Small-section water conveyance tunnel construction method based on prefabricated arch piece structure
Through prefabricated arch structure and dry spray concrete technology, the problems of low construction efficiency and large material losses in small-section tunnel construction are solved, and a rapid, economical and reliable construction effect is achieved.
Patent Information
- Application Number
- CN202411027530.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-11-12
AI Technical Summary
During the construction of existing small-section tunnels, mechanical overall formwork trolleys are difficult to put into use, resulting in low construction efficiency, large material loss, poor appearance and hole quality.
The construction method of small-section water transport tunnel based on prefabricated arch structure is adopted, including bottom arch arch, first side arch arch, second side arch arch, dry hard concrete, cement mortar and polysulfide sealing paste, through precise positioning Install arches with small transport vehicles, combining dry spray concrete and backfill grouting technology to achieve rapid construction and high-quality lining.
The rapid construction of small-section tunnels has been achieved, the construction cost and material consumption have been reduced, and the construction speed and hole-forming quality have been improved.
Smart Images

Figure CN118933849A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of tunnel construction, and in particular to a small-section water conveyance tunnel construction method based on a prefabricated arch piece structure. Background Art
[0002] In recent years, in order to solve the problem of water shortage for people, livestock and crops in some water-scarce areas, the country has continuously increased the construction of water conservancy projects, and more and more areas have built new water diversion tunnels. In order to avoid waste of construction investment, some areas with small water transfer volume have adopted small-section tunnels. Due to the small cross-sectional size and limited space, the existing shield machines cannot meet the requirements of long-distance tunnels with a diameter of less than 2.5 meters, and the construction cost of large equipment such as shield machines is high. Therefore, small-section tunnel diameter dark excavation construction is widely used. However, the existing small-section tunnel diameter dark excavation construction adopts the method of cast-in-place construction of the second lining, which is applied to small-section tunnels. The mechanical integral formwork trolley is limited by the narrow construction environment and is difficult to put into use. The combined construction of the bracket formwork faces problems such as low construction efficiency, large material loss, poor appearance and tunnel quality.
[0003] Application Contents
[0004] The purpose of the present application is to provide a small-section water conveyance tunnel construction method based on a prefabricated arch structure to solve the technical problems described in the background technology.
[0005] A small-section water conveyance tunnel construction method based on a prefabricated arch piece structure, the arch piece structure comprising: a bottom arch piece, a first side arch piece, a second side arch piece, dry hard concrete, cement mortar and polysulfide sealing paste; before installing the arch piece, the arch piece installation axis is accurately determined, dry hard concrete is laid at the bottom hinge position, and the bottom arch piece is transported and installed by an installation trolley before initial setting; dry hard concrete is laid in the arc-shaped reserved groove of the bottom arch, and the first side arch piece and the second side arch piece are transported and installed by an installation trolley before initial setting; cement mortar and polysulfide sealing paste are used to fill the gaps of the arch pieces, and finally dry hard cement mortar is injected at the reserved hole on the top;
[0006] The construction method of a small-section water conveyance tunnel based on a prefabricated arch structure comprises the following steps:
[0007] S100: tunnel section excavation - S200: erection of steel arch and steel mesh - S300: dry shotcrete;
[0008] S400: Prefabricated tunnel arch: The construction of prefabricated components is equipped with fixed formwork, and the concrete is transported by small concrete tank trucks, manually installed, and compacted by vibrating rods. During the vibration process, attention should be paid to manual filling to ensure the size of the components; the prefabricated arches that have reached the acceptance strength are transported to the site by truck cranes, neatly stacked, and then transported into the tunnel by small transport vehicles for installation;
[0009] S500: Installation of tunnel arch structure:
[0010] S510: After the cavern excavation is completed, measurement and layout should be carried out before the arch is installed to accurately determine the arch installation axis;
[0011] S520: The bottom arch is transported vertically to the installation position by the bottom arch installation vehicle, and then hoisted by a winch to rotate 90 degrees. The bottom arch is installed on the cushion leveled with C15 concrete with manual assistance. After the four bottom arches are installed (that is, when the arch lining is 3m away from the tunnel face), the expansion joint size (5cm wide) is adjusted and the bottom arch pre-shrinkage cement mortar is filled;
[0012] S530: The two side arches are transported vertically to the installation position by the side arch installation vehicle and then hoisted. When the two side arches are perpendicular to the bottom arch, the hydraulic jacks on the left and right sides are opened to push the two side arches into the bottom hinge (the bottom hinge position must be paved with C20 dry hard concrete in advance). Finally, the side arches are manually corrected by pushing, prying, etc. to ensure that the arch line is smooth, there is no misalignment, and the gap spacing meets the design requirement of 5cm width;
[0013] S540: Use a 5cm PVC pipe to seal the expansion joint inside the side arch, fill the space between the side arch and the surrounding rock with 15cm thick C20 dry hard concrete, use wooden sticks and other tamping tools to compact the concrete, then excavate the cavern and proceed to the next cycle of arch piece installation construction;
[0014] S600: Backfill grouting.
