Temporary tunnel face supporting method for highway tunnel excavation
Through the combination technology of hydraulic support and flexible net, temporary reinforcement of the palm surface of soft rock tunnel is achieved, landslide problems caused by surrounding rock deformation are solved, construction efficiency and safety are improved, cost and dust pollution are reduced, and green is met. Construction requirements.
Patent Information
- Application Number
- CN202411074151.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-07
- Publication Date
- 2024-11-12
AI Technical Summary
During the construction of soft rock tunnels, large deformation of the surrounding rock leads to landslide surface collapse. The existing technologies such as backfilling of the cave slag and sealing of jet concrete have problems such as long construction period, high cost, and dust pollution, which are difficult to meet the requirements of quality projects and green construction.
The hydraulic support and flexible net are used for temporary support of the palm. By placing the hydraulic support on the bottom plate of the upper step, the upper end of the hydraulic support is tilted on the palm surface and connected to the flexible net, and fixed with the steel arch frame and anchor rod. Gradually excavate and support the tunnel, and the construction will be completed.
It achieves safer and more efficient reinforcement of the palm surface, shortens construction time, reduces costs, improves construction progress and safety, and reduces dust pollution.
Smart Images

Figure CN118933931A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of tunnel excavation, and in particular relates to a method for temporarily supporting a heading face in highway tunnel excavation. Background Art
[0002] The NATM tunnel construction process is divided into face excavation, initial support and secondary lining. Generally, the initial support can only be carried out after the face is stable. However, soft rock tunnels are often accompanied by large deformation of the surrounding rock and collapse of the face, making it impossible to successfully complete the initial support construction.
[0003] The industry traditionally adopts measures such as backfilling with slag and sealing the tunnel face with shotcrete to deal with the above situation, but there are problems such as repeated handling of slag, waste of concrete, long construction period, and high cost, which do not meet the requirements of quality engineering and green construction. In addition, the method of backfilling the tunnel face with slag can easily lead to unfavorable factors such as weak backpressure control effect, slag occupying the initial support construction space, and high dust pollution.
[0004] Therefore, it is necessary to provide an improved technical solution to address the above-mentioned deficiencies in the prior art. Summary of the invention
[0005] The purpose of the present invention is to overcome the above-mentioned deficiencies in the prior art. The present invention provides a method for temporarily supporting the heading face of a highway tunnel excavation.
[0006] In order to achieve the above object, the present invention provides the following technical solutions:
[0007] A method for temporarily supporting the face of a highway tunnel excavation comprises the following steps:
[0008] Step S1, excavating the tunnel entrance to form a construction section corresponding to the tunnel, setting up a pipe shed on the construction section and performing grouting;
[0009] Step S2, blasting and excavating the upper step, and after the upper step is constructed to a preset position, blasting and clearing the tunnel face;
[0010] After blasting and clearing the danger, multiple hydraulic supports are placed on the upper step bottom plate, the upper ends of the hydraulic supports are tilted and supported on the upper step face, and one end of the multiple hydraulic supports that abuts against the upper step face is connected to a flexible net;
[0011] Step S3, erecting a steel arch frame on the upper step and fixing it with a locking anchor pipe, and installing anchor rods after initial concrete spraying on the inner wall of the tunnel corresponding to the upper step;
[0012] Step S4, performing blasting excavation on the middle step, extending the steel arch frame of the middle step excavation part, fixing the extended part with a locking foot anchor pipe, and then continuing blasting excavation on the lower step, extending the steel arch frame corresponding to the lower step excavation part, and fixing the extended part to the invert arch;
[0013] After initial concrete spraying on the inner walls of the tunnel corresponding to the middle step, lower step and invert, anchor bolts are installed.
[0014] Step S5, after removing the hydraulic support, repeat steps S2 to S4 to perform a cyclic construction until the tunnel excavation is completed.
