lead to concrete adhesion and surface damage, and the reverse operation method increases labor intensity.

Method used

The concrete surface treatment is carried out using auxiliary devices, including mounting bases, support bridges and support components, allowing staff to work forward on the device, reduce concrete contact with clothing, and improve surface flatness through vibration and trowel treatment.

Benefits of technology

It improves the operation convenience and safety of staff, reduces damage to concrete surfaces, reduces labor intensity, and reduces thermal stress through temperature control, and improves the quality and durability of concrete.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933012A_ABST
    Figure CN118933012A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of wind power generation and building construction, and discloses a fan bearing platform pouring method which comprises the steps of bearing platform size design, foundation pit excavation, reinforcement cage manufacturing and fixing, concrete pouring, surface treatment on concrete through an auxiliary device, later maintenance and formwork removal inspection. By means of the auxiliary device, it can be avoided that a worker steps on the concrete surface for operation, on one hand, concrete adhering to clothes of the worker can be reduced, and the work cleanliness is guaranteed; a backward working mode is changed into a forward working mode, so that the operation of workers is facilitated, and the labor intensity of the workers is reduced; finally, by arranging an auxiliary device, the concrete surface treatment efficiency and quality can be improved; by monitoring the internal and external temperatures of the bearing platform and performing a corresponding cooling strategy on the bearing platform, the internal and surface temperature difference of the concrete can be effectively controlled, and the thermal stress caused by the temperature difference is reduced, so that the risk of cracks is reduced, and the overall quality and durability of the concrete are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of wind power generation and building construction, in particular to a method for casting a wind turbine foundation. Background Art

[0002] The wind turbine cap is a structural foundation specially designed to support and fix the wind turbine or wind turbine. In the field of wind power generation, the cap is one of the most important components. It must have sufficient strength and stability to withstand the various forces generated by the operation of the wind turbine, including wind load, gravity and power. The design and construction of the cap directly affects the safety, stability and efficiency of the entire wind power generation system.

[0003] In the existing technology, when pouring the cap, workers usually stand on the steel cage to perform the surface treatment of the concrete. This operation method causes the concrete to easily adhere to the workers' clothes. In addition, in order to prevent the workers from stepping on the surface-treated concrete, they usually perform the surface treatment operation on the cap backwards from bottom to top. This backward operation method makes the workers' operation extremely inconvenient, and other workers are likely to damage the surface-treated concrete when walking on the cap. Summary of the invention

[0004] The purpose of the present invention is to provide a method for casting a fan cap, so as to solve the problem of inconvenience in operation for workers when performing surface treatment on the cap in the prior art.

[0005] The present invention is implemented by the following technical solution: A method for casting a fan cap comprises the following steps: Step S1: Design the size of the foundation and the specifications of the steel bars according to the wind turbine model and engineering requirements; Step S2: clear the site and excavate the foundation pit according to the drawings; Step S3: manufacturing and assembling a steel cage according to design requirements, placing the steel cage in the foundation pit and supporting and fixing it; Step S4: making a corresponding platform template, installing it to a predetermined position, and checking its sealing performance; Step S5: pouring concrete gradually from one end to the other end until it is cast and formed, and then performing surface treatment of the concrete using auxiliary devices; Step S6: curing the poured concrete; Step S7: After the concrete strength reaches the standard, the formwork is removed and inspected.

[0006] In order to better implement the present invention, further, in step S5, the concrete needs to be vibrated during concrete pouring, and the specific vibration method is: the vibration points are arranged in a plum blossom shape, and the vibration is performed in a fast insertion and slow withdrawal manner; wherein the moving spacing of the inserted vibrator is not greater than 1.5 times the effective radius of the vibrator, and the vibrator needs to be inserted into the lower layer of concrete when vibrating the upper layer of concrete, and the insertion depth is greater than 5 cm.

[0007] In order to better implement the present invention, further, after the concrete is vibrated, a wooden trowel is used to level the surface according to a predetermined elevation line and the surface is covered with a plastic film in time.