[0015] Furthermore, the bottom arch piece is 20cm thick, with an arc length of 2.0-2.5m, the first and second side arch pieces are 15cm thick, with an arc length of 2.0-2.5m, and a longitudinal length of 0.7m. Side arch arc grooves are reserved on both sides of the bottom arch, and a 3cm groove is reserved at the contact of the arch pieces. C30 reinforced concrete is used, and the prefabrication factory customizes the formwork for production. Customized arch piece transportation and installation vehicles are used.
[0016] Furthermore, the circumferential contact joints and longitudinal contact gaps of the arch pieces are filled with cement mortar and 4 cm polysulfide sealing paste.
[0017] Furthermore, the lower part of the bottom arch is filled with a 5 cm thick C15 concrete cushion layer with a wire mesh in the middle, and the contact position between the side arch and the bottom arch is filled with a layer of dry hard 1:2 cement mortar.
[0018] Furthermore, 5 cm grouting holes are reserved at the contact point of the two side arches at the arch top, and 1:2 dry hard cement mortar is used to backfill the back of the arch through the reserved holes.
[0019] Compared with the prior art, the advantages and positive effects of the present invention are: solving the technical problem of rapid construction of secondary lining of small-section tunnels, and having the characteristics of low tunnel cost, fast construction speed, material saving, and reliable quality. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0021] Figure 1 The present invention is a schematic diagram of an arch structure of an embodiment of a small-section water conveyance tunnel construction method based on a prefabricated arch structure.
[0022] Figure 2 The present invention is a process flow chart of an embodiment of a small-section water conveyance tunnel construction method based on a prefabricated arch structure.
[0023] Figure 3 The present invention is a schematic diagram of the structure of the annular contact seam and longitudinal contact gap of the arch piece according to an embodiment of a construction method for a small-section water conveyance tunnel based on a prefabricated arch piece structure.
[0024] Figure 4 The present invention is a schematic diagram of the contact position between the side arch and the bottom arch in one embodiment of a small-section water conveyance tunnel construction method based on a prefabricated arch segment structure.
[0025] Figure 5 The present invention is a cross-sectional view of tunnel excavation according to an embodiment of a small-section water conveyance tunnel construction method based on a prefabricated arch structure.
[0026] Figure 6 The present invention is a schematic diagram of a steel arch structure according to an embodiment of a small-section water conveyance tunnel construction method based on a prefabricated arch structure.
[0027] Figure 7 The present invention is a shotcrete construction process flow chart of an embodiment of a small-section water conveyance tunnel construction method based on a prefabricated arch structure. DETAILED DESCRIPTION
[0028] In order to make the purpose, technical solution and advantages of the embodiments of the present invention more clearly understood, the embodiments of the present invention are further described in detail below in conjunction with the embodiments and drawings. Here, the illustrative embodiments of the present invention and their description are used to explain the present invention, but are not intended to limit the present invention.