[0015] Preferably, there are 8 hydraulic supports, of which 2 support points between the hydraulic supports and the tunnel face are spaced apart in the longitudinal direction along the tunnel centerline, and 6 support points between the hydraulic supports and the tunnel face are evenly distributed along the tunnel arch line.
[0016] Preferably, the flexible net is adapted to the shape of the upper step tunnel face, a back plate is provided between the hydraulic support and the tunnel face, and the flexible net is detachably connected to the back plate.
[0017] Preferably, a plurality of connection structures are distributed on one side of the back plate close to the palm face, and the connection structure includes two fasteners, one end of which is fixed to the back plate by a smooth transition, and the other end of the fastener extends parallel to the back plate to form an opening corresponding to the flexible net, and the two fastener openings of the same connection structure are in opposite directions.
[0018] Preferably, the distance between the two fasteners of the same connecting structure is greater than the diameter of the wire of the flexible net.
[0019] Preferably, the back plate is provided with a plurality of clearance grooves corresponding to the connection structure, the depth of the clearance grooves is not less than the height of the fasteners, and the edges of the clearance grooves extend to the end face of the back plate through a smooth transition.
[0020] Preferably, a base is provided at one end of the hydraulic support corresponding to the upper step bottom plate, and a sleeve corresponding to the inclination angle of the hydraulic support is provided on the base.
[0021] Preferably, the bases corresponding to the plurality of hydraulic supports are connected as one, and a limiting groove corresponding to the base is provided in the middle of the upper step bottom plate.
[0022] Preferably, the length of the bottom plate is no greater than half of the corresponding span of the upper step.
[0023] Beneficial effects: This application proposes a safer, more efficient and material-consolidating construction method to temporarily reinforce the face, which can reinforce the face that may collapse in advance, ensure construction safety, improve project progress, reduce construction costs and speed up construction progress. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] The drawings constituting a part of the present application are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. Among them:
[0025] Figure 1 A schematic diagram of the support point distribution of the hydraulic props on the upper step face in a specific embodiment provided by the present invention;
[0026] Figure 2 A support schematic diagram of a hydraulic support in a specific embodiment provided by the present invention;
[0027] Figure 3 This is a schematic diagram of the installation of the sleeve in the specific embodiment provided by the present invention;
[0028] Figure 4 A schematic diagram of the distribution of fasteners in a specific embodiment provided by the present invention;
[0029] Figure 5 It is a simplified side view of the back plate in the specific embodiment provided by the present invention.
[0030] In the figure: 1. upper step; 2. middle step; 3. lower step; 4. inverted arch; 5. flexible net; 6. support point; 7. steel arch frame; 8. hydraulic support; 9. sleeve; 10. base; 11. back plate; 12. fastener; 13. connecting pipe DETAILED DESCRIPTION
[0031] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. All other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention belong to the scope of protection of the present invention.
[0032] In the description of the present invention, the terms "longitudinal", "lateral", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and do not require that the present invention must be constructed and operated in a specific orientation. Therefore, they should not be understood as limitations on the present invention. The terms "connected" and "connected" used in the present invention should be understood in a broad sense. For example, they can be fixed connections or detachable connections; they can be directly connected or indirectly connected through intermediate components. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.
[0033] The present invention will be described in detail below with reference to the accompanying drawings and in combination with embodiments. It should be noted that the embodiments and features in the embodiments of the present invention can be combined with each other without conflict.
[0034] like Figure 1-5 As shown, a method for temporary support of the heading face of highway tunnel excavation includes the following steps: step S1, laying out the tunnel section according to the tunnel excavation route, excavating the portal to form the construction section of the corresponding tunnel, setting up a pipe shed and grouting on the construction section based on the geological survey method, specifically, setting up a small guide tube for advance support in the tunnel section with poor geological conditions and the section with poor surrounding rock, and using a large pipe shed for advance support in the tunnel portal section; step S2, blasting and excavating the upper step 1, after the upper step 1 is constructed to a preset position, blasting and clearing the heading face, the excavation progress of each excavation cycle of the upper step 1, the middle step 2 and the lower step 3 is 2-3 steps, and during the first excavation, the excavation progress of the upper step 1 is 3 excavation cycles, so that three steps can be formed when the middle step 2 and the lower step 3 are excavated, and the subsequent construction excavates one excavation cycle each time from top to bottom.