[0008] In order to better implement the present invention, further, the concrete surface treatment step mainly includes: Step S51: assembling and fixing the auxiliary device according to the size of the platform; Step S52: Within 3 to 4 hours of pouring, the worker stands on the auxiliary device and uses a scraper to initially scrape the concrete surface flat; Step S53: Before the initial setting, the worker stands on the auxiliary device and uses a wooden trowel to flatten and compact the surface, and then uses an iron trowel to finish the surface.

[0009] In order to better realize the present invention, further, the auxiliary device mainly includes a mounting seat, a support bridge, and a support assembly; the support assembly is used to support and adjust the height of the mounting seat, and the support bridge is installed on the mounting seat for people to stand.

[0010] The mounting base includes a circular ring table unit, a driving gear, an arc-shaped rack, and a driving motor; the supporting bridge includes a top plate, a connecting plate, a side plate, and a connecting piece; the top plate includes a second top plate unit and a first top plate unit, and the side plate includes a first side plate unit and a second side plate unit; the top plate and the side plate are both provided with locking holes; the connecting piece includes a limit sleeve, a first connecting head, a second connecting head, a limit nut, and a limit screw.

[0011] The specific assembly steps of the auxiliary device in step S51 are: Step S511: placing an arc-shaped rack into a circular ring stage unit; Step S512: Connect and tighten the multiple circular ring stage units end to end with bolts to form a circular ring stage; Step S513: placing a plurality of support components, placing the circular ring stage on the support components, and adjusting the height of the support components to adjust the height of the circular ring stage; Step S514: installing the driving gear on the output end of the driving motor, installing the driving motor on the circular ring stage, and making the driving gear mesh with the arc-shaped rack; Step S515: embed the second side plate unit into the first side plate unit and use bolts to pass through the locking holes to relatively fix the first side plate unit and the second side plate unit to form a side plate; embed the second top plate unit into the first top plate unit and use bolts to pass through the locking holes to relatively fix the second top plate unit and the first top plate unit to form a top plate; Step S516: embed the first connector into the second connector, adjust the angle between the second connector and the first connector, and then insert the limiting sleeve into the first connector and the second connector to fix the angle; after the limiting screw passes through the limiting sleeve, screw the limiting nut onto the limiting screw to limit the limiting sleeve; Step S517: Use connectors with corresponding angles to connect two connecting plates to both sides of the top plate respectively, install two connectors with corresponding angles at both ends of the side plate, one end of the side plate is connected to the connecting plate through the connector, and the other end is connected to an arc-shaped rack through the connector.

[0012] In order to better realize the present invention, further, the support assembly includes a support seat, an adjusting motor, a screw, a first adjusting plate, a second adjusting plate, a third adjusting plate, an adjusting gear, and a rack; the first adjusting plate is slidably connected to the support seat, the second adjusting plate is slidably connected to the first adjusting plate, the third adjusting plate is slidably connected to the second adjusting plate, the adjusting motor is installed on the support seat, the screw is installed on the adjusting motor, and the screw is threadedly connected to the first adjusting plate; two racks are installed on the support seat, the first adjusting plate, the second adjusting plate, and the third adjusting plate, two adjusting gears are installed on the second adjusting plate and the first adjusting plate, the adjusting gear on the first adjusting plate is respectively meshed with the racks on the support seat and the second adjusting plate, and the adjusting gear on the second adjusting plate is respectively meshed with the racks on the first adjusting plate and the third adjusting plate.

[0013] In order to better implement the present invention, further, a level is installed on the circular ring stage unit.

[0014] In order to better implement the present invention, further, the curing of the concrete in step S6 includes: recording the internal and external temperature values ​​of the concrete to ensure that the internal and external temperature difference of the concrete is not greater than 25°; sprinkling water on the concrete surface or covering it with a film and geotextile according to the temperature difference.

