Settlement-adjustable floor structure and settlement adjusting method thereof
By setting up pile cap components and grouting pipe components on the floor, grouting is used to expand the pile cap components and lift the floor, the problem of uneven settlement of the foundation is solved, and simple construction, short construction period and good economicality is achieved Floor settlement adjustment effect.
Patent Information
- Application Number
- CN202411048807.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-01
- Publication Date
- 2024-11-12
AI Technical Summary
When building a large logistics storage factory on a deep soft soil foundation on a coastal blown fill, improper foundation treatment leads to uneven settlement of the floor, affecting the normal use of the factory. The existing technology has shortcomings in the treatment effect and economy.
The pile cap assembly and grouting pipe assembly are used to adopt the reduced sinking composite pile diffusing foundation, and the pile cap assembly is installed. Through grouting, the pile cap assembly is expanded and the floor is lifted up, so as to achieve leveling and lifting of the floor.
The floor settlement adjustment is achieved with simple construction, short construction period and good economicality, and the negative impact of uneven settlement on the use of the factory is avoided.
Smart Images

Figure CN118933100A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of building construction, and in particular to a settlement-adjustable floor structure and a settlement adjustment method thereof. Background Art
[0002] When building a large logistics storage plant on a deep soft soil foundation of coastal fill soil, if the foundation treatment method is improper, under the action of large-area stacking load, the storage floor often suffers from uneven settlement, which seriously affects the normal use of the plant, and even requires demolition and reconstruction, resulting in large economic losses. At present, the commonly used methods for this type of foundation treatment include four categories: high-pressure rotary grouting (cement mixing pile) composite foundation, vacuum preloading method, pure pile foundation and rigid pile composite foundation. Among them, the pure pile foundation treatment has the best floor settlement control effect because the pile end enters the hard soil layer, but the treatment cost is the highest; and the other three treatment methods are relatively economical and reasonable in cost, but in actual engineering applications, it is found that the floor is in the shape of a pot bottom, and the differential settlement is obvious, which seriously affects the subsequent normal use. Therefore, from the perspectives of treatment effect and economy, the present invention proposes a settlement-adjustable floor structure and its settlement adjustment method. That is, a settlement-reducing composite sparse pile foundation is used for the floor, and a special device is set on the pile top. When uneven settlement occurs in the later stage, the adjustable device installed on the pile top is used to repeatedly grout the floor to lift and level it. The advantages of the invention are simple construction, short construction period and good economy. Summary of the invention
[0003] The object of the present invention is to provide a settlement-adjustable floor structure and a settlement adjustment method thereof, so as to solve the problems raised in the above-mentioned background technology.
[0004] To achieve the above object, the present invention provides the following technical solutions:
[0005] A settlement adjustable floor structure comprises a floor body, a pile beam and a settlement control pile. The pile beam is arranged at the bottom of the floor body. The pile beam is a ring structure and surrounds a pile hole at the bottom of the floor body. The upper end of the settlement control pile is inserted into the pile hole. A pile cap assembly is arranged on the top of the settlement control pile. The pile cap assembly is used to support the floor body. The pile cap assembly has a cavity. A grouting pipe assembly is arranged on the pile cap assembly. The grouting pipe assembly is used to grout the cavity of the pile cap assembly to expand the pile cap assembly and lift the floor body.
[0006] Furthermore, the pile cap assembly includes a plurality of pile cap units that are telescopically slidably mounted up and down, a first cavity is formed between adjacent pile cap units, the grouting pipe assembly includes a first grouting pipe for grouting the first cavity, and the top of the uppermost pile cap unit supports the floor body.
[0007] Furthermore, a second cavity is formed between the pile cap unit at the lower end of the pile cap assembly and the controlled sinking pile, and the grouting pipe assembly includes a second grouting pipe for grouting the second cavity.
[0008] Furthermore, a padding plate is provided inside the pile cap unit, and adjacent pile cap units are connected by the padding plate to form a first cavity, and the lowermost pile cap unit is connected with the controlled sinking pile by the padding plate to form a second cavity.
[0009] Furthermore, the pile cap unit is a cylindrical structure with an open bottom and a closed top.
[0010] Furthermore, the pile cap assembly includes two pile cap units that are telescopically and slidably mounted up and down.
[0011] Furthermore, one end of the grouting pipe assembly is connected to the cavity of the pile cap assembly, and the other end extends from the floor body.
[0012] Furthermore, the cross-sectional height h of the pile-enclosing beam is:
[0013] h=h 1 +2h 2
[0014] where h 1 h is the thickness of the floor body; 2 is the height of the pile cap assembly.