[0035] After blasting and clearing, multiple hydraulic supports 8 are placed on the bottom plate of the upper step 1. The upper end of the hydraulic supports 8 is tilted and supported on the upper step 1. The hydraulic supports 8 support the face by tightening. The ends of the multiple hydraulic supports 8 that touch the face of the upper step 1 are connected to the flexible net 5, which is a wire mesh. Thus, the face is temporarily reinforced by points, effectively balancing the stress of the face, controlling the deformation of the face, and providing a safe construction environment for the initial support construction. The temporary support measures of hydraulic support + flexible net 5 are short in time, and the support can be completed within 0.5 hours. Compared with the 2-3 hours of backfilling of the slag, the work efficiency is significantly improved.
[0036] Step S3, erect a steel arch frame 7 on the upper step 1 and fix it through a locking anchor pipe to fix the steel arch frame 7. After fixing the steel arch frame 7, perform initial concrete spraying and sealing on the inner wall of the tunnel corresponding to the upper step 1, then install anchor rods, and connect anchor nets between the anchor rods to support the tunnel surrounding rock.
[0037] Step S4, carry out blasting excavation of the middle step 2, extend the steel arch frame 7 of the excavated part of the middle step 2, the extended part contacts the bottom plate of the middle step 2, and fix the extended part with the locking foot anchor pipe, and then continue to carry out blasting excavation of the lower step 3 after fixing the extended part with the locking foot anchor pipe, extend the steel arch frame 7 corresponding to the excavated part of the lower step 3, and fix the extended part to the inverted arch 4, after the excavation of the middle step 2 is completed, the lower step 3 and the corresponding inverted arch 4 are directly constructed without anchor rod driving and concrete spraying, after the outer sides of the lower step 3 and the inverted arch 4 are constructed, the extended part of the steel arch frame 7 corresponding to the inverted arch 4 steel frame and the lower step 3 is connected to the middle step 2 part, and then the inner walls of the tunnel corresponding to the middle step 2, the lower step 3 and the inverted arch 4 are initially sprayed with concrete and anchor rods are driven, and anchor nets are set between the anchor rods.
[0038] Step S5, after removing the hydraulic support 8, repeat steps S2 to S4 to carry out cyclic construction, and each subsequent construction cycle is 2-3 steel frames until the tunnel excavation is completed.
[0039] In an optional embodiment, there are 8 hydraulic supports 8, of which 2 hydraulic supports 8 and the support points 6 of the tunnel face are spaced apart in the longitudinal direction along the tunnel centerline, thereby ensuring support for the middle of the tunnel face, and 6 hydraulic supports 8 and the support points 6 of the tunnel face are evenly distributed along the tunnel arch line, thereby supporting the arched part of the tunnel face. In this embodiment, there are three rows of hydraulic supports 8 on the tunnel face in the longitudinal direction.
[0040] The two supporting points in the middle of the face are located in the second and third rows from top to bottom. Specifically, there are two hydraulic supports in the top row, and the vertical distance from the arch is about 40 cm. The part above the upper step is divided into three parts after deducting this 40 cm. The second and bottom rows of hydraulic supports are arranged at this spacing, with 3 hydraulic supports in each row, evenly arranged.
[0041] In this embodiment, the eight hydraulic supports 8 are connected to the hydraulic station through control valves respectively, so that the eight hydraulic supports 8 can be independently controlled as needed.
[0042] In an optional embodiment, the flexible net 5 is adapted to the shape of the upper step 1, so that the face can be temporarily supported by forming a face from points. After the face is blasted and cleared, the face is reinforced immediately to avoid deformation and collapse of the face and affect subsequent processes, thereby improving construction efficiency and safety. In addition, the hydraulic support and the flexible net 5 can be reused to further reduce construction costs.