[0015] Compared with the prior art, the present invention has the following advantages and beneficial effects: (1) The present invention can prevent workers from stepping on the concrete surface during work by using auxiliary devices. On the one hand, it can reduce the amount of concrete adhering to the workers' clothes and ensure the cleanliness of the work; on the other hand, it can prevent workers from damaging the treated surface when walking on the platform; finally, the backward working mode is changed to the forward working mode, which is convenient for workers to operate and reduces their labor intensity; (2) The present invention can effectively control the temperature difference between the interior and surface of the concrete by monitoring the internal and external temperatures of the foundation and implementing corresponding cooling strategies, thereby alleviating the thermal stress caused by the temperature difference, thereby reducing the risk of cracks and improving the overall quality and durability of the concrete; (3) The present invention can help improve the structural integrity and appearance quality of the concrete surface by performing surface treatment on the concrete, and also help control the occurrence of surface cracks. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the process of the present invention.

[0017] Figure 2 This is a schematic diagram of the installation position of the auxiliary device and the base.

[0018] Figure 3 This is a cross-sectional view of the auxiliary device structure.

[0019] Figure 4 It is a cross-sectional view of the circular ring table unit, driving gear, and arc rack structure.

[0020] Figure 5 Schematic diagram of the connection between the side plate and the arc-shaped rack Figure 1 .

[0021] Figure 6 Schematic diagram of the connection between the side plate and the arc-shaped rack Figure 2 .

[0022] Figure 7 This is an exploded view of the connector structure.

[0023] Figure 8 It is a schematic diagram of the connection relationship between the side plate, connecting plate and top plate.

[0024] Fig. 9 A schematic diagram of the supporting component structure.

[0025] Among them: 1-mounting seat; 2-support bridge; 3-support assembly; 101-circular ring stage unit; 102-driving gear; 103-arc rack; 104-driving motor; 105-level; 201-first side plate unit; 202-locking hole; 203-anti-slip groove; 204-second side plate unit; 205-connecting plate; 206-second top plate unit; 207-first top plate unit; 208-limiting sleeve; 209-first connecting head; 210-limiting screw; 211-second connecting head; 212-limiting nut; 301-support seat; 302-adjusting motor; 303-screw; 304-first adjusting plate; 305-second adjusting plate; 306-third adjusting plate; 307-adjusting gear; 308-rack. DETAILED DESCRIPTION

[0026] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0027] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0028] Embodiment 1: This embodiment provides a method for casting a fan cap. Figure 1 As shown, the following steps are included: Step S1: Design the size, shape and reinforcement configuration of the foundation according to the wind turbine model and engineering requirements; prepare the required concrete, reinforcement, formwork and other materials; Step S2: remove debris and loose soil from the foundation, and excavate the foundation pit according to the drawings; if the soil is soft, perform foundation treatment, such as compaction or pile foundation; Step S3: manufacturing and assembling a steel cage according to design requirements, placing the steel cage in the foundation pit and supporting and fixing it; Step S4: making a corresponding foundation template, installing it at a predetermined position, and checking its sealing to ensure that no leakage occurs during the pouring process; Step S5: pouring concrete gradually from one end to the other end until it is cast into shape; then using auxiliary devices to perform surface treatment on the concrete; Step S6: curing the poured concrete; Step S7: After the concrete strength reaches the standard, the formwork is removed and the size, shape and structural integrity of the foundation are checked to ensure that there are no cracks or other defects.

[0029] Embodiment 2: This embodiment further expands the concrete pouring method based on the embodiment 1. In the step S5, the concrete needs to be vibrated during the concrete pouring. The specific vibrating method is: the vibrating points are arranged in a plum blossom shape, and the vibration is performed in a fast insertion and slow withdrawal manner. The duration of each vibration point is to meet the requirements of the surface showing floating slurry, no bubbles and no sinking. When pouring to the bottom of the foundation ring, the material should be evenly distributed around the foundation ring to avoid collision with steel bars, formwork, embedded parts, embedded pipes, etc. After the concrete is poured, the center position and elevation of the foundation ring are re-measured; wherein the moving spacing of the inserted vibrator is not greater than 1.5 times the action radius of the vibrator, and the vibrator needs to be inserted into the lower layer of concrete when vibrating the upper layer of concrete, and its insertion depth is greater than 5cm, so that the upper and lower layers of concrete are fully combined. According to the wind turbine foundation structure, the foundation concrete is poured once and no construction joints are provided.

[0030] Through the above method, the pouring quality of the foundation can be improved and quality problems such as honeycomb, exposed reinforcement, and voids can be avoided.