[0029] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0030] It should be understood that the terms "include / comprise", "consist of..." or any other variations are intended to cover non-exclusive inclusion, so that a product, device, process or method that includes a series of elements includes not only those elements, but also may include other elements not explicitly listed when necessary, or also includes elements inherent to such product, device, process or method. In the absence of more restrictions, the elements defined by the sentence "include / comprise...", "consist of..." do not exclude the presence of other identical elements in the product, device, process or method that includes the elements.
[0031] It is also necessary to understand that terms such as "upper", "lower", "front", "back", "left", "right", "top", "bottom", "inside" and "outside" to indicate directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device, component or structure must have a specific direction, be constructed or operate in a specific direction, and should not be understood as a limitation on the present invention.
[0032] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0033] As the instruction manual Figure 1-7 As shown:
[0034] A small-section water conveyance tunnel construction method based on a prefabricated arch piece structure, the arch piece structure comprising: a bottom arch piece, a first side arch piece, a second side arch piece, dry hard concrete, cement mortar and polysulfide sealing paste; before installing the arch piece, the arch piece installation axis is accurately determined, dry hard concrete is laid at the bottom hinge position, and the bottom arch piece is transported and installed by an installation trolley before initial setting; dry hard concrete is laid in the arc-shaped reserved groove of the bottom arch, and the first side arch piece and the second side arch piece are transported and installed by an installation trolley before initial setting; cement mortar and polysulfide sealing paste are used to fill the gaps of the arch pieces, and finally dry hard cement mortar is injected at the reserved hole on the top;
[0035] The construction method of a small-section water conveyance tunnel based on a prefabricated arch structure comprises the following steps:
[0036] S100: tunnel section excavation - S200: erection of steel arch and steel mesh - S300: dry shotcrete;
[0037] S400: Prefabricated tunnel arch: The construction of prefabricated components is equipped with fixed formwork, and the concrete is transported by small concrete tank trucks, manually installed, and compacted by vibrating rods. During the vibration process, attention should be paid to manual filling to ensure the size of the components; the prefabricated arches that have reached the acceptance strength are transported to the site by truck cranes, neatly stacked, and then transported into the tunnel by small transport vehicles for installation;
[0038] S500: Installation of tunnel arch structure:
[0039] S510: After the cavern excavation is completed, measurement and layout should be carried out before the arch is installed to accurately determine the arch installation axis;
[0040] S520: The bottom arch is transported vertically to the installation position by the bottom arch installation vehicle, and then hoisted by a winch to rotate 90 degrees. The bottom arch is installed on the cushion leveled with C15 concrete with manual assistance. After the four bottom arches are installed (that is, when the arch lining is 3m away from the tunnel face), the expansion joint size (5cm wide) is adjusted and the bottom arch pre-shrinkage cement mortar is filled;
[0041] S530: The two side arches are transported vertically to the installation position by the side arch installation vehicle and then hoisted. When the two side arches are perpendicular to the bottom arch, the hydraulic jacks on the left and right sides are opened to push the two side arches into the bottom hinge (the bottom hinge position must be paved with C20 dry hard concrete in advance). Finally, the side arches are manually corrected by pushing, prying, etc. to ensure that the arch line is smooth, there is no misalignment, and the gap spacing meets the design requirement of 5cm width;
[0042] S540: Use a 5cm PVC pipe to seal the expansion joint inside the side arch, fill the space between the side arch and the surrounding rock with 15cm thick C20 dry hard concrete, use wooden sticks and other tamping tools to compact the concrete, then excavate the cavern and proceed to the next cycle of arch piece installation construction;
[0043] S600: Backfill grouting.
[0044] In this embodiment, the technical problem of rapid construction of secondary lining of a small-section tunnel is solved, and the invention has the characteristics of low tunnel cost, fast construction speed, material saving, and reliable quality.
[0045] Specifically, the bottom arch piece is 20cm thick and has an arc length of 2.0 to 2.5m; the first and second side arch pieces are 15cm thick and have an arc length of 2.0 to 2.5m; the longitudinal length is 0.7m; side arch arc grooves are reserved on both sides of the bottom arch; a 3cm groove is reserved at the contact point of the arch pieces; C30 reinforced concrete is used, and the prefabrication plant uses customized formwork for production; customized arch piece transportation and installation vehicles are used.