[0015] The present invention also provides a floor settlement adjustment method, comprising:
[0016] Design stage: Design the floor into a settlement adjustable floor structure as described above;
[0017] Adjustment stage: When the floor settles, expandable cement is poured into the cavity of the pile cap assembly through the grouting pipe assembly, causing the pile cap assembly to expand and lift up the floor, thereby raising the floor height.
[0018] Compared with the prior art, the beneficial effects of the present invention are: from the two aspects of treatment effect and economy, the present invention proposes a settlement-adjustable floor structure and a settlement adjustment method thereof, that is, settlement-controlled piles are used for the floor, and pile cap assemblies and grouting pipe assemblies are arranged on the pile tops. When uneven settlement occurs in the later stage, the pile cap assemblies and grouting pipe assemblies installed on the pile tops are used to perform multiple grouting to lift and level the floor, which has the advantages of simple construction, short construction period and good economy. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 The present invention is a schematic diagram of a floor structure with adjustable settlement.
[0020] Figure 2 for Figure 1 Cross-section view at AA.
[0021] Figure 3 The present invention is a schematic plan view of a floor structure with adjustable settlement.
[0022] In the figure: floor body 1, surrounding pile beam 2, control sinking pile 3, pile hole 4, pile cap assembly 5, first pile cap unit 501, second pile cap unit 502, first grouting pipe 6, first cavity 7, second cavity 8, second grouting pipe 9. DETAILED DESCRIPTION
[0023] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0024] See also Figure 1-Figure 3 A settlement adjustable floor structure includes a floor body 1, a pile beam 2, and a settlement control pile 3. The pile beam 2 is arranged at the bottom of the floor body 1. The pile beam 2 is a ring structure, which surrounds a pile hole 4 at the bottom of the floor body 1. The upper end of the settlement control pile 3 is inserted into the pile hole 4. A pile cap assembly 5 is arranged on the top of the settlement control pile 3. The pile cap assembly 5 is used to support the floor body 1. The pile cap assembly 5 has a cavity. A grouting pipe assembly is arranged on the pile cap assembly 5. The grouting pipe assembly is used to grout the cavity of the pile cap assembly 5, so that the pile cap assembly 5 expands and lifts the floor body 1.
[0025] Continue reading Figure 1 and Figure 2 In one embodiment of the present invention, the cavity of the pile cap assembly 5 includes a first cavity 7 and a second cavity 8. The pile cap assembly 5 includes a plurality of pile cap units that are telescopically slidably mounted up and down. The pile cap unit is a cylindrical structure with an open bottom and a closed top. A first cavity 7 is formed between adjacent pile cap units. The top of the uppermost pile cap unit supports the floor body 1. A second cavity 8 is formed between the lowermost pile cap unit and the control sinking pile 3. The grouting pipe assembly is used for grouting the first cavity 7 and the second cavity 8.
[0026] Specifically, the pile cap assembly 5 includes a second pile cap unit 502 and a first pile cap unit 501 which are telescopically and slidably mounted up and down. The second pile cap unit 502 is mounted on the outside of the first pile cap unit 501, and the first pile cap unit 501 is mounted on the outside of the controlled sinking pile 3. Two raising plates 503 are vertically arranged inside the second pile cap unit 502 and the first pile cap unit 501. The second pile cap unit 502 and the first pile cap unit 501 are blocked by the raising plates 503 to form a first cavity 7. The pile cap unit at the lower end is blocked by the controlled sinking pile 3 through the raising plates 503 to form a second cavity 8.
[0027] Continue reading Figure 1 and Figure 2In one embodiment of the present invention, the grouting pipe assembly includes a first grouting pipe 6 and a second grouting pipe 9. The lower end of the first grouting pipe 6 is connected to the first cavity 7 of the pile cap assembly 5, and the upper end extends from the floor body 1. One end of the second grouting pipe 9 is connected to the second cavity 8 of the pile cap assembly 5, and the upper end extends from the floor body 1. Valves are provided on the portions of the first grouting pipe 6 and the second grouting pipe 9 extending from the floor body 1. Grouting can be performed in the first cavity 7 and the second cavity 8 respectively through the first grouting pipe 6 and the second grouting pipe 9.
[0028] Continue reading Figure 1 In one embodiment of the invention, the cross-sectional height h of the pile beam 2 is:
[0029] h=h 1 +2h 2
[0030] where h 1 h is the thickness of the floor body 1; 2 is the height of pile cap assembly 5.
[0031] The present invention also provides a floor settlement adjustment method, comprising:
[0032] Design stage: Design the floor into a settlement adjustable floor structure as described above.