[0031] The other parts of this embodiment are the same as those of the above embodiment and will not be described in detail.

[0032] Embodiment 3: This embodiment is further expanded on the basis of embodiment 2. After the concrete is vibrated, a wooden trowel is used to level the surface according to a predetermined elevation line and the surface is promptly covered with a plastic film or a straw mat.

[0033] Leveling is to ensure that the concrete surface is flat and meets the designed elevation, eliminate the irregular heights of the concrete surface, and ensure the overall consistency and aesthetics of the structure; covering protection is to maintain the humidity of the concrete, control the temperature, and prevent pollution.

[0034] The other parts of this embodiment are the same as those of the above embodiment and will not be described in detail.

[0035] Embodiment 4: This embodiment is further expanded on the basis of Embodiment 3, and the concrete surface treatment steps mainly include: Step S51: assembling and fixing the auxiliary device according to the size of the platform; Step S52: Within 3 to 4 hours of pouring, the worker stands on the auxiliary device and uses a scraper to initially scrape the concrete surface flat; Step S53: Before the initial setting, the worker stands on the auxiliary device and uses a wooden trowel to flatten and compact the concrete, so as to make the concrete surface smoother and help the aggregate inside the concrete sink, so that the cement paste floats. This process helps to reduce bubbles and insufficiently compacted areas, thereby enhancing the overall structural strength of the concrete.

[0036] Then use an iron trowel to further smooth the concrete surface and compact the surface to make it smoother and denser. The hardness and weight of the iron trowel can help compact the surface and reduce tiny surface unevenness and holes, thereby helping to control the evaporation rate of water on the concrete surface, thereby reducing shrinkage cracks caused by excessive evaporation of water.

[0037] The above arrangement helps to improve the structural integrity and appearance quality of the concrete surface layer, and also helps to control the occurrence of surface cracks.

[0038] The other parts of this embodiment are the same as those of the above embodiment and will not be described in detail.

[0039] Embodiment 5: This embodiment further expands the auxiliary device on the basis of Embodiment 4, specifically as follows Figure 2-Figure 8 As shown, the auxiliary device mainly includes a mounting seat 1, a supporting bridge 2, and a supporting assembly 3; the supporting assembly 3 is used to support and adjust the height of the mounting seat 1, and the supporting bridge 2 is installed on the mounting seat 1 for people to stand.

[0040] The mounting base 1 includes a circular ring stage unit 101, a driving gear 102, an arc rack 103, and a driving motor 104; the supporting bridge 2 includes a top plate, a connecting plate 205, a side plate, and a connecting piece; the top plate includes a second top plate unit 206 and a first top plate unit 207, and the side plate includes a first side plate unit 201 and a second side plate unit 204; the top plate and the side plate are both provided with locking holes 202 and anti-slip grooves 203; the connecting piece includes a limiting sleeve 208, a first connecting head 209, a second connecting head 211, a limiting nut 212, and a limiting screw 210.

[0041] When assembling the auxiliary device, first put an arc-shaped rack 103 into a circular ring stage unit 101; then connect and tighten multiple circular ring stage units 101 end to end with bolts to form a circular ring stage; place multiple support assemblies 3, place the circular ring stage on the support assemblies 3, and adjust the height of the support assemblies 3 to adjust the height of the circular ring stage; install the driving gear 102 at the output end of the driving motor 104, install the driving motor 104 on the circular ring stage, and make the driving gear 102 mesh with the arc-shaped rack 103; embed the second side plate unit 204 into the first side plate unit 201 and use bolts to pass through the locking holes 202 thereon to relatively fix the first side plate unit 201 and the second side plate unit 204 to form a side plate; embed the second top plate unit 206 into the first top plate unit 207, and use bolts to pass through the locking holes 202 thereon The second top plate unit 206 and the first top plate unit 207 are relatively fixed to form a top plate; the first connecting head 209 is embedded in the second connecting head 211, the angle between the second connecting head 211 and the first connecting head 209 is adjusted, and then the limiting sleeve 208 is inserted into the first connecting head 209 and the second connecting head 211 to fix the angle; after the limiting screw 210 passes through the limiting sleeve 208, the limiting nut 212 is screwed on the limiting screw 210 to limit the limiting sleeve 208; the two connecting plates 205 are respectively connected to the two sides of the top plate by connecting pieces with corresponding angles, and the two connecting pieces with corresponding angles are installed at both ends of the side plates, one end of the side plate is connected to the connecting plate 205 through the connecting piece, and the other end is connected to an arc-shaped rack 103 through the connecting piece, so as to form a support bridge 2 with a fixed shape and parallel to the surface of the platform.