[0043] A back plate 11 is provided between the hydraulic support 8 and the tunnel face. The back plate 11 is used to improve the stability of contact with the tunnel face on the one hand, and is used to connect the flexible net 5 on the other hand. The flexible net 5 is connected to the back plate 11 in a detachable manner to facilitate construction and disassembly. The hydraulic support 8 adopts DW28-30 / 100B single hydraulic prop. The model of the flexible net 5 is JD PET 120×120MS, and the mesh size (mm) is 100×100.
[0044] In an optional embodiment, a plurality of connection structures are distributed on one side of the back plate 11 close to the palm face. Specifically, there may be four connection structures distributed in a square shape to adapt to the mesh size of the flexible net 5 and ensure the stability of supporting the flexible net 5. The connection structure includes two fasteners 12. The two fasteners 12 are close to each other. The fasteners 12 are metal plates, metal strips or metal columns. One end of the fasteners 12 is fixed to the back plate 11 through a smooth transition. The other end of the fasteners 12 extends parallel to the back plate 11. The spacing between the fasteners 12 and the back plate 11 (the bottom of the give way groove) is adapted to the diameter of the mesh wire of the flexible net 5, thereby forming an opening corresponding to the flexible net 5. The opening directions of the two fasteners 12 of the same connection structure are opposite. The two sides of the mesh wire of the flexible net 5 are clamped by the two fasteners 12, thereby forming a restriction structure for the flexible net 5.
[0045] In an optional embodiment, the spacing between two fasteners 12 of the same connecting structure is greater than the diameter of the mesh wire of the flexible net 5, and the flexible net 5 is installed and removed by bending the mesh wire of the flexible net 5 and passing it between the two fasteners 12. In order to prevent the fasteners 12 from being deformed by stress caused by the palm face during the jacking process, a plurality of clearance grooves relative to the connecting structure are provided on the back plate 11, and the depth of the clearance grooves is not less than the height of the fasteners 12, so that the back plate 11 can contact the palm face, and the edge of the clearance groove extends to the end face of the back plate 11 through a smooth transition, thereby reducing the damage to the flexible net 5 caused by the vertical extrusion of the clearance groove. Furthermore, in order to improve the anti-slip shoes, an anti-slip protrusion is provided on the side of the back plate 11 corresponding to the palm face.
[0046] Of course, in another embodiment, the flexible net 5 is arranged on a side of the back plate 11 away from the palm face, so that the clearance groove is not arranged wirelessly.
[0047] In an optional embodiment, a base 10 is provided at one end of the hydraulic support 8 corresponding to the bottom plate of the upper step 1. The base 10 is a steel plate so that it can be stably placed on the bottom plate of the upper step 1. A sleeve 9 corresponding to the inclination angle of the hydraulic support 8 is provided on the base 10. The sleeve 9 is fixed to the base 10 and inclined at a preset angle. The hydraulic support 8 can be placed in the sleeve 9 to be installed at the pre-examined angle and point to support the face.
[0048] Correspondingly, a connecting pipe 13 corresponding to the hydraulic support 8 is provided on the back plate 11, and the connecting pipe 13 is inclined to the back plate 11 at an angle adapted to the sleeve 9, so that a detachable operation can be achieved.
[0049] Furthermore, in order to improve the support efficiency, the bases 10 corresponding to the multiple hydraulic supports 8 are connected as a whole, so as to achieve the purpose of rapid support. The multiple sleeves 9 on the base 10 are installed at a preset angle, so that the hydraulic support 8 can be directly installed. In this embodiment, in order to improve the support stability, a limiting groove corresponding to the base 10 is provided in the middle of the bottom plate of the upper step 1. The limiting groove is opened on the bottom plate of the upper step 1 by a pneumatic pick and is located at the center line of the tunnel. The length of the bottom plate is not more than half of the corresponding span of the upper step 1, which is convenient for disassembly and transportation. After the hydraulic support 8 is placed, the corresponding back plate 11 is connected at the piston end of the hydraulic support 8 through a connecting pipe 13. After the flexible net 5 is installed on the back plate 11, the hydraulic support 8 is started to extend, thereby forming support.