[0046] Specifically, the circumferential contact joints and longitudinal contact gaps of the arch pieces are filled with cement mortar and 4 cm polysulfide sealing paste.
[0047] Specifically, the lower part of the bottom arch is filled with a 5cm C15 concrete cushion layer with wire mesh in the middle, and the contact position between the side arch and the bottom arch is filled with a layer of dry hard 1:2 cement mortar.
[0048] Specifically, a 5 cm grouting hole is reserved at the contact point of the two side arches at the arch top, and 1:2 dry hard cement mortar is used to backfill the back of the arch through the reserved hole.
[0049] Specifically, tunnel section excavation S100 also includes:
[0050] S110: Manual excavation of the first area ① is carried out with an electric pickaxe. The dump truck removes the mucking simultaneously. The excavation is continued until the contour area is reached and trimming is carried out. Mucking is then completed.
[0051] S120: After manual trimming to the contour line, carry out partial steel arch support in the second area ②, erect the steel arch (lay out I14 I-beams close to the rock surface, with a spacing of 0.5 to 1m), hang steel mesh, weld steel connecting bars (φ22mm, circumferential spacing of 1m) on the inner side of the steel arch, hang steel mesh (φ8mm@200×200mm) at 180° on the top arch, overlap 200mm, and spray 15cm of C20 concrete after the erection and hanging of the mesh are completed.
[0052] S130: After the bottom arch is erected, construct the third area ③ of the cushion layer with 30cm 10% cement soil.
[0053] In this embodiment, manual excavation is adopted to realize full-section excavation, and combined with "conveyor belt + manual" ballast loading, the ballast is unloaded by a self-unloading ballast truck, the working space is large and the excavation speed is fast, which improves the construction speed and reduces the construction cost.
[0054] Specifically, erecting the steel arch frame and the steel mesh S200 also includes:
[0055] S210: Measurement and positioning: On-site measurement and positioning according to the designed position. First, determine the center line of the tunnel and determine the elevation, and then determine the longitudinal position of the steel arch; the plane of the steel arch must be perpendicular to the center line of the tunnel.
[0056] S220: Site preparation: The unit steel arch frames transported to the site are stacked in units, and the cross-sectional dimensions are checked before installation. The under-excavation and intrusion into the clearance are dealt with in a timely manner to ensure that the steel arch frames are correctly installed. Before installing the bottom arch, the loose slag under the pad is removed and the steel arch frame support steel plate is placed on solid rock.
[0057] S230: The steel arch frame must be installed immediately after the on-site danger elimination is completed and placed on a stable stratum. When installing, prepare an electric pick to remove individual protruding parts at any time to ensure that the steel arch frame is accurately positioned and reliably stressed.
[0058] S240: The steel arch frame is in close contact with the surrounding rock. During the installation process, when there is a large gap between the steel arch frame and the surrounding rock surface, concrete blocks are used to fill it. The installation of the steel arch frame matches the excavation advance. The steel arch frames are connected as a whole with Φ22mm longitudinal connecting bars with a circumferential spacing of 1m.
[0059] S250: Steel mesh is used between the steel arches to form a retaining net, which is firmly connected to the steel arches to prevent the surrounding rock from falling. The steel arches have an outline error of ±3cm along the perimeter of the hole and a plane warping deviation of ±2cm. The steel arches are erected immediately after excavation according to the designed position, with a position deviation of ±5mm. The steel arches are perpendicular to the horizontal line, and the verticality deviation is ±2°.
[0060] S260: After the steel arch frame is installed, the steel mesh should be laid immediately and the concrete should be sprayed in layers between the steel arch frames, first spraying the steel arch frame, and then spraying the concrete between the steel arch frames until the designed thickness is reached.