[0033] Adjustment stage: When the floor settles, expansion cement is poured into the cavity of the pile cap assembly 5 through the grouting pipe assembly, so that the pile cap assembly 5 expands and lifts up the floor, thereby raising the floor height.
[0034] Specifically, it can be divided into the following processes:
[0035] Step 1: According to the soil conditions and the floor load, calculate the number of settlement control piles 3 required according to the settlement reduction composite sparse pile foundation, and select the installation position of the settlement control piles 3. The settlement control piles 3 use friction piles.
[0036] Step 2: Rationally estimate the settlement, determine the height of the pile cap assembly 5, and reserve the grouting pipe assembly.
[0037] Step 3: The pile cap assembly is designed as a hollow structure, which is welded from multiple steel plates. It is placed on the top of the pile and clamps the pile body through two wing steel plates, and is connected to the pile body by sliding.
[0038] Step 4: The floor body 1 is made of reinforced concrete floor, the thickness should generally be no less than 200mm, C30 concrete, and configured with double-layer two-way 12@200 steel mesh. A 300mm thick gravel cushion layer is set at the bottom of the floor body 1, and the cross-sectional height h of the surrounding pile beam 2 should be calculated as follows:
[0039] h=h 1 +2h 2
[0040] where h 1 h is the thickness of the floor body 1; 2 is the height of the pile cap assembly 5 (in mm).
[0041] Step 5: Grouting parameters: grouting pressure 3-10Mpa, grouting material uses expansive cement.
[0042] Step 6: When differential settlement occurs on the floor during use, grout is first injected into the second cavity 8 of the pile cap assembly 5 through the second grouting pipe 9, and the top position of the pile cap assembly 5 is lifted by the expansion of cement, thereby lifting the floor and achieving leveling. If differential settlement occurs again in the future, grout is injected into the first cavity 7 of the pile cap assembly 5 to complete the secondary leveling.
[0043] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A settlement adjustable floor structure, characterized in that: The invention comprises a floor body (1), a pile-enclosing beam (2), and a controlled sinking pile (3). The pile-enclosing beam (2) is arranged at the bottom of the floor body (1). The pile-enclosing beam (2) is an annular structure and surrounds a pile hole (4) at the bottom of the floor body (1). The upper end of the controlled sinking pile (3) is inserted into the pile hole (4). A pile cap assembly (5) is arranged on the top of the controlled sinking pile (3). The pile cap assembly (5) is used to support the floor body (1). A grouting pipe assembly is arranged on the pile cap assembly (5). The grouting pipe assembly is used to grout the cavity of the pile cap assembly (5) so that the pile cap assembly (5) expands and lifts up the floor body (1).
2. The settling adjustable floor structure according to claim 1, characterized in that: The pile cap assembly (5) comprises a plurality of pile cap units that are telescopically slidably mounted up and down, a first cavity (7) is formed between adjacent pile cap units, the grouting pipe assembly comprises a first grouting pipe (6) for grouting the first cavity (7), and the top of the uppermost pile cap unit supports the floor body (1).
3. The settling adjustable floor structure according to claim 2, characterized in that: A second cavity (8) is formed between the lowermost pile cap unit in the pile cap assembly (5) and the controlled sinking pile (3), and the grouting pipe assembly comprises a second grouting pipe (9) for grouting the second cavity (8).
4. The settling adjustable floor structure according to claim 3 is characterized in that: A padding plate (503) is arranged inside the pile cap unit, and adjacent pile cap units are connected by the padding plate (503) to form a first cavity (7), and the lowermost pile cap unit is connected to the controlled sinking pile (3) by the padding plate (503) to form a second cavity (8).
5. The settling adjustable floor structure according to claim 2, characterized in that: The pile cap unit is a cylindrical structure with an open bottom and a closed top.
6. The settling adjustable floor structure according to claim 2, characterized in that: The pile cap assembly (5) comprises two pile cap units which are telescopically and slidably mounted up and down.
7. The settling adjustable floor structure according to claim 1 is characterized in that: One end of the grouting pipe assembly is connected to the cavity of the pile cap assembly (5), and the other end extends out from the floor body (1).
8. The settling adjustable floor structure according to claim 1, characterized in that: The cross-sectional height h of the pile-enclosing beam (2) is: h=h1+2h2 Wherein h1 is the thickness of the floor body (1); h2 is the height of the pile cap assembly (5).
9. A method for adjusting floor settlement, characterized in that: include: Design stage: design the floor into a settlement-adjustable floor structure as described in any one of claims 1-8; Adjustment stage: When the floor settles, expansion cement is poured into the cavity of the pile cap assembly (5) through the grouting pipe assembly, so that the pile cap assembly (5) expands and lifts up the floor, thereby raising the floor height.