[0050] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention are within the scope of protection of the pending claims of the present invention.
Claims
1. A method for temporary support of the heading face of a highway tunnel excavation, characterized in that: The following steps are involved: Step S1, excavating the tunnel entrance to form a construction section corresponding to the tunnel, setting up a pipe shed on the construction section and performing grouting; Step S2, blasting and excavating the upper step, and after the upper step is constructed to a preset position, blasting and clearing the tunnel face; After blasting and clearing the danger, multiple hydraulic supports are placed on the upper step bottom plate, the upper ends of the hydraulic supports are tilted and supported on the upper step face, and one end of the multiple hydraulic supports that abuts against the upper step face is connected to a flexible net; Step S3, erecting a steel arch frame on the upper step and fixing it with a locking anchor pipe, and installing anchor rods after initial concrete spraying on the inner wall of the tunnel corresponding to the upper step; Step S4, performing blasting excavation on the middle step, extending the steel arch frame of the middle step excavation part, fixing the extended part with a locking foot anchor pipe, and then continuing blasting excavation on the lower step, extending the steel arch frame corresponding to the lower step excavation part, and fixing the extended part to the invert arch; After initial concrete spraying on the inner walls of the tunnel corresponding to the middle step, lower step and invert, anchor bolts are installed. Step S5, after removing the hydraulic support, repeat steps S2 to S4 to perform a cyclic construction until the tunnel excavation is completed.
2. The method for temporary support of the heading face of a highway tunnel excavation according to claim 1 is characterized in that: There are eight hydraulic supports, of which two support points between the hydraulic supports and the tunnel face are spaced apart in the longitudinal direction along the tunnel centerline, and six support points between the hydraulic supports and the tunnel face are evenly distributed along the tunnel arch line.
3. The method for temporary support of the heading face of a highway tunnel excavation according to claim 1 is characterized in that: The flexible net is adapted to the shape of the upper step tunnel face, a back plate is provided between the hydraulic support and the tunnel face, and the flexible net is detachably connected to the back plate.
4. The method for temporary support of the heading face of a highway tunnel excavation according to claim 3 is characterized in that: A plurality of connection structures are distributed on one side of the back plate close to the palm face, and the connection structure includes two fasteners, one end of which is fixed to the back plate by a smooth transition, and the other end of the fastener extends parallel to the back plate to form an opening corresponding to the flexible net, and the two fastener openings of the same connection structure are in opposite directions.
5. The method for temporary support of the heading face of a highway tunnel excavation according to claim 4 is characterized in that: The distance between the two fasteners of the same connecting structure is greater than the diameter of the wire of the flexible net.
6. The method for temporary support of the heading face of a highway tunnel excavation according to claim 4, characterized in that: The back plate is provided with a plurality of clearance grooves corresponding to the connection structure, the depth of the clearance grooves is not less than the height of the fasteners, and the edges of the clearance grooves extend to the end surface of the back plate through a smooth transition.
7. The method for temporary support of the heading face of a highway tunnel excavation according to claim 1, characterized in that: The hydraulic support is provided with a base at one end corresponding to the upper step bottom plate, and the base is provided with a sleeve corresponding to the inclination angle of the hydraulic support.
8. The method for temporary support of the heading face of a highway tunnel excavation according to claim 7, characterized in that: The bases corresponding to the plurality of hydraulic supports are connected as one body, and a limiting groove corresponding to the base is provided in the middle of the upper step bottom plate.
9. The method for temporary support of the heading face of a highway tunnel excavation according to claim 8, characterized in that: The length of the bottom plate is no greater than half of the corresponding span of the upper step.