[0061] S270: If the steel arch frame is unstable due to special circumstances such as geological fragmentation, a locking anchor rod should be installed. A locking anchor rod should be installed on each side 30 cm above the bottom of the side arch. The anchor rod should be driven into the surrounding rock at a downward angle of 20° and welded to the steel arch frame with L-bar.
[0062] Specifically, dry shotcrete S300 also includes:
[0063] S310: Shotcrete spraying should be carried out in sections, slices and layers, and the spraying sequence should be from bottom to top. When spraying, first roughly level the low-lying areas, and then spray in layers and reciprocatingly from bottom to top.
[0064] S320: When spraying concrete in sections, a slope should be reserved for the last spraying of concrete. The width of the slope should be 200 to 300 mm. The slope needs to be moistened with pressurized water before spraying concrete.
[0065] S330: Spraying should be done from bottom to top, first spraying the concrete between the steel frame and the wall, then spraying the concrete between the two steel frames. The side wall spraying concrete should be sprayed upward from the foot of the wall to prevent the rebound from wrapping up the last spray layer.
[0066] S340: When spraying in layers, the next layer should be sprayed after the previous layer of concrete has finally set. If spraying is carried out 1 hour after final setting, the surface of the sprayed layer should be cleaned with Feng Shui first. The thickness of the sprayed concrete should be such that the sprayed concrete does not slip or fall. It should not be too thick to affect the bonding and cohesion of the sprayed concrete, nor should it be too thin to increase the rebound. The thickness of the sprayed concrete for the side wall should be controlled at 7-10cm, and the thickness of the arch should be controlled at 5-6cm, and the thickness of the sprayed layer should be kept uniform. When spraying concrete on the top, in order to avoid falling, the interval between the two times should be 2-4h.
[0067] S350: The spraying speed should be appropriate to facilitate the compaction of concrete. If the wind pressure is too high, the spraying speed will increase and the rebound will increase; if the wind pressure is too low, the spraying speed will be too low and the compaction force will be small, which will affect the strength of the sprayed concrete. Therefore, pay attention to the wind pressure after starting the machine. Only when the initial wind pressure reaches 0.5MPa can the operation be started, and the wind pressure should be adjusted according to the nozzle discharge situation. General working wind pressure: 0.3~0.5MPa for side walls and 0.4~0.65MPa for arches.
[0068] S360: When spraying, keep the nozzle at an appropriate distance from the sprayed surface, and the spraying angle should be as close to 90° as possible to obtain maximum compaction and minimum rebound. The distance between the nozzle and the sprayed surface should be 0.6 to 1m; the nozzle should be moved horizontally and slowly in a circular motion, with one circle pressing half a circle. The circular circle drawn by the sprayer is 40 to 60cm horizontally and 15 to 20cm high; if the sprayed surface is covered by a steel frame or steel mesh, the nozzle can be slightly tilted, but it should not be less than 70°. If the angle between the nozzle and the sprayed surface is too large, the concrete material will roll on the sprayed surface, resulting in an uneven wave-shaped spray surface, increasing the rebound amount, and affecting the quality of the sprayed concrete.
[0069] In this embodiment, the dry shotcrete is first mixed evenly in a mixing plant near the cave entrance, then loaded into the dry shotcrete machine for mixing, and at the same time, an accelerator is added according to the mix ratio. The dry mix is sent to the nozzle through a hose by air force (compressed air). The nozzle is connected to a water pipe. The dry mix is mixed with water in the nozzle and then sprayed out from the nozzle. Relying on the spraying pressure, the concrete is bonded to the surface of the surrounding rock or other materials and can be quickly solidified and hardened.
[0070] Specifically, the backfill grouting S600 is constructed in two sequence holes, first sequence hole I and then sequence hole II. The time interval for grouting of each sequence hole is not less than 48h, and the sequence holes I and II are classified and numbered; each grouting area can be grouted separately, and the end of each section is tightly sealed after concrete pouring. Backfill grouting can only be carried out after all the holes of the same sequence in the same area are drilled.