[0042] When the worker is working, he starts the drive motor 104, and the drive motor 104 drives the drive gear 102 to rotate, and the drive gear 102 drives the arc-shaped rack 103, and the adjacent arc-shaped racks 103 are squeezed and pushed in turn to start rotating. At this time, the support bridge 2 starts to rotate under the drive of the arc-shaped rack 103. After the personnel stand on the support bridge 2, they will not step on the processed concrete below, so they can perform surface treatment on the concrete at different positions of the foundation in a forward operation mode.

[0043] Through the above-mentioned settings, people can avoid stepping on the concrete surface while working. On the one hand, it can reduce the amount of concrete adhering to the workers' clothes and ensure the cleanliness of the work; on the other hand, it can prevent people from damaging the treated surface when walking on the platform; finally, by setting up auxiliary devices, the efficiency and quality of concrete surface treatment can be improved.

[0044] The other parts of this embodiment are the same as those of the above embodiment and will not be described in detail.

[0045] Embodiment 6: This embodiment further expands the support assembly 3 on the basis of Embodiment 5. Specifically, Fig. 9As shown, the support assembly 3 includes a support base 301 , an adjustment motor 302 , a lead screw 303 , a first adjustment plate 304 , a second adjustment plate 305 , a third adjustment plate 306 , an adjustment gear 307 , and a rack 308 .

[0046] The support seat 301 is slidably connected to the first adjustment plate 304, the first adjustment plate 304 is slidably connected to the second adjustment plate 305, the second adjustment plate 305 is slidably connected to the third adjustment plate 306, the support seat 301 is installed with an adjusting motor 302, the adjusting motor 302 is installed with a lead screw 303, and the lead screw 303 is threadedly connected to the first adjustment plate 304; two racks 308 are installed on the support seat 301, the first adjustment plate 304, the second adjustment plate 305, and the third adjustment plate 306, and two adjusting gears 307 are installed on the second adjustment plate 305 and the first adjustment plate 304, the adjusting gear 307 on the first adjustment plate 304 is respectively meshed with the racks 308 on the support seat 301 and the second adjustment plate 305, and the adjusting gear 307 on the second adjustment plate 305 is respectively meshed with the racks 308 on the first adjustment plate 304 and the third adjustment plate 306.

[0047] When adjusting the height of the support assembly 3, the adjusting motor 302 is started, and the adjusting motor 302 drives the lead screw 303 to rotate. At this time, the first adjusting plate 304 starts to move longitudinally. While moving, the first adjusting plate 304 will drive the adjusting gear 307 thereon to move longitudinally. Due to the meshing relationship between the adjusting gear 307 and the rack 308 on the support seat 301, the adjusting gear 307 on the first adjusting plate 304 starts to rotate at this time, so the adjusting gear 307 will drive the rack 308 on the second adjusting plate 305 to move longitudinally, thereby realizing the longitudinal movement of the second adjusting plate 305, and similarly realizing the longitudinal movement of the third adjusting plate 306; that is, when the first adjusting plate 304 moves upward, the second adjusting plate 305 and the third adjusting plate 306 move upward synchronously, and when the first adjusting plate 304 moves downward, the second adjusting plate 305 and the third adjusting plate 306 move downward synchronously.

[0048] Through the above arrangement, the height of the support base 301 can be reduced while ensuring that the height adjustment value of the support assembly 3 remains unchanged, thereby facilitating transportation.

[0049] The other parts of this embodiment are the same as those of the above embodiment and will not be described in detail.

[0050] Embodiment 7: This embodiment further expands the mounting base 1 on the basis of Embodiment 5. Specifically, Fig. 9 As shown, a level 105 is installed on the circular ring stage unit 101.