[0071] Specifically, backfill grouting S600 also includes: the backfill grouting sequence starts from the lower end of the tunnel and moves to the higher end. The specific method of pushing grouting is: the first hole at the lower end is used as a grouting hole, and the adjacent holes are used for drainage and exhaust. After the thickest first-level slurry is discharged, the hole is immediately closed and then changed to a slurry inlet hole until the grouting of all the holes in the sequence reaches the end standard; when the designed specified pressure is reached, the grouting hole stops absorbing slurry at the specified pressure and continues for 10 minutes.
[0072] The above are all preferred embodiments of the present application, and are not intended to limit the protection scope of the present application. Any feature disclosed in this specification (including the abstract and drawings), unless otherwise stated, can be replaced by other equivalent or alternative features with similar purposes. That is, unless otherwise stated, each feature is only an example of a series of equivalent or similar features.
Claims
1. A small-section water conveyance tunnel construction method based on a prefabricated arch structure, characterized in that: The arch piece structure comprises: a bottom arch piece, a first side arch piece, a second side arch piece, dry hard concrete, cement mortar and polysulfide sealing paste; before installing the arch piece, the arch piece installation axis is accurately determined, dry hard concrete is laid at the bottom hinge position, and the bottom arch piece is transported and installed by an installation trolley before initial setting; dry hard concrete is laid in the arc-shaped reserved groove of the bottom arch, and the first side arch piece and the second side arch piece are transported and installed by an installation trolley before initial setting; cement mortar and polysulfide sealing paste are used to fill the gaps of the arch pieces, and finally dry hard cement mortar is injected at the reserved hole on the top; The small-section water conveyance tunnel construction method based on the prefabricated arch structure comprises the following steps: S100: tunnel section excavation - S200: erection of steel arch and steel mesh - S300: dry shotcrete; S400: Prefabricated tunnel arch: Prefabricated components are equipped with fixed formwork for construction. Concrete is transported by small concrete tank trucks, manually installed, and compacted by vibrating rods. During the vibration process, attention should be paid to manual filling to ensure the size of the components. The prefabricated arches that have reached the acceptance strength are transported to the site by truck cranes, neatly stacked, and then transported into the tunnel by small transport vehicles for installation. S500: Installation of tunnel arch structure: S510: After the cavern excavation is completed, measurement and layout should be carried out before the arch is installed to accurately determine the arch installation axis; S520: The bottom arch is transported vertically to the installation position by the bottom arch installation vehicle, and then hoisted by a winch to rotate 90 degrees. The bottom arch is installed on the cushion leveled with C15 concrete with manual assistance. After the four bottom arches are installed (that is, when the arch lining is 3m away from the tunnel face), the expansion joint size (5cm wide) is adjusted and the bottom arch pre-shrinkage cement mortar is filled; S530: The two side arches are transported vertically to the installation position by the side arch installation vehicle and then hoisted. When the two side arches are perpendicular to the bottom arch, the hydraulic jacks on the left and right sides are opened to push the two side arches into the bottom hinge (the bottom hinge position must be paved with C20 dry hard concrete in advance). Finally, the side arches are manually corrected by pushing, prying, etc. to ensure that the arch line is smooth, there is no misalignment, and the gap spacing meets the design requirement of 5cm width; S540: Use a 5cm PVC pipe to seal the expansion joint inside the side arch, fill the space between the side arch and the surrounding rock with 15cm thick C20 dry hard concrete, use wooden sticks and other tamping tools to compact the concrete, then excavate the cavern and proceed to the next cycle of arch piece installation construction; S600: Backfill grouting.
2. The small-section water conveyance tunnel construction method based on the prefabricated arch structure according to claim 1 is characterized in that: The thickness of the bottom arch piece is 20cm, the arc length is 2.0~2.5m, the thickness of the first and second side arch pieces is 15cm, the arc length is 2.0~2.5m, the longitudinal length is 0.7m, side arch arc grooves are reserved on both sides of the bottom arch, and a 3cm groove is reserved at the contact point of the arch pieces. C30 reinforced concrete is used, and the prefabrication plant customizes the formwork for production; customized arch piece transportation and installation vehicles are used.