[0051] When adjusting the height of the support assembly 3, the level meter 105 is observed by naked eyes to ensure that the circular stage is in a horizontal state to prevent the situation in which the person is standing unsteadily due to the tilt of the circular stage.

[0052] The other parts of this embodiment are the same as those of the above embodiment and will not be described in detail.

[0053] Embodiment 8: This embodiment further expands the concrete curing method based on Embodiment 1. The curing of the concrete in step S6 includes: recording the internal and external temperature values ​​of the concrete to ensure that the internal and external temperature difference of the concrete is not greater than 25°; and sprinkling water on the concrete surface or covering it with a film and geotextile according to the temperature difference.

[0054] Specifically: curing begins within 12 to 18 hours after concrete pouring, and the curing period is 14 days. According to the requirements of the construction drawings, 4 temperature measuring tubes are laid, with a total of 8 temperature measuring points. During the construction and curing period, temperature observations must meet the following requirements: a. The external temperature is measured manually, 4 times a day, and records are kept; b. The maximum and minimum temperatures are observed on the outside of the concrete every day; the inside of the concrete is measured once every hour, and records are kept; c. The temperature measuring holes are buried, and the internal temperature of the concrete is measured with a temperature sensor or a glass thermometer, and records are kept; d. During sudden drops in temperature and cold waves, the number of temperature observations should be increased; e. When the difference between the internal maximum temperature of the concrete and the ambient temperature is less than 25°C for 3 consecutive days, and the cooling rate is less than 2°C / d, and the temperature difference between the inside and outside is less than the control value shown in Table 1 below, the temperature measurement operation can be stopped.

[0055] Table 1 Through the above arrangement, the temperature difference between the interior and surface of the concrete can be effectively controlled, and the thermal stress caused by the temperature difference can be alleviated, thereby reducing the risk of cracks and improving the overall quality and durability of the concrete.

[0056] The other parts of this embodiment are the same as those of the above embodiment and will not be described in detail.

[0057] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Any simple modification or equivalent change made to the above embodiment based on the technical essence of the present invention shall fall within the protection scope of the present invention.

Claims

1. A method for casting a fan cap, characterized in that: The steps include: Step S1: Design the size of the foundation and the specifications of the steel bars according to the wind turbine model and engineering requirements; Step S2: clear the site and excavate the foundation pit according to the drawings; Step S3: manufacturing and assembling a steel cage according to design requirements, placing the steel cage in the foundation pit and supporting and fixing it; Step S4: making a corresponding platform template, installing it to a predetermined position, and checking its sealing performance; Step S5: pouring concrete gradually from one end to the other end until it is cast and formed, and then performing surface treatment of the concrete using auxiliary devices; Step S6: curing the poured concrete; Step S7: After the concrete strength reaches the standard, the formwork is removed and inspected.

2. A method for casting a fan cap according to claim 1, characterized in that: In step S5, the concrete needs to be vibrated during pouring, and the specific vibration method is: the vibration points are arranged in a plum blossom shape, and the vibration is performed in a manner of fast insertion and slow withdrawal; wherein the moving spacing of the inserted vibrator is not greater than 1.5 times the effective radius of the vibrator, and the vibrator needs to be inserted into the lower layer of concrete when vibrating the upper layer of concrete, and the insertion depth is greater than 5 cm.

3. A method for casting a fan cap according to claim 2, characterized in that: After the concrete is vibrated, a wooden trowel is used to level the surface according to a predetermined elevation line and the surface is promptly covered with a plastic film.

4. A method for casting a fan cap according to claim 3, characterized in that: The concrete surface treatment step in step S5 mainly includes: Step S51: assembling and fixing the auxiliary device according to the size of the platform; Step S52: Within 3 to 4 hours of pouring, the worker stands on the auxiliary device and uses a scraper to initially scrape the concrete surface flat; Step S53: Before the initial setting, the worker stands on the auxiliary device and uses a wooden trowel to flatten and compact the surface, and then uses an iron trowel to finish the surface.