3. The small-section water conveyance tunnel construction method based on prefabricated arch structure according to claim 2 is characterized in that: The circumferential contact joints and longitudinal contact gaps of the arch pieces are filled with cement mortar and 4 cm polysulfide sealant.
4. The method for constructing a small-section water conveyance tunnel based on a prefabricated arch structure according to claim 3, characterized in that: The lower part of the bottom arch is filled with a 5cm C15 concrete cushion with wire mesh in the middle, and the contact position between the side arch and the bottom arch is filled with a layer of dry hard 1:2 cement mortar.
5. The method for constructing a small-section water conveyance tunnel based on a prefabricated arch structure according to claim 4, characterized in that: A 5cm grouting hole is reserved at the contact point of the two side arches at the arch top, and 1:2 dry hard cement mortar is used to backfill the back of the arch through the reserved hole.
6. The method for constructing a small-section water conveyance tunnel based on a prefabricated arch structure according to any one of claims 1 to 5, characterized in that: Tunnel Section Excavation S100 also includes: S110: Manually excavate the first area (① range) with an electric pick, and use a dump truck to remove the mucking at the same time. Excavate to the contour area for trimming, and then the mucking is completed; S120: After manual trimming to the contour line, the second area (part ②) is supported by steel arch frame, erecting the steel arch frame (laying I14 I-beams close to the rock surface with a spacing of 0.5-1m), hanging steel mesh, welding steel connecting bars (φ22mm, circumferential spacing of 1m) on the inner side of the steel arch frame, hanging steel mesh (φ8mm@200×200mm) at 180° on the top arch with a 200mm overlap, and spraying C20 concrete for 15cm after the frame erection and mesh hanging are completed; S130: After the bottom arch is erected, construct the third area (part ③) of the cushion layer with 30cm of 10% cement soil.
7. The method for constructing a small-section water conveyance tunnel based on a prefabricated arch structure according to any one of claims 1 to 5, characterized in that: The installation of steel arch and steel mesh S200 also includes: S210: Measurement and positioning: On-site measurement and positioning according to the designed position; first determine the tunnel centerline and determine the elevation, and then determine the longitudinal position of the steel arch; the plane of the steel arch must be perpendicular to the tunnel centerline; S220: Site preparation: The unit steel arch frames transported to the site are stacked in units, and the cross-sectional dimensions are checked before installation. The under-excavation and intrusion into the clearance are promptly handled to ensure that the steel arch frames are correctly installed. Before installing the bottom arch, the loose ballast under the pad is removed, and the steel arch frame strength steel plate is placed on solid rock; S230: The steel arch frame must be installed immediately after the on-site hazard elimination is completed and placed on a stable stratum. During installation, electric picks should be prepared to remove individual protruding parts at any time to ensure that the steel arch frame is accurately positioned and reliably stressed. S240: The steel arch frame is in close contact with the surrounding rock. During the installation process, when there is a large gap between the steel arch frame and the surrounding rock surface, concrete blocks are used to plug it tightly. The installation of the steel arch frame matches the excavation footage. The steel arch frames are connected as a whole with Φ22mm longitudinal connecting bars with a circumferential spacing of 1m; S250: Steel mesh is used between the steel arches to form a retaining net, which is firmly connected to the steel arches to prevent the surrounding rock from falling off; the steel arches have a contour error of ±3cm along the perimeter of the hole, and a plane warping deviation of ±2cm; the steel arches are immediately erected according to the designed position after excavation, with a position deviation of ±5mm, and the steel arches are perpendicular to the horizontal line, with a verticality deviation of ±2°; S260: After the steel arch is installed, the steel mesh should be laid immediately and the concrete should be sprayed in layers between the steel arches, first spraying the steel arches, then spraying the concrete between the steel arches until the designed thickness is reached; S270: If the steel arch frame is unstable due to special circumstances such as geological fragmentation, a locking anchor rod should be installed. A locking anchor rod should be installed on each side 30 cm above the bottom of the side arch. The anchor rod should be driven into the surrounding rock at a downward angle of 20° and welded to the steel arch frame with L-bar.
8. The method for constructing a small-section water conveyance tunnel based on a prefabricated arch structure according to any one of claims 1 to 5, characterized in that: Dry Shotcrete S300 also includes: S310: Shotcrete operations should be carried out in sections, slices and layers, and the spraying sequence should be from bottom to top. When spraying, first roughly level the low-lying areas, and then spray in layers and reciprocatingly from bottom to top; S320: When spraying concrete in sections, a slope should be reserved for the last spraying of concrete. The width of the slope should be 200-300mm. The slope should be moistened with pressurized water before spraying concrete. S330: Spraying should be done from bottom to top, first spraying the concrete between the steel frame and the wall, then spraying the concrete between the two steel frames; spraying concrete on the side wall should be sprayed from the foot of the wall upwards to prevent the rebound from being wrapped into the last spray layer; S340: When spraying in layers, the next layer should be sprayed after the previous layer of concrete has finally set. If spraying is carried out 1 hour after final setting, the surface of the sprayed layer should be cleaned with Feng Shui first; the thickness of the sprayed concrete should be such that the sprayed concrete does not slip or fall. It should not be too thick to affect the bonding and cohesion of the sprayed concrete, nor too thin to increase the rebound amount; the thickness of the sprayed concrete for the side wall should be controlled at 7-10cm, and the thickness of the arch should be controlled at 5-6cm, and the thickness of the sprayed layer should be kept uniform; when spraying concrete on the top, in order to avoid falling, the interval between two times should be 2-4h; S350: The spraying speed should be appropriate to facilitate the compaction of concrete. If the wind pressure is too high, the spraying speed will increase and the rebound will increase. If the wind pressure is too low, the spraying speed will be too low and the compaction force will be small, which will affect the strength of the sprayed concrete. Therefore, pay attention to the wind pressure after starting the machine. Only when the initial wind pressure reaches 0.5MPa can the operation be started, and the wind pressure should be adjusted according to the nozzle discharge situation. The general working wind pressure: 0.3~0.5MPa for the side wall, 0.4~0.65MPa for the arch. S360: When spraying, keep an appropriate distance between the nozzle and the sprayed surface, and the spraying angle should be as close to 90° as possible to obtain maximum compaction and minimum rebound; the distance between the nozzle and the sprayed surface should be 0.6-1m; the nozzle should move continuously and slowly in a horizontal circular motion, one circle and half a circle, and the circular circle drawn by the sprayer is 40-60cm horizontally and 15-20cm high; if the sprayed surface is covered by a steel frame or a steel mesh, the nozzle can be slightly tilted, but it should not be less than 70°; if the angle between the nozzle and the sprayed surface is too large, the concrete material will roll on the sprayed surface, producing an uneven wavy spray surface, increasing the rebound amount, and affecting the quality of the sprayed concrete.
9. The method for constructing a small-section water conveyance tunnel based on a prefabricated arch structure according to any one of claims 1 to 5, characterized in that: Backfill grouting S600 is constructed in two sequence holes, first sequence hole Ⅰ and then sequence hole Ⅱ. The time interval between grouting of each sequence hole is not less than 48h, and sequence holes Ⅰ and Ⅱ are classified and numbered. Each grouting area can be grouted separately, and the end of each section is tightly sealed after concrete pouring. Backfill grouting can only be carried out after all holes of the same sequence in the same area are drilled.
10. The method for constructing a small-section water conveyance tunnel based on a prefabricated arch structure according to claim 9, characterized in that: Backfill grouting S600 also includes: backfill grouting sequence, starting from the lower end of the tunnel and moving toward the higher end, the specific method of pushing grouting: the first hole at the lower end is used as a grouting hole, and the adjacent holes are used for drainage and exhaust, and the hole is immediately closed after the thickest first-level slurry is discharged, and then changed to a slurry inlet hole, until the grouting of all the holes in the sequence reaches the end standard; when the design specified pressure is reached, at the specified pressure, the grouting hole stops absorbing slurry and continues for 10 minutes.