5. A method for casting a fan cap according to claim 4, characterized in that: The auxiliary device mainly comprises a mounting seat (1), a support bridge (2), and a support assembly (3); the support assembly (3) is used to support and adjust the height of the mounting seat (1), and the support bridge (2) is installed on the mounting seat (1) for a person to stand on; The mounting seat (1) comprises a circular ring stage unit (101), a driving gear (102), an arc-shaped rack (103), and a driving motor (104); the supporting bridge (2) comprises a top plate, a connecting plate (205), a side plate, and a connecting piece; the top plate comprises a second top plate unit (206) and a first top plate unit (207); the side plate comprises a first side plate unit (201) and a second side plate unit (204); the top plate and the side plate are both provided with locking holes (202); the connecting piece comprises a limiting sleeve (208), a first connecting head (209), a second connecting head (211), a limiting nut (212), and a limiting screw (210); The specific assembly steps of the auxiliary device in step S51 are: Step S511: placing an arc-shaped rack (103) into a circular ring stage unit (101); Step S512: connecting and fastening a plurality of circular ring stage units (101) end to end with bolts to form a circular ring stage; Step S513: placing a plurality of support components (3), placing the circular ring stage on the support components (3), and adjusting the height of the support components (3) to adjust the height of the circular ring stage; Step S514: installing the driving gear (102) at the output end of the driving motor (104), installing the driving motor (104) on the circular ring stage, and making the driving gear (102) mesh with the arc-shaped rack (103); Step S515: embedding the second side plate unit (204) into the first side plate unit (201) and using bolts to pass through the locking holes (202) thereon to relatively fix the first side plate unit (201) and the second side plate unit (204) to form a side plate; embedding the second top plate unit (206) into the first top plate unit (207) and using bolts to pass through the locking holes (202) thereon to relatively fix the second top plate unit (206) and the first top plate unit (207) to form a top plate; Step S516: embedding the first connector (209) into the second connector (211), adjusting the angle between the second connector (211) and the first connector (209), and then inserting the limiting sleeve (208) into the first connector (209) and the second connector (211) to fix the angle; after the limiting screw (210) passes through the limiting sleeve (208), screwing the limiting nut (212) onto the limiting screw (210) to limit the limiting sleeve (208); Step S517: Use connecting pieces with corresponding angles to connect two connecting plates (205) to the two sides of the top plate respectively, and install two connecting pieces with corresponding angles at both ends of the side plate. One end of the side plate is connected to the connecting plate (205) through the connecting piece, and the other end is connected to an arc-shaped rack (103) through the connecting piece.

6. A method for casting a fan cap according to claim 5, characterized in that: The support assembly (3) comprises a support seat (301), an adjustment motor (302), a lead screw (303), a first adjustment plate (304), a second adjustment plate (305), a third adjustment plate (306), an adjustment gear (307), and a rack (308); the support seat (301) is slidably connected to the first adjustment plate (304), the first adjustment plate (304) is slidably connected to the second adjustment plate (305), the second adjustment plate (305) is slidably connected to the third adjustment plate (306), the adjustment motor (302) is installed on the support seat (301), the lead screw (303) is installed on the adjustment motor (302), and the lead screw (303) is connected to the first adjustment plate (304). The adjustment plate (304) is threadedly connected; two racks (308) are installed on the support seat (301), the first adjustment plate (304), the second adjustment plate (305), and the third adjustment plate (306); two adjustment gears (307) are installed on the second adjustment plate (305) and the first adjustment plate (304); the adjustment gear (307) on the first adjustment plate (304) is respectively meshed with the racks (308) on the support seat (301) and the second adjustment plate (305); the adjustment gear (307) on the second adjustment plate (305) is respectively meshed with the racks (308) on the first adjustment plate (304) and the third adjustment plate (306).

7. A method for casting a fan cap according to claim 5, characterized in that: A level (105) is installed on the circular ring stage unit (101).

8. A method for casting a fan cap according to claim 1, characterized in that: The curing of the concrete in step S6 includes: recording the internal and external temperature values ​​of the concrete to ensure that the internal and external temperature difference of the concrete is not greater than 25°; and sprinkling water or covering the concrete surface with a film or geotextile according to the temperature